CN208674830U - 一种大阻尼防舞动装置 - Google Patents
一种大阻尼防舞动装置 Download PDFInfo
- Publication number
- CN208674830U CN208674830U CN201821552508.2U CN201821552508U CN208674830U CN 208674830 U CN208674830 U CN 208674830U CN 201821552508 U CN201821552508 U CN 201821552508U CN 208674830 U CN208674830 U CN 208674830U
- Authority
- CN
- China
- Prior art keywords
- weight
- damping
- conductor spacer
- galloping device
- effect
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Suspension Of Electric Lines Or Cables (AREA)
Abstract
一种大阻尼防舞动装置,包括间隔棒框体,所述的间隔棒框体与连接板的一端连接,连接板的另一端与线夹连接,联板通过固定螺栓固定安装在间隔棒框体上,联板上设有重锤。采用上述结构,实现了通过阻尼颗粒之间以及阻尼颗粒与重锤内腔壁的碰撞来耗能达到多维度减振的效果,能使系统由原来的不稳定状态变为稳定状态,具有防止舞动、消除舞动的效果特别好的优点。
Description
技术领域
本实用新型涉及输电线路辅助装置领域,特别是一种大阻尼防舞动装置。
背景技术
在架空超高压输电时,与单根导线相比,分裂导线能使输电线的电感减小、电容增大,使其对交流电的波阻抗减小,提高线路的输电能力,所以一般采用分裂导线。但是,分裂导线在风力作用下经常会产生舞动,这种舞动对导线会产生过大的张力,使导线由于疲劳累积而短线、掉线,严重时,这种舞动现象会对如铁塔构件、绝缘子串一类输电设备造成机械性损伤,更有甚者,舞动会导致铁塔倒塌。在我国电网灾害事故中,架空导线舞动一旦发生、其影响范围广、造成损失大。随着我国电网规模的快速发展和恶劣气象的频繁出现,进入新世纪以来,电网发生舞动事故的频率明显增加,危害程度明显增大,几乎每年都发生大范围的舞动事故,造成了严重的经济损失和社会影响,因此,采取有效的方式防止输电线路的舞动是亟待解决的问题。现有技术采用大阻尼防舞装置来抑制或减弱架空电线的舞动,但现有大阻尼防舞装置只是对架空电线上下舞动的抑制能力较好,但对架空电线横向与扭向等其他舞动方向的抑制能力较差。
发明内容
本实用新型所要解决的技术问题是提供一种大阻尼防舞动装置,通过阻尼颗粒之间以及阻尼颗粒与重锤内腔壁的碰撞来耗能达到多维度减振的效果,且空腔内还预先加入了适量的填充防冻液,防冻液经过阻尼颗粒之间的间隙时会产生粘滞阻尼耗能,进一步增强消能效果,能使系统由原来的不稳定状态变为稳定状态,故和其他防舞动装置相比,具有防止舞动、消除舞动的效果特别好的优点。
为解决上述技术问题,本实用新型所采用的技术方案是:一种大阻尼防舞动装置,包括间隔棒框体,所述的间隔棒框体与连接板的一端连接,连接板的另一端与线夹连接,联板通过固定螺栓固定安装在间隔棒框体上,联板上设有重锤。
优选的方案中,所述的重锤为两个,两个重锤分别设置在联板的两端。
优选的方案中,所述的重锤为中空腔体。
优选的方案中,所述的重锤内填充有阻尼颗粒。
优选的方案中,所述的重锤内填充有防冻液。
本实用新型所提供的一种大阻尼防舞动装置,通过采用上述结构,具有以下有益效果:
(1)实现了通过阻尼颗粒之间以及阻尼颗粒与重锤内腔壁的碰撞来耗能达到多维度减振,提升了防舞动效果;
(2)实现了通过填充防冻液,使防冻液经过阻尼颗粒之间的间隙时会产生粘滞阻尼耗能,进一步增强消能效果;
(3)整个装置结构简单,操作方便,性价比高,实用性强。
附图说明
下面结合附图和实施例对本实用新型作进一步说明:
图1为本实用新型的整体结构示意图。
图2为本实用新型的重锤结构示意图。
图中:线夹1,连接板2,间隔棒框体3,联板4,重锤5,防冻液6,阻尼颗粒7,固定螺栓8。
具体实施方式
如图1-2中,一种大阻尼防舞动装置,包括间隔棒框体3,所述的间隔棒框体3与连接板2的一端连接,连接板2的另一端与线夹1连接,联板4通过固定螺栓8固定安装在间隔棒框体3上,联板4上设有重锤5。
本实用新型的使用方法为:将本装置安装在架空输电线路上。
本实用新型的有益效果:通过阻尼颗粒7之间以及阻尼颗粒7与重锤5内腔壁的碰撞,以及防冻液6经过阻尼颗粒7之间的间隙时会产生粘滞阻尼耗能,多维度的减轻架空电线各种方向与扭向的舞动,相较于现有防舞动装置,提升了防止舞动和消除舞动的效果。
优选的方案中,所述的重锤5为两个,两个重锤5分别设置在联板4的两端。这种结构的有益效果在于:提升了防止舞动和消除舞动的效果。
优选的方案中,所述的重锤5为中空腔体。这种结构的有益效果在于:提升了防止舞动和消除舞动的效果。
优选的方案中,所述的重锤5内填充有阻尼颗粒7。这种结构的有益效果在于:提升了防止舞动和消除舞动的效果。
优选的方案中,所述的重锤5内填充有防冻液6。这种结构的有益效果在于:提升了防止舞动和消除舞动的效果。
Claims (5)
1.一种大阻尼防舞动装置,包括间隔棒框体(3),其特征在于:所述的间隔棒框体(3)与连接板(2)的一端连接,连接板(2)的另一端与线夹(1)连接,联板(4)通过固定螺栓(8)固定安装在间隔棒框体(3)上,联板(4)上设有重锤(5)。
2.根据权利要求1所述的一种大阻尼防舞动装置,其特征在于:所述的重锤(5)为两个,两个重锤(5)分别设置在联板(4)的两端。
