CN208701520U - A kind of hanging-filling beam suspension basket stretch-draw jack mobile device - Google Patents

A kind of hanging-filling beam suspension basket stretch-draw jack mobile device Download PDF

Info

Publication number
CN208701520U
CN208701520U CN201821269219.1U CN201821269219U CN208701520U CN 208701520 U CN208701520 U CN 208701520U CN 201821269219 U CN201821269219 U CN 201821269219U CN 208701520 U CN208701520 U CN 208701520U
Authority
CN
China
Prior art keywords
trolley
cantilevered
track
lifting lug
box girder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821269219.1U
Other languages
Chinese (zh)
Inventor
赵银超
陈家勇
张江全
胡雪峰
刘江西
谢盼盼
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway 11th Bureau Group Co Ltd
First Engineering Co Ltd of China Railway 11th Bureau Group Co Ltd
Original Assignee
China Railway 11th Bureau Group Co Ltd
First Engineering Co Ltd of China Railway 11th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway 11th Bureau Group Co Ltd, First Engineering Co Ltd of China Railway 11th Bureau Group Co Ltd filed Critical China Railway 11th Bureau Group Co Ltd
Priority to CN201821269219.1U priority Critical patent/CN208701520U/en
Application granted granted Critical
Publication of CN208701520U publication Critical patent/CN208701520U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

A kind of hanging-filling beam suspension basket stretch-draw jack mobile device, it is characterized in that: on the lower end surface of identical first cantilevered concreting box girder of structure, the second cantilevered concreting box girder and third cantilevered concreting box girder;With the first pin shaft and the second pin shaft by the upper brace in the first triangle hanger, the second triangle hanger and third triangle hanger, it is fixed in the U-lag of the first U-shaped lifting lug and the second U-shaped lifting lug;Identical first trolley of structure, the second trolley and third trolley are attached separately on the first walking rails, the second walking rails and third walking rails;In the two ends of the first walking rails, it is respectively welded first limiter;Second walking track is fixed on together with the first trolley, the second trolley and third trolley bottom surface respectively, the both ends of the second walking track;On the second walking rails, electric block is mounted on the 4th trolley idler wheel in 4th trolley transmission device, forms a kind of hanging-filling beam suspension basket stretch-draw jack mobile device.

Description

A kind of hanging-filling beam suspension basket stretch-draw jack mobile device
Technical field
The utility model relates to a kind of continuous beam suspended bracket cantilever casting stretch-draw jack hanging devices, specifically a kind of Hanging-filling beam suspension basket stretch-draw jack mobile device.
Background technique
With the fast development of China's Line for Passenger Transportation and high-speed railway, large span prestressed box beam structure overpass is obtained extensively General application.Prestressed reinforced concrete construction effectively increases the rigidity and crack resistance of bridge member, mitigates dead load, increases bridge Across footpath increases the durability of structure.After the completion of each segment of cantilever casting pours, it is both needed to carry out tensioning to longitudinal prestressing, Prestress wire tensioning is the key process of science of bridge building, and stretch-draw jack is prestressed stretch-draw capital equipment again, and big ton Position jack weight is big, and installation site is narrow.After lifting radius beyond tower crane, transfer is extremely inconvenient;In a segmental construction, Jack is installed, has enough to meet the need, removes stage makeup and costume, and requires repeatedly to lift, and chain block is mostly used to carry out jack transfer, low efficiency at present Under, the amount of labour is big, installs time-consuming and laborious.
Summary of the invention
The purpose of this utility model is to provide a kind of hang for the existing outstanding deficiency for filling the movement of beam longitudinal direction stretch-draw jack and fill Beam Hanging Basket stretch-draw jack mobile device which solves the lifting of Hanging Basket stretch-draw jack, movement, is installed, the problem of dismounting, Execute-in-place is facilitated, working efficiency is improved, so that working procedure is more smooth, has saved construction cost.
The utility model technical scheme applied to solve the technical problem is: a kind of hanging-filling beam suspension basket stretch-draw jack shifting Dynamic device, including cantilevered concreting box girder, triangle hanger, lifting lug, transmission device, walking rails, electric block, stretch-draw jack, limit Position device and pin shaft.
A kind of hanging-filling beam suspension basket stretch-draw jack mobile device, in identical first cantilevered concreting box girder of structure, second On the lower end surface of cantilevered concreting box girder and third cantilevered concreting box girder, it is respectively welded the first U-shaped lifting lug and the second U-shaped lifting lug;In the first U-shaped First shaft hole and the second axis hole are respectively equipped on the two sidewalls of lifting lug and the second U-shaped lifting lug;With the first pin shaft and the second pin shaft point Not by the upper brace (channel steel) in the first triangle hanger, the second triangle hanger and third triangle hanger, installation is solid respectively It is scheduled in the U-lag of the first U-shaped lifting lug and the second U-shaped lifting lug;Identical first trolley of structure, the second trolley and third trolley point The first walking rails in the first triangle hanger, the second triangle hanger and third triangle hanger are not installed and (mounted) On (I-steel), the second walking rails (I-steel) and third walking rails (I-steel);It is walked in the first walking rails, second The two ends of row track and third walking rails are respectively welded first limiter (angle steel);Second walking track (I-steel) It is fixed on together with the first trolley, the second trolley and third trolley bottom surface respectively, the both ends of the second walking track;4th is small On the second walking rails, electric block is mounted on the 4th trolley idler wheel in vehicle transmission device, forms a kind of outstanding filling beam Hanging Basket stretch-draw jack mobile device.
The triangle hanger: by upper brace (channel steel), track (I-steel), first support bar, second support bar and Third support rod is welded into triangle hanger;The angle β in triangle hanger is an angle of 90 degrees;The both ends of upper brace (channel steel), respectively Equipped with the third axis hole and the 4th axis hole that are matched on the U-shaped lifting lug that welds on outstanding filling soffit.
The cantilevered concreting box girder: the first cantilevered concreting box girder, the second cantilevered concreting box girder and third cantilevered concreting box girder and be installed below three Angular hanger can be increased and decreased according to requirement of engineering.
The Rhombic Truss: the first cantilevered concreting box girder, the second cantilevered concreting box girder and third cantilevered concreting box girder top surface are equipped with hinge One end hinge of the identical 3 drawings beam of structure is mounted in first hinge seat, second hinge seat and third hinge seat respectively by seat On, the drawing beam other end is mounted on Rhombic Truss respectively, Rhombic Truss is mounted on the first track in beams and prestress concrete continuous On the second track, the first track and the second track installation are fixed in beams and prestress concrete continuous.
The beneficial effects of the utility model are: a kind of hanging-filling beam suspension basket stretch-draw jack mobile device, which solves The lifting of Hanging Basket stretch-draw jack, mobile, installation, the problem removed, while alternative large-scale crane is to materials such as construction member, templates The lifting problem of material, facilitates execute-in-place, improves working efficiency, saved and be constructed into, ensure that construction safety.
Detailed description of the invention
The utility model embodiment is described in detail with reference to the accompanying drawings and examples.
Fig. 1 is the schematic perspective view of the utility model.
Fig. 2 is the left view schematic enlarged-scale view of Fig. 1.
The 1, first pin shaft in figure, 2, U-shaped lifting lug 2,3, upper brace (channel steel), the 4, second U-shaped lifting lug, 5a, the first outstanding filling Box beam, 5b, the second cantilevered concreting box girder, 5c, third cantilevered concreting box girder, the 6, second pin shaft, 7, first limiter, the 8, first walking rails, 9, the first traveling trolley, 10, second limiter, the 11, second walking rails, 12, transmission device, 13, electric block, 14, tensioning Jack, 15, second support bar 16,17, third support rod, 18, first hinge seat, 19, first hinge seat, 20, first axle Seat, 21, drawing beam.
Specific embodiment
It is provided in Fig. 1 and Fig. 2 embodiment in the utility model, a kind of hanging-filling beam suspension basket stretch-draw jack mobile device, On the lower end surface of the identical first cantilevered concreting box girder 5a of structure, the second cantilevered concreting box girder 5b and third cantilevered concreting box girder 5c, it is respectively welded There are the first U-shaped lifting lug 2 and the second U-shaped lifting lug 4;Is respectively equipped on the two sidewalls of the first U-shaped lifting lug 2 and the second U-shaped lifting lug 4 One axis hole and the second axis hole;With the first pin shaft 1 and the second pin shaft 6 respectively by the first triangle hanger, the second triangle hanger and Upper brace (channel steel) 3 in third triangle hanger, is fixed on the U-shaped of the first U-shaped lifting lug 2 and the second U-shaped lifting lug 4 respectively In slot;The identical first trolley 9h of structure, the second trolley 9m and third trolley 9n are installed (mount) respectively and hang in the first triangle The first walking rails (I-steel) 8d, the second walking rails 8e in frame, the second triangle hanger and third triangle hanger On (I-steel) and third walking rails 8f (I-steel);In the first walking rails 8d, the second walking rails 8e and third traveling The two ends of track 8f are respectively welded first limiter (angle steel) 7;Second walking track 11 (I-steel) is small with first respectively Vehicle 9h, the second trolley 9m and the bottom surface third trolley 9n are fixed on together, the both ends of the second walking track 11;4th trolley 12 On the second walking rails 11, electric block 13 is mounted on the 4th trolley 12 idler wheel in transmission device, is formed a kind of outstanding Hanging-filling beam basket stretch-draw jack mobile device.
The triangle hanger: it is supported by upper brace (channel steel) 3, track (I-steel) 8, first support bar 15, second Bar 16 and third support rod 17, are welded into triangle hanger;The angle β in triangle hanger is an angle of 90 degrees;Upper brace (channel steel) 3 Both ends are respectively equipped with the third axis hole and the 4th axis hole matched on the outstanding U-shaped lifting lug for filling and welding on soffit.
The Rhombic Truss: it is set on the first cantilevered concreting box girder 5a, the second cantilevered concreting box girder 5b and the top surface third cantilevered concreting box girder 5c There is hinge seat 18, respectively by one end hinge of the identical 3 drawings beam 21 of structure in first hinge seat 18, second hinge seat 19 and second hinge seat 20 on, respectively will drawing 21 other end of beam on Rhombic Truss (not drawing), Rhombic Truss is mounted on On the first track and the second track in beams and prestress concrete continuous, the first track and the second track installation are fixed on pre-stress concrete company On continuous beam (not drawing).
The cantilevered concreting box girder: the first cantilevered concreting box girder 5a, the second cantilevered concreting box girder 5b and third cantilevered concreting box girder 5c and below peace The triangle hanger of dress, can be increased and decreased according to requirement of engineering.
Working principle (construction procedure): stretch-draw jack 14 is moved to hanging-filling beam suspension basket respectively with fork truck by step 1 It draws below jack mobile device, adjusts longitudinal separation of the first traveling trolley 9 on the first track;
Step 2: starting electric block 13 promotes power switch, after stretch-draw jack 14 is sling in place, closes electronic calabash 13 lifting switch of reed;Then the power switch (forward) for starting transmission device 12, is moved to installation station for stretch-draw jack 14 Top, restart the power switch (decline) of electric block 13 and stretch-draw jack 14 be placed on installation station.
Remaining stretch-draw jack is identical as the stretch-draw jack lifting in step 1 and step 2, transfer, installation method.
When needing to remove stretch-draw jack, jack is drawn to unload down from the station on concrete box top surface of the beam, adjusted Position of the first traveling trolley 9 on the first track starts the power switch of transmission device 12, dynamic electric block 13 is moved to The top of stretch-draw jack turns off the power switch after the movement in place of electric block 13;It is torn open being mounted in electric block 13 It unloads on post-stretching jack link, starts the power switch of electric block 13, electric block 13 is by stretch-draw jack from concrete It unloads and puts it on the ground on station on box beam top surface, be then shut off the power switch of electric block 13.It repeats the above steps, just Entire stretch-draw jack disassembly can be sequentially completed.

Claims (3)

1. a kind of hanging-filling beam suspension basket stretch-draw jack mobile device, including cantilevered concreting box girder, triangle hanger, lifting lug, transmission device, Walking rails, electric block, stretch-draw jack, limiter and pin shaft;It is characterized in that: identical first cantilevered concreting box girder of structure, On the lower end surface of second cantilevered concreting box girder and third cantilevered concreting box girder, it is respectively welded the first U-shaped lifting lug and the second U-shaped lifting lug;? First shaft hole and the second axis hole are respectively equipped on the two sidewalls of one U-shaped lifting lug and the second U-shaped lifting lug;It is sold with the first pin shaft and second Axis is respectively by the upper brace in the first triangle hanger, the second triangle hanger and third triangle hanger, and installation is fixed respectively In the U-lag of the first U-shaped lifting lug and the second U-shaped lifting lug;Identical first trolley of structure, the second trolley and third trolley difference It is mounted on the first triangle hanger, the second triangle hanger and the first walking rails in third triangle hanger, the second traveling On track and third walking rails;In the two ends of the first walking rails, the second walking rails and third walking rails, weld respectively It is connected to first limiter;Second walking track is fixed on one with the first trolley, the second trolley and third trolley bottom surface respectively It rises, the both ends of the second walking track;Idler wheel in 4th trolley transmission device is on the second walking rails, electric block installation On the 4th trolley, a kind of hanging-filling beam suspension basket stretch-draw jack mobile device is formed.
2. a kind of hanging-filling beam suspension basket stretch-draw jack mobile device according to claim 1, it is characterized in that: by upper brace, Track, first support bar, second support bar and third support rod, are welded into triangle hanger;The angle β in triangle hanger is 90 Spend angle;The both ends of upper brace are respectively equipped with the third axis hole and the 4th matched on the outstanding U-shaped lifting lug for filling and welding on soffit Axis hole.
3. a kind of hanging-filling beam suspension basket stretch-draw jack mobile device according to claim 1, it is characterized in that: the first outstanding filling case Beam, the second cantilevered concreting box girder and third cantilevered concreting box girder top surface are equipped with hinge seat, respectively cut with scissors one end of the identical drawing beam of 3 structures The drawing beam other end is mounted on Rhombic Truss, Rhombic Truss is mounted on beams and prestress concrete continuous by chain respectively on hinge seat On the first track and the second track on, the first track and the second track installation are fixed in beams and prestress concrete continuous.
CN201821269219.1U 2018-08-08 2018-08-08 A kind of hanging-filling beam suspension basket stretch-draw jack mobile device Active CN208701520U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821269219.1U CN208701520U (en) 2018-08-08 2018-08-08 A kind of hanging-filling beam suspension basket stretch-draw jack mobile device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821269219.1U CN208701520U (en) 2018-08-08 2018-08-08 A kind of hanging-filling beam suspension basket stretch-draw jack mobile device

Publications (1)

Publication Number Publication Date
CN208701520U true CN208701520U (en) 2019-04-05

Family

ID=65941839

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821269219.1U Active CN208701520U (en) 2018-08-08 2018-08-08 A kind of hanging-filling beam suspension basket stretch-draw jack mobile device

Country Status (1)

Country Link
CN (1) CN208701520U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112900285A (en) * 2021-03-10 2021-06-04 中铁二十局集团第六工程有限公司 Tensioning method for prestressed bundles adjacent to existing line box girder

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112900285A (en) * 2021-03-10 2021-06-04 中铁二十局集团第六工程有限公司 Tensioning method for prestressed bundles adjacent to existing line box girder

Similar Documents

Publication Publication Date Title
JP3885584B2 (en) Construction method of composite truss bridge
CN202936736U (en) Cable-stayed bridge composite beam construction bridge floor crane
CN101781878B (en) Integral lifting template of main pylon of single-pylon cable-stayed bridge without dorsal cables and lifting construction method thereof
CN205223872U (en) Drag and hang novel string of basket structure of convolution
CN111717798A (en) Multi-machine cooperative hoisting system and process for box girder of over-built railway cutting highway bridge
CN104328734A (en) Multi-connection and multi-span continuous steel truss girder bridge and construction method thereof
JPH09221718A (en) Girder erection method of bridge
CN110700119A (en) Upper traveling system of assembled Bailey beam hanging basket and design method thereof
CN101831876B (en) Movable bridge fabrication machine and bridging method thereof
CN108625270A (en) Nose girder gantry crane installs bridge prefabrication box girder construction method
CN208701520U (en) A kind of hanging-filling beam suspension basket stretch-draw jack mobile device
CN103132702A (en) Longspan pipe truss pulling bar lifting and overhead rotating emplacing construction method
CN201746781U (en) Diagonal draw type bracket for cast-in-place of continuous beam
CN212505899U (en) Lightweight prestressing trackless construction hanging basket
CN203639037U (en) Mobile type SS-level guard bar formwork quick hanging and disassembling vehicle
CN203583378U (en) Floor plate truss trolley for mounting bridge deck slab of composite structure bridge
CN105088962B (en) A kind of integral hoisting method of Wavelike steel webplate part
CN108729360A (en) A kind of hanging-filling beam suspension basket stretch-draw jack mobile device
CN209652772U (en) Box girder bridge cantilever construction main truss cradle system
CN102587678A (en) Device for slipping node of steel structure
CN106320190A (en) Platform of bridge maintenance, consolidation and suspension construction
CN206800228U (en) Remove the frame mounting of arch bridge
CN215592333U (en) Multi-adaptability double-guide-beam bridge crane lifting appliance device with adjustable hole pitch
CN204940130U (en) A kind of integral lifting device of Wavelike steel webplate parts
CN204940131U (en) A kind of hanging basket device of Wavelike steel webplate parts

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant