CN208586627U - Avoid-dismantle catch pit bed die - Google Patents

Avoid-dismantle catch pit bed die Download PDF

Info

Publication number
CN208586627U
CN208586627U CN201821176341.4U CN201821176341U CN208586627U CN 208586627 U CN208586627 U CN 208586627U CN 201821176341 U CN201821176341 U CN 201821176341U CN 208586627 U CN208586627 U CN 208586627U
Authority
CN
China
Prior art keywords
hole
bed die
stencil body
avoid
catch pit
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821176341.4U
Other languages
Chinese (zh)
Inventor
鄢光军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Metallurgical Construction Engineering Group Co Ltd
Original Assignee
China Metallurgical Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Metallurgical Construction Engineering Group Co Ltd filed Critical China Metallurgical Construction Engineering Group Co Ltd
Priority to CN201821176341.4U priority Critical patent/CN208586627U/en
Application granted granted Critical
Publication of CN208586627U publication Critical patent/CN208586627U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The utility model discloses a kind of avoid-dismantle catch pit bed dies, it includes stencil body, it is characterized in that, the stencil body is the interior concrete prefabricated board for setting steel mesh, multiple vibrate hole and multiple through-holes for being used to install sealing up screw along the setting of its thickness direction are equipped on stencil body;The through-hole and hole of vibrating are staggered.The avoid-dismantle catch pit bed die that the utility model obtains is the interior concrete prefabricated board for setting steel mesh, it is from great, intensity is high, it only needs less sealing up screw that can be fixed, prevents from floating, the usage amount and distribution density of sealing up screw can be reduced, reduce installation strength, simultaneously as being concrete prefabricated board, one can be formed with the concrete poured, later period does not have to demoulding, reduces the process of demoulding;And prefabricated board is easier to control compared with cast-in-place concrete quality, more closely knit, not easy to leak, is equivalent to and has set road waterproof layer in hole, and impervious effect is more preferable.