3.根据权利要求1所述的一种大阻尼防舞动装置,其特征在于:所述的重锤(5)为中空腔体。
4.根据权利要求1所述的一种大阻尼防舞动装置,其特征在于:所述的重锤(5)内填充有阻尼颗粒(7)。
5.根据权利要求1所述的一种大阻尼防舞动装置,其特征在于:所述的重锤(5)内填充有防冻液(6)。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821552508.2U CN208674830U (zh) | 2018-09-21 | 2018-09-21 | 一种大阻尼防舞动装置 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821552508.2U CN208674830U (zh) | 2018-09-21 | 2018-09-21 | 一种大阻尼防舞动装置 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208674830U true CN208674830U (zh) | 2019-03-29 |
Family
ID=65842169
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821552508.2U Expired - Fee Related CN208674830U (zh) | 2018-09-21 | 2018-09-21 | 一种大阻尼防舞动装置 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208674830U (zh) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111834969A (zh) * | 2020-07-22 | 2020-10-27 | 重庆科技学院 | 一种带刚度浮动式减振器 |
CN112332352A (zh) * | 2020-10-20 | 2021-02-05 | 山东电力工程咨询院有限公司 | 一种可变阻尼握力的复合型抑制舞动间隔棒 |
-
2018
- 2018-09-21 CN CN201821552508.2U patent/CN208674830U/zh not_active Expired - Fee Related
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111834969A (zh) * | 2020-07-22 | 2020-10-27 | 重庆科技学院 | 一种带刚度浮动式减振器 |
CN111834969B (zh) * | 2020-07-22 | 2021-07-13 | 重庆科技学院 | 一种带刚度浮动式减振器 |
CN112332352A (zh) * | 2020-10-20 | 2021-02-05 | 山东电力工程咨询院有限公司 | 一种可变阻尼握力的复合型抑制舞动间隔棒 |
CN112332352B (zh) * | 2020-10-20 | 2022-03-01 | 山东电力工程咨询院有限公司 | 一种可变阻尼握力的复合型抑制舞动间隔棒 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102684124B (zh) | 一种输电线路用五杆式防导线舞动动力减振器 | |
CN103594997B (zh) | 一种弹簧减震型相间防舞动间隔棒 | |
CN208674830U (zh) | 一种大阻尼防舞动装置 | |
CN104979790A (zh) | 一种相间间隔棒弹簧阻尼装置 | |
CN203352101U (zh) | 一种架空输电线路的防振系统 | |
CN203589658U (zh) | 一种弹簧减震型相间防舞动间隔棒 | |
CN102227077A (zh) | 电缆终端杆塔布置结构 | |
CN102966257B (zh) | 一种750kV复合材料横担 | |
CN204131064U (zh) | 一种架空输电导线防震锤的连接结构 | |
CN202678896U (zh) | 防滑预绞防震装置 | |
CN203674668U (zh) | 预绞式线夹防振锤 | |
CN203617660U (zh) | 电力通信opgw通信线路防振结构 | |
CN204793962U (zh) | 一种相间间隔棒弹簧阻尼装置 | |
CN102306921B (zh) | 一种悬垂绝缘子串防风致断裂方法 | |
CN201829902U (zh) | 预绞、回转线夹间隔棒式双摆防舞器 | |
CN203760992U (zh) | 一种双弹簧端部消振型相间间隔棒 | |
CN201656395U (zh) | 一种架空输电线路用组合型防振锤 | |
CN204517336U (zh) | 一种环形四分裂防舞器 | |
CN104242211B (zh) | 全方位防止导线震荡的装置 | |
CN205595734U (zh) | 一种环形防舞器 | |
CN208986557U (zh) | 一种绝缘子串的防风偏装置 | |
CN204243481U (zh) | 一种1000kV高抗回路悬吊管母结构 | |
CN204538621U (zh) | 一种多自由度防舞器 | |
CN104242210B (zh) | 一种架空输电导线防震锤的连接结构 | |
CN208908347U (zh) | 一种新型大阻尼防舞动装置 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190329 Termination date: 20190921 |