CN208742233U - A kind of new waste gas absorption cleaning processing unit - Google Patents

A kind of new waste gas absorption cleaning processing unit Download PDF

Info

Publication number
CN208742233U
CN208742233U CN201820417579.5U CN201820417579U CN208742233U CN 208742233 U CN208742233 U CN 208742233U CN 201820417579 U CN201820417579 U CN 201820417579U CN 208742233 U CN208742233 U CN 208742233U
Authority
CN
China
Prior art keywords
gas
guide board
exhaust
gas guide
processing unit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820417579.5U
Other languages
Chinese (zh)
Inventor
吴伟枝
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Foshan City Environmental Protection Equipment Co Ltd Armour Of God
Original Assignee
Foshan City Environmental Protection Equipment Co Ltd Armour Of God
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Foshan City Environmental Protection Equipment Co Ltd Armour Of God filed Critical Foshan City Environmental Protection Equipment Co Ltd Armour Of God
Priority to CN201820417579.5U priority Critical patent/CN208742233U/en
Application granted granted Critical
Publication of CN208742233U publication Critical patent/CN208742233U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model discloses a kind of new waste gas absorption cleaning processing units, it is related to technical field of waste gas treatment, it includes shell, is successively set on the intracorporal spiral board of the shell, packing layer, atomization spray tower and demister from bottom to top, it further include having the gas guide board component that the housing cavity bottom end is set, the gas guide board component is located at exhaust inlet pipe outlet top, and the gas guide board component includes the gas guide board that multiple groups interval is arranged in parallel in the housing cavity vertically;This programme is by being provided with the gas flow guiding plate component structure of new structure, the gas flow guiding plate component structure of improved structure form enables to the exhaust gas by being entered in gas guide board component in flue gas leading can be more uniformly to be flowed, and the flow velocity for making exhaust gas flow through the gas guide board component is retarded, to carry out more fully exhaust gas preliminary purification processing, and then finally guarantee the purified treatment effect of exhaust gas.

Description

A kind of new waste gas absorption cleaning processing unit
Technical field
The utility model relates to technical field of waste gas treatment, and in particular to a kind of new waste gas absorption cleaning processing unit.
Background technique
Currently, both at home and abroad for organic exhaust gas treatment method mainly have heating power destruction method, active carbon adsorption, low temperature etc. from Daughter, microorganism treatment and absorption process etc..Common absorbing and purifying device mainly has moisture film tower, fills out in absorption process exhaust-gas treatment Expect tower, rotating stream tray scrubber and spray column etc..Wherein various absorbing and purifying devices have it is respective have disadvantage, single use in practice Certain apparatus structure carries out exhaust-gas treatment, and exhaust-gas treatment result just has certain limitation, it is difficult to reach efficient purification effect Fruit.Such as a number of patent application is practical new for the China of 200720062065.4 " complex organic waste gas absorption purifier " Type patent, disclose it is a kind of existing above-mentioned common wet absorption technology is combined, overcome above-mentioned single skill The insufficient defect of waste gas purification brought by art.Although it can effectively purify exhaust gas, since it is still adopted For conventional gas guide board structure, in practical work process, exhaust gas is flowing to other devices by gas guide board In the process, the time of contact of exhaust gas and air flow guiding plate is too short (general exhaust gas flow velocity is very fast), thus at opposite exhaust gas In the limited time of purified treatment, and then it will lead to and exhaust gas occur in incomplete phenomenon is purified, particularly with complicated component Exhaust gas for.Therefore in view of this, can effectively ensure that the full and uniform progress of exhaust gas is preliminary net for how to search out one kind The gas guide board structure of change is just particularly important.
Summary of the invention
In view of the deficiencies in the prior art, the purpose of this utility model is to provide a kind of new waste gas absorption cleanings Waste exhaust gases preferably uniformly can be evacuated, be formed several by processing unit, the new waste gas absorption cleaning processing unit Stock off-gas flows handle operation to carry out more fully effective exhaust gas preliminary purification.
To achieve the above object, the technical solution adopted in the utility model is as follows:
A kind of new waste gas absorption cleaning processing unit includes shell, is successively set in the shell from bottom to top Spiral board, packing layer, atomization spray tower and demister, be respectively arranged with exhaust inlet pipe and row on the housing bottom two sides Liquid pipe, the case top are provided with exhaust pipe, further include having the gas flow guiding board group that the housing cavity bottom end is arranged in Part, the gas guide board component are located at exhaust inlet pipe outlet top, and the gas guide board component includes multiple groups Interval is arranged in parallel in the gas guide board of the housing cavity vertically, and each gas guide board is in continuous bending template shape Structure, each its bending part of the gas guide board is provided with the card slot extended with exhaust gas flow direction opposite direction, adjacent The airflow channel for exhaust gas flowing is provided between the gas guide board, wherein exhaust gas is through in the gas guide board component The bottom end of airflow channel enters and flows out from its top.
Further, it is successively set in distance inside and outside gas guide board between adjacent card slot on each gas guide board On two sides.
Further, the card slot is integrally formed with the gas guide board and is made.
It further, further include having the exhaust fan being arranged at the exhaust pipe.
It further, further include having the air blower being arranged at the housing bottom.
Compared with prior art, the advantageous effects that this programme has are as follows: this programme is by being provided with new structure shape The gas flow guiding plate component structure of formula, the gas flow guiding plate component structure of improved structure form enable to by flue gas leading into Entering can be more uniformly to be flowed to the exhaust gas in gas guide board component, and exhaust gas is made to flow through the gas flow guiding The flow velocity of board group part is retarded, to carry out more fully exhaust gas preliminary purification processing, and then finally guarantees the net of exhaust gas Change treatment effect.
Detailed description of the invention
Fig. 1 is the waste gas purification absorption treating device structural schematic diagram in the present embodiment.
Fig. 2 is the gas guide board component schematic perspective view in the present embodiment.
Fig. 3 is the gas guide board component longitudinal section the schematic diagram of the section structure in the present embodiment.
Fig. 4 is the schematic diagram of the waste exhaust gases gas coming through baffle assembly in the present embodiment.
Description of symbols in figure:
1- exhaust inlet pipe, 2- gas guide board component, 21- gas guide board, 211- inner card cage, 212- exterior bayonet slot, 22- airflow channel, 3- spiral board, 4- packing layer, 5- atomization spray tower, 6- demister, 7- exhaust pipe, 8- drain pipe, 9- air blast Machine, 10- exhaust fan, 11- shell.
Specific embodiment
The utility model is described in further detail with specific embodiment with reference to the accompanying drawings of the specification.
It is conventional existing structure that this programme, which is for gas guide board structure in existing emission-control equipment, and exhaust gas exists During flowing through it, since the general flow velocity of waste exhaust gases is very fast, so that exhaust gas can not be sufficiently carried out at preliminary purification Reason, and the phenomenon that exhaust gas cannot equably be flowed out through existing gas guide board, and a kind of new waste gas proposed absorb it is net Change processing unit, which preferably uniformly can evacuate by waste exhaust gases, if being formed Carried interest off-gas flows handle operation to carry out more fully effective exhaust gas preliminary purification.
Referring to shown in attached drawing 1 to 3, one of the present embodiment new waste gas absorption cleaning processing unit, the new waste gas Absorption cleaning processing unit includes shell 11, the spiral board being successively set in shell 11 from bottom to top 3, packing layer 4, mist Change spray column 5 and demister 6, exhaust inlet pipe 1 and drain pipe 8,11 top of shell are respectively arranged on 11 bottom end two sides of shell It is provided with exhaust pipe 7, further includes having the gas guide board component 2 that 11 inner cavity bottom end of shell is set, gas guide board component 2 Top is exported positioned at exhaust inlet pipe 1, for carrying out water conservancy diversion to the exhaust gas of entrance, gas guide board component 2 includes between multiple groups Every the gas guide board 21 for being arranged in parallel in 11 inner cavity of shell vertically, each gas guide board 21 is in continuous bending template shape knot Structure, each its bending part of gas guide board 21 are provided with the card slot extended with exhaust gas flow direction opposite direction, adjacent gas The airflow channel 22 for exhaust gas flowing is provided between deflector 21, wherein exhaust gas is logical through air-flow in gas guide board component 2 The bottom end in road 22 enters and flows out from its top.It is whole in order to make exhaust gas during gas coming through baffle assembly 2 The more uniform and flowing time of a waste exhaust gases distribution is longer, adjacent card slot on each gas guide board 21 in the present embodiment Between be successively set in distance inside and outside gas guide board 21 on, i.e., at gas guide board 21 thereon Adjacent fold, according to It is secondary to be provided with an exterior bayonet slot 212 and inner card cage 211.The setting of card slot can make exhaust gas in the mistake of gas coming through deflector 21 Cheng Zhong forms temporary pause, can be come into full contact with corresponding scavenging solution, on the other hand can also subtract to a certain extent The flow velocity of light waste exhaust gases.In addition, the gas guide board 21 in the present embodiment uses the structure type of continuous bending, also for Guarantee the carry out preliminary purification operation processing that exhaust gas can be more full and uniform.Preferentially, the gas guide board in the present embodiment 21 and card slot be integrally formed and be made, such as stainless steel material can be used in practice and be made.
Finally, in order to enable exhaust gas can have in 11 inner cavity of shell flow velocity appropriate (guarantee exhaust gas flow velocity not because The effect of gas guide board 21 and it is excessively too low), i.e., so that entire emission-control equipment has suitable working efficiency, this implementation Example is provided with air blower 9 in 11 bottom end of shell, for enabling waste exhaust gases to pass through gas guide board with flow velocity appropriate 21 (specific 9 working efficiency size of air blower in practice, should be according to the specific of actual 11 inner cavity size of shell and exhaust gas Input flow velocity and be adjusted), while it is defeated in order to allow to carry out the carry out that the exhaust gas that is fully cleaned up that treated can be stable Out, the present embodiment is also equipped with exhaust fan 10 at air-exhausting duct air inlet, and exhaust gas is arranged in time such that treated Out.
Referring to shown in attached drawing 4, the exhaust gas flowed into through exhaust inlet pipe 1, exhaust gas is led to by air-flow in gas guide board component 2 The bottom end in road 22 enters and flows out from its top, and exhaust gas is during flowing, with the absorbing liquid flow down above shell 11 It is contacted, to carry out preliminary purified treatment operation.
Obviously, it is practical without departing from this can to carry out various modification and variations to the utility model by those skilled in the art Novel spirit and scope.If in this way, these modifications and variations of the present invention belong to the utility model claims and Within the scope of its equivalent technology, then the utility model is also intended to include these modifications and variations.

Claims (5)

  1. It include shell, to be successively set on the shell from bottom to top intracorporal 1. a kind of new waste gas absorption cleaning processing unit Spiral board, packing layer, atomization spray tower and demister are respectively arranged with exhaust inlet pipe and drain on the housing bottom two sides Pipe, the case top are provided with exhaust pipe, it is characterised in that: further include having the gas that the housing cavity bottom end is arranged in Baffle assembly, the gas guide board component are located at exhaust inlet pipe outlet top, the gas guide board component packet The gas guide board that multiple groups interval is arranged in parallel in the housing cavity vertically is included, each gas guide board is in continuous folding Curved plate structure, each its bending part of the gas guide board are provided with the card extended with exhaust gas flow direction opposite direction Slot is provided with the airflow channel for exhaust gas flowing between the adjacent gas guide board, and wherein exhaust gas is led through the gas The bottom end of airflow channel enters and flows out from its top in flowing plate component.
  2. 2. a kind of new waste gas absorption cleaning processing unit according to claim 1, it is characterised in that: each gas On being successively set in distance between adjacent card slot inside and outside gas guide board on deflector.
  3. 3. a kind of new waste gas absorption cleaning processing unit according to claim 1 or 2, it is characterised in that: the card slot It is integrally formed and is made with the gas guide board.
  4. 4. a kind of new waste gas absorption cleaning processing unit according to claim 1, it is characterised in that: further include having setting Exhaust fan at the exhaust pipe.
  5. 5. a kind of new waste gas absorption cleaning processing unit according to claim 1 or 4, it is characterised in that: further include having Air blower at the housing bottom is set.
CN201820417579.5U 2018-03-26 2018-03-26 A kind of new waste gas absorption cleaning processing unit Expired - Fee Related CN208742233U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820417579.5U CN208742233U (en) 2018-03-26 2018-03-26 A kind of new waste gas absorption cleaning processing unit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820417579.5U CN208742233U (en) 2018-03-26 2018-03-26 A kind of new waste gas absorption cleaning processing unit

Publications (1)

Publication Number Publication Date
CN208742233U true CN208742233U (en) 2019-04-16

Family

ID=66050609

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820417579.5U Expired - Fee Related CN208742233U (en) 2018-03-26 2018-03-26 A kind of new waste gas absorption cleaning processing unit

Country Status (1)

Country Link
CN (1) CN208742233U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111514598A (en) * 2020-05-09 2020-08-11 北京翰东环境工程有限公司 High-efficiency energy-saving ammonia water gasification device

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111514598A (en) * 2020-05-09 2020-08-11 北京翰东环境工程有限公司 High-efficiency energy-saving ammonia water gasification device

Similar Documents

Publication Publication Date Title
CN201026440Y (en) Absorption, oxidation, concentration combined desulfurizing tower
CN208742233U (en) A kind of new waste gas absorption cleaning processing unit
CN206996270U (en) A kind of curing fume gathers cleaning system
CN209735306U (en) Waste gas collecting and treating device
CN202136916U (en) Flue gas purification system
CN205867863U (en) Flue gas purification treatment device
CN105999938B (en) A kind of flue gas processing device of heat-recoverable
CN205796820U (en) A kind of desulfurating dust-removing equipment
CN202151545U (en) Environment-friendly, energy-saving and efficient multi-stage dust remover
CN208927915U (en) A kind of flue gas purification device
CN209049172U (en) A kind of industrial waste gas processing system
JP3221952U (en) High efficiency desulfurization denitration exhaust gas purification device
CN203355583U (en) Flue gas purifier
CN105854580B (en) A kind of flue gas processing device
CN209348418U (en) White cigarette gas smoke abatement device
CN214209898U (en) Purification device for treating dust-containing tail gas
CN212142034U (en) Workshop dust and gas treatment equipment
CN209475974U (en) A kind of high efficiency spray desulfurization equipment
CN208493303U (en) Self-loopa liquid collecting spray cooling device with flue gas deep purifying and de- contour painting energy
CN209997381U (en) paint waste gas treatment system
CN208959584U (en) Adsoption catalysis integrated treatment unit
CN203281217U (en) Bag type dedusting device capable of carrying out wet desulphurization and wet denitrification
CN214233412U (en) Asphalt flue gas purification treatment device
CN203577536U (en) Tail gas treatment system
CN214261237U (en) Flue gas desulfurization and dust removal device for calcining furnace

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190416

Termination date: 20200326

CF01 Termination of patent right due to non-payment of annual fee