A kind of foundation pit construction water circulation utilization system
Technical field
The utility model is a kind of foundation pit construction water circulation utilization system, belongs to the realm of building construction.
Background technique
China is the serious country of drought and water shortage, and current water conservation, water conservation have become fundamental policy, face
When it is not high to water quality requirement with water when, e.g., car washing water, flushing facility, fugitive dust sprinkling, concrete curing, mud mixing etc. are each
Item technique auxiliary water must use tap water or the higher works scope of water quality, domestic water, concrete, mortar, cement slurry
Etc. mixings water, with the continuous development and extension of engineering construction, remote districts have entered the high speed development stage, much in region
The predicament for directly restricting production and living without real political affairs water water supply supply is faced in first stage of construction to specially design to cope with this situation
Water circulation utilization system.
Prior art discloses application No. is a kind of 201420010117.3 construction site water circulation utilization system, packets
It includes well group, high-level water storage pond, coagulative precipitation tank, sterilization pool and high-order water tower, the well group and lattice is passed through by collecting conduit
It is connected after grid with the water inlet end in the high-level water storage pond;The water outlet in the high-level water storage pond is heavy by gravity filter and coagulation
The water inlet end in shallow lake pond is connected;The water outlet of the coagulative precipitation tank is connected with the water inlet end of sterilization pool;The water outlet of the sterilization pool
End is connected with high-order water tower.The utility model makes the water resource in engineering obtain the utilization of greatest benefit, saves construction cost, section
About water resource, accomplishes real green construction, but prior art periphery is general mating not perfect, municipal water plug into a little compared with
It is more, it is difficult to meet the needs of engineering construction, municipal water and blowdown are costly, and site construction water consumption is big, and is much
Construction auxiliary water, has the condition recycled, the higher cost if not recycling using rear direct blowdown.
Utility model content
In view of the deficienciess of the prior art, the utility model aim is to provide a kind of foundation pit construction water circulation use system
System, general mating not perfect to solve periphery, municipal water is plugged into a little less, is difficult to meet the needs of engineering construction, municipal administration use
Water and blowdown are costly, and site construction water consumption is big, and many for construction auxiliary water, the condition with recycling,
If not recycled using rear direct blowdown the problem of higher cost.
To achieve the goals above, the utility model is achieved through the following technical solutions: a kind of foundation pit construction water
Cyclic utilization system, structure include: Guamishi, steel reinforcement cage, well, the first water pump, flow pipe, reservoir, the first filtering ponds,
Second filtering ponds, third filtering ponds, tee tube, the second water pump, the steel reinforcement cage are located at the medial surface of well and connect with its activity
It connects, first water pump is fixedly connected by being located at the flow pipe of its front surface with reservoir, the reservoir and the first filtering
Pond is parallel to each other and is flexibly connected by flow pipe, and second water pump is set to the inside of reservoir and is firmly connected with it,
The tee tube is fixedly mounted on the front surface of flow pipe, and the Guamishi is set to the interior surface of steel reinforcement cage.
Further, second filtering ponds are located at the right of the first filtering ponds and are fixedly connected by flow pipe.
Further, the third filtering ponds are located at the right of the second filtering ponds and are flexibly connected by flow pipe.
Further, first filtering ponds, the second filtering ponds and third filtering ponds are parallel to each other.
Further, second water pump is fixedly connected with flow pipe.
Further, the well is mutually perpendicular to steel reinforcement cage.
Further, the first water pump is made of metal material.
Beneficial effect
A kind of foundation pit construction water circulation utilization system of the utility model can achieve general mating more perfect, the city in periphery
Political affairs are plugged into a little less with water, can satisfy the needs of engineering construction, municipal water and blowdown expense are lower, site construction water consumption
It is small and many for construction auxiliary water, there is the condition recycled, can be used direct blowdown water circulation use then cost compared with
Low purpose.
Detailed description of the invention
Upon reading the detailed description of non-limiting embodiments with reference to the following drawings, other spies of the utility model
Sign, objects and advantages will become more apparent upon:
Fig. 1 is a kind of structural schematic diagram of foundation pit construction water circulation utilization system of the utility model.
In figure: Guamishi -1, steel reinforcement cage -2, well -3, the first water pump -4, flow pipe -5, reservoir -6, the first filtering
Pond -7, the second filtering ponds -8, third filtering ponds -9, tee tube -10, the second water pump -11.
Specific embodiment
To be easy to understand the technical means, creative features, achievement of purpose, and effectiveness of the utility model, below
In conjunction with specific embodiment, the utility model is further described.
Referring to Fig. 1, the utility model provides a kind of foundation pit construction water circulation utilization system, structure includes: Guamishi
1, steel reinforcement cage 2, well 3, the first water pump 4, flow pipe 5, reservoir 6, the first filtering ponds 7, the second filtering ponds 8, third filtering ponds
9, tee tube 10, the second water pump 11, the steel reinforcement cage 2 are located at the medial surface of well 3 and are flexibly connected with it, first water pump
4 are fixedly connected by being located at the flow pipe 5 of its front surface with reservoir 6, and the reservoir 6 and the first filtering ponds 7 are parallel to each other
And be flexibly connected by flow pipe 5, second water pump 11 is set to the inside of reservoir 6 and is firmly connected with it, described three
Siphunculus 10 is fixedly mounted on the front surface of flow pipe 5, and the Guamishi 1 is set to the interior surface of steel reinforcement cage 2, second filtering
Pond 8 is located at the right of the first filtering ponds 7 and is fixedly connected by flow pipe 5, and the third filtering ponds 9 are located at the second filtering ponds 8
Right and be flexibly connected by flow pipe 5, first filtering ponds 7, the second filtering ponds 8 and third filtering ponds 9 are mutually flat
Row, second water pump 11 are fixedly connected with flow pipe 5, and the well 3 is mutually perpendicular to steel reinforcement cage 2, and the first water pump 4 uses
Metal material is made.
First water pump 4 described in the utility model is a kind of pressure to increase liquid or gas, is allowed to transport flow
Machinery.
Big according to geologic information selection top sand good water permeability, reservoir storage after into building site, lower part bedrock fracture is relatively sent out
It educates, pile foundation and material stockyard, road etc. are avoided according to design document in the big stratum of hydraulic pressure, and it sets position and prepares construction well,
To make full use of data well 3 that can be arranged by the position of dewatering well, the construction of well 3 can also use Percussion Piles with rotary drilling rig
Machine is reached in bedrock fracture layer using mud off pore-forming, disposes steel reinforcement cage 2, the close mesh filter screen of steel reinforcement cage outsourcing, strainer outer ring
It is fixed around steel wire, backfills Guamishi, can maintain to set up water in hole wall stabilization and the quick seepage flow to hole of periphery water storage
Pump, water is continually pumped into sedimentation basin, then set up water pump in reservoir, water is pumped into flow pipe, flow pipe is pre- every 30m
Three-way connection is stayed, construction area is can be convenient and directly fetches water use, construction auxiliary is pumped after gutter flows into sedimentation basin again with water
Enter ditch, through three-level sedimentation basin, into reservoir, recycling is pumped into flow pipe supply construction water.
The Guamishi 1, steel reinforcement cage 2, well 3, the first water pump 4, flow pipe 5, reservoir 6, first of the utility model filter
Pond 7, the second filtering ponds 8, third filtering ponds 9, tee tube 10,11 component of the second water pump are universal standard part or art technology
The component that personnel know, structure and principle are all that this technology personnel can be learnt by technical manual or by routine experiment side
Method knows, the utility model solves the problems, such as it is that periphery is general mating not perfect, and municipal water is plugged into a little more, is difficult to meet work
The needs of journey construction, municipal water and blowdown are costly, and site construction water consumption is big, and many is construction auxiliary water,
Condition with recycling, if not recycled using rear direct blowdown the problem of higher cost, the utility model passes through
Above-mentioned component is combined with each other, and it is general mating more perfect to can achieve periphery, and municipal water is plugged into a little less, can satisfy work
The needs of journey construction, municipal water and blowdown expense are lower, and site construction water consumption is small, and many for construction auxiliary water, tool
There is the condition of recycling, direct blowdown water circulation use then lower-cost purpose can be used, described in detail below:
The steel reinforcement cage 2 is located at the medial surface of well 3 and is flexibly connected with it, before first water pump 4 is by being located at it
The flow pipe 5 on surface is fixedly connected with reservoir 6, and the reservoir 6 and the first filtering ponds 7 are parallel to each other and by flow pipe 5
It is flexibly connected, second water pump 11 is set to the inside of reservoir 6 and is firmly connected with it, the fixed peace of the tee tube 10
Mounted in the front surface of flow pipe 5, the Guamishi 1 is set to the interior surface of steel reinforcement cage 2, and second filtering ponds 8 are located at first
It the right of filtering ponds 7 and is fixedly connected by flow pipe 5, the third filtering ponds 9 are located at the right of the second filtering ponds 8 and lead to
Cross the flexible connection of flow pipe 5.
The basic principles and main features of the present invention and the advantages of the present invention have been shown and described above, for
For those skilled in the art, it is clear that the present invention is not limited to the details of the above exemplary embodiments, and without departing substantially from this
In the case where the spirit or essential attributes of utility model, the utility model can be realized in other specific forms.Therefore, no matter
From the point of view of which point, the present embodiments are to be considered as illustrative and not restrictive, and the scope of the utility model is by institute
Attached claim rather than above description limit, it is intended that will fall within the meaning and scope of the equivalent elements of the claims
All changes are embraced therein.It should not treat any reference in the claims as limiting related right
It is required that.
In addition, it should be understood that although this specification is described in terms of embodiments, but not each embodiment is only wrapped
Containing an independent technical solution, this description of the specification is merely for the sake of clarity, and those skilled in the art should
It considers the specification as a whole, the technical solutions in the various embodiments may also be suitably combined, forms those skilled in the art
The other embodiments being understood that.