CN208857665U - Have both the foot bridge for opening bridge deck of piping lane function - Google Patents

Have both the foot bridge for opening bridge deck of piping lane function Download PDF

Info

Publication number
CN208857665U
CN208857665U CN201821391043.7U CN201821391043U CN208857665U CN 208857665 U CN208857665 U CN 208857665U CN 201821391043 U CN201821391043 U CN 201821391043U CN 208857665 U CN208857665 U CN 208857665U
Authority
CN
China
Prior art keywords
girder
bridge
piping lane
foot
top plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821391043.7U
Other languages
Chinese (zh)
Inventor
傅大宝
刘金福
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fuzhou planning and Design Institute Group Co.,Ltd.
Original Assignee
Fuzhou Planning Design and Research Institute
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fuzhou Planning Design and Research Institute filed Critical Fuzhou Planning Design and Research Institute
Priority to CN201821391043.7U priority Critical patent/CN208857665U/en
Application granted granted Critical
Publication of CN208857665U publication Critical patent/CN208857665U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model relates to a kind of foot bridges for opening bridge deck for having both piping lane function, girder including laterally spaced setting, bottom plate is provided between the bottom of adjacent two girder, it is provided with the top plate with girder releasable connection between the top of adjacent two girder, forms the chamber for laying the line between adjacent two girder with the region that corresponding bottom plate and top plate surround.The foot bridge is compact-sized, facilitates the maintenance of the dilatation of gap bridge pipeline and gap bridge pipeline.

Description

Have both the foot bridge for opening bridge deck of piping lane function
Technical field
The utility model relates to a kind of foot bridges for opening bridge deck for having both piping lane function.
Background technique
Various Option of Piping across Bridge are considered in municipal administration Bridge Design at present.The design scheme of newly building bridge Option of Piping across Bridge is basic Have following several:
(1) the big pipe such as feed pipe passes through from the vane position evacuated under pavement, i.e. pumping Liang Guoguan;(2) feed pipe etc. Big pipe is set to outside bridge;(3) pipelines such as telecommunication cable and distribution cable are under side walk slab or the position taken out passes through;(4) by It is limited in by bridge type and across footpath, some pipelines can not pass through from bridge, need to build special pipe bridge for Option of Piping across Bridge, will both manage Line is suspended on outside bridge, and pipeline support structure is connect with bridge web or top flange cantilever end, or the bar planting on bent cap, pours one section Cantilever end is for Option of Piping across Bridge.
Line gap bridge is crossed at present is primarily present following problems:
(1) bridge is unable to satisfy the needs of pipeline dilatation.The bridge built up is needed to lay gap bridge pipeline First remove bridge certain components, to pipelining after pour again.The way not only causes a large amount of fund to waste, and And urban operating mechanism is again and again teared down and built, and also results in adverse effect to city;
(2) pipeline is placed on outside bridge, influences urban landscape.Upper part scheme is that pipeline is placed on to bridge structure body Outside, which influences urban landscape;
(3) maintenance of gap bridge pipeline is more difficult.Since pipelining is in bridge structure body, repair more difficult.
Summary of the invention
The purpose of this utility model is to provide a kind of foot bridge for opening bridge deck for having both piping lane function, structure is tight It gathers, facilitates the maintenance of the dilatation of gap bridge pipeline and gap bridge pipeline.
The technical solution of the utility model is: a kind of foot bridge for opening bridge deck having both piping lane function, including The girder of laterally spaced setting is provided with bottom plate between the bottom of adjacent two girder, positioned at the top of adjacent two girder Between be provided with top plate with girder releasable connection, the region surrounded between adjacent two girder with corresponding bottom plate and top plate is formed Chamber for laying the line.
Further, the side wall of the girder is provided with to be provided on the bracket and/or bottom plate for laying the line and be used for The mounting base laid the line.
Further, the both sides of the top plate are longitudinally spaced is provided with counterbore, the edge of a wing setting at the top of the girder There is the bolt for passing through counterbore from bottom to top, the nut for fixing top plate is bolted on the bolt, blocking in the counterbore has The rubber sleeve that can be pulled out.
Further, shear connector is evenly equipped on the top plate, the both sides of top plate are additionally provided with hanging ring.
Further, by box or I-shaped and be made of steel, the top plate is coagulation local soil type in the section of the girder Plywood.
Further, the both sides of the bottom plate mutually weld with girder lower end respectively or are connected through bolt with girder lower end It connects, draining hole is evenly equipped on bottom plate.
Further, the bottom plate is made of steel plate.
Compared with prior art, the utility model has the advantage that this had both piping lane function opens bridge deck The bridge deck of foot bridge can open, facilitate maintenance personal to overhaul;It is capable of providing the space of pipeline dilatation in beam body, facilitates pipeline Dilatation.
Detailed description of the invention
Fig. 1 is the foot bridge structural schematic diagram of the utility model;
Fig. 2 is the top board structure schematic diagram of the utility model;
Fig. 3 is the top plate of the utility model and the removable structure schematic diagram of girder;
Fig. 4 is the structural diagram of base plate of the utility model.
Specific embodiment
In order to make the above-mentioned features and advantages of the utility model more obvious and understandable, special embodiment below, and cooperate attached drawing, It is described in detail below, but the utility model is not limited to this.
Referring to figs. 1 to Fig. 4
A kind of foot bridge for opening bridge deck having both piping lane function, foot bridge are mutually indepedent with vehicular bridge.Foot bridge Girder 1 including laterally spaced setting is provided with bottom plate 3 between the bottom of adjacent two girder, is located at adjacent two girder Top between be provided with top plate 2 with girder releasable connection, surrounded between adjacent two girder with corresponding bottom plate and top plate Region formed for lay the line 4 chamber 14.
In the present embodiment, in order to preferably install pipeline, the side wall of the girder is provided with the bracket for laying the line 5 and/or bottom plate on be provided with mounting base 51 for laying the line.
In the present embodiment, the both sides of the top plate are longitudinally spaced to be provided with counterbore 7, and the edge of a wing at the top of the girder is set It is equipped with the bolt 6 for passing through counterbore from bottom to top, the nut 10 for fixing top plate, envelope in the counterbore are bolted on the bolt It is stifled to have the rubber sleeve 11 that pulled out, prevent nuts and bolt from getting rusty by the closure of rubber sleeve, and prevent sundries from entering in counterbore. When needing bridge floor to open (when i.e. top plate is opened), rubber sleeve is pulled out, nut is unscrewed, top plate is sling i.e. using minor crane It can.
In the present embodiment, in order to improve the connection between top plate steel and concrete, shearing resistance company is evenly equipped on the top plate Fitting 8.In order to preferably open top plate, the both sides of the top plate are additionally provided with hanging ring 9.
In the present embodiment, in order to improve the intensity of girder, the section of the girder is box or I-shaped and by steel system At;In order to draw materials conveniently, the top plate is concrete combined board.
In the present embodiment, the bottom plate is made of steel plate, and the both sides of bottom plate are mutually welded with girder lower end respectively or bottom plate Both sides longitudinally spaced be provided with several bolts hole and be connected through bolt 13 with girder lower end.Drainage hole is evenly equipped on bottom plate Hole 12, to avoid beam body internal water accumulation.
Have both piping lane function to open foot bridge construction procedure as follows: set up girder;Mounting base, using bolt or weldering Connecing will connect between bottom plate and girder;In the side wall mounting bracket of girder, lay the line;Top plate, tightening nuts are installed, and are being sunk Rubber sleeve is installed in hole;Pour concrete roof;When bridge deck need to be opened to overhaul pipeline or increase gap bridge pipeline, pull out first Except rubber sleeve, nut is then unscrewed, top plate is sling using minor crane.
The above is only the preferred embodiment of the present invention, it is all done according to present utility model application the scope of the patents it is equal Deng variation and modification, it should all belong to the covering scope of the utility model.

Claims (7)

1. a kind of foot bridge for opening bridge deck for having both piping lane function, which is characterized in that including laterally spaced setting Girder is provided with bottom plate between the bottom of adjacent two girder, is provided between the top of adjacent two girder and girder The top plate of releasable connection, the region surrounded between adjacent two girder with corresponding bottom plate and top plate form the chamber for laying the line Room.
2. the foot bridge according to claim 1 that open bridge deck for having both piping lane function, which is characterized in that the master The side wall of beam is provided with the mounting base being provided on the bracket and/or bottom plate for laying the line for laying the line.
3. the foot bridge according to claim 1 or 2 that open bridge deck for having both piping lane function, which is characterized in that institute State top plate both sides it is longitudinally spaced be provided with counterbore, the edge of a wing at the top of the girder is provided with from bottom to top across counterbore Bolt is bolted with the nut for fixing top plate on the bolt, and blocking in the counterbore has the rubber sleeve that can be pulled out.
4. the foot bridge according to claim 3 that open bridge deck for having both piping lane function, which is characterized in that the top Shear connector is evenly equipped on plate, the both sides of top plate are additionally provided with hanging ring.
5. the foot bridge according to claim 1,2 or 4 that open bridge deck for having both piping lane function, which is characterized in that By box or I-shaped and be made of steel, the top plate is concrete combined board in the section of the girder.
6. the foot bridge according to claim 1,2 or 4 that open bridge deck for having both piping lane function, which is characterized in that The both sides of the bottom plate mutually weld with girder lower end respectively or are connected through bolt with girder lower end, and draining is evenly equipped on bottom plate Hole.
7. the foot bridge according to claim 6 that open bridge deck for having both piping lane function, which is characterized in that the bottom Plate is made of steel plate.
CN201821391043.7U 2018-08-28 2018-08-28 Have both the foot bridge for opening bridge deck of piping lane function Active CN208857665U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821391043.7U CN208857665U (en) 2018-08-28 2018-08-28 Have both the foot bridge for opening bridge deck of piping lane function

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821391043.7U CN208857665U (en) 2018-08-28 2018-08-28 Have both the foot bridge for opening bridge deck of piping lane function

Publications (1)

Publication Number Publication Date
CN208857665U true CN208857665U (en) 2019-05-14

Family

ID=66415897

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821391043.7U Active CN208857665U (en) 2018-08-28 2018-08-28 Have both the foot bridge for opening bridge deck of piping lane function

Country Status (1)

Country Link
CN (1) CN208857665U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114790691A (en) * 2022-04-14 2022-07-26 通号建设集团有限公司 Construction method for steel structure pipe gallery channel under bridge

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114790691A (en) * 2022-04-14 2022-07-26 通号建设集团有限公司 Construction method for steel structure pipe gallery channel under bridge
CN114790691B (en) * 2022-04-14 2023-10-20 通号建设集团有限公司 Construction method for under-bridge steel structure pipe gallery channel

Similar Documents

Publication Publication Date Title
CN106049707B (en) Prefabricated wall, prefabricated building construction and method of construction
CN205999782U (en) A kind of pre-buried closed bridge drainage system
CN109183614B (en) Cable trough main bearing T-beam composite sidewalk and installation method thereof
CN208167794U (en) Monoblock type forms cast-in-place concrete cable duct
CN109898550A (en) A kind of prefabricated assembled cantilever retaining wall being connected by screw bolts mode
CN208857665U (en) Have both the foot bridge for opening bridge deck of piping lane function
CN110295624A (en) Crossroad underground pedestrian walk and pipe gallery build structure and its construction method jointly
CN206521696U (en) A kind of bridge drainage system
CN106436591A (en) Steel cantilever combined bridge deck slab widening and reconstruction structure and construction method thereof
CN109898551A (en) A kind of prefabricated assembled cantilever retaining wall using bolt block connection type
CN106087711A (en) Antinode work beam-steel concrete top board-external prestressing combines T-shaped simply supported beam
CN208280171U (en) A kind of city integrated piping lane
CN207062989U (en) Underground pipe gallery node structure outside corridor in sewage pipe access corridor
CN209260907U (en) A kind of C-type steel purlin being easily installed
CN109024561A (en) A kind of flange form connection structure at steel-pipe pile top and I-shaped gooseneck
CN208803382U (en) A kind of CFST Arch Bridge intermediate transverse girder promotion positioning apparatus
CN211772819U (en) Special water drain pipe of adjustable high formula highway reinforced concrete combination carriageway plate structure
CN210830796U (en) Small-size utility tunnel device on bridge central authorities' division strip
CN209429275U (en) The pre-buried fixed end structure of sunpender monoblock type
CN204418728U (en) A kind of precast monolithic washroom
CN210563429U (en) Shear wall template reinforcing member
CN210049373U (en) Assembly type I-steel composite floor slab mounting structure
CN209620300U (en) Overlapped shear wall plate and overlapped shear wall
CN209066871U (en) A kind of Pipe installing standard element of Preembedded of tier building
CN219343528U (en) Basic connection structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 350108 No.1 Gaoxin Avenue, high tech Zone, Minhou County, Fuzhou City, Fujian Province

Patentee after: Fuzhou planning and Design Institute Group Co.,Ltd.

Address before: 350108 No.1 Gaoxin Avenue, high tech Zone, Minhou County, Fuzhou City, Fujian Province