CN208586519U CN201820821717.6U CN201820821717U CN208586519U CN 208586519 U CN208586519 U CN 208586519U CN 201820821717 U CN201820821717 U CN 201820821717U CN 208586519 U CN208586519 U CN 208586519U
Authority
CN
China
Prior art keywords
road
pedestal frame
guide rail
left rail
rail
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820821717.6U
Other languages
Chinese (zh)
Inventor
花雪莲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Seiko Luqiao Equipment Technology Co., Ltd.
Original Assignee
Chengdu Creation Bio Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Chengdu Creation Bio Technology Co Ltd filed Critical Chengdu Creation Bio Technology Co Ltd
Priority to CN201820821717.6U priority Critical patent/CN208586519U/en
Application granted granted Critical
Publication of CN208586519U publication Critical patent/CN208586519U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

The utility model relates to anti-collision wall construction equipment technical fields, especially a kind of construction equipment of road and bridge anti-collision wall, including road and bridge ontology and pedestal frame, left rail is installed on the left of the upper surface of the road and bridge ontology, the upper surface of the left rail is equipped with the first bearing block, and right guide rail is equipped on the right side of the left rail.Left rail and right guide rail are installed on the basis of original in the utility model, threaded rod is mounted in two guide rail interiors, simultaneously using protective fence upper end close to the control box of connection steelframe edge installation, control the motor rotation of two guide rail rear end installations, to drive threaded rod to rotate, utilize the mating connection of threaded rod and pushing block, it pushes and control pedestal frame is moved along two guide rail direction stabilizations, staff on workbench can control pedestal frame according to condition of construction oneself and drive movable workbench, manpower is reduced to use, it may be implemented accurately to position construction simultaneously.

Description

A kind of construction equipment of road and bridge anti-collision wall
Technical field
The utility model relates to anti-collision wall construction equipment technical fields more particularly to a kind of construction of road and bridge anti-collision wall to set It is standby.
Background technique
Overpass has become more and more in present traffic route, because overpass generally outmatches common ground On road, some crossroads etc. are avoided, the unobstructed degree of road can be improved, it is well known that, overpass is to place oneself above On surface road, because its height is relatively high, it is necessary to anti-collision wall be arranged on the both sides of overpass, had in construction It constructs by special constructing device.
In the prior art, a kind of construction device for anti-collision wall of viaduct of patent CN201320704034.X, including it is placed in height Pedestal frame on bridge formation road surface, pedestal top of the trellis are equipped with the stretching frame to extension on the outside of anti-collision wall, stretch out in frame outermost end and hang There is basket of work, using the mobile constructing device of the movable pulley of pedestal frame bottom surface installation, existing constructing device when in use, needs Multiple staff push pedestal frame, by the mobile constructing device of movable pulley, while the hand steered fixation of staff are needed after moving Just with the stabilization of holding meanss the staff in hanging basket can be worked on, it is therefore desirable to a large amount of manpower output, Simultaneously existing device be by a large amount of rod piece weld it is assembled, be self-possessed it is small, construction personnel when carrying a large amount of tools, In the presence of the security risk turned on one's side, thus it is proposed that a kind of construction equipment of road and bridge anti-collision wall.
Utility model content
Purpose of the utility model is to solve problems of the prior art, therefore a kind of road and bridge anticollision proposed The construction equipment of wall.
To achieve the goals above, the utility model adopts the technical scheme that
Design a kind of construction equipment of road and bridge anti-collision wall, including road and bridge ontology and pedestal frame, the upper table of the road and bridge ontology Left side of face is equipped with left rail, and the upper surface of the left rail is equipped with the first bearing block, is equipped on the right side of the left rail Right guide rail, the upper surface of the right guide rail are equipped with the second bearing block, and the left side wall of the pedestal frame is in the left rail The holding tank interior welds that portion opens up are fixed with pushing block, and the right side wall of the pedestal frame is close to the left side of second bearing block It is welded with gag lever post, the gag lever post runs through second bearing block, and the right end of the gag lever post is held close to described second Sliding block is installed in the sliding slot opened up inside pouring weight, movable pulley, the pedestal frame are installed below the inner sidewall of the pedestal frame Upper end be fixedly installed with tripod, the left end of the tripod is fixedly installed with connection steelframe, the lower end of the connection steelframe It is fixedly installed with workbench, the upper surface of the workbench is equipped with protective fence, and the upper surface of the protective fence is close to the company The edge for connecing steelframe is fixedly installed with control box, and the lateral wall rear of the left rail is fixedly installed with motor, and the left side is led Rail is internally provided with threaded rod, and the lateral wall of the threaded rod is arranged with bearing close to the lateral wall of the left rail, described Pedestal frame and the left rail are sequentially connected by the pushing block and the threaded rod, and the motor electrically connects with external power supply It connects.
Preferably, there are two the motor is arranged altogether, and two motors respectively correspond be mounted on the left rail and The lateral wall rear of the right guide rail.
Preferably, there are two the threaded rod is arranged altogether, and two threaded rods respectively correspond be mounted on the left rail and The inside of the right guide rail, main shaft of two threaded rods respectively with two motors are welded and fixed.
Preferably, the pedestal frame is held with second bearing block by the gag lever post, the sliding block and described second The sliding slot opened up inside pouring weight is slidably connected.
Preferably, the width of the tripod bottom surface is twice of the pedestal frame width, the right end of the tripod with The pedestal frame alignment is welded and fixed, and the left end of the tripod extends outwardly.
The utility model proposes a kind of road and bridge anti-collision wall construction equipment, beneficial effect is: in the utility model Left rail and right guide rail are installed on the basis of original, are mounted on threaded rod in two guide rail interiors, while utilizing protective fence Upper end controls the motor rotation of two guide rail rear end installations, to drive spiral shell close to the control box of connection steelframe edge installation Rasp bar rotation pushes using the mating connection of threaded rod and pushing block and control pedestal frame is moved along two guide rail directions are stable Dynamic, the staff on workbench can control pedestal frame according to condition of construction oneself and drive movable workbench, and reducing manpower makes With, while may be implemented accurately to position construction, in addition, there are two bearing blocks in the installation of the top of two guide rails, utilize Bearing block increases the self weight of device, stablizes its installation, prevents to turn on one's side.
Detailed description of the invention
Fig. 1 be the utility model proposes a kind of road and bridge anti-collision wall construction equipment schematic view of the front view;
Fig. 2 be the utility model proposes a kind of road and bridge anti-collision wall construction equipment in guide rail structure schematic diagram;
Fig. 3 be the utility model proposes a kind of road and bridge anti-collision wall the portion construction equipment A enlarged structure schematic diagram.
In figure: connection steelframe 1, the first bearing block 2, control box 3, protective fence 4, workbench 5, road and bridge ontology 6, left rail 7, Pushing block 8, movable pulley 9, right guide rail 10, sliding block 11, gag lever post 12, the second bearing block 13, pedestal frame 14, tripod 15, motor 16, threaded rod 17, bearing 18.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.
Referring to Fig.1-3, a kind of construction equipment of road and bridge anti-collision wall, including road and bridge ontology 6 and pedestal frame 14, pedestal frame 14 with Second bearing block 13 is slidably connected by the sliding slot opened up inside gag lever post 12, sliding block 11 and the second bearing block 13, in pedestal frame When 14 movement, by 13 stabilizing base frame 14 of the second bearing block, security risk caused by occurring to turn on one's side is avoided.
Left rail 7 is installed on the left of the upper surface of road and bridge ontology 6, the upper surface of left rail 7 is equipped with the first bearing block 2, The right side of left rail 7 is equipped with right guide rail 10, and the upper surface of right guide rail 10 is equipped with the second bearing block 13, the left side of pedestal frame 14 The holding tank interior welds that wall opens up inside left rail 7 are fixed with pushing block 8, and the right side wall of pedestal frame 14 is held close to second The left side of pouring weight 13 is welded with gag lever post 12, and gag lever post 12 runs through the second bearing block 13, and the right end of gag lever post 12 is close to the Sliding block 11 is installed in the sliding slot opened up inside two bearing blocks 13, movable pulley 9, pedestal are installed below the inner sidewall of pedestal frame 14 The upper end of frame 14 is fixedly installed with tripod 15, and the width of 15 bottom surface of tripod is twice of 14 width of pedestal frame, tripod 15 Right end be aligned and be welded and fixed with pedestal frame 14, the left end of tripod 15 extends outwardly, convenient for utilizing the extension branch of tripod 15 Frame slings workbench 5, and construction working is carried out on the outside of road and bridge ontology 6 convenient for staff.
The left end of tripod 15 is fixedly installed with connection steelframe 1, and the lower end of connection steelframe 1 is fixedly installed with workbench 5, work The upper surface for making platform 5 is equipped with protective fence 4, and the upper surface of protective fence 4 is fixedly installed with operation close to the edge of connection steelframe 1 Case 3, the lateral wall rear of left rail 7 are fixedly installed with motor 16, and there are two the total settings of motor 16, and two motors 16 are right respectively It should be mounted on the lateral wall rear of left rail 7 and right guide rail 10, two motors 16 rotate synchronously synchronous stopping, convenient for control pedestal Frame 14 is mobile.
Left rail 7 is internally provided with threaded rod 17, and there are two the total settings of threaded rod 17, and two threaded rods 17 are right respectively It should be mounted on the inside of left rail 7 and right guide rail 10, main shaft of two threaded rods 17 respectively with two motors 16 is welded and fixed, benefit With the cooperation of threaded rod 17 and pushing block 8 that two guide rail interiors are installed, pedestal frame 14 is remained a constant speed stable shifting It is dynamic, so that workbench 5 stablizes movement, reduces and shake, avoid excessive shaking bring security risk.
The lateral wall of threaded rod 17 is arranged with bearing 18 close to the lateral wall of left rail 7, and pedestal frame 14 passes through with left rail 7 Pushing block 8 and threaded rod 17 are sequentially connected, and motor 16 and external power supply are electrically connected.
Working principle: in use, left rail 7 and right guide rail 10 to be mounted on to the upper surface of road and bridge ontology 6, then by first Bearing block 2 and the first bearing block 2 are respectively and fixedly installed to 10 upper surface of left rail 7 and right guide rail, by two guide rail fixing-stables, Then the pushing block 8 that 14 two sides of pedestal frame are welded is set in 17 lateral wall of threaded rod of two guide rail interiors installation, later will Device is connected to external power supply, and subsequent staff is entered inside workbench 5 using lift, controls two by control box 3 Guide rail rear installation two motors 16 rotation, drive threaded rod 17 rotate so that pedestal frame 14 by movable pulley 9 along Two guide rails are mobile, and workbench 5 is adjusted to construction location, convenient for 5 position of construction personnel's autonomous control workbench to road and bridge Anti-collision wall construct, until the construction of this section of road and bridge anti-collision wall finishes, device is moved into next section of road and bridge and continues construction.
The preferable specific embodiment of the above, only the utility model, but the protection scope of the utility model is not It is confined to this, anyone skilled in the art is within the technical scope disclosed by the utility model, practical according to this Novel technical solution and its utility model design are subject to equivalent substitution or change, should all cover the protection model in the utility model Within enclosing.

Claims (5)

1. a kind of construction equipment of road and bridge anti-collision wall, including road and bridge ontology (6) and pedestal frame (14), which is characterized in that the road It is equipped with left rail (7) on the left of the upper surface of bridge ontology (6), the upper surface of the left rail (7) is equipped with the first bearing block (2), it is equipped with right guide rail (10) on the right side of the left rail (7), the upper surface of the right guide rail (10) is equipped with the second load-bearing Block (13), the holding tank interior welds that the left side wall of the pedestal frame (14) opens up inside the left rail (7) are fixed with The right side wall of pushing block (8), the pedestal frame (14) is welded with gag lever post on the left of second bearing block (13) (12), the gag lever post (12) runs through second bearing block (13), and the right end of the gag lever post (12) is held close to described second It is equipped with sliding block (11) in the sliding slot opened up inside pouring weight (13), movable pulley is installed below the inner sidewall of the pedestal frame (14) (9), the upper end of the pedestal frame (14) is fixedly installed with tripod (15), and the left end of the tripod (15) is fixedly installed with company It connects steelframe (1), the lower end of connection steelframe (1) is fixedly installed with workbench (5), the upper surface installation of the workbench (5) Have protective fence (4), the upper surface of the protective fence (4) is fixedly installed with control box close to the edge of connection steelframe (1) (3), the lateral wall rear of the left rail (7) is fixedly installed with motor (16), and the left rail (7) is internally provided with screw thread The lateral wall of bar (17), the threaded rod (17) is arranged with bearing (18), the pedestal close to the lateral wall of the left rail (7) Frame (14) and the left rail (7) are sequentially connected by the pushing block (8) and the threaded rod (17), the motor (16) and External power supply is electrically connected.
2. a kind of construction equipment of road and bridge anti-collision wall according to claim 1, which is characterized in that the motor (16) sets altogether There are two setting, and two motors (16) respectively correspond the outside for being mounted on the left rail (7) and the right guide rail (10) Wall rear.
3. a kind of construction equipment of road and bridge anti-collision wall according to claim 1, which is characterized in that the threaded rod (17) is altogether There are two settings, and two threaded rods (17) respectively correspond the inside for being mounted on the left rail (7) and the right guide rail (10), Main shaft of two threaded rods (17) respectively with two motors (16) is welded and fixed.
4. a kind of construction equipment of road and bridge anti-collision wall according to claim 1, which is characterized in that the pedestal frame (14) with Second bearing block (13) inside the gag lever post (12), the sliding block (11) and second bearing block (13) by opening up Sliding slot be slidably connected.
5. a kind of construction equipment of road and bridge anti-collision wall according to claim 1, which is characterized in that tripod (15) bottom The width in face is twice of pedestal frame (14) width, and the right end of the tripod (15) is aligned weldering with the pedestal frame (14) Fixation is connect, the left end of the tripod (15) extends outwardly.
CN201820821717.6U 2018-05-30 2018-05-30 A kind of construction equipment of road and bridge anti-collision wall Active CN208586519U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820821717.6U CN208586519U (en) 2018-05-30 2018-05-30 A kind of construction equipment of road and bridge anti-collision wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820821717.6U CN208586519U (en) 2018-05-30 2018-05-30 A kind of construction equipment of road and bridge anti-collision wall

Publications (1)

Publication Number Publication Date
CN208586519U true CN208586519U (en) 2019-03-08

Family

ID=65534704

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820821717.6U Active CN208586519U (en) 2018-05-30 2018-05-30 A kind of construction equipment of road and bridge anti-collision wall

Country Status (1)

Country Link
CN (1) CN208586519U (en)

Similar Documents

Publication Publication Date Title
CN207073272U (en) A kind of decoration mobile working platform
CN101752804A (en) Two-arm swing obstacle-clearing type line walking robot body
CN106199490A (en) A kind of ammeter detection device
CN207839937U (en) A kind of cable wire for crane fixed length anticreep cutter device
CN208586519U (en) A kind of construction equipment of road and bridge anti-collision wall
CN207845014U (en) Photovoltaic operation and maintenance unmanned aerial vehicle automatic lifting platform
CN205640141U (en) Projection frame is used in portable international economics and trade teaching
CN209686255U (en) A kind of bridge construction platform
CN103056419B (en) A kind of ceiling perforating device
CN108183405A (en) A kind of outdoor electricity distribution cabinet with cooling and bird dispelling function
CN103042252B (en) Drilling equipment
CN209509441U (en) A kind of automatic up-down scaffold
CN107089602A (en) The double gantries for setting loop wheel machine running of twin beams
CN207647143U (en) A kind of construction coherent-wall scaffolding cantilever arrangement
CN108611978A (en) A kind of liftable monorail Bridge Erector
CN211072636U (en) Clamping device for part machining
CN212024720U (en) Electric power detection auxiliary device convenient to use
CN210212404U (en) Air-rail comprehensive operation train inspection line convenient to open and close
CN207986552U (en) A kind of train detection equipment transfer device
CN208381970U (en) A kind of construction lighting device
CN209703976U (en) A kind of architectural engineering scaffold being readily transported
CN209211878U (en) A kind of traction device of creeping formwork folding
CN220585848U (en) Electrified crossing device for extra-high voltage transmission line construction
CN107161923B (en) Energy storage power station staff protection device
CN205879968U (en) Ammeter detection device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20190527

Address after: 272000 Shimenshan Town Industrial Park, Qufu City, Jining City, Shandong Province

Patentee after: Shandong Seiko Luqiao Equipment Technology Co., Ltd.

Address before: 610000 Jincheng Avenue, Chengdu High-tech Zone, Sichuan Province

Patentee before: Chengdu creation Bio Technology Co., Ltd.