Description

Avoid-dismantle catch pit bed die
Technical field
The utility model relates to a kind of catch pit mold for forming, and in particular to a kind of avoid-dismantle catch pit bed die.
Background technique
Architectural engineering is in excavation of foundation pit, if level of ground water is relatively high, and needs when substrate absolute altitude is under level of ground water Catch pit is set, and around the bottom of hole or gutter is excavated in center, moves the water to flow into catch pit, then uses dredge pump (submersible sewage pump) It takes away.Catch pit section is in U-shape, and is made of bottom plate and side wall.It, need to be according to the design mark of catch pit in catch pit forming process High and shape, the welded reinforcement bracket on the baseplate reinforcing bar bound, to install bed die and side form on it.Existing entirety Formula catch pit template mostly uses greatly plank sheathing, glued mould or PVC template to be made, therefore, in casting concrete since its is heavy The phenomenon that power is inadequate, is easy to appear floating.For these reasons, catch pit Form floating leads in installation template in order to prevent Often can on blinding layer the pre-buried water-stopping pull rod with seal ring, and water-stopping pull rod and the bed die in catch pit template are consolidated It is fixed, meanwhile, multiple girts being fixedly connected with reinforcement foundation are fixedly mounted on side form, are drawn by girt and sealing Bar fixes side form and bed die, to prevent a kind of its (catch pit anti-floating integral mold plate that such as notification number is 105862894 that floats Installation method).
The above-mentioned mode installation process for preventing Form floating is complicated, meanwhile, after concrete formation, disassembly template is also needed, Long construction period, large labor intensity.In addition, existing bed die is in rectangle mostly, and after template is installed, casting concrete When, it cannot vibrate to bed die concrete below, influence the compactness and Forming Quality of concrete.For these reasons, Applicant considers that designing one kind does not have to demoulding, template and baseplate reinforcing bar stable connection, is not in Form floating, simultaneously, moreover it is possible to Enough realize the bed die to vibrate to template lower concrete.
Summary of the invention
In view of the above shortcomings of the prior art, the technical problem to be solved by the utility model is to how to provide a kind of peace Dress is firm and easy for installation, can effectively shorten construction period, and can vibrate to the following concrete of template, and raising is catchmented Cheat the avoid-dismantle catch pit bed die of Forming Quality.
In order to solve the above-mentioned technical problem, the utility model uses the following technical solution:
A kind of avoid-dismantle catch pit bed die, it includes stencil body, which is characterized in that the stencil body sets steel to be interior The concrete prefabricated board of muscle net is equipped with multiple holes and multiple for installing of vibrating along the setting of its thickness direction on stencil body The through-hole of sealing up screw;The through-hole and hole of vibrating are staggered.In this way, setting the concrete prefabricated board conduct of steel mesh in Bed die, the intensity of template compared to common plank sheathing, PVC board for, intensity is higher, simultaneously as be concrete prefabricated board, because This, the concrete that can be poured with the later period is bonded well, is formed together foundation pit, and be not necessarily to demoulding after foundation pit molding, is reduced The process of demoulding, can shorten the construction period.In addition, since bed die is concrete prefabricated board, it is self-possessed larger, it can be appropriate Reduce the density of setting of segmented sealing up screw.And the through-hole on stencil body is set and can be used for the installation of sealing up screw, no It is drilled with installation of the hole for sealing up screw with scene, many manpowers can be saved.Set hole of vibrating can be used as concrete vibration Smash, at the same also function to concrete under observation verifying bed die whether pour it is full, pour real peep hole effect.
Further, multiple dowels, one end of the dowel are also fixedly installed in the front or back of stencil body It is fixedly connected with the steel mesh in bed die, the other end stretches out outside bed die and is in hook.In this way, dowel can make bed die and bottom steel Muscle further fixes, by the dual fixation of segmented sealing up screw and dowel, so that bed die fixation, is not in float The phenomenon that.Meanwhile after casting concrete, dowel and segmented sealing up screw part are embedded in concrete, increase coagulation The integral strength and anti-permeability performance of soil.And by the both ends of dowel respectively in stencil body steel mesh and bottom reinforcement bars fix, So that dowel connect very secured with template and bottom reinforcement bars, the outer end of dowel is set as hook, can convenient for dowel fixation and Installation.
Further, dowel is distributed in trellis, and the spacing between adjacent dowel is 300-500mm.In this way, dowel is in template It is evenly distributed on ontology, so as to ensure that stencil body all directions all uniform forces, service life are high.And between dowel Spacing is too big, and good anchoring effect is not achieved, and the workload anchored if spacing is too small will increase, and above-mentioned spacing technical ability meets Good anchoring effect, the workload of anchoring are not very big again.
Further, described to vibrate hole and through-hole is in trellis distribution, the spacing between adjacent hole of vibrating is 500- 800mm, the spacing between adjacent through-holes are 500-800mm.After being distributed vibrate hole and through-hole in this way, it can be ensured that quality of vibrating, It can ensure that the distributed quantity of sealing up screw in cellar area, it is ensured that the bonding strength and firmness of stencil body and bottom reinforcement bars.
Further, the stencil body with a thickness of 35mm-45mm, on stencil body, each vibrate hole corresponding position One is equipped with for blocking the plugging block in hole of vibrating, at least two are equipped with around each hole of vibrating for fixing plugging block Flexible fixed strip.In this way, can be blocked to hole of vibrating after the completion of vibrating, when closure, the binding of flexible fixed strip is being sealed On sprue, so that plugging block be fixed.
Further, the flexible fixed strip is galvanized wire or steel wire, when flexible fixed strip is equipped with two, two flexible fixed strips It is separately positioned on the left and right sides of through-hole, when flexible fixed strip is equipped with three, distribution triangular in shape, flexible fixed strip is equipped with four When, be square distribution.Using galvanized wire or steel wire can either antirust, and cut convenient for the later period, simultaneously, additionally it is possible to realize bending, tie up The purpose of bundle.And the distributing position of flexible fixed strip, it can be ensured that every fixed strip uniform force, and the fixation of sealing strip is steady enough Gu.
Compared with prior art, the avoid-dismantle catch pit that the utility model obtains is had the advantages that with bed die
1, bed die is the interior concrete prefabricated board for setting steel mesh, from great, intensity is high, only needs less sealing up screw just It can be fixed, prevent from floating, the usage amount and distribution density of sealing up screw can be reduced, reduce installation strength, simultaneously as It is concrete prefabricated board, one can be formed with the concrete poured, the later period does not have to demoulding, reduces the process of demoulding.And it is pre- Making sheet is easier to control compared with cast-in-place concrete quality, more closely knit, not easy to leak, is equivalent to and has set road waterproof layer in hole, impervious effect Fruit is more preferable.
2, the sealing up screw that the anchor pole on bed die can be installed with the later period matches, and carries out dual fixation to bed die, whole Body, stability are higher, impervious, anti-floating performance is more preferable, and anchor pole is prefabricated on bed die, install very efficient and convenient.
3, it is formed due to bed die using concrete for making, do not have to demoulding, when installation need to only fasten sealing up screw and anchor Bar can greatly shorten construction period, reduce the workload of worker.
Detailed description of the invention
Fig. 1 is the planar structure schematic diagram of avoid-dismantle catch pit bed die in embodiment;
Fig. 2 is the mounting structure schematic diagram of bed die in embodiment.
In figure: stencil body 1, hole 11 of vibrating, through-hole 12, dowel 13, flexible fixed strip 14, sealing up screw 2, plugging block 3.
Specific embodiment
The present invention will be further described with reference to the accompanying drawings and examples.
Embodiment:
As shown in Figure 1, avoid-dismantle catch pit bed die provided in this embodiment, includes stencil body 1, the stencil body 1 For the interior concrete prefabricated board for setting steel mesh, multiple holes 11 and more of vibrating along the setting of its thickness direction are equipped on stencil body A through-hole 12 for being used to install sealing up screw 2;The through-hole 12 and hole 11 of vibrating are staggered;Stencil body 1 front or Multiple dowels 13 are also fixedly installed on reverse side, one end of the dowel 13 is fixedly connected with the steel mesh in stencil body 1, separately One end is stretched out outside stencil body 1 and is in hook.Above-mentioned through-hole 12 is rounded, and hole 11 of vibrating is in rectangle.
Specifically, above-mentioned dowel 13 is distributed in trellis, the spacing between adjacent dowel 13 is 400mm.The hole 11 of vibrating It is distributed in trellis with through-hole 12, the spacing between adjacent hole 11 of vibrating is 600mm, and the spacing between adjacent through-holes 12 is 600mm.Certainly, in the specific implementation, dowel 13 can not be distributed according to trellis, as long as ensuring that every square metre at least has one A dowel 13.
Stencil body 1 in the present embodiment with a thickness of 40mm, on stencil body 1, each 11 corresponding position of hole of vibrating is equal Equipped with one for blocking the plugging block 3 in hole 11 of vibrating, at least two are equipped with around each hole 11 of vibrating for fixed envelope The flexible fixed strip 14 of sprue 3.Specifically, the flexibility fixed strip 14 is galvanized wire or steel wire, when flexible fixed strip is equipped with two, Two flexible fixed strips 14 are separately positioned on the left and right sides of through-hole, and when flexible fixed strip 14 is equipped with three, distribution triangular in shape is soft Property fixed strip 14 be equipped with four when, be square distribution.In the above-mentioned plugging block 3 of fixation,
When installing bed die, prefabricated bed die is transported to by foundation pit, then segmented sealing up screw 2 is installed, specifically, According to the position of through-hole 12 on bed die 2, sealing up screw 2 is fixedly mounted on the reinforcing bar of bottom surface, bed die is then had into dowel 13 One side towards bottom surface reinforcing bar direction spiral-lock, finally sealing up screw is the locked, fastening with locking nut again.As shown in Fig. 2, in order to So that sealing up screw 2 has stronger support force, on each sealing up screw 2, below ground mould, it is fixedly installed with multiple oblique Support.In addition, the sealing up screw 2 in the present embodiment is segmented sealing up screw for the ease of dismantling sealing up screw 2.
Finally, it should be noted that above embodiments are merely intended for describing the technical solutions of the present application, but not for limiting the present application technology Scheme, although applicant is described in detail the utility model referring to preferred embodiment, those skilled in the art Should be appreciated that those, the technical solution of the present invention is modified or equivalently replaced, without departing from the technical program Objective and range should all cover in the scope of the claims of the utility model.

Claims (6)

1. a kind of avoid-dismantle catch pit bed die, it includes stencil body (1), which is characterized in that the stencil body (1) is interior If the concrete prefabricated board of steel mesh, it is equipped on stencil body multiple along the holes of vibrating (11) that its thickness direction is arranged and multiple For installing the through-hole (12) of sealing up screw (2);The through-hole (12) and hole of vibrating (11) are staggered.
2. avoid-dismantle catch pit bed die according to claim 1, which is characterized in that stencil body (1) front or It is also fixedly installed on reverse side multiple dowels (13), one end and the steel mesh in stencil body (1) of the dowel (13) are fixed Connection, the other end stretch out stencil body (1) outside and are in hook.
3. avoid-dismantle catch pit bed die according to claim 2, which is characterized in that dowel (13) is distributed in trellis, phase Spacing between adjacent dowel (13) is 300-500mm.
4. avoid-dismantle catch pit bed die according to claim 1 or 2 or 3, which is characterized in that the hole of vibrating (11) and Through-hole (12) is distributed in trellis, and the spacing between adjacent hole of vibrating (11) is 500-800mm, between adjacent through-holes (12) between Away from for 500-800mm.
5. avoid-dismantle catch pit bed die according to claim 4, which is characterized in that the thickness of the stencil body (1) For 35mm-45mm, on stencil body (1), each vibrate hole (11) corresponding position be equipped with one for block vibrate hole (11) Plugging block (3), at least two are equipped with around each hole of vibrating (11) for fixing the flexible fixed strips of plugging block (3) (14).
6. avoid-dismantle catch pit bed die according to claim 5, which is characterized in that the flexibility fixed strip (14) is lead Silk or steel wire, when flexible fixed strip is equipped with two, two flexible fixed strips (14) are separately positioned on the left and right sides of through-hole, and flexibility is solid When determining item (14) equipped with three, distribution triangular in shape, when flexible fixed strip (14) is equipped with four, be square distribution.
CN201821176341.4U 2018-07-24 2018-07-24 Avoid-dismantle catch pit bed die Active CN208586627U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821176341.4U CN208586627U (en) 2018-07-24 2018-07-24 Avoid-dismantle catch pit bed die

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821176341.4U CN208586627U (en) 2018-07-24 2018-07-24 Avoid-dismantle catch pit bed die

Publications (1)

Publication Number Publication Date
CN208586627U true CN208586627U (en) 2019-03-08

Family

ID=65541888

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821176341.4U Active CN208586627U (en) 2018-07-24 2018-07-24 Avoid-dismantle catch pit bed die

Country Status (1)

Country Link
CN (1) CN208586627U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113605517A (en) * 2021-05-28 2021-11-05 广东电白建设集团有限公司 Small concrete cast-in-place water collecting well construction method and disassembly-free template system structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113605517A (en) * 2021-05-28 2021-11-05 广东电白建设集团有限公司 Small concrete cast-in-place water collecting well construction method and disassembly-free template system structure
CN113605517B (en) * 2021-05-28 2023-08-08 广东电白建设集团有限公司 Construction method of small concrete cast-in-situ water collecting well and disassembly-free template system structure

Similar Documents

Publication Publication Date Title
CN106677533A (en) Basement exterior wall single-side formwork supporting system and method
CN108842796A (en) The installation method of catch pit anti-floating monoblock type template system and the template system
CN106968692B (en) Tunnel excavation supporting structure and construction method thereof
CN208586627U (en) Avoid-dismantle catch pit bed die
CN101235679A (en) Door type solar energy warm booth production method
CN201801843U (en) Overwater gravity type earth-retaining structure with anchoring structure
CN209353363U (en) Steel concrete compound tube and foundation connection joint structure
CN108193815B (en) A kind of float Structure and its construction method of cast-in-place concrete hollow building roof
CN207739164U (en) A kind of road culvert structure
CN105649107B (en) Reinforced earth corrugated steel retaining wall structure
CN211114261U (en) Precast concrete shear force wall panel structure
CN208586626U (en) Catch pit anti-floating type template system
CN219157761U (en) Basement bottom plate high-low span connection structure
CN208918024U (en) Connecting joint structure and assembled architecture
CN210151748U (en) Foundation pit water collection surface drainage dewatering system
CN107558483A (en) A kind of building foundation and its construction method for installing wallboard
CN208280038U (en) A kind of arch culvert template system
CN208235550U (en) A kind of friction pile-ripple steel arch-drawing anchor combination slope protection structure
CN210507502U (en) Prefabricated assembled concrete slab bed structure
CN107268617A (en) Construction technology and device after a kind of anti-float anchor rod
CN107989025A (en) The construction method of diaphram wall connection structure and diaphram wall
CN210887608U (en) Assembled reinforced concrete structure
KR101219459B1 (en) The water-storage tank of assembly type and method for constructing thereof
CN106368346A (en) Sandwiched thermal insulation concrete external wall board having external wall boards and bay window boards which are prefabricated simultaneously
CN109339094B (en) Method for mounting vertical prestressed steel hoop concrete assembled retaining wall for road

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant