CN208702145U CN201821349840.9U CN201821349840U CN208702145U CN 208702145 U CN208702145 U CN 208702145U CN 201821349840 U CN201821349840 U CN 201821349840U CN 208702145 U CN208702145 U CN 208702145U
Authority
CN
China
Prior art keywords
mould
supporting rib
bar
bar chair
support device
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821349840.9U
Other languages
Chinese (zh)
Inventor
刘钊
姚禹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Metallurgical Construction Engineering Group Co Ltd
Original Assignee
China Metallurgical Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Metallurgical Construction Engineering Group Co Ltd filed Critical China Metallurgical Construction Engineering Group Co Ltd
Priority to CN201821349840.9U priority Critical patent/CN208702145U/en
Application granted granted Critical
Publication of CN208702145U publication Critical patent/CN208702145U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

Mould is hung the utility model discloses one kind to install with support device, it is characterized in that, symmetrically it is bent into the bar chair of "door" type downward vertically including the both ends by a reinforcing bar, the support foot hight of the bar chair two sides is greater than the height of concrete main reinforcement, make the stabilizer blade vertical supporting of the bar chair when on the horizontal shuttering of floor, there is gap between the top and bar chair of concrete main reinforcement;The bar chair upper end is vertically welded with two and is used to support the supporting rib for hanging mould, and the upper end level of two supporting ribs flushes.The utility model has reasonable in design, installs conveniently, is easy to fixed, can prevent the advantages that running mould, advantageously ensuring that construction precision, improve pouring quality.

Description

One kind, which being hung mould and installed, uses support device
Technical field
The utility model relates to technical field of building construction, hang mould in particular to one kind and install and use support device.
Background technique
Mould is hung, also cries and hangs mould, be commonly used in and turn over the position that jowar etc. has difference of height, most significantly with other template constructions Side is lower mouth without supporting or taking particular form to be fixed support, typically receiving lateral load, keeps its stability, energy Concrete modular level degree, verticality is set to reach requirement;Currently, hanging mould has two when installing, one is hung mould Side wall lacks corresponding support, so that the intensity for hanging mould is poor, in casting process, is easy to happen swollen mould, influences pouring molding Quality.Another be exactly hang mould fixation difficulty it is big, be easy to happen race mould, cause construction precision not up to standard.
For problem one, applicant devises a kind of formwork structure for hanging mould, including is located to pouring structure body width side To the side wall template of two sides, and it is fixedly connected on the crossbeam above two side wall templates;The length of the crossbeam is greater than To the width of pouring structure body, both ends all extend to the side wall die shape into cantilever, the cantilever of the crossbeam with it is described The diagonal brace being obliquely installed is also connected between the lower end of side wall template.In this way, side wall can be increased by the diagonal brace being obliquely installed The intensity of template lower end avoids that swollen mould occurs when concreting.However, how the formwork structure steadily to be propped up be located at it is to be poured Construction area is built as urgent problem to be solved.
Utility model content
In view of the above shortcomings of the prior art, the technical problem to be solved by the utility model is to how to provide a kind of knot Structure design rationally, installs conveniently, is easy to fixed, can prevent from running mould, advantageously ensure that construction precision, improve hanging for pouring quality Mould, which installs, uses support device.
In order to solve the above-mentioned technical problem, the utility model uses the following technical solution:
One kind being hung mould and installed with support device, which is characterized in that symmetrically downward vertically including the both ends by a reinforcing bar It is bent into the bar chair of "door" type, the support foot hight of the bar chair two sides is greater than the height of concrete main reinforcement, makes the reinforcing bar The stabilizer blade vertical supporting of seat has gap when on the horizontal shuttering of floor between the top and bar chair of concrete main reinforcement;Institute It states bar chair upper end and is vertically welded with two and be used to support the supporting rib for hanging mould, the upper end level of two supporting ribs flushes.
Using the above structure, since bar chair is bent downward vertically by the both ends of a reinforcing bar, so that bar chair It can be easily inserted into the gap of concrete main reinforcement, be fixed convenient for bar chair and concrete main reinforcement, in this way, can be indirectly sharp Bar chair is reinforced with concrete main reinforcement, is conducive to improve the stability for hanging mould, prevents to run mould.And bar chair Vertical supporting has gap, this way it is secured that steel when on horizontal shuttering between the top and bar chair of concrete main reinforcement The upper end of muscle seat remains horizontality, is further ensured that supporting rib is vertically arranged, and it is horizontally-supported will to hang mould, so as to To control template in the horizontal direction, construction precision is improved.
Further, it there are two the bar chair is arranged side by side, and is welded with and is correspondingly arranged on each bar chair Supporting rib, be located on two bar chairs and be welded between two supporting ribs of face setting transverse bar (, make The support component forms steadily frame structure.
Since support component includes two bar chairs, so that there are four stabilizer blades for support component tool, it being capable of more stable twelve Earthly Branches Support is on the horizontal shuttering of floor, so that operation is more convenient.Transverse bar is welded between supporting rib, and supporting rib is positioned to be poured In building structure body, there is no interfere with concrete main reinforcement.
Further, vertical muscle is also welded between the supporting rib on the same bar chair, adjacent is described vertical Reinforcing rib is welded between muscle and transverse bar.
In this way, the frame stability of support component can be improved.
It further, further include the mandril being correspondingly arranged with the supporting rib, the mandril hangs mould for being fixedly connected;Institute It states and is connected with casing between supporting rib and the corresponding mandril, be provided with partition in the middle part of described sleeve pipe, and partition both ends Aperture is consistent with the diameter of the corresponding supporting rib and mandril respectively;The height of the supporting rib is lower than to pouring structure body Height is 5~20mm, and when described sleeve pipe is sleeved on the supporting rib, and the upper end of described sleeve pipe is higher than to pouring structure body.
In this way, the height of supporting rib is slightly below the height to pouring structure body, and it is connect by casing with mandril, to coagulation After soil solidification, the lower end of casing is set in concrete, and mandril can be extracted from casing, so that the dismounting of template is very square Just.After pouring construction, casing is only stayed to stretch out structural body, and casing is thin-wall construction, intensity is lower, can be in masonry wall It is struck in passing using brick knife or nail hammer flat when body, makes it not and influence later period masonry, be conducive to the reinforcing bar excision work for saving the later period, letter Change working procedure, improves construction efficiency.
Further, described sleeve pipe is formed using metal casting, and whole is in up big and down small circular platform type.
In this way, one layer of release agent can be applied on casing before construction, after concrete formation, by casing from concrete It extracts, recycling, is conducive to save cost.
Further, described sleeve pipe is formed using plastic injection.
Casing strength made of plastics is lower, when brick wall is built, brick knife can be used and directly chop back.
Further, the distance of two supporting ribs is less than the width to pouring structure part, and each supporting rib To the minimum range on the outside of pouring structure part be 2~4cm.
In conclusion the utility model have it is reasonable in design, install conveniently, be easy to fixed, can prevent run mould, have The advantages that conducive to guaranteeing construction precision, improving pouring quality.
Detailed description of the invention
Fig. 1 is the formed by integrally casting construction template structure schematic diagram of the anti-bank in toilet.
Fig. 2 is the structural schematic diagram of support component.
Fig. 3 is the structural schematic diagram of diagonal brace.
Fig. 4 is the structural schematic diagram of side wall template.
Fig. 5 is the structural schematic diagram of internal corner formwork.
Specific embodiment
Below with reference to a kind of anti-bank in toilet formed by integrally casting construction formwork and its construction method to the utility model make into The detailed description of one step.
When specific implementation: as shown in fig. 1~fig. 5, a kind of formed by integrally casting construction template structure of the anti-bank in toilet, including mould Board group part 1 and the support component 2 for being used to support template component 1, the template component 1 include being located at wait pour anti-bank width side To the side wall template 11 of two sides, and it is fixedly connected on the crossbeam 12 of two 11 tops of side wall template;The support component 2 Including the supporting rib 21 being vertically provided between two side wall templates 11, the lower end of the supporting rib 21 is fixedly connected on mixed In solidifying soil main reinforcement, upper end is fixedly supported on the lower section of the crossbeam 12, and the lower section of each crossbeam 12 is arranged along its length There are at least two supporting ribs 21;The lower end of the side wall template 11 on the inside of toilet is also connected with internal corner formwork 16, on the internal corner formwork 16 tool there are two orthogonal forming surface, one of forming surface and the side wall template 11 Forming surface is concordant, another forming surface is concordant with floor upper surface to be formed;Two forming surfaces of the internal corner formwork 16 Intersection is arc-shaped, and with the corner of walling body to be poured to smear arc radius consistent for radius.
In above structure, supporting rib is vertically fixed in concrete main reinforcement, then by cross beam support at least two supports On muscle, so that it may which the fixation for realizing crossbeam and the side wall template connected with crossbeam prevents from occurring to run mould when concreting, just In control construction precision, concrete formation quality is improved.After concrete formation, supporting rib is also set in the anti-bank of molding, due to Supporting rib is vertically arranged, will not be formed and be extended transversely through on anti-bank, so as to avoid supporting rib and concrete junction from seeping water, Improve the waterproof performance of anti-bank.Said structure design is ingenious, convenient for disassembly and assembly, is easy to implement anti-bank and applies with floor main body formed by integrally casting Work, construction precision is high, is conducive to the waterproof performance for improving anti-bank.Meanwhile it can be when pouring by corner using internal corner formwork Arc one-pass molding is smeared, intensity is good, and waterproof performance is good, also helps the cost for smearing arc construction for saving the later period.
When it is implemented, being located at the supporting rib of two sides to wait pour the distance on the outside of anti-bank as 2~4cm.In this way, can protect Card supporting rib is integrally wrapped in anti-bank after molding.
Specifically, the length of the crossbeam 12 is greater than the width wait pour anti-bank, both ends all extend to the side wall mould Cantilever is formed outside plate 11, be also connected between the cantilever of the crossbeam 12 and the lower end of the side wall template 11 be obliquely installed it is oblique Support 13.
To guarantee that anti-bank waterproof performance after molding does not allow in supporting module using wall-crossing opposite-drawing bolt or iron wire Deng reinforcing to template, so that the lower end of side wall template forms cantilever design, in casting and compacting of concrete, side wall template be will receive The extruding of concrete causes the lower end of side wall template to expand outwardly and cause swollen mould, influences construction quality.It, will in above structure The both ends of crossbeam extend outward to form cantilever, then install diagonal brace between cantilever and the lower end of side wall template, and side wall can be improved The intensity of template lower end prevents swollen mould, is conducive to improve construction quality.
As shown in figure 3, the both ends of the diagonal brace 13 are respectively hinged on the crossbeam 12 and the side wall template 11;It is described Diagonal brace 13 includes the casing for being located at both ends, and the adjusting threaded rod being connected between two described sleeve pipes, the adjusting screw thread The both ends of bar are respectively provided with oppositely arranged screw thread, and middle part has vertically disposed torsion bar;The inner hole of two described sleeve pipes point The internal screw thread that Ju You not be correspondingly arranged with the adjusting threaded rod.
In this way, the length of diagonal brace can be changed by adjusting threaded rod by rotation, both may be implemented to being supported on side wall mould The adjusting of amount of force on plate can also fit the side wall template on different location according to the width of different anti-banks It answers.
As shown in Fig. 2, the support component 2 further includes symmetrically being bent into " door " downward vertically by the both ends of a reinforcing bar The bar chair 22 of type, the support foot hight of 22 two sides of bar chair are greater than the height of concrete main reinforcement, make the bar chair 22 Stabilizer blade vertical supporting has gap when on the horizontal shuttering of floor between the top and bar chair 22 of concrete main reinforcement;It is described Supporting rib 21 is welded on the bar chair 22, and is fixedly connected in concrete main reinforcement by the bar chair 22.
Since bar chair is bent downward vertically by the both ends of a reinforcing bar, bar chair is conveniently inserted Into the gap of concrete main reinforcement.And the vertical supporting of bar chair is when on horizontal shuttering, the top of concrete main reinforcement and steel Between muscle seat there is gap to be further ensured that supporting rib this way it is secured that the upper end of bar chair remains horizontality It is vertically arranged, can be horizontally-supported by crossbeam, so as to control template in the horizontal direction, improve construction precision.Specific implementation When, the support foot hight of bar chair is greater than 2~10mm of height of concrete main reinforcement.In this manner it is ensured that after concreting, reinforcing bar Seat is whole to be wrapped in concrete, carries out cutting operation without the later period, is advantageously reduced working procedure, is saved construction cost.
Specifically, the support component 2 includes two groups of bar chairs 22 arranged side by side and is welded on bar chair 22 Supporting rib 21;It is located on two bar chairs 22, and is welded between two supporting ribs 21 of face setting Transverse bar 23 makes the support component 2 form steadily frame structure.
Since support component includes two bar chairs, so that there are four stabilizer blades for support component tool, it being capable of more stable twelve Earthly Branches Support is on the horizontal shuttering of floor, so that operation is more convenient.Transverse bar is welded between supporting rib, and supporting rib is positioned to be poured In the anti-bank built, there is no interfere with concrete main reinforcement.
When implementation, vertical muscle 24, adjacent institute are also welded between the supporting rib 21 on the same bar chair 22 It states and is welded with reinforcing rib between vertical muscle 24 and transverse bar 23, there are two the vertical muscle and transverse bar are vertically arranged.
In this way, the frame stability of support component can be improved.
When implementation, the height of the supporting rib 21 is lower than 5 ~ 20mm of height wait pour anti-bank, the lower section of the crossbeam 12 With the mandril 14 being correspondingly arranged with the supporting rib 21, set is connected between the supporting rib 21 and the corresponding mandril 14 Pipe 3, the middle part of described sleeve pipe 3 are provided with partition, and the aperture at partition both ends respectively with the corresponding supporting rib 21 and mandril 14 diameter is consistent.When described sleeve pipe 3 is sleeved on the supporting rib 21, the upper end of described sleeve pipe 3 is higher than to pouring structure body.
Since the height of supporting rib is slightly below the height of anti-bank, and it is connect and is supported on the mandril of crossbeam bottom by casing The lower section of crossbeam, after concrete setting, the lower end of casing is set in concrete, and mandril can be extracted from casing, is made The dismounting for obtaining template is very convenient.After pouring construction, casing is only stayed to stretch out anti-bank, and casing is thin-wall construction, intensity It is lower, it can be struck in passing using brick knife or nail hammer in masonry panel flat, make it not and influence later period masonry, be conducive to save the later period Reinforcing bar cut off work, simplify working procedure, improve construction efficiency.
When it is implemented, casing 3 can also be the whole circular platform type pig metal that present under size, when construction, outside it One layer of release agent is applied on disc can extract casing after concrete formation from concrete, reuse.It can also adopt With plastic production described sleeve pipe 3, casing strength made of plastics is lower, when brick wall is built, brick knife can be used and directly chop back.
As shown in Figure 4 and Figure 5, the side wall template 11 and internal corner formwork are aluminum alloy mould plate, include along length side To the longitudinal rib of setting, the cross rib being arranged in the width direction, and the panel being laid in longitudinal rib and cross rib, the longitudinal rib and cross rib On all have the pin hole being placed equidistant with;The crossbeam 12 is made of aluminium alloy quarter bend, and is slideably set with slide 15, The width direction of crossbeam 12 described in the lower end edge of the slide 15 extends outward to form interconnecting piece, on the interconnecting piece of the slide 15 Pin hole with vertically communicated setting;The side wall template 11 is fixedly connected on described by pin and matched arc selling sheet On slide 15;The upper end of the slide 15 also has the clamping screw being arranged towards the crossbeam 12, and the clamping screw abuts On the crossbeam 12.
In this way, adjust the spacing between two side walls template using slide with can be convenient, to make that it is suitable for differences The anti-bank of width improves applicability.In addition, the stable structure of aluminum alloy mould plate, weight is relatively light, advantageously reduces formwork Difficulty improves the Forming Quality of concrete.High recycling rate advantageously reduces construction cost.
When implementation, the both ends of the crossbeam 12 are additionally provided with movable balance weight block 17.
Lower end due to being located at the side wall template on the inside of toilet is also equipped with internal corner formwork, so that the weight of the template of two sides Amount is uneven, be easy to cause and hangs mould appearance race mould phenomenon.By movable balance weight block on crossbeam, adjustable crossbeam both ends Balance guarantees that crossbeam and template can be propped up steadily and be located on supporting rib, prevents from running mould, is conducive to improve the stability for hanging mould, Improve construction quality.
When implementation, the both ends of the crossbeam 12 are provided with the clump weight 17, and are located at two cunnings The outside of seat 15;There is through-hole compatible with the crossbeam 12 in the middle part of the clump weight 17, and be slideably sleeved on described On crossbeam 12.
When construction, using following steps:
Unwrapping wire is first measured according to casting position of the drawing to the anti-bank in toilet, determines the construction area that anti-bank pours;
Keep the stabilizer blade of support component perpendicular in construction area along the length direction equidistant placement wait pour anti-bank support component To concrete main reinforcement is passed through, and it is supported on the horizontal shuttering below concrete main reinforcement, support component is fixed into binding with iron wire In concrete main reinforcement;
It after side wall template, internal corner formwork and crossbeam segmented assembly, lifts to support component, with casing by the top of crossbeam Bar and supporting rib are coaxially connected, after the completion of template overall package, carry out an acceptance inspection to template;
When pouring, first main structure is poured, after the completion of main structure concreting in 30 minutes, pours anti-bank And it is inserted using reinforcing bar real;The form removal after concrete reaches strength of mould stripping completes pouring construction.Being inserted using reinforcing bar can keep away in fact Without vibration has an impact to mould is hung, and causes to run mould and swollen mould.
The above is only the preferred embodiment of the utility model only, is not limitation with the utility model, all at this Made any modifications, equivalent replacements, and improvements etc., should be included in the utility model within the spirit and principle of utility model Protection scope within.

Claims (7)

1. one kind is hung mould and is installed with support device, which is characterized in that symmetrically curved downward vertically including the both ends by a reinforcing bar It is converted into the bar chair (22) of "door" type, the support foot hight of bar chair (22) two sides is greater than the height of concrete main reinforcement, makes institute The stabilizer blade vertical supporting of bar chair (22) is stated when on the horizontal shuttering of floor, the top of concrete main reinforcement and bar chair (22) it Between have gap;Bar chair (22) upper end is vertically welded with two and is used to support the supporting rib (21) for hanging mould, described in two The upper end level of supporting rib (21) flushes.
2. hanging mould as described in claim 1 to install with support device, which is characterized in that the bar chair (22), which is arranged side by side, to be had Two, and the supporting rib (21) being correspondingly arranged is welded on each bar chair (22), it is located at two reinforcing bars It is welded with transverse bar (23) on seat (22) and between two supporting ribs (21) of face setting, forms steadily frame structure.
3. hanging mould as claimed in claim 2 to install with support device, which is characterized in that be located at the same bar chair (22) On supporting rib (21) between be also welded with vertical muscle (24), be welded with reinforcement between the adjacent vertical muscle (24) and transverse bar (23) Muscle.
4. hanging mould as described in claim 1 to install with support device, which is characterized in that further include right with the supporting rib (21) The mandril (14) that should be arranged, the mandril (14) hang mould for being fixedly connected;The supporting rib (21) and the corresponding mandril (14) be connected between casing (3), be provided with partition in the middle part of described sleeve pipe (3), and the aperture at partition both ends respectively with it is corresponding The supporting rib (21) it is consistent with the diameter of mandril (14);The height of the supporting rib (21) is lower than the height to pouring structure body Degree is 5~20mm, and when described sleeve pipe (3) is sleeved on the supporting rib (21), and the upper end of described sleeve pipe (3) is higher than wait pour Structural body.
5. hanging mould as claimed in claim 4 to install with support device, which is characterized in that described sleeve pipe (3) uses metal casting It forms, and whole is in up big and down small circular platform type.
6. hanging mould as claimed in claim 4 to install with support device, which is characterized in that described sleeve pipe (3) uses plastic injection It forms.
7. hanging mould as described in claim 1 to install with support device, which is characterized in that the distance of two supporting ribs (21) Less than the width to pouring structure part, and each supporting rib is to being 2~4cm to the minimum range on the outside of pouring structure part.
CN201821349840.9U 2018-08-21 2018-08-21 One kind, which being hung mould and installed, uses support device Active CN208702145U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821349840.9U CN208702145U (en) 2018-08-21 2018-08-21 One kind, which being hung mould and installed, uses support device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821349840.9U CN208702145U (en) 2018-08-21 2018-08-21 One kind, which being hung mould and installed, uses support device

Publications (1)

Publication Number Publication Date
CN208702145U true CN208702145U (en) 2019-04-05

Family

ID=65943756

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821349840.9U Active CN208702145U (en) 2018-08-21 2018-08-21 One kind, which being hung mould and installed, uses support device

Country Status (1)

Country Link
CN (1) CN208702145U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110469107A (en) * 2019-07-12 2019-11-19 中国华冶科工集团有限公司 The construction of toilet root shaper and construction method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110469107A (en) * 2019-07-12 2019-11-19 中国华冶科工集团有限公司 The construction of toilet root shaper and construction method

Similar Documents

Publication Publication Date Title
CN109057339A (en) A kind of one-time-concreting construction method of the anti-bank in toilet
CN206636228U (en) A kind of cast in place concrete form early tears structure open
CN208702145U (en) One kind, which being hung mould and installed, uses support device
CN109025262A (en) A kind of molding construction method of concrete flanging one-time-concreting
CN109024987A (en) Construction method is poured after a kind of toilet shear wall
CN208088822U (en) A kind of caisson of toilet formwork structure
CN207327246U (en) A kind of precast beam molding die
CN108979142A (en) One kind hanging mould pouring construction structure
CN208668938U (en) One-time-concreting molding structure hanging mould structure
CN108979136A (en) A kind of formed by integrally casting construction template structure of the anti-bank in toilet
CN208702139U (en) A kind of construction template structure of toilet wall
CN210857752U (en) Structure falls board and hangs split heads muscle for mould
CN206233573U (en) A kind of beam die plate reinforcing device
CN211286623U (en) Secondary structure concrete inverted beam template reinforcing apparatus
CN207727997U (en) Concrete floor slab placement construction frame body platform structure for building construction
CN203626264U (en) Protective layer control apparatus for hogging moment reinforced steel bar suspension construction
CN208633518U (en) Prestressed concrete laminated floor slab hangs mould pouring construction structure
CN217106117U (en) Opening-closable steel formwork for construction of main structure of super high-rise building
CN202164555U (en) Bottom support of concrete box culvert template bracket post
CN206110424U (en) Floor convenient to dismantle template
CN217557719U (en) Multifunctional floor thickness control device capable of being used as aluminum mold diagonal bracing auxiliary tool
CN209942234U (en) Anti-bank of falling board district concrete hangs mould positioning tool
CN205616260U (en) Landing stage frame bracket and whole structure of watering of support girder
CN103410312A (en) Template system beam partially supported, plate free of supporting and size adjustable
CN212656549U (en) Large-section inclined column template construction structure for constructional engineering

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant