CN208717686U - Pavement tile work calibrating installation - Google Patents
Pavement tile work calibrating installation Download PDFInfo
- Publication number
- CN208717686U CN208717686U CN201720823163.9U CN201720823163U CN208717686U CN 208717686 U CN208717686 U CN 208717686U CN 201720823163 U CN201720823163 U CN 201720823163U CN 208717686 U CN208717686 U CN 208717686U
- Authority
- CN
- China
- Prior art keywords
- brick
- straight
- channel steel
- slot
- steering shaft
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Road Paving Machines (AREA)
Abstract
The utility model proposes a kind of pavement tile work calibrating installations, including moving parts, calibrator unit and brick folding component, the calibrator unit includes two parallel straight flanges, the straight flange is that straight channel steel is constituted, the opening of channel steel is inverted downward, support rod is horizontally connected between two straight flanges, brick folding component is connected on the support rod, the moving parts includes idler wheel and steering shaft, the steering shaft is connected in channel steel, idler wheel is also connected in channel steel by steering shaft, the brick folding component includes setting brick slot and brick clamp, the brick slot of setting is laid flat with straight flange Relative vertical, the surface for setting brick slot is arranged in brick clamp.The component for playing calibration function is mainly straight channel steel as straight flange, play the role of indicating straight line well, a certain number of floor tiles can be held by setting brick slot and brick clamp, it is aligned before laying, and what straight floor tile can be neat after opening sets brick slot and release brick clamp be placed on ground, working efficiency can be improved, calibration degree is also more preferable.
Description
Technical field
The utility model relates to a kind of urban construction equipment, specifically a kind of pavement tile work calibrating installation.
Background technique
Pavement is that is be separated out in road specialize in the part of walk, and the ground on pavement is usually laid with floor tile, ground
Brick is generally laid with by the way of artificial, artificial to be laid with the problem of offsetting, and by deviation accumulation, can be generated biggish
Displacement, causes the waste of material.
Utility model content
The purpose of the utility model is to overcome the above deficiencies in the existing technologies, and providing one kind can be in tile work
During the device calibrated.
The technical scheme in the invention for solving the above technical problem is: including moving parts, calibrator unit and brick folding
Component, the calibrator unit include two parallel straight flanges, and the straight flange is that straight channel steel is constituted, the opening of channel steel be inverted to
Under, it is horizontally connected with support rod between two straight flanges, brick folding component is connected on the support rod, the moving parts includes rolling
Wheel and steering shaft, the steering shaft are connected in channel steel, and idler wheel is also connected in channel steel by steering shaft, the brick folding component packet
It includes and sets brick slot and brick clamp, the brick slot of setting is laid flat with straight flange Relative vertical, and the surface for setting brick slot is arranged in brick clamp.Play calibration
The component of function is mainly straight channel steel as straight flange, plays the role of indicating straight line well, sets brick slot and brick clamp energy
A certain number of floor tiles are held, are aligned before laying, and set brick slot and floor tile straight after release brick clamp opening
It neatly can be placed on ground, working efficiency can be improved, calibration degree is also more preferable.
The edge formation of the straight flange has fillet, and is enclosed with vibration-absorptive material.The CONTACT WITH FRICTION at edge is more, so will not
Relevant edge rounding, reducing error influences.
The brick clamp includes the clamping limb of cross-articulation, and the end of clamping limb is shaped to clamping opening, the clamping opening downward vertically
The interior regular Z-Correct bump mapping Z-correct of molding.Clamping opening directly clamps brick, clamps great efforts.
Drawing is connected with spring between two ends at the top of the clamping limb.The work effect of clamping limb can be improved in spring
Rate can be rapidly separated when needing to loosen.
The brick clamp is connected on support rod by bracket.
The utility model compared with prior art, has the following advantages that and effect: the component for playing calibration function is mainly
Straight channel steel plays the role of indicating straight line well as straight flange, set brick slot and brick clamp can hold it is a certain number of
Brick is aligned before laying, and what straight floor tile after opening sets brick slot and release brick clamp can be neat be placed on ground
Face, can improve working efficiency, and calibration degree is also more preferable.
Detailed description of the invention
Fig. 1 is the positive structure schematic of the utility model.
Fig. 2 is the overlooking structure diagram of the utility model.
In figure: 1, straight flange, 2, channel steel, 3, support rod, 4, idler wheel, 5, steering shaft, 6, set brick slot, 7, brick clamp, 71, clamping
Arm, 72, clamping opening, 8, spring, 9, bracket.
Specific embodiment
The utility model is described in further detail with reference to the accompanying drawing and by embodiment, and following embodiment is pair
The explanation of the utility model and the utility model is not limited to following embodiment.
Moving parts, calibrator unit and brick folding component are specifically included, the calibrator unit includes two parallel straight flanges 1,
The straight flange 1 is that straight channel steel 2 is constituted, and the opening of channel steel 2 is inverted downwards, is horizontally connected with support rod 3 between two straight flanges 1,
Brick folding component is connected on the support rod 3, the moving parts includes idler wheel 4 and steering shaft 5, and the steering shaft 5 connects
In channel steel 2, idler wheel 4 is also connected in channel steel 2 by steering shaft 5, and the brick folding component includes setting brick slot 6 and brick clamp 7, institute
It states and sets brick slot 6 and laid flat with 1 Relative vertical of straight flange, the surface for setting brick slot 6 is arranged in brick clamp 7.
The edge formation of the straight flange 1 has fillet, and is enclosed with vibration-absorptive material.
The brick clamp 7 includes the clamping limb 71 of cross-articulation, and the end of clamping limb 71 is shaped to clamping opening 72, institute downward vertically
State the regular Z-Correct bump mapping Z-correct of molding in clamping opening 72.
Drawing is connected with spring 8 between two ends at 71 top of clamping limb.
The brick clamp 7 is connected on support rod 3 by bracket 9.
Claims (3)
1. a kind of pavement tile work calibrating installation, including moving parts, calibrator unit and brick folding component, it is characterised in that: described
Calibrator unit includes two parallel straight flanges (1), and the straight flange (1) is that straight channel steel (2) is constituted, and the opening of channel steel (2) is fallen
It sets downwards, is horizontally connected between two straight flanges (1) support rod (3), is connected with brick folding component, the shifting on the support rod (3)
Dynamic component includes idler wheel (4) and steering shaft (5), and the steering shaft (5) is connected in channel steel (2), and idler wheel (4) passes through steering shaft
(5) it is also connected in channel steel (2), the brick folding component includes setting brick slot (6) and brick clamp (7), described to set brick slot (6) and straight flange
(1) Relative vertical is laid flat, and brick clamp (7) is arranged in the surface for setting brick slot (6).
2. tile work calibrating installation in pavement according to claim 1, it is characterised in that: the edge formation of the straight flange (1)
There is fillet, and is enclosed with vibration-absorptive material.
3. tile work calibrating installation in pavement according to claim 1, it is characterised in that: the brick clamp (7) passes through bracket (9)
It is connected on support rod (3).
Applications Claiming Priority (2)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720317307 | 2017-03-29 | ||
CN2017203173073 | 2017-03-29 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208717686U true CN208717686U (en) | 2019-04-09 |
Family
ID=65967487
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720823163.9U Active CN208717686U (en) | 2017-03-29 | 2017-07-10 | Pavement tile work calibrating installation |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208717686U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110373976A (en) * | 2019-08-01 | 2019-10-25 | 三门星凯智能科技有限公司 | It is a kind of can be quickly to pavement surface tile work equipment |
-
2017
- 2017-07-10 CN CN201720823163.9U patent/CN208717686U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110373976A (en) * | 2019-08-01 | 2019-10-25 | 三门星凯智能科技有限公司 | It is a kind of can be quickly to pavement surface tile work equipment |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206485370U (en) | A kind of installation haulage equipment | |
CN208717686U (en) | Pavement tile work calibrating installation | |
CN205618933U (en) | Spinning machine strutting arrangement | |
CN201661013U (en) | Binding-free self-positioning steel bar spacer block | |
CN107988980A (en) | A kind of municipal administration bituminous concrete hollow pavement of road ponding processing equipment | |
CN107653756A (en) | A kind of city rail U-type groove plate-type ballastless railway roadbed track plates supporting adjuster and its application method | |
CN204023791U (en) | Embedding anchor bolts device | |
CN204111223U (en) | T-shaped tool track recovery track crane | |
CN204023362U (en) | A kind of paver paves leveling unit | |
CN202705872U (en) | Paving type pavement structure layer side mold stabilizing and supporting device | |
CN202672011U (en) | Arch camber type cement concrete paver with arbitrarily-adjustable width | |
CN205663170U (en) | Small concrete levelling means is used on indoor ground | |
CN202936710U (en) | Steel chisel for road paving construction layout | |
CN204343146U (en) | A kind of rigid pavement forming machine | |
CN204252403U (en) | A kind of positioning stool for Bars In Poured Concrete Slab negative bending moment rib | |
CN206988713U (en) | A kind of Fast Installation component for green building construction | |
CN204055419U (en) | Cantilever base device for installing and adjusting | |
CN207714237U (en) | A kind of municipal administration bituminous concrete hollow pavement of road ponding processing equipment | |
CN208413331U (en) | It is a kind of for accumulating the automatic plate fetching machine of corrugated board | |
CN205294120U (en) | Clear coal ware with adjustable belt conveyor uses | |
CN208107319U (en) | A kind of adjustable support of water process pipeline | |
CN103374872A (en) | Arch type cement and concrete spreading machine capable of randomly adjusting breadth | |
CN112443141A (en) | Vertical automatic wall tile sticking device for building construction | |
CN206352234U (en) | It is a kind of to spread the support frame changed trains for track plate railway roadbed | |
CN206084817U (en) | Pipeline clamp |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |