CN208824091U - A kind of wet plume condensation takes off white device - Google Patents

A kind of wet plume condensation takes off white device Download PDF

Info

Publication number
CN208824091U
CN208824091U CN201821488419.6U CN201821488419U CN208824091U CN 208824091 U CN208824091 U CN 208824091U CN 201821488419 U CN201821488419 U CN 201821488419U CN 208824091 U CN208824091 U CN 208824091U
Authority
CN
China
Prior art keywords
wet
cyclone
air
flue gas
white
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821488419.6U
Other languages
Chinese (zh)
Inventor
孙文发
张刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanxi Renda Xinyue Environmental Protection Technology Co Ltd
Original Assignee
Shanxi Renda Xinyue Environmental Protection Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanxi Renda Xinyue Environmental Protection Technology Co Ltd filed Critical Shanxi Renda Xinyue Environmental Protection Technology Co Ltd
Priority to CN201821488419.6U priority Critical patent/CN208824091U/en
Application granted granted Critical
Publication of CN208824091U publication Critical patent/CN208824091U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A50/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE in human health protection, e.g. against extreme weather
    • Y02A50/20Air quality improvement or preservation, e.g. vehicle emission control or emission reduction by using catalytic converters
    • Y02A50/2351Atmospheric particulate matter [PM], e.g. carbon smoke microparticles, smog, aerosol particles, dust

Landscapes

  • Chimneys And Flues (AREA)

Abstract

The utility model discloses a kind of wet plume condensations to take off white device, including water blocking device, air pipeline, condensate reflux line, cyclone, air blower and control device;Cyclone is installed above desulfurizing tower, air pipeline is equipped with above cyclone, air pipeline bottom is connect with air blower, air pipeline is led directly in Wet chimney, the outlet end of air pipeline is equipped with nozzle, cyclone side is equipped with condensate reflux line close to Wet chimney inner wall, and sink is received at the top of condensate reflux line, and condensate reflux line leads to outside desulfurizing tower;Cyclone side opening is equipped with environment monitoring mouth;Water blocking device is equipped with above cyclone, water blocking device small big loudspeaker barrel structure under being, water blocking device upper end is fixedly connected with the inner wall of Wet chimney.The utility model solves the pollution problem that industrial coal equipment is discharged fume to atmosphere, not only removes the moisture contained in flue gas, pays off the quality that can be further improved discharge flue gas except the fine dust particles object in flue gas.

Description

A kind of wet plume condensation takes off white device
Technical field
The utility model relates to a kind of wet plume condensations to take off white device, belong to flue gas desulfurization technique field.
Background technique
Desulfurization fume status: for the flue-gas temperature being discharged from desulfurizing tower generally between 50 DEG C~55 DEG C, flue gas is wet saturation State, after flue gas discharge, white smog, referred to as wet plume is commonly called as " white cigarette ".If wet saturated flue gas, which is expelled directly out, to be brought Two kinds of adverse consequences: first is that the lifting ability of flue gas is low, being unfavorable for flue gas dilution diffusion, may be formed about water mist in chimney, Cause the local pollution of the environment, i.e. so-called flue gas " under wash ";Second is that cooling through air, wet saturated vapor is solidifying after flue gas discharge Form acidic liquid sedimentation, i.e., it is so-called " rainy ", that is, environment is polluted, and cause to corrode to equipment and building.Therefore de- In sulphur system, the wet saturated steam for reducing or removing in flue gas is particularly important.
Take off in the world to wet flue gas at present white mainly using following technique: flue gas reheats mode and directly heats and indirectly Two kinds of heating.1000~1100 DEG C of high temperature cigarette heat that the mode of directly heating can be generated using natural gas or light diesel fuel burning, It can directly be mixed using the untreated hot fume in part, no matter which kind of mode be used, it need to be based on thermal balance, not drop Based on low emission requires.
Developed country usually uses flue gas reheat technique in processing desulfurization wet flue gas, i.e., will be taken off using the former flue gas of boiler Sulphur flue gas is heated at least to 80 DEG C or more, is then discharged into atmosphere again.This flue gas reheat technique is can to eliminate white cigarette vision, But the moisture percentage in flue gas is not can be reduced, therefore be a kind of palliative measure.
There is also heater surfaces easily to adhere to grit for flue gas reheat technique, causes the reduction of heater heat transfer efficiency, even It causes heat transmitter to block, flue gas reheat is made to fail.Steam is blown into desulfurization wet flue gas to heat desulfurization fume there are also a kind of Technique, this technique will largely waste heat source, it is clear that not meet national conditions, therefore more undesirable.
Many years effort is passed through in China in terms of environmental improvement, the smoke evacuation of current industrial coal combustion equipment by dedusting, desulfurization and Denitration process greatly reduces pollution of the coal combustion equipment to atmosphere.But wet process is mostly used to the smoke evacuation of coal combustion equipment processing Thus sulfur removal technology also brings the white cigarette problem that moisture percentage is high in the flue gas discharged after wet desulphurization.The white cigarette of discharge can band Carry out following consequence: first is that the lifting ability of flue gas is low, being unfavorable for flue gas dilution diffusion, misty rain may be formed about in chimney, made At local environmental pollution, make the phenomenon that sprinkling around chimney;Second is that having acid since flue-gas temperature reduces in an atmosphere Property liquid condenses out from flue gas, causes to corrode to equipment and building.
Summary of the invention
The utility model is intended to provide a kind of wet plume condensation and takes off white device, reduces the exhaust gas of industrial production discharge, should Technique with it is traditional take off white technique compared with, do not consume thermal energy (not needing flue gas reheating), be not required to special messenger's operation, expeditiously clearly Except the moisture in wet flue gas, Plant in good condition utilization rate can reach 95% or more, securely and reliably.
In the utility model, first with air blower by outdoor air feeding eddy flow take off white device, to desulfurization wet flue gas into Row is cooled to summer≤48 DEG C, and winter≤45 DEG C make the water vapour in desulfurization wet flue gas be condensed into small water droplet.Condensed cigarette Gas generates centrifugal force because of rotation, condensate is cast to eddy flow above the barrel for taking off white device, separates the air-liquid of flue gas, reach To " taking off white " purpose.
The condensate of eddy flow removing is discharged into water receiving tank under the effect of gravity, is back to shower water pond through pipeline and is used. The moisture that eddy flow takes off white technique and can not only eliminate in desulfurization fume (including the tiny particles content carried in flue gas, improves dedusting effect Rate), moreover it is possible to the motive force for increasing secondary lifting to flue gas mitigates the load of smoke exhaust fan.Before taking off white device into eddy flow Amount containing wet flue gas, flow velocity, temperature and pressure, setting field control and remote PLC control mode controls the operation ginseng of air blower Number reaches qualified de- white effect.
The utility model provides a kind of wet plume condensation and takes off white device, which is mounted on above desulfurizing tower, takes off white dress It sets including water blocking device, air pipeline, condensate reflux line, cyclone, air blower and control device;Eddy flow is installed above desulfurizing tower Device, cyclone are located in the middle part of Wet chimney, are screwed;Air pipeline, air pipeline bottom and drum are equipped with above cyclone Blower connection, air pipeline are led directly in Wet chimney, and the outlet end of air pipeline is equipped with nozzle;Cyclone bottom outside is equipped with Water receiving tank, water receiving tank are circular ring shape, and water receiving tank lower part connects condensate reflux line, and condensate reflux line leads to outside desulfurizing tower; Cyclone downside opening is equipped with environment monitoring mouth;Water blocking device, water blocking device small big cone under being are equipped with above cyclone Structure, water blocking device upper end are fixedly connected with the inner wall of Wet chimney;
Control device includes sensor, on-site supervision instrument, PLC control device;Flue gas is installed in the exit of cyclone Temperature sensor, pressure sensor and on-site supervision instrument;Above the air nozzle at 1m installation flue-gas temperature sensor and On-site supervision instrument;In the outlet of water blocking device installation temperature, pressure and humidity sensor and on-site supervision instrument;On-site supervision Instrument includes thermometer, pressure gauge, humidometer;Sensor is controlled by PLC controller, and PLC control device passes through above-mentioned monitor The air capacity of the data control air blower conveying of table acquisition.
In above-mentioned apparatus, water receiving tank is cirque structure, is arranged in cyclone bottom outside;The internal diameter and cyclone of annulus Outer rim bottom edge connection, annulus outer rim connection Wet chimney barrel.Work of the condensate generated after flue gas condensing in centrifugal force After lower cast onto the barrel of Wet chimney, under gravity, flow in annulus, then be discharged into and follow through condensate reflux line Cisterna ambiens.
In above-mentioned apparatus, operating platform is equipped on the outside of the cyclone, operating platform is fixed on platform support.Operation is flat Platform is repaired for operator's tours of inspection and to equipment.
In above-mentioned apparatus, the air blower is controlled by blower variable frequency device, adjusts air inflow.According to humidity and pressure sensing The parameter adjustment air blower operation of device measurement, cools down wet flue gas and centrifugal force, by wet flue gas Dehumidification controlling in best shape State.
In above-mentioned apparatus, cyclone is mounted on Wet chimney environment monitoring mouth top, is located in the middle part of Wet chimney.It does not influence to ring Protect the normal monitoring of dedusting, denitration, desulfurization.Because taking off white is to be cooled down with air to the wet flue gas after desulfurization, if installation Can have an impact to environment monitoring in desulfurizing tower or below the environment monitoring mouth of Wet chimney.
In above-mentioned apparatus, the air nozzle is mounted at the 0.5m barrel of cyclone deflector exhanst gas outlet, air spray Mouth is arranged obliquely, and the elevation angle is 25 °.
In above-mentioned apparatus, amount containing wet flue gas, flow velocity, temperature and pressure before white device are taken off according to entering, determines air blower Revolving speed and pressure and cooling supply air quantity, and control device is set, including on-site supervision and remote PLC control device.Control device packet It includes: in the exit installation flue-gas temperature and pressure sensor for taking off white device cyclone, and, field controlling instrument includes: temperature Spend table, pressure gauge, humidometer.Flue-gas temperature sensor and thermometer, pressure gauge, humidity are installed at 1m above the air nozzle Table.In the outlet of water blocking device installation temperature, pressure and humidity sensor temperature table, pressure gauge, humidometer.PLC control device is logical The air capacity for crossing the data control air blower conveying of above-mentioned monitoring device acquisition is white to achieve the purpose that take off, mainly by above-mentioned The temperature of temperature remote transmission instrument acquisition, the air capacity that control air blower enters swirl-flow devices, which reaches, makes flue gas condensing to summer≤48 DEG C, winter≤45 DEG C.
Spiral stairs are installed below operating platform.Operation and dimension in order to facilitate operations staff to eddy flow cooling device It repairs and installs the operating platform.Operating platform is arranged separately on platform support, does not have any connection with desulfurizing tower, therefore do not increase The load of desulfurizing tower, has no effect to desulfurizing tower.Since common desulfurizing tower is all cylindrical, eddy flow cooling device behaviour The stair activity for making platform is the rotary annular stair for surrounding desulfurizing tower construction.
The air nozzle is mounted at the 0.5m barrel of cyclone deflector exhanst gas outlet, and air nozzle is set obliquely It sets, the elevation angle is 25 °.
Ben Tuobai device is circular configuration, when the wet flue gas after desulfurization flows through cyclone, in cyclone internal diversion plate Under the action of, with 25 ° of the elevation angle, the rotation speed of 6m/s carries out rotational flow along the barrel of device, but wet full in flue gas And steam is still without achieving the purpose that separate with flue gas.In order to remove the wet saturated steam in flue gas, this technique is on cyclone The air nozzle at 25 ° of elevations angle is installed, nozzle ejects the high-speed air flow of 15~20m/s, and high-speed air flow is along dress at square 0.5m The round tube wall set is rotated and is mixed with wet flue gas, will be in flue gas after wet flue gas cooling (summer≤48 DEG C, winter≤45 DEG C) Wet saturated steam be condensed into condensate.High-speed air flow also drives wet flue gas to rotate, the rotation wet flue gas stream that cyclone is discharged Speed increases to 9~12m/s.Wet flue gas improves rotation flow velocity, necessarily increases the centrifugal force of flue gas, makes condensate in flue gas from cigarette It is separated in gas, additionally, due to the increase of wet flue gas flow velocity, generates the negative of 50~70Pa in cyclone inclined plate smoke outlet Pressure, this, which is beneficial to improve, takes off putting to idle discharge for white rear flue gas.The air sprayed in device provides air by air blower.
The present apparatus is automatically controlled using PLC, passes through flue-gas temperature, humidity and the pressure of monitoring cyclone discharge, control drum The operation of blower, reasonably conveys air capacity, makes to take off in white device flue-gas temperature≤48 DEG C in summer (April~October), takes off white Flue gas moisture percentage≤9.5% afterwards, flue-gas temperature≤45 DEG C in winter (November~March next year), the flue gas moisture percentage of Tuo Baihou are small In 8.5%.Worker carries out tours of inspection to white device is taken off for ease of operation, and operating platform is arranged in the present apparatus, and operator passes through Spiral stairs around circle desulfurizing tower reach operating platform.
The utility model technique is on the basis of flue gas takes off white successful experience both at home and abroad at present for summary, through researching and developing The completely new wet flue gas of one kind out takes off white technique.This process structure is simple, is made of all-glass fibre reinforced plastic, wear-resistant, corrosion-resistant, For equipment substantially without maintenance, operating cost is low, and dehumidification efficiency is high, is not required to special messenger and participates in operation, takes off white technics comparing with conventional, can save Save 50% or more investment construction expense.
The utility model has the beneficial effects that
(1) pollution problem that industrial coal equipment is discharged fume to atmosphere is solved, the moisture contained in flue gas is not only removed, pays off Except the fine dust particles object in flue gas, the quality of discharge flue gas can be further improved.
(2) to take off it is white after flue gas increase discharge chimney power.
(3) the heating tube bonding dust for thoroughly solving dehumidifying smoke re-heater influences flue gas heat exchange, and equipment is caused to stop transport The problem of.
Detailed description of the invention
Fig. 1 is the formation mechenism figure of wet plume.
Fig. 2 is the elimination mechanism figure of wet plume.
Fig. 3 is the schematic diagram that the wet plume condensation of the utility model takes off white device.
Fig. 4 is the top view of water receiving tank.
In figure: 1, water blocking device, 2 be air pipeline, and 3 be cyclone, and 4 be operating platform, and 5 be environment monitoring mouth, and 6 be platform Bracket, 7 be condensate reflux line, and 8 be desulfurizing tower, and 9 be air blower, and 10 be Wet chimney, and 11 be water receiving tank, and 12 be water transport port;A is Eddy flow flue gas, b are air, and c is de- white cigarette gas.
Specific embodiment
The utility model is further illustrated below by embodiment, but is not limited to following embodiment.
The formation mechenism of wet plume is as shown in Figure 1, the curve in figure is the saturation curve of humid air, it is assumed that wet flue gas is in cigarette The state in chimney exit is located at A point, the saturation curve of gas, it is assumed that wet flue gas is located at A point in the state of chimney outlet, and ring The state of border air is located at F point, and flue gas is when leaving chimney in unsaturated state.Wet flue gas and surrounding air mixed process Start to change along AB line, flue gas becomes being saturated wet flue gas after reaching B point, and hereafter the mixing of humid air and surrounding air is along song Line BDE variation, and extra water vapour will condense into the small water droplet of liquid, form wet plume.
Flue gas, which reheats technology, to be heated to the wet saturated flue gas of desulfurization outlet, so that flue gas relative temperature is far from full And moisture curve.Wet plume eliminates mechanism as shown in Fig. 2, wet flue gas original state is located at A point, by AB liter after heating Temperature, then along BC blending, be cooled to ambient condition point C, entire ABC change procedure is non-intersecting with saturated humidity curve, therefore Wet plume is not generated.
As shown in Figure 3,4, a kind of wet plume condensation takes off white device, which is mounted on 8 top of desulfurizing tower, takes off white device packet Include water blocking device 1, air pipeline 2, condensate reflux line 7, cyclone 3, air blower 9 and control device;Rotation is installed above desulfurizing tower 8 Device 3 is flowed, cyclone 3 is located at 10 middle part of Wet chimney, is screwed;Air pipeline 2, air pipeline 2 are equipped with above cyclone 3 Bottom is connect with air blower 9, and air pipeline 2 is led directly in Wet chimney 10, and the outlet end of air pipeline 2 is equipped with nozzle;Eddy flow 3 bottom outside of device is equipped with water receiving tank 11, and water receiving tank 11 is circular ring shape, and 11 lower part of water receiving tank connects condensate reflux line 7, and condensate is returned Flow tube road 7 leads to outside desulfurizing tower 8;3 downside of cyclone opening is equipped with environment monitoring mouth 5;Water blocking device is equipped with above cyclone 3 1, the small big loudspeaker barrel structure under being of water blocking device 1,1 upper end of water blocking device is fixedly connected with the inner wall of Wet chimney 10;
Control device includes sensor, on-site supervision instrument, PLC control device;Flue gas is installed in the exit of cyclone 3 Temperature sensor, pressure sensor and on-site supervision instrument;Above the air nozzle at 1m installation flue-gas temperature sensor and On-site supervision instrument;In the outlet of water blocking device installation temperature, pressure and humidity sensor and on-site supervision instrument;On-site supervision Instrument includes thermometer, pressure gauge, humidometer;Sensor is controlled by PLC controller, and PLC control device passes through above-mentioned monitor The air capacity of the data control air blower conveying of table acquisition.
In above-mentioned apparatus, water receiving tank 11 is cirque structure, is arranged in 3 bottom outside of cyclone;The internal diameter of annulus and rotation Flow the bottom edge connection of the outer rim of device, the barrel of the outer rim connection Wet chimney of annulus.The condensate generated after flue gas condensing is in centrifugal force Under the action of cast onto the barrel of Wet chimney after, under gravity, flow in annulus, then arranged through condensate reflux line Enter circulatory pool.
In above-mentioned apparatus, operating platform 4 is equipped on the outside of the cyclone 3, operating platform 4 is fixed on platform support 6.Behaviour Make platform 4 to repair for operator's tours of inspection and to equipment.
The air blower 9 is controlled by blower variable frequency device, adjusts air inflow.According to the ginseng of humidity and determination of pressure sensor Number adjustment air blowers operation, cools down wet flue gas and centrifugal force, by wet flue gas Dehumidification controlling in optimum state.
In above-mentioned apparatus, cyclone is mounted on Wet chimney environment monitoring mouth top, is located in the middle part of Wet chimney.Take off white device peace Mounted in 5 top of Wet chimney environment monitoring mouth, do not influence to Environmental-protecting dust-removing, denitration, desulfurization normal monitoring.Because taking off white is with sky Gas cools down the wet flue gas after desulfurization, if be mounted in desulfurizing tower or the environment monitoring mouth of Wet chimney below can be to environmental protection Monitoring has an impact.
The air nozzle is mounted at the 0.5m barrel of cyclone deflector exhanst gas outlet, and air nozzle is set obliquely It sets, the elevation angle is 25 °.
In above-mentioned apparatus, amount containing wet flue gas, flow velocity, temperature and pressure before white device are taken off according to entering, determines air blower Revolving speed and pressure and cooling supply air quantity, and control device is set, including on-site supervision and remote PLC control device.Control device packet It includes: in the exit installation flue-gas temperature and pressure sensor for taking off white device cyclone, and, field controlling instrument includes: temperature Spend table, pressure gauge, humidometer.Flue-gas temperature sensor and thermometer, pressure gauge, humidity are installed at 1m above the air nozzle Table.In the outlet of water blocking device installation temperature, pressure and humidity sensor temperature table, pressure gauge, humidometer.PLC control device is logical The air capacity for crossing the data control air blower conveying of above-mentioned monitoring device acquisition is white to achieve the purpose that take off, mainly by above-mentioned The temperature of temperature remote transmission instrument acquisition, the air capacity that control air blower enters swirl-flow devices, which reaches, makes flue gas condensing to summer≤48 DEG C, winter≤45 DEG C.
The installation method provided by the utility model for taking off white device:
The Wet chimney of user is truncated above the environmental protection tests mouth at about 5m during installation and in incision position welded flange, Then the cyclone made according to the outer diameter of Wet chimney is mounted on above the Wet chimney of truncation, and is fixed cyclone with screw On Wet chimney, the top Wet chimney of truncation is also being burn-on flange in truncated position, the top of cyclone is installed in crane Portion is screwed.Water blocking device is small big loudspeaker barrel structure under one, and water blocking device lower part is towards cyclone.Water receiving tank is One plate annulus is installed again in the outside of cyclone, the outside of annulus is connect with the round tube wall for taking off white device, in plate circle A circular hole is opened on ring, and condensate reflux line is mounted below circular hole.Apparatus control system is to generate workshop processing It completes, the working principle of PLC control system: central processing unit is sent by the parameter of signal acquisition (pressure, temperature, humidity) (CPU), after being diagnosed by central processing unit, make instruction control such as: the parameter of various needs shown, the valve switch of pipeline, The switch of electrical equipment, the automatic running of equipment, the intelligentized apparatus control system such as breakdown judge of equipment.
Various appliance controling elements meet controlled device systems use.
Detailed Spiral-flow condensing equipment below is done to the present invention below:
1, swirl-flow devices include;Cylindrical cylinder, flue gas cyclone, air pipeline and nozzle and monitoring wet flue gas are wet The field instrument and remote transmission instrument of degree, pressure and temperature.Its main function be by after wet desulphurization containing wet flue gas by 25 ° to Heart inclined plate is uniformly discharged with the swirl velocity of 6m/s.Upward 25 ° of the air nozzle of installation at .0.5m, spray above the cyclone Mouth is mixed with the flow velocity injection air of 15~20m/s with the wet flue gas that inclined plate is discharged, and plays the role of reducing wet flue gas temperature.Spray The air capacity penetrated is obtained reasonably by the monitoring device teletransmission data installed in device by PLC automatic control system control air blower Air capacity.Air sprays the effect for not only acting as the wet flue gas temperature that lowers the requirement, moreover it is possible to play speed-raising to the flue gas of inclined plate discharge Effect, make inclined plate be discharged wet flue gas flow velocity increase to 9~12m/s, due to wet flue gas flow velocity improve, make inclined plate exit produce The negative pressure of raw 50~70Pa, this negative pressure are beneficial to the smoke evacuation of desulphurization system.
2, outdoor air feed system
Outdoor air feed system includes: air blower and air pipeline.The selection of air blower is according to desulfurization wet flue gas Total release and the temperature of wet flue gas determine that the air mass flow that air blower provides is according to the monitoring device in eddy flow cooling device Teletransmission data are obtained by control blower variable frequency motor.Airflow pipe can select carbon steel according to the physical condition at scene Pipeline or GRP pipe.
3, liquid and particulate collection device
Liquid and particulate collection device include: cone form drag hydrophone, water receiving tank, condensate reflux line.Through what is condensed Wet flue gas under the influence of centrifugal force, condensate is thrown on the round tube wall of Spiral-flow condensing equipment, is trickled under gravity To water receiving tank, Sprayer Circulation pond then is flowed back to along pipeline.The flue gas that the condensate on barrel is rotated in order to prevent carries out chimney, One conical water blocking device is installed in the outlet of eddy flow cooling device.Water blocking device can effectively prevent flue gas with water.
4, operating platform and spiral stairs
The Operation and maintenance of eddy flow cooling device are installed the operating platform in order to facilitate operations staff.Operating platform is independent Mounting platform braced frame does not have any connection with desulfurizing tower, therefore does not increase the load of desulfurizing tower, to desulfurizing tower without any shadow It rings.Since common desulfurizing tower is all cylinder, the stair activity of eddy flow cooling device operating platform is to surround desulfurizing tower The circular stair of construction
Utility model device is in application, the outdoor air amount of blending is determined according to the wet flue gas temperature after blending, by temperature The temperature value adjust automatically air blower that show of degree sensor, controls into air capacity, by wet flue gas temperature control summer (April~ October) flue-gas temperature≤48 °, flue gas moisture percentage≤9.5% of Tuo Baihou, the flue-gas temperature in winter (November~March next year)≤ 45 °, flue gas moisture percentage≤8.5% of Tuo Baihou.
Mean temperature is according to 25 DEG C outside summer room, and 55 DEG C of wet flue gas temperature calculating, exhaust gas volumn are set as 300,000 cubes after desulfurization M/h, when flue gas is by 55 DEG C near 48 DEG C, need≤48000m3The outdoor air of/h condenses wet flue gas.
Mean temperature is according to 10 DEG C outside winter room, and wet flue gas temperature 50 C calculates after desulfurization, and exhaust gas volumn is set as 300,000 cubes M/h, when flue gas is by 50 DEG C near 45 DEG C, need≤33000m3The outdoor air of/h condenses wet flue gas.

Claims (7)

1. a kind of wet plume condensation takes off white device, it is characterised in that: including water blocking device, air pipeline, condensate reflux line, eddy flow Device, air blower and control device;Cyclone is installed, cyclone is located in the middle part of Wet chimney, is screwed above desulfurizing tower;Rotation It flows and is equipped with air pipeline above device, air pipeline bottom is connect with air blower, and air pipeline is led directly in Wet chimney, air hose The outlet end in road is equipped with nozzle;Cyclone bottom outside is equipped with water receiving tank, and water receiving tank is circular ring shape, and water receiving tank lower part connects condensate Reflux line, condensate reflux line lead to outside desulfurizing tower;Cyclone downside opening is equipped with environment monitoring mouth;Above cyclone Equipped with water blocking device, water blocking device small big loudspeaker barrel structure under being, water blocking device upper end is fixedly connected with the inner wall of Wet chimney;
Control device includes sensor, on-site supervision instrument, PLC control device;Flue-gas temperature is installed in the exit of cyclone Sensor, pressure sensor and on-site supervision instrument;Flue-gas temperature sensor and scene are installed at 1m above the air nozzle Monitoring device;In the outlet of water blocking device installation temperature, pressure and humidity sensor and on-site supervision instrument;On-site supervision instrument Including thermometer, pressure gauge, humidometer;Sensor is controlled by PLC controller, and PLC control device is adopted by above-mentioned monitoring device The air capacity of the data control air blower conveying of collection.
2. wet plume condensation according to claim 1 takes off white device, it is characterised in that: water receiving tank is cirque structure, if It sets in cyclone bottom outside;The bottom edge of the outer rim of the internal diameter and cyclone of annulus connects, the outer rim connection Wet chimney of annulus Barrel.
3. wet plume condensation according to claim 1 takes off white device, it is characterised in that: the air blower is by blower variable frequency Device control, adjusts air inflow.
4. wet plume condensation according to claim 1 takes off white device, it is characterised in that: cyclone is mounted on Wet chimney environmental protection Mouth top is monitored, is located in the middle part of Wet chimney.
5. wet plume condensation according to claim 1 takes off white device, it is characterised in that: the air nozzle is mounted on eddy flow At the 0.5m barrel of device deflector exhanst gas outlet, air nozzle is arranged obliquely, and the elevation angle is 25 °.
6. wet plume condensation according to claim 1 takes off white device, it is characterised in that: be equipped with operation on the outside of the cyclone Platform, operating platform are fixed on platform support.
7. wet plume condensation according to claim 6 takes off white device, it is characterised in that: be equipped with rotation below operating platform Turn stair.
CN201821488419.6U 2018-09-12 2018-09-12 A kind of wet plume condensation takes off white device Active CN208824091U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821488419.6U CN208824091U (en) 2018-09-12 2018-09-12 A kind of wet plume condensation takes off white device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821488419.6U CN208824091U (en) 2018-09-12 2018-09-12 A kind of wet plume condensation takes off white device

Publications (1)

Publication Number Publication Date
CN208824091U true CN208824091U (en) 2019-05-07

Family

ID=66312986

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821488419.6U Active CN208824091U (en) 2018-09-12 2018-09-12 A kind of wet plume condensation takes off white device

Country Status (1)

Country Link
CN (1) CN208824091U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111024889A (en) * 2019-11-05 2020-04-17 上海环钻环保科技股份有限公司 Device and method for rapidly monitoring, evaluating and selecting wet smoke plume

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111024889A (en) * 2019-11-05 2020-04-17 上海环钻环保科技股份有限公司 Device and method for rapidly monitoring, evaluating and selecting wet smoke plume

Similar Documents

Publication Publication Date Title
CN207413082U (en) Wet desulfurization flue gas eliminates plume system
CN108465341B (en) Hyperbolic natural ventilation, condensation, water extraction and white smoke elimination integrated device
CN107648978B (en) Wet desulfurization flue gas smoke plume eliminating system and method
WO2017173802A1 (en) System and method for recycling waste heat from drying machine
CN201807285U (en) Wet-type combination smoke dust removal desulphurization device
CN108640188A (en) Bypass flue air-stream spraying dries desulfurizing waste water processing device and method
CN208574445U (en) A kind of high effective flue gas dehydration device
CN103446872B (en) A kind of desulfurizing and purifying method and apparatus of low-temperature sintering flue gas
CN208990512U (en) A kind of flue gas of wet desulphurization disappears white system
CN106512456A (en) Four-stage evaporation device and method for desulfurized waste water
CN208824091U (en) A kind of wet plume condensation takes off white device
CN208553614U (en) A kind of plume governing system mitigating flue gas resistance
CN207270943U (en) A kind of cooperative control system of coal steam-electric plant smoke flue dust
CN101837239B (en) System for dehydration of acid mist dust of plaster and dust removal and desulfurization of fluidized bed furnace by baking by using residual heat
CN206081680U (en) Four sections method evaporation plant of desulfurization waste water
CN209378486U (en) A kind of device for eliminating condensable particulate matter
CN201949811U (en) Flue gas spraying, cooling and washing system
CN209726240U (en) Desulfurization and the flue gas waste heat recovery equipment of wet plume can be eliminated
CN201322294Y (en) Exhaust energy retracting device
CN201157744Y (en) Swirl type humidifying pre-dedusting apparatus
CN209221854U (en) A kind of new side position spray smoke absorption tower
CN108579316A (en) A kind of flue gas for wet desulfuration tower disappears white plumage governing system
CN107469475A (en) A kind of air swirl wet desulphurization plume purifier and application
CN113426282A (en) Flue gas distributor device with automatic ash removal function
CN210741118U (en) Flue gas cooling system for calcining furnace

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant