CN208586985U - Power transmission line steel pipe rod Online Video monitor mounting platform - Google Patents
Power transmission line steel pipe rod Online Video monitor mounting platform Download PDFInfo
- Publication number
- CN208586985U CN208586985U CN201821254231.5U CN201821254231U CN208586985U CN 208586985 U CN208586985 U CN 208586985U CN 201821254231 U CN201821254231 U CN 201821254231U CN 208586985 U CN208586985 U CN 208586985U
- Authority
- CN
- China
- Prior art keywords
- anchor ear
- transmission line
- power transmission
- mounting platform
- upper ledge
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 42
- 239000010959 steel Substances 0.000 title claims abstract description 42
- 230000005540 biological transmission Effects 0.000 title claims abstract description 13
- 238000012544 monitoring process Methods 0.000 abstract description 10
- 238000009434 installation Methods 0.000 abstract description 5
- 101100460844 Mus musculus Nr2f6 gene Proteins 0.000 description 4
- 238000010276 construction Methods 0.000 description 3
- 230000005611 electricity Effects 0.000 description 2
- 238000011900 installation process Methods 0.000 description 2
- 238000000034 method Methods 0.000 description 2
- 229910000746 Structural steel Inorganic materials 0.000 description 1
- 239000000463 material Substances 0.000 description 1
- 239000000203 mixture Substances 0.000 description 1
- 238000012827 research and development Methods 0.000 description 1
- 239000007787 solid Substances 0.000 description 1
Landscapes
- Suspension Of Electric Lines Or Cables (AREA)
Abstract
A kind of power transmission line steel pipe rod Online Video monitor mounting platform, including being located at the rectangular upper ledge of upper plane, being used to support the supporting steel structure of fixed upper ledge and lower anchor ear positioned at the upper anchor ear of upper plane, positioned at circular lower anchor ear, the right and left of lower plane;Upper anchor ear is bolted in the front frame for being connected in upper ledge, and the upper and lower side of supporting steel structure passes through adapter lug respectively and is fixed on upper ledge and lower anchor ear.The upper end of the two supporting steel structure of left and right is separately fixed at the rear end of the left and right sides frame of upper ledge, and lower end is separately fixed at the left and right outside of the annulus of lower anchor ear.The utility model structure is simple, at low cost, safe and reliable, is available in the load bearing equipment of the installation monitoring on steel tube tower, is further ensured that the safety of power grid.
Description
Technical field
The utility model belongs to field of power transmission, is related to a kind of video monitoring mounting platform.
Background technique
The video monitoring of transmission line of electricity is mostly installed on angle steel tower at this stage, and the construction under steel tube tower line is managed,
Due to there is no to carry tower material, in power system industry at present mainly in such a way that the spy of tour personnel patrols based on, while it is comprehensive local
Both had ready conditions, be aided with phone contact mechanism, visit, the other modes such as forum carry out assistance control;And due to transmission line of electricity
Distance is longer, certain provisional other units' constructions built is difficult to understand in time and follow-up, the installation of video monitoring for
Ensure that the importance of line security is increasingly apparent.
Utility model content
The purpose of this utility model seeks to solve problem above, provides a kind of video that power transmission line steel pipe rod is general prison
Control load bearing equipment.Designer combines the actual conditions of current cityization construction, the characteristic that comprehensive steel tube tower itself has, research and development
A kind of load bearing equipment for the installation monitoring being available on steel tube tower out, is further ensured that the safety of power grid.
The purpose of this utility model is achieved like this: a kind of road steel pipe pole Online Video monitor mounting platform,
Feature is: including being located under the rectangular upper ledge, the upper anchor ear positioned at upper plane, the annular shape positioned at lower plane of upper plane
Anchor ear, the right and left are used to support the supporting steel structure of fixed upper ledge and lower anchor ear;Upper anchor ear, which is bolted, is connected in upper ledge
Front frame on, the upper and lower side of supporting steel structure passes through adapter lug respectively and is fixed on upper ledge and lower anchor ear.
Further, the upper end of the two supporting steel structure (4) of left and right is separately fixed at the left and right sides frame of upper ledge (1)
Rear end, lower end are separately fixed at the left and right outside of the annulus of lower anchor ear (2).
Further, the upper ledge (1) uses the angle steel of 3*3, long 100cm, wide 110cm.
Further, the supporting steel structure (4) uses the angle steel of 4*4, long 80cm.
Further, upper anchor ear (3) diameter is 80cm.
Further, the lower anchor ear (2) is made of the semicircle merging that two radiuses are 50cm.
The utility model structure is simple, at low cost, safe and reliable, and the carrying for the installation monitoring being available on steel tube tower is set
It is standby, it is further ensured that the safety of power grid.
Now in conjunction with drawings and examples, the utility model is described in further detail.
Detailed description of the invention
Fig. 1 is the schematic front view of the utility model.
Fig. 2 is the schematic side view of the utility model.
Fig. 3 is the schematic top plan view of the utility model.
Fig. 4 is the schematic top plan view of the utility model embodiment.
In Fig. 1: 1, upper ledge;2, lower anchor ear;3, upper anchor ear;4, supporting steel structure;5, adapter lug.
Specific embodiment
From Fig. 1 to Fig. 3: a kind of road steel pipe pole Online Video monitor mounting platform of the utility model includes positioned at upper
The rectangular upper ledge 1 of plane, the upper anchor ear 3 positioned at upper plane, the circular ring shape positioned at lower plane lower anchor ear 2, the right and left
For the supporting steel structure 4 of upper ledge 1 and lower anchor ear 2 of being fixedly connected;Upper anchor ear 3 is bolted the front frame for being connected in upper ledge 1
On, by parbuckle screw, the size of adjustable anchor ear;Two supporting steel structures 4 of left and right pass through adapter lug 5 for upper ledge 1 and lower armful
Hoop 2 links up, and the upper end of two supporting steel structures 4 of left and right is separately fixed at the rear end of the left and right sides frame of upper ledge 1, and lower end is solid respectively
It is scheduled on the left and right outside of the annulus of lower anchor ear 2.
Upper ledge 1 is used to install camera, power supply box, solar energy electroplax of video monitoring etc..
Fig. 4 is as it can be seen that angle steel of the upper ledge 1 using 3*3, long 100cm, wide 110cm;Angle steel of the supporting steel structure 4 using 4*4, length
80cm;Upper 3 diameter 80cm of anchor ear, lower anchor ear 2 are that the semicircle that two radiuses are 50cm merges composition.
In the installation process of video monitoring, bar is stepped on to suitable position by operating personnel, consolidates anchor ear first with screw etc.
Due to tower body, in conjunction with the physical location in steel tube tower location, installed respectively on external angle-iron frame video monitoring camera,
Power supply box, solar energy electroplax etc..
In actual installation process, bar is stepped on by operating personnel and selects suitable installation site, it will be originally practical first with screw
Novel lower anchor ear is fixed on tower body, then installs the camera, power supply box, the sun of video monitoring respectively in upper ledge and upper anchor ear
It can battery plate, windmill.In the detailed process of implementation, it is contemplated that influence of this load bearing equipment to steel tube tower ladder etc..
Claims (6)
1. a kind of power transmission line steel pipe rod Online Video monitor mounting platform, it is characterised in that: the length including being located at upper plane
Rectangular upper ledge (1), the upper anchor ear (3) positioned at upper plane, the circular lower anchor ear (2) positioned at lower plane, the right and left are used
In the supporting steel structure (4) for supporting fixed upper ledge (1) and lower anchor ear (2);Upper anchor ear (3), which is bolted, is connected in upper ledge (1)
Front frame on, the upper and lower side of supporting steel structure (4) passes through adapter lug (5) respectively and is fixed on upper ledge and lower anchor ear.
2. a kind of power transmission line steel pipe rod Online Video monitor mounting platform according to claim 1, it is characterised in that:
The upper end of the two supporting steel structure (4) of left and right is separately fixed at the rear end of the left and right sides frame of upper ledge (1), and lower end is fixed respectively
In the left and right outside of the annulus of lower anchor ear (2).
3. a kind of power transmission line steel pipe rod Online Video monitor mounting platform according to claim 1 or 2, feature exist
In: the upper ledge (1) uses the angle steel of 3*3, long 100cm, wide 110cm.
4. a kind of power transmission line steel pipe rod Online Video monitor mounting platform according to claim 1 or 2, feature exist
In: the supporting steel structure (4) uses the angle steel of 4*4, long 80cm.
5. a kind of power transmission line steel pipe rod Online Video monitor mounting platform according to claim 1 or 2, feature exist
In: upper anchor ear (3) diameter is 80cm.
6. a kind of power transmission line steel pipe rod Online Video monitor mounting platform according to claim 1 or 2, feature exist
In: the lower anchor ear (2) is made of the semicircle merging that two radiuses are 50cm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821254231.5U CN208586985U (en) | 2018-08-06 | 2018-08-06 | Power transmission line steel pipe rod Online Video monitor mounting platform |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821254231.5U CN208586985U (en) | 2018-08-06 | 2018-08-06 | Power transmission line steel pipe rod Online Video monitor mounting platform |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208586985U true CN208586985U (en) | 2019-03-08 |
Family
ID=65543129
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821254231.5U Active CN208586985U (en) | 2018-08-06 | 2018-08-06 | Power transmission line steel pipe rod Online Video monitor mounting platform |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208586985U (en) |
-
2018
- 2018-08-06 CN CN201821254231.5U patent/CN208586985U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207233347U (en) | A kind of municipal works windproof advertising board | |
CN207184156U (en) | A kind of transmission line online monitoring system | |
CN208586985U (en) | Power transmission line steel pipe rod Online Video monitor mounting platform | |
CN207231471U (en) | A kind of device for monitoring inclination of electric power line pole tower | |
CN203386774U (en) | Adjustable photovoltaic bracket | |
CN205647344U (en) | New energy monitoring camera power supply unit | |
CN202651135U (en) | Integrated photovoltaic support foundation pile | |
CN205081747U (en) | Pole of mountable photovoltaic power generation support | |
CN203640371U (en) | Online monitoring system installation device used for power transmission tower | |
CN208923638U (en) | A kind of box-type substation | |
CN203857982U (en) | Pipe network data detection device | |
CN205743214U (en) | A kind of electric pole of band illumination | |
CN108054983A (en) | Photovoltaic module support and its mounting process | |
CN204676932U (en) | The solar airflow generating sunlight booth that braced structures is stable | |
CN204676933U (en) | Can the solar airflow generating sunlight booth of automatic snow | |
CN211740580U (en) | Positioning and monitoring device for looseness fault of bolt of power transmission tower | |
CN107612458A (en) | A kind of new energy monitoring camera electric supply installation | |
CN206346867U (en) | A kind of wind power generation plant for being easily installed and overhauling | |
CN206975075U (en) | A kind of arrester checks data remote transmission system vasculum | |
CN106013925B (en) | A kind of electric force pole tower | |
CN202109159U (en) | Anchor bolt for mounting a solar energy battery assembly | |
CN202299578U (en) | Transmission line video monitoring system bracket for installation of angle steel tower main material | |
CN203010155U (en) | Monitor support | |
CN206330642U (en) | Water level monitoring integrated apparatus | |
CN204668759U (en) | Lobby formula inversion communication system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |