- CN208779969U CN208779969U CN201821279159.1U CN201821279159U CN208779969U CN 208779969 U CN208779969 U CN 208779969U CN 201821279159 U CN201821279159 U CN 201821279159U CN 208779969 U CN208779969 U CN 208779969U
- Authority
- CN
- China
- Prior art keywords
- cooling chamber
- pipe
- fixedly installed
- calcium carbide
- legal system
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Abstract
The utility model relates to cooling tower technical fields, and disclose a kind of calcium carbide legal system acetylene technique gas colling tower, including mounting plate, liquid storing barrel is fixedly installed at the top of the mounting plate, the inner cavity rear wall of the liquid storing barrel is fixedly installed with the evaporator that quantity is two, and the bottom wall of inner cavity of the liquid storing barrel and the front for being located at evaporator are fixedly installed with the support rod that quantity is two.The calcium carbide legal system acetylene technique gas colling tower, pass through the heat sink being arranged on the cold water pipe and cooling chamber on Y-pipe, user is when using equipment, user starts booster water pump, booster water pump extracts the liquid in liquid storing barrel and is sprayed by output water pipe, Y-pipe and cold water pipe from spray head, the outside for the liquid runs down cooling chamber that spray head sprays is flowed down by heat sink, the heat of cooling chamber is pulled away, eliminating influences equipment because of the leaving heat of cooling chamber to the trouble of the cooling effect of gas, the use for the person of being convenient to use.
Description
Technical field
The utility model relates to cooling tower technical field, specially a kind of calcium carbide legal system acetylene technique gas colling tower.
Background technique
Cooling tower is to use water as circulating coolant, heat dissipation is absorbed from a system into atmosphere, to reduce water temperature
Device, cold is that cold and hot exchange generation steam is carried out after contact using the flowing of water and air, and steam, which volatilizees, to be taken away heat and reach
The principles such as evaporative heat loss, convective heat transfer and radiant heat transfer reduce temperature to disperse the waste heat generated in industrial or refrigeration air-conditioner
Evaporating radiator, to guarantee the normal operation of system, device is generally tubbiness, and therefore named is cooling tower.
Traditional calcium carbide legal system acetylene technique with gas colling tower be typically all only internal unit filling part cold water with
Reach gas cooling purpose, and the temperature that cooling tower tower body absorbs high-temperature gas causes device temperature to increase not opposite drop
Warm device, apparatus body temperature is high, first can be by tower when entering which results in cold water inside traditional gas cooling tower
Body is once heated up, and the effect that equipment cools down to gas is made a discount, and the desired effect of user is not achieved, and affects use
The use of person, so propose a kind of calcium carbide legal system acetylene technique gas colling tower.
Utility model content
(1) the technical issues of solving
In view of the deficiencies of the prior art, the utility model provides a kind of calcium carbide legal system acetylene technique gas colling tower,
Have the advantages that tower body rapid heat dissipation, gas cooling effect is good, solves traditional calcium carbide legal system acetylene technique gas colling tower
There was only internal unit filling part cold water typically to reach gas cooling purpose, and cooling tower tower body absorbs high-temperature gas
Temperature causes device temperature to increase but not opposite cooling device, and apparatus body temperature is high, and which results in tradition
It can once be heated up by tower body first when cold water enters inside gas colling tower, equipment has beaten folding to the effect that gas cools down
Button, the problem of the desired effect of user is not achieved, affects the use of user.
(2) technical solution
To realize that above-mentioned tower body rapid heat dissipation, the good purpose of gas cooling effect, the utility model provide the following technical solutions:
A kind of calcium carbide legal system acetylene technique gas colling tower, including mounting plate are fixedly installed with liquid storing barrel at the top of the mounting plate,
It is two evaporators that the inner cavity rear wall of the liquid storing barrel, which is fixedly installed with quantity, the bottom wall of inner cavity of the liquid storing barrel and is located at
The front of evaporator is fixedly installed with the support rod that quantity is two, and the top of two support rods, which is fixed with cooling chamber, to be connected
It connects, one end is fixedly installed on the left of the cooling chamber and runs through and extend to the air inlet pipe inside cooling chamber, the cooling chamber
Left side and it is located above air inlet pipe and is fixedly installed with one end and runs through and extend to the escape pipe inside cooling chamber, the cooling chamber
Right side be fixedly installed with one end and run through and extend to the outlet pipe inside cooling chamber, control is communicated on the right side of the outlet pipe
Valve, the top of the mounting plate and is located on the right side of liquid storing barrel and is fixedly installed with installation riser, and the left side of the installation riser is solid
Dingan County is equipped with booster water pump, and the water inlet end of the booster water pump is communicated with one end and extends to suction hose above liquid storing barrel inner wall,
The water outlet of the booster water pump is communicated with one end and extends to output water pipe above cooling chamber, and the output water pipe is far from pressurization
One end of water pump is communicated with Y-pipe, and one end is communicated on the left of the Y-pipe and extends to hose above cooling chamber, described
The bottom of hose is communicated with one end and runs through and extend to the sparge pipe inside cooling chamber, is communicated with one end at the top of the Y-pipe
The cold water pipe above hose is extended to, the cold water pipe is communicated with spray head, the right side of the cooling chamber far from one end of Y-pipe
And be located above outlet pipe and be fixedly installed with the heat sink that quantity is no less than five, quantity is offered at the top of the heat sink
For nine heat release holes for extending through heat sink bottom.
Preferably, the heat sink is isodistantly spaced the right side for being distributed in cooling chamber, and the heat sink is made of fine copper.
Preferably, the output water pipe and suction hose are that steel is made, and the outside of the output water pipe and suction hose is plated
There are zinc layers.
Preferably, the right side of the cooling chamber and strut is fixedly installed between outlet pipe and heat sink, the suction
The outside of water pipe is socketed with the positioning sleeve that one end is fixedly connected with strut.
Preferably, the junction of the air inlet pipe and cooling chamber is fixedly installed with the junction of outlet pipe and cooling chamber
Sealing ring, the sealing ring are made of rubber.
Preferably, it is described installation riser left side and be located at booster water pump outside be fixedly installed with protective cover, the increasing
The outside of water pump is socketed with stop collar, and the top and bottom of the stop collar are fixedly installed with one end and the fixed company of protective cover
The gag lever post connect.
Beneficial effect
Compared with prior art, the utility model provides a kind of calcium carbide legal system acetylene technique gas colling tower, has
Below the utility model has the advantages that
1, calcium carbide legal system acetylene technique gas colling tower, by being arranged on the cold water pipe and cooling chamber on Y-pipe
Heat sink, for user when using equipment, user starts booster water pump, and the liquid that booster water pump extracts in liquid storing barrel passes through
It exports water pipe, Y-pipe and cold water pipe to spray from spray head, heat sink stream is passed through in the outside for the liquid runs down cooling chamber that spray head sprays
Under, the heat of cooling chamber is pulled away, and eliminates the cooling effect that equipment is influenced because of the leaving heat of cooling chamber to gas
Trouble, the use for the person of being convenient to use.
2, the calcium carbide legal system acetylene technique gas colling tower passes through the booster water pump and liquid storage being arranged on installation riser
Evaporator on bucket, traditional cooling tower use running water cooling more, i.e., by the cold continuous access device absorbed inside heat of tap water
Amount is so great waste to water resource and uneconomical, and user is used when being cooled down using cold water to equipment internal gas
The indoor heating liquid of cooling can be discharged in liquid storing barrel by person by control valve, and user opens evaporator and drops liquid
Liquid after cooling is drawn into cooling chamber by temperature by booster water pump, is eliminated user one day and is not stopped using tap water
It spends, has saved water resource, further facilitated the use of user.
Detailed description of the invention
Fig. 1 is the utility model positive structure schematic;
Fig. 2 is the utility model heat sink top view.
In figure: 1 mounting plate, 2 liquid storing barrels, 3 evaporators, 4 support rods, 5 cooling chambers, 6 air inlet pipe, 7 escape pipes, 8 water outlets
Pipe, 9 control valves, 10 installation risers, 11 booster water pumps, 12 suction hoses, 13 output water pipes, 14 Y-pipes, 15 hoses, 16 water sprays
Pipe, 17 cold water pipes, 18 spray heads, 19 heat sinks, 20 heat release holes.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model
Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole
Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work
Every other embodiment obtained, fall within the protection scope of the utility model.
A kind of calcium carbide legal system acetylene technique gas colling tower referring to FIG. 1-2, including mounting plate 1, the top of mounting plate 1
Portion is fixedly installed with liquid storing barrel 2, and the inner cavity rear wall of liquid storing barrel 2 is fixedly installed with the evaporator 3 that quantity is two, liquid storing barrel 2
Bottom wall of inner cavity and be located at the front of evaporator 3 to be fixedly installed with quantity be two support rods 4, the top of two support rods 4
It is fixedly connected with cooling chamber 5, the left side of cooling chamber 5 is fixedly installed with one end and runs through and extend to the air inlet inside cooling chamber 5
Pipe 6, the left side of cooling chamber 5 and the top for being located at air inlet pipe 6 are fixedly installed with one end and run through and extend to going out inside cooling chamber 5
Tracheae 7, the right side of cooling chamber 5 are fixedly installed with one end and run through and extend to the outlet pipe 8 inside cooling chamber 5,6 He of air inlet pipe
The junction of the junction of cooling chamber 5 and outlet pipe 8 and cooling chamber 5 is fixedly installed with sealing ring, and sealing ring is made of rubber,
Prevent equipment leak, the right side of outlet pipe 8 is communicated with control valve 9, the top of the mounting plate 1 and right side for being located at liquid storing barrel 2 is fixed
Installation riser 10 is installed, the left side of installation riser 10 is fixedly installed with booster water pump 11, installs the left side of riser 10 and is located at
The outside of booster water pump 11 is fixedly installed with protective cover, and the outside of booster water pump 11 is socketed with stop collar, the top of stop collar and
Bottom is fixedly installed with the gag lever post that one end is fixedly connected with protective cover, and fixed booster water pump 11 prevents booster water pump 11 from shaking
Dynamic, the model JWS-BZ of booster water pump 11, the water inlet end of booster water pump 11 is communicated with one end and extends to above 2 inner wall of liquid storing barrel
Suction hose 12, the water outlet of booster water pump 11 is communicated with the output water pipe 13 that one end extends to the top of cooling chamber 5, exports water pipe
13 and suction hose 12 be that steel is made, the outside for exporting water pipe 13 and suction hose 12 is coated with zinc layers, and equipment is prevented to be rusted, defeated
Outlet pipe 13 is communicated with Y-pipe 14 far from one end of booster water pump 11, the left side of Y-pipe 14 be communicated with one end extend to it is cold
But the hose 15 of the top of room 5, the bottom of hose 15 are communicated with one end and run through and extend to the sparge pipe 16 inside cooling chamber 5, and three
The top of breeches pipe 14 is communicated with the cold water pipe 17 that one end extends to 15 top of hose, the one end of cold water pipe 17 far from Y-pipe 14
It is communicated with spray head 18, the right side of the cooling chamber 5 and top for being located at outlet pipe 8 is fixedly installed with the heat sink that quantity is no less than five
19, heat sink 19 is isodistantly spaced the right side for being distributed in cooling chamber 5, and heat sink 19 is made of fine copper, and the heat dissipation performance of copper is preferable, side
Just it radiates to cooling chamber 5, the right side of cooling chamber 5 and is fixedly installed with strut, suction hose between outlet pipe 8 and heat sink 19
12 outside is socketed with the positioning sleeve that one end is fixedly connected with strut, prevents suction hose 12 to be displaced, the top of heat sink 19 opens up
Having quantity is nine heat release holes 20 for extending through 19 bottom of heat sink, the cold water pipe 17 by being arranged on Y-pipe 14 and cold
But the heat sink 19 on room 5, for user when using equipment, user starts booster water pump 11, and booster water pump 11 extracts liquid storage
Liquid in bucket 2 is sprayed by output water pipe 13, Y-pipe 14 and cold water pipe 17 from spray head 18, the liquid runs down that spray head 18 sprays
The outside of cooling chamber 5 is flowed down by heat sink 19, and the heat of cooling chamber 5 is pulled away, and is eliminated because cooling chamber 5 leaves heat
And equipment is influenced to the trouble of the cooling effect of gas, the use for the person of being convenient to use, by being arranged on installation riser 10
Evaporator 3 on booster water pump 11 and liquid storing barrel 2, traditional cooling tower uses running water cooling more, i.e., cold tap water is continuous
Access device absorbed inside heat is so great waste to water resource and uneconomical, and user is in use cold water to equipment
When internal gas cools down, the heating liquid in cooling chamber 5 can be discharged in liquid storing barrel 2 by user by control valve 9, be used
Person opens evaporator 3 and liquid cools down, and the liquid after cooling is drawn into cooling chamber 5 by booster water pump 11, eliminating makes
User's cost not stopped using tap water in one day, has saved water resource, has further facilitated the use of user.
When in use, user will need cooling other to access from air inlet pipe 6, collect gas after cooling from escape pipe 7
Body.
In conclusion the calcium carbide legal system acetylene technique gas colling tower, passes through the cold water pipe being arranged on Y-pipe 14
17 and cooling chamber 5 on heat sink 19, for user when using equipment, user starts booster water pump 11, and booster water pump 11 is taken out
The liquid in liquid storing barrel 2 is taken to spray by output water pipe 13, Y-pipe 14 and cold water pipe 17 from spray head 18, what spray head 18 sprayed
The outside of liquid runs down cooling chamber 5 is flowed down by heat sink 19, and the heat of cooling chamber 5 is pulled away, and is eliminated because of cooling chamber 5
It leaves heat and influences equipment to the trouble of the cooling effect of gas, the use for the person of being convenient to use is perpendicular in installation by setting
The evaporator 3 on booster water pump 11 and liquid storing barrel 2 on plate 10, traditional cooling tower use running water cooling more, i.e., by it is cold from
The continuous access device absorbed inside heat of water is so great waste to water resource and uneconomical, and user is using cold
When water cools down to equipment internal gas, the heating liquid in cooling chamber 5 can be discharged to liquid storing barrel by control valve 9 by user
In 2, user opens evaporator 3 and liquid cools down, and the liquid after cooling is drawn into cooling chamber 5 by booster water pump 11,
User's cost not stopped using tap water in one day is eliminated, water resource has been saved, has further facilitated the use of user, is solved
The calcium carbide legal system acetylene technique gas colling tower for having determined traditional is typically all only internal unit filling part cold water to reach
Gas cooling purpose, and the temperature that cooling tower tower body absorbs high-temperature gas causes device temperature to increase not opposite cooling dress
Set, apparatus body temperature is high, when entering which results in cold water inside traditional gas cooling tower first can by tower body into
The primary heating of row, the effect that equipment cools down to gas make a discount, the desired effect of user are not achieved, affects user's
The problem of use.
It should be noted that, in this document, relational terms such as first and second and the like are used merely to a reality
Body or operation are distinguished with another entity or operation, are deposited without necessarily requiring or implying between these entities or operation
In any actual relationship or order or sequence.Moreover, the terms "include", "comprise" or its any other variant are intended to
Non-exclusive inclusion, so that the process, method, article or equipment including a series of elements is not only wanted including those
Element, but also including other elements that are not explicitly listed, or further include for this process, method, article or equipment
Intrinsic element.In the absence of more restrictions, the element limited by sentence "including a ...", it is not excluded that
There is also other identical elements in process, method, article or equipment including the element.
While there has been shown and described that the embodiments of the present invention, for the ordinary skill in the art,
It is understood that these embodiments can be carried out with a variety of variations in the case where not departing from the principles of the present invention and spirit, repaired
Change, replacement and variant, the scope of the utility model is defined by the appended claims and the equivalents thereof.
Claims (6)
1. a kind of calcium carbide legal system acetylene technique gas colling tower, including mounting plate (1), it is characterised in that: the mounting plate (1)
Top be fixedly installed with liquid storing barrel (2), it is two evaporations that the inner cavity rear wall of the liquid storing barrel (2), which is fixedly installed with quantity,
Device (3), the bottom wall of inner cavity of the liquid storing barrel (2) and the front for being located at evaporator (3) are fixedly installed with the support that quantity is two
The top of bar (4), two support rods (4) is fixedly connected with cooling chamber (5), the fixed peace in the left side of the cooling chamber (5)
Run through and extend to the internal air inlet pipe (6) of cooling chamber (5) equipped with one end, the left side of the cooling chamber (5) and is located at air inlet pipe
(6) one end is fixedly installed with above to run through and extend to the internal escape pipe (7) of cooling chamber (5), the right side of the cooling chamber (5)
Side is fixedly installed with one end and runs through and extend to the internal outlet pipe (8) of cooling chamber (5), the right side connection of the outlet pipe (8)
Have control valve (9), the top of the mounting plate (1) and be located at liquid storing barrel (2) on the right side of be fixedly installed with installation riser (10), institute
It states and is fixedly installed with booster water pump (11) on the left of installation riser (10), the water inlet end of the booster water pump (11) is communicated with one end
The suction hose (12) above liquid storing barrel (2) inner wall is extended to, the water outlet of the booster water pump (11) is communicated with one end and extends to
Output water pipe (13) above cooling chamber (5), output water pipe (13) are communicated with trident far from the one end of booster water pump (11)
It manages (14), one end is communicated on the left of the Y-pipe (14) and extends to hose (15) above cooling chamber (5), the hose
(15) bottom is communicated with one end and runs through and extend to the internal sparge pipe (16) of cooling chamber (5), the top of the Y-pipe (14)
Portion is communicated with one end and extends to cold water pipe (17) above hose (15), the one end of the cold water pipe (17) far from Y-pipe (14)
It is communicated with spray head (18), the right side of the cooling chamber (5) and is located above outlet pipe (8) and is fixedly installed with quantity and is no less than five
A heat sink (19), quantity is offered at the top of the heat sink (19) is nine and extend through dissipating for heat sink (19) bottom
Hot hole (20).
2. a kind of calcium carbide legal system acetylene technique gas colling tower according to claim 1, it is characterised in that: the heat dissipation
Plate (19) is isodistantly spaced the right side for being distributed in cooling chamber (5), and the heat sink (19) is made of fine copper.
3. a kind of calcium carbide legal system acetylene technique gas colling tower according to claim 1, it is characterised in that: the output
Water pipe (13) and suction hose (12) are that steel is made, and the outside of output water pipe (13) and suction hose (12) is coated with zinc layers.
4. a kind of calcium carbide legal system acetylene technique gas colling tower according to claim 1, it is characterised in that: the cooling
The right side of room (5) and strut is fixedly installed between outlet pipe (8) and heat sink (19), the outside of the suction hose (12)
It is socketed with the positioning sleeve that one end is fixedly connected with strut.
5. a kind of calcium carbide legal system acetylene technique gas colling tower according to claim 1, it is characterised in that: the air inlet
The junction and outlet pipe (8) of pipe (6) and cooling chamber (5) and the junction of cooling chamber (5) are fixedly installed with sealing ring, described
Sealing ring is made of rubber.
6. a kind of calcium carbide legal system acetylene technique gas colling tower according to claim 1, it is characterised in that: the installation
The left side of riser (10) and be located at booster water pump (11) outside be fixedly installed with protective cover, the outside of the booster water pump (11)
It is socketed restraining position ring block, the top and bottom of the stop collar are fixedly installed with the gag lever post that one end is fixedly connected with protective cover.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821279159.1U CN208779969U (en) | 2018-08-09 | 2018-08-09 | A kind of calcium carbide legal system acetylene technique gas colling tower |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821279159.1U CN208779969U (en) | 2018-08-09 | 2018-08-09 | A kind of calcium carbide legal system acetylene technique gas colling tower |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208779969U true CN208779969U (en) | 2019-04-23 |
Family
ID=66156391
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821279159.1U Expired - Fee Related CN208779969U (en) | 2018-08-09 | 2018-08-09 | A kind of calcium carbide legal system acetylene technique gas colling tower |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208779969U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111336750A (en) * | 2020-04-14 | 2020-06-26 | 苏州新华美塑料有限公司 | High polymer material processing cooling circulation device |
-
2018
- 2018-08-09 CN CN201821279159.1U patent/CN208779969U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111336750A (en) * | 2020-04-14 | 2020-06-26 | 苏州新华美塑料有限公司 | High polymer material processing cooling circulation device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN203893703U (en) | Evaporative cooler closed circulating cooling water device for thermal power plant | |
CN104315875B (en) | Power plant's spike cooling evaporative condenser | |
CN105020832B (en) | Suitable for the integrated air conditioner unit in subway | |
CN208779969U (en) | A kind of calcium carbide legal system acetylene technique gas colling tower | |
CN110779125B (en) | Condensate water recycling system of combined air conditioner | |
CN205261805U (en) | Evaporation formula condensing equipment based on separated heat pipe precooling | |
CN104457317A (en) | Stand-pipe indirect-direct two-stage evaporative cooling tower | |
CN204255132U (en) | Bushing type composite condensation cooling device | |
CN104406422B (en) | Bushing type composite condensation cooling device | |
CN206235183U (en) | A kind of refrigerator cooling system | |
CN209672658U (en) | A kind of curved surface plate evaporative condenser | |
CN204301556U (en) | A kind of nested type double tower body double flash evaporation cooling tower | |
CN206876011U (en) | A kind of water vapor recovery device used for cooling tower | |
CN206583326U (en) | Evaporative condenser | |
CN203964693U (en) | High-efficiency condensation device | |
CN203671999U (en) | Water-consumption-free scale-free energy-saving combined condenser | |
CN205957530U (en) | Water wind combined cooling formula vapor compression circulating water unit | |
CN205957341U (en) | Outer machine of water wind combined cooling formula air conditioner and air conditioning unit | |
CN205174937U (en) | Sleeve pipe evaporative condenser with fin | |
CN209197508U (en) | Dry and wet or so arranges integrated enclosed cooling device | |
CN208349649U (en) | A kind of combined type heat exchange cooling device | |
CN209415849U (en) | Except overheat evaporative condenser | |
CN205897629U (en) | Zero incrustation scale is energy -conserving combination condenser of water consumption not | |
CN207649433U (en) | A kind of heat pipe evaporating condensation type heat exchanger | |
CN206131540U (en) | Built -in heat exchange calandria not water consumption does not have energy -conserving compound condenser of dirt |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CB03 | Change of inventor or designer information |
Inventor after: Wang Zhixiang Inventor after: Sheng Zhaode Inventor before: Wang Zhixiang |
|
CB03 | Change of inventor or designer information | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190423 Termination date: 20200809 |
|
CF01 | Termination of patent right due to non-payment of annual fee |