CN208792736U - A kind of pre-buried scaffold wall connecting piece that can be recycled - Google Patents
A kind of pre-buried scaffold wall connecting piece that can be recycled Download PDFInfo
- Publication number
- CN208792736U CN208792736U CN201821499152.0U CN201821499152U CN208792736U CN 208792736 U CN208792736 U CN 208792736U CN 201821499152 U CN201821499152 U CN 201821499152U CN 208792736 U CN208792736 U CN 208792736U
- Authority
- CN
- China
- Prior art keywords
- sleeve
- prismatics
- chamber
- connecting piece
- nut
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Joining Of Building Structures In Genera (AREA)
Abstract
The utility model discloses a kind of pre-buried scaffold wall connecting piece that can be recycled, including sleeve, six prismatics chamber, nut, male threaded stub, sleeve rear cover, internal screw thread end cap, round fixinig plate and screw rod, described sleeve one end is coaxially arranged with six prismatics chamber, the compatible nut of the intracavitary embedment size shape of six prismatics, the six prismatics chamber is provided with male threaded stub at port, the sleeve rear cover is connect using internal screw thread end cap with the male threaded stub on six prismatics chamber, round fixinig plate is coaxially arranged at the outer of the sleeve other end, the screw rod sequentially passes through round fixinig plate, it is connect after sleeve with nut.Through the above way, the utility model provides a kind of pre-buried scaffold wall connecting piece that can be recycled, have many advantages, such as low manufacture cost, easy to operate, safe and reliable, recyclable be used in turn, the human and material resources investment that construction can sufficiently be mitigated, saves significantly on construction cost, accelerates speed of application.
Description
Technical field
The utility model relates to scaffold wall connecting piece fields, more particularly to a kind of pre-buried scaffold connecting that can be recycled
Part.
Background technique
It now, must be using exterior wall scaffold come auxiliary construction, either in the most of building engineering construction in China
Traditional fastener type external scaffolding or novel spigot-and-socket external scaffolding all be unable to do without the setting of wall-connecting piece.Previous exterior wall
Two kinds nothing more than of the company's of mostly using wall mode in scaffold construction, one is " pre-buried linkings ";Another kind is " penetrating anchoring type ".
The first connects wall mode often excessive dependency structure construction, and built-in fitting (mostly steel pipe) position is limited in operating process, operative employee
Sequence is cumbersome, is easily destroyed in the process, and additional consumption is artificial, many drawbacks such as input cost height.And second of company's wall mode is not only
There is the every construction disadvantage of the first, there is also the risks for destroying structural elements, bring hidden danger and inconvenience for subsequent construction.Together
When, once it is limited by operating space and safety requirements using above two even wall mode, inevitably causes cutting for some finished-product materials
It cuts, also results in a part of waste of material.For the application status of above two traditional wall-connecting piece, we have proposed one kind can
Enough meet construction requirement, and convenient for operation, reduces input cost, but also recyclable external scaffolding connects wall mode.
Utility model content
The utility model is mainly solving the technical problems that provide a kind of pre-buried scaffold wall connecting piece that can be recycled, tool
Have the advantages that low manufacture cost, it is easy to operate, safe and reliable, recyclable be used in turn, can sufficiently mitigate construction manpower,
Material resources investment saves significantly on construction cost, accelerates speed of application.
In order to solve the above technical problems, the technical solution that the utility model uses is: providing a kind of pre-buried recyclable
The scaffold wall connecting piece used, including sleeve, six prismatics chamber, nut, male threaded stub, sleeve rear cover, internal screw thread end cap, circle
Shape fixinig plate and screw rod, described sleeve one end are coaxially arranged with six prismatics chamber, the intracavitary embedment size shape of six prismatics
The compatible nut of shape, male threaded stub is provided at six prismatics chamber port, and the sleeve rear cover utilizes female end
Cap is connect with the male threaded stub on six prismatics chamber, is coaxially arranged with round fixinig plate at the outer of the sleeve other end,
The screw rod is connect after sequentially passing through round fixinig plate, sleeve with nut.
In one preferred embodiment of the utility model, the interconnecting piece of the circle fixinig plate and the sleeve, which is provided with, to be added
Strengthening tendons.
In one preferred embodiment of the utility model, the fixed nail hole of several templates is offered on the circle fixinig plate.
In one preferred embodiment of the utility model, the size shape of the screw rod is adapted with the sleeve, described
Nut is adapted with the screw size.
The beneficial effects of the utility model are: the pre-buried scaffold connecting that can be recycled of one kind provided by the utility model
Part, have many advantages, such as low manufacture cost, it is easy to operate, safe and reliable, recyclable be used in turn, can sufficiently mitigate construction
Human and material resources investment saves significantly on construction cost, accelerates speed of application.
Detailed description of the invention
It, below will be to required in embodiment description in order to illustrate more clearly of the technical scheme in the embodiment of the utility model
Attached drawing to be used is briefly described, it should be apparent that, the accompanying drawings in the following description is only some realities of the utility model
Example is applied, it for those of ordinary skill in the art, without creative efforts, can also be according to these attached drawings
Obtain other attached drawings, in which:
Fig. 1 is a kind of structure of a preferred embodiment of the pre-buried scaffold wall connecting piece that can be recycled of the utility model
Figure;
Fig. 2 is a kind of structure chart of a preferred embodiment of the pre-buried scaffold wall connecting piece that can be recycled of the utility model
Fig. 3 is a kind of structure of a preferred embodiment of the pre-buried scaffold wall connecting piece that can be recycled of the utility model
Figure.
Specific embodiment
Below by the technical scheme in the utility model embodiment is clearly and completely described, it is clear that described
Embodiment is only a part of the embodiment of the utility model, instead of all the embodiments.Based on the implementation in the utility model
Example, all other embodiment obtained by those of ordinary skill in the art without making creative efforts belong to
The range of the utility model protection.
As shown in Figure 1-3, the utility model embodiment includes:
A kind of pre-buried scaffold wall connecting piece that can be recycled, including sleeve 1, six prismatics chamber 2, nut 3, male end
First 4, sleeve rear cover 5, internal screw thread end cap 6, round fixinig plate 7 and screw rod 8, described 1 one end of sleeve are coaxially arranged with hexagonal prisms
Type chamber 2, the six prismatics chamber 2 is interior to be embedded to the compatible nut 3 of size shape, is provided at 2 port of six prismatics chamber
Male threaded stub 4, the sleeve rear cover 5 is connect using internal screw thread end cap 6 with the male threaded stub 4 on six prismatics chamber 2, described
Round fixinig plate 7 is coaxially arranged at the outer of 1 other end of sleeve, after the screw rod 8 sequentially passes through round fixinig plate 7, sleeve 1
It is connect with nut 3.
Wherein, the interconnecting piece of the round fixinig plate 7 and the sleeve 1 is provided with reinforcing rib 9.
Further, the fixed nail hole 10 of several templates is offered on the round fixinig plate 7.
Further, the size shape of the screw rod 8 is adapted with the sleeve 1, the nut 3 and 8 ruler of screw rod
It is very little to be adapted.By the above-mentioned means, the nut 3 is pre-buried into structural elements together with sleeve 1, while being connected with screw rod 8, spiral shell
The also dismountable recycling of bar 8.
One preferred embodiment of the utility model is as follows:
1, according to the customized mold of detail drawing sizing specification book, batch production processing.
2, nut 3 is placed in sleeve 1, is blocked with sleeve rear cover 5, is completed the assembling of the preburied component of the utility model.
3, in exterior wall concrete component (beam, column, wallboard) template installation process, mould is utilized in the position that wall-connecting piece need to be arranged
The preburied component of the fixed nail hole location and installation the utility model of plate, round fixinig plate 7 is followed closely lean in as shown in the figure with 4 tingles
Elevationally outward (8 hole of screw rod utilizes adhesive tape or removable filler to block in advance) in template.
4, after the completion of concrete component pours, vertical formwork is removed, removes adhesive tape and filler.
5, iron plate with holes is soldered to short steel pipes in advance, is connect patch with preburied component with screw rod 8.(torque wrench school
Core can increase expansion gasket)
6, the short steel pipes other end is connected with upright bar fastener on the outside of outrigger, completes outrigger and connects wall.
In conclusion the utility model provides a kind of pre-buried scaffold wall connecting piece that can be recycled, has and be fabricated to
This low, easy to operate, safe and reliable, recyclable the advantages that being used in turn, the human and material resources that can sufficiently mitigate construction are thrown
Enter, saves significantly on construction cost, accelerates speed of application.The utility model type construction technology compensates for many disadvantages of traditional handicraft
End, reduces the human and material resources of construction, the investment of financial resources, has both saved construction cost, in turn ensure that security civilization is applied
Work.Meanwhile reduce destruction to building structural element, greatly promote speed of application, have the advantages that conveniently, it is reliable, practical.
The above description is only the embodiments of the present invention, and therefore it does not limit the scope of the patent of the utility model, all
Using equivalent structure or equivalent flow shift made by the utility model description, it is applied directly or indirectly in other phases
The technical field of pass, is also included in the patent protection scope of the utility model.
Claims (4)
1. a kind of pre-buried scaffold wall connecting piece that can be recycled, which is characterized in that including sleeve, six prismatics chamber, nut, outer
Threaded end, sleeve rear cover, internal screw thread end cap, round fixinig plate and screw rod, described sleeve one end are coaxially arranged with hexagonal prisms
Type chamber, the compatible nut of the intracavitary embedment size shape of six prismatics, the six prismatics chamber are provided with outer spiral shell at port
Line end, the sleeve rear cover are connect using internal screw thread end cap with the male threaded stub on six prismatics chamber, and the sleeve is another
Round fixinig plate is coaxially arranged at the outer at end, the screw rod is connect after sequentially passing through round fixinig plate, sleeve with nut.
2. the pre-buried scaffold wall connecting piece that can be recycled according to claim 1, which is characterized in that described round fixed
The interconnecting piece of piece and the sleeve is provided with reinforcing rib.
3. the pre-buried scaffold wall connecting piece that can be recycled according to claim 1, which is characterized in that described round fixed
On piece offers the fixed nail hole of several templates.
4. the pre-buried scaffold wall connecting piece that can be recycled according to claim 1, which is characterized in that the screw rod it is big
Small shape is adapted with the sleeve, and the nut is adapted with the screw size.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821499152.0U CN208792736U (en) | 2018-09-13 | 2018-09-13 | A kind of pre-buried scaffold wall connecting piece that can be recycled |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821499152.0U CN208792736U (en) | 2018-09-13 | 2018-09-13 | A kind of pre-buried scaffold wall connecting piece that can be recycled |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208792736U true CN208792736U (en) | 2019-04-26 |
Family
ID=66209484
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821499152.0U Expired - Fee Related CN208792736U (en) | 2018-09-13 | 2018-09-13 | A kind of pre-buried scaffold wall connecting piece that can be recycled |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208792736U (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112696003A (en) * | 2020-12-29 | 2021-04-23 | 中建七局(上海)有限公司 | Novel shear force wall is wall spare even |
CN112696002A (en) * | 2020-12-29 | 2021-04-23 | 曹晓良 | Scaffold wall connecting piece manufacturing system |
CN113374091A (en) * | 2021-07-08 | 2021-09-10 | 发达控股集团有限公司 | Reusable wall connecting bolt |
CN113605677A (en) * | 2021-09-02 | 2021-11-05 | 重庆万力新材料有限公司 | Wall connecting piece for building construction and use method thereof |
-
2018
- 2018-09-13 CN CN201821499152.0U patent/CN208792736U/en not_active Expired - Fee Related
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112696003A (en) * | 2020-12-29 | 2021-04-23 | 中建七局(上海)有限公司 | Novel shear force wall is wall spare even |
CN112696002A (en) * | 2020-12-29 | 2021-04-23 | 曹晓良 | Scaffold wall connecting piece manufacturing system |
CN113374091A (en) * | 2021-07-08 | 2021-09-10 | 发达控股集团有限公司 | Reusable wall connecting bolt |
CN113605677A (en) * | 2021-09-02 | 2021-11-05 | 重庆万力新材料有限公司 | Wall connecting piece for building construction and use method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN208792736U (en) | A kind of pre-buried scaffold wall connecting piece that can be recycled | |
CN204418380U (en) | A kind of prefabricated component connector | |
CN206903215U (en) | Girder with rolled steel section en cased in concrete is without scaffold formwork | |
CN209228042U (en) | A kind of corner constructional column erecting device | |
CN201460198U (en) | Concrete poured template | |
CN105888244A (en) | Energy-saving sectional type water stop split screw rod device | |
CN113152893A (en) | Template for building construction and using method | |
CN205077870U (en) | It is split type to drawing screw rod and template drawknot structure | |
CN101832025A (en) | Sealing up screw | |
CN207633740U (en) | The novel anchor of builder's jack | |
CN207999071U (en) | A kind of wall column root concrete capping tools | |
CN106381999A (en) | Fair-faced concrete wall intaglio character die plate construction method | |
CN105201278A (en) | Assembly type fence wall made of construction waste | |
CN204609303U (en) | A kind of template split bolt device | |
CN204941567U (en) | A kind of structure accelerating construction of tunnel vault pouring concrete speed | |
CN208996433U (en) | A kind of stay bolt combined simple scaffold wall connecting piece | |
CN106760509A (en) | A kind of T-shaped constructional column horse tooth trough does not damage the mold method of wall | |
CN206513030U (en) | Split bolt formwork reinforcement is pegged body | |
CN207436500U (en) | A kind of three sections of split bolt continued accesses combination unit | |
CN203145454U (en) | Wall internal corner formwork | |
CN207392754U (en) | A kind of screw rod pulling-on piece adaptor connector | |
CN207063524U (en) | The detachable sealing beam framework fixer of architectural engineering | |
CN201671338U (en) | Water-stop screw rod | |
CN211850809U (en) | Formwork system of thin-wall steel formwork | |
CN104141319A (en) | Mounting fixer for concrete retaining wall pouring form |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190426 |