CN208576026U - A kind of hybrid system of efficient well cementing operation - Google Patents
A kind of hybrid system of efficient well cementing operation Download PDFInfo
- Publication number
- CN208576026U CN208576026U CN201820667334.8U CN201820667334U CN208576026U CN 208576026 U CN208576026 U CN 208576026U CN 201820667334 U CN201820667334 U CN 201820667334U CN 208576026 U CN208576026 U CN 208576026U
- Authority
- CN
- China
- Prior art keywords
- aggregated
- high energy
- diffusion chamber
- clear water
- hybrid system
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Preparation Of Clay, And Manufacture Of Mixtures Containing Clay Or Cement (AREA)
Abstract
The utility model relates to petroleum equipment technical fields, more particularly to a kind of hybrid system of efficient well cementing operation, it is aggregated into including measuring tank, water pipe, upper ash pipe is aggregated into, high energy mixers, slurry mixing tank and mud line manifold assembly, slurry mixing tank is at least connected with there are two high energy mixers, the inlet of slurry mixing tank is connect with diffusion chamber, diffusion chamber is connect with high energy mixers, and high energy mixers discharging is directed into slurry mixing tank by diffusion chamber, at least one diffusion chamber is connect with density control system.The utility model covers mixer more and integrates, with existing operating condition, it can be achieved that huge discharge, efficient mixed effect.
Description
Technical field
The utility model relates to petroleum equipment technical fields, more particularly to a kind of hybrid system of efficient well cementing operation.
Background technique
It is reported that oilfield applications drilling period was reduced to about half 75 days or so from 175 days;And U.S.'s shale gas is from 2013
Start in year just to have proposed effect 40%.With the raising of oilfield applications operating efficiency, the appearance of ultradeep well and curing sleeve distance
Increase, for example, horizontal segment can only accomplish 1000 meters in the past, buried depth can only accomplish 2500 meters, can accomplish to current horizontal segment
2500 meters, buried depth increases to more than 4300 meters, and such operation is to the well cementing operation demand of huge discharge it is also proposed that higher and higher wants
It asks.On the other hand, due to the limitation of field operation condition, for example, the quality of live dry ash, the factors such as speed and size for ash,
For the mixed of mixer generally in 1.5m3/min, operating efficiency is lower, and mixing discharge capacity is small, cannot achieve continuous operation.
Summary of the invention
The deficiency of the utility model in order to overcome the above technical problems provides a kind of mixed stocker of efficient well cementing operation
System, can be fully solved above-mentioned technical problem.
The technical solution for solving above-mentioned technical problem is as follows:
A kind of hybrid system of efficient well cementing operation, including measuring tank, water pipe are aggregated into, upper ash pipe is aggregated into, high energy
Mixer, slurry mixing tank and mud line manifold assembly, the slurry mixing tank are at least connected with there are two high energy mixers, the slurry mixing tank
Inlet connect with diffusion chamber, the diffusion chamber is connect with high energy mixers, and the high energy mixers discharge by spreading
Case is directed into slurry mixing tank, at least one diffusion chamber is connect with density control system.
The diffusion chamber is at least one.
Water pipe is aggregated into and is provided with injection centrifugal pump, y-type filter and clear water flow meter, clear water flow meter can be shown
The flow for showing clear water can adjust uninterrupted according to design requirement, keep mud mixing more equal according to the clear water flow of display
It is even.
The measuring tank includes the room A and the room B, and the room A and the room B can realize independent metering, can also two Room intercommunications, pass through discharge
Butterfly valve empties raffinate, and the discharge butterfly valve is pneumatic control, and strainer is arranged in the tank bottom exit of the measuring tank.Measuring tank
It can be with the discharge capacity of metering liquid and mixing water capacity, it can also be used to investment and batch mixed chemical addition agent.
The mud line manifold assembly includes circular centrifugal pump and perfusion centrifugal pump, and the circular centrifugal is pumped from slurry mixing tank
Middle sucking cement slurry, then by circular centrifugal pump discharge, circulation manifold, high energy mixers, in diffusion chamber with dry ash and
Water carries out secondary mixing, then cement slurry is discharged to completion secondary cycle slurry in slurry mixing tank, keeps cement slurry mixed effect more preferable, protects
It is uniform to demonstrate,prove cement slurry density;And centrifugal pump is perfused by being delivered in diffusion chamber after density control system, utilize density domination
Sensor in system tests actual density of the cement slurry by manifold, and measuring numerical value can directly show on the touchscreen,
It can be directly displayed on secondary meter.
The water pipe is aggregated into from measuring tank or external source sucking clear water, and the centrifugal pump that water pipe is aggregated into is more
Independent injection centrifugal pump is covered, clear water is delivered in high energy mixers after being aggregated into pressurization, summarizes with from upper ash pipe by water pipe
Tentatively mixed at the dry ash of entrance, but also with circulation manifold in mud carry out it is secondary mix, so as to more fill
Divide ground mixing mud.The clear water flow that can be measured using clear water flow meter can directly display on the touchscreen, according to test institute
Data are obtained, rotational handle adjusts clear water flow to suitable size, keeps mud mixing more uniform.Spray centrifugal pump simultaneously
The water source of certain pressure is provided for the post-job cleaning of vehicle, meets the needs of cleaning.
It is to provide the pipeline of solid carbon dioxide plaster for the hybrid system of efficient well cementing operation, including connect that the upper ash pipe, which is aggregated into,
Adapter tube line, upper grey sebific duct and ash discharging valve.The solid carbon dioxide plaster of ash can is connected to ash discharging valve, high energy mixers high speed by connecting pipeline
The water flow of injection forms vacuum suck solid carbon dioxide plaster and mixes with fluid.Mixed cement slurry agitated blade in cement stock tank
Further mixing, circular centrifugal pump realize the secondary and multiple mixing of cement slurry.Cement slurry density meter is by the true close of cement slurry
Degree feeds back to computer.Flowmeter is installed in injection line, the flow signal of water is fed back to computer by it.Computer root
The injection rate that solid carbon dioxide plaster and clear water are automatically controlled according to the cement slurry density and clear water flow collected, to reach setting
Cement slurry density value.
The high energy mixers by the clear water that entrance is aggregated by water pipe and the ash discharging valve being aggregated by upper ash pipe into
The concrete grey entered and the cement slurry by circulation manifold circulation are mixed together.High energy mixers are that entire slurry system is total
Core component in is the main component for carrying out mud mixture.
The beneficial effects of the utility model are:
The utility model provides a kind of hybrid system of efficient well cementing operation, and the mixers that cover integrated more, with existing work
Industry condition is, it can be achieved that huge discharge.The system can realize being quickly converted for automatic slurry and manual slurry, easy to operate practical.It is logical
It crosses and acquires and show the data such as several centrifugation pump pressures, density, discharge capacity and clear water flow, controlled by computer, realize density
It automatically controls.Purge valve, ash discharging valve are automatically controlled using bivariate, slurry mixing tank liquid automatic control.The utility model have with
Lower feature: coordinated control, i.e., multiple mixers, realization control respectively, can also jointly control;Hand automatically controls, i.e., multiple clear
Water valve, multiple ash discharging valves are realized and carry out hand automatic control respectively;Automatic distribution, i.e., it is to cover mixer more, cover purge valve and lower ash more
Valve realizes that a part is quickly adjusted, and a part fine tuning can also use multiple automatically controlled toggle switch, and controls simultaneously manually clear
Water valve or ash discharging valve movement, realize that density is adjusted simultaneously.
The utility model core is to promote mixed using multiple mixers and matched component, but still retains former
Some automatic premixings and automatic density slurry function.Well plate improved efficiency is drilled inside current industry to well cementation mixing to meet
The requirements at the higher level that ability proposes also successfully overcome the problems, such as that the various limitation bring mixed of field operation condition reduce.
For the utility model using more set mixers and matching component, clear water centrifugal pump both can be independently as injection centrifugation
Pump can also be used as side for waterside and spray centrifugal pump, and centrifugal pump can also be spare;Centrifugal slurry pump, both can be independently as following
Ring centrifugal pump can also be used as and centrifugal pump is perfused in circulation, and centrifugal pump can also be spare;More set hybrid systems can also be used as
It is spare, reduce hybrid system damage risk.
For the utility model using more set hybrid systems, construction operation scene needs to guarantee hybrid density unification and automatic control
System, to the utility model proposes another technological difficulties, therefore the utility model solves in the following ways: 1, realizing mixing
System water, ash are independent to be automatically controlled;2, multiple hybrid system schemes realize a density, and multiple mixers are simultaneously or separately controlled
System, reaches a density, the requirement of huge discharge.
The utility model solve be drilled inside current industry well plate improved efficiency to well cementation mixed propose more
High request also successfully overcomes the problems, such as that the various limitation bring mixed of field operation condition reduce, changes immediately following operation technique
Paces are improved into bring equipment, are the development of petroleum equipment field cementing equipment, the milestone new into one!
Detailed description of the invention
Utility model will be further described in detail below with reference to the attached drawings and specific embodiments.
The electric control theory schematic diagram that Fig. 1 is the utility model high energy mixers when being 2;
Fig. 2 is the flow diagram of the utility model embodiment 1;
Fig. 3 is the flow diagram of the utility model embodiment 2;
Fig. 4 is the flow diagram of the utility model embodiment 3;
In figure: 1 is aggregated into for water pipe, and 2 be circulation manifold, and 3 be mud line manifold assembly, and 4 are aggregated into for upper ash pipe, and C1 is
Centrifugal pump is sprayed, C2 is circular centrifugal pump, and C3 is perfusion centrifugal pump, and Y is y-type filter, and FM is clear water flow meter, and E is density
Control system, D1 are centering type ash discharging valve, and D2 is diffusion chamber, and D3 is high energy mixers.
Specific embodiment
Embodiment 1:
As shown in Fig. 2, a kind of hybrid system of efficient well cementing operation, including measuring tank, water pipe are aggregated into 1, upper ash pipe
It is aggregated into 4, high energy mixers D3, slurry mixing tank and mud line manifold assembly 3, there are two high energy mixers D3, slurries for slurry mixing tank connection
The inlet of tank is connect with diffusion chamber D2, and diffusion chamber D2 is connect with high energy mixers D3, and high energy mixers D3 discharges by diffusion chamber
D2 is directed into slurry mixing tank, and density control system E is concatenated on mud line manifold assembly 3.Diffusion chamber is two.
Water pipe, which is aggregated on 1, is provided with injection centrifugal pump C1, y-type filter Y and clear water flow meter FM, clear water flow meter
FM can show the flow of clear water, according to the clear water flow of display, can adjust uninterrupted according to design requirement, mix mud
It is more uniform.
Measuring tank includes the room A and the room B, and the room A and the room B can realize independent metering, can also two Room intercommunications, pass through discharge butterfly valve row
Empty raffinate, discharge butterfly valve are pneumatic control, and strainer is arranged in the tank bottom exit of measuring tank.Measuring tank can be with the discharge capacity of metering liquid
With mixing water capacity, it can also be used to investment and batch mixed chemical addition agent.
Mud line manifold assembly 3 includes circular centrifugal pump C2 and perfusion centrifugal pump C3, and circular centrifugal pump C2 is inhaled from slurry mixing tank
Enter cement slurry, C2 outlet, circulation manifold 2, high energy mixers D3 are then pumped by circular centrifugal, it is in diffusion chamber D2 and dry
Ash and water carry out secondary mixing, then cement slurry is discharged to completion secondary cycle slurry in slurry mixing tank, make cement slurry mixed effect more
It is good, guarantee that cement slurry density is uniform;And centrifugal pump C3 is perfused and is delivered in diffusion chamber D2 later by density control system E, benefit
Actual density of the cement slurry by manifold is tested with the sensor on density control system E, measuring numerical value can directly touch
Screen display can also directly display on secondary meter.
Water pipe is aggregated into 1 from measuring tank or external source sucking clear water, and the centrifugal pump that water pipe is aggregated into is two sets only
Clear water is delivered in high energy mixers D3 by vertical injection centrifugal pump C1, water pipe after being aggregated into 1 pressurization, and from upper grey manifold
Assembly 4 enter dry ash tentatively mixed, but also with circulation manifold 2 in mud progress it is secondary mix, so as to more
Add and is sufficiently mixed mud.The clear water flow that can be measured using clear water flow meter FM, can directly display on the touchscreen, according to
The data obtained is tested, rotational handle adjusts clear water flow to suitable size, keeps mud mixing more uniform.Spray centrifugal pump
C1 also provides the water source of certain pressure simultaneously for the post-job cleaning of vehicle, meets the needs of cleaning.
It is to provide the pipeline of solid carbon dioxide plaster, including connecting tube for the hybrid system of efficient well cementing operation that upper ash pipe, which is aggregated into 4,
Line, upper grey sebific duct and centering type ash discharging valve D1.The solid carbon dioxide plaster of ash can is connected to centering type ash valve D1, high energy by connecting pipeline
The water flow of mixer D3 high speed injection forms vacuum suck solid carbon dioxide plaster and mixes with fluid.Mixed cement slurry is in cement stock tank
In agitated blade further mix, circular centrifugal pump C2 realize cement slurry secondary and multiple mixing.Cement slurry density meter will
The real density of cement slurry feeds back to computer.Flowmeter is installed in injection line, it feeds back to the flow signal of water
Computer.Computer automatically controls the injection of solid carbon dioxide plaster and clear water according to the cement slurry density and clear water flow collected
Amount, to reach the cement slurry density value of setting.
High energy mixers D3 is by the clear water for being aggregated into 1 entrance by water pipe and the centering type ash discharging valve being aggregated by upper ash pipe
The concrete grey and mixed together by the cement slurry that circulation manifold 2 recycles that D1 enters.High energy mixers D3 is entire mixed
The core component in system synthesis is starched, is the main component for carrying out mud mixture.
Embodiment 2:
As shown in figure 3, a kind of hybrid system of efficient well cementing operation, including measuring tank, water pipe are aggregated into 1, upper ash pipe
It is aggregated into 4, high energy mixers D3, slurry mixing tank and mud line manifold assembly 3, there are two high energy mixers D3, slurries for slurry mixing tank connection
The inlet of tank is connect with diffusion chamber D2, and diffusion chamber D2 is connect with high energy mixers D3, and high energy mixers D3 discharges by diffusion chamber
D2 is directed into slurry mixing tank, is recycled and is serially connected with density control system E, diffusion chamber two on manifold 2 and mud line manifold assembly 3
It is a.
Water pipe, which is aggregated on 1, is provided with injection centrifugal pump C1, y-type filter Y and clear water flow meter FM, clear water flow meter
FM can show the flow of clear water, according to the clear water flow of display, can adjust uninterrupted according to design requirement, mix mud
It is more uniform.
Measuring tank includes the room A and the room B, and the room A and the room B can realize independent metering, can also two Room intercommunications, pass through discharge butterfly valve row
Empty raffinate, discharge butterfly valve are pneumatic control, and strainer is arranged in the tank bottom exit of measuring tank.Measuring tank can be with the discharge capacity of metering liquid
With mixing water capacity, it can also be used to investment and batch mixed chemical addition agent.
Mud line manifold assembly 3 includes circular centrifugal pump C2 and perfusion centrifugal pump C3, and circular centrifugal pump C2 is inhaled from slurry mixing tank
Enter cement slurry, C2 outlet, circulation manifold 2, high energy mixers D3 are then pumped by circular centrifugal, it is in diffusion chamber D2 and dry
Ash and water carry out secondary mixing, then cement slurry is discharged to completion secondary cycle slurry in slurry mixing tank, make cement slurry mixed effect more
It is good, guarantee that cement slurry density is uniform;And centrifugal pump C3 is perfused and is delivered in diffusion chamber D2 later by density control system E, benefit
Actual density of the cement slurry by manifold is tested with the sensor on density control system E, measuring numerical value can directly touch
Screen display can also directly display on secondary meter.
Water pipe is aggregated into 1 from measuring tank or external source sucking clear water, and the centrifugal pump that water pipe is aggregated into is two sets only
Clear water is delivered in high energy mixers D3 by vertical injection centrifugal pump C1, water pipe after being aggregated into 1 pressurization, and from upper grey manifold
Assembly 4 enter dry ash tentatively mixed, but also with circulation manifold 2 in mud progress it is secondary mix, so as to more
Add and is sufficiently mixed mud.The clear water flow that can be measured using clear water flow meter FM, can directly display on the touchscreen, according to
The data obtained is tested, rotational handle adjusts clear water flow to suitable size, keeps mud mixing more uniform.Spray centrifugal pump
C1 also provides the water source of certain pressure simultaneously for the post-job cleaning of vehicle, meets the needs of cleaning.
It is to provide the pipeline of solid carbon dioxide plaster, including connecting tube for the hybrid system of efficient well cementing operation that upper ash pipe, which is aggregated into 4,
Line, upper grey sebific duct and centering type ash discharging valve D1.The solid carbon dioxide plaster of ash can is connected to centering type ash valve D1, high energy by connecting pipeline
The water flow of mixer D3 high speed injection forms vacuum suck solid carbon dioxide plaster and mixes with fluid.Mixed cement slurry is in cement stock tank
In agitated blade further mix, circular centrifugal pump C2 realize cement slurry secondary and multiple mixing.Cement slurry density meter will
The real density of cement slurry feeds back to computer.Flowmeter is installed in injection line, it feeds back to the flow signal of water
Computer.Computer automatically controls the injection of solid carbon dioxide plaster and clear water according to the cement slurry density and clear water flow collected
Amount, to reach the cement slurry density value of setting.
High energy mixers D3 is by the clear water for being aggregated into 1 entrance by water pipe and the centering type ash discharging valve being aggregated by upper ash pipe
The concrete grey and mixed together by the cement slurry that circulation manifold 2 recycles that D1 enters.High energy mixers D3 is entire mixed
The core component in system synthesis is starched, is the main component for carrying out mud mixture.
Embodiment 3:
As shown in figure 4, a kind of hybrid system of efficient well cementing operation, including measuring tank, water pipe are aggregated into 1, upper ash pipe
It is aggregated into 4, high energy mixers D3, slurry mixing tank and mud line manifold assembly 3, there are two high energy mixers D3, slurries for slurry mixing tank connection
The inlet of tank is connect with diffusion chamber D2, and diffusion chamber D2 is connect with high energy mixers D3, and high energy mixers D3 discharges by diffusion chamber
D2 is directed into slurry mixing tank, and density control system E is concatenated on mud line manifold assembly 3.Diffusion chamber is one.
Water pipe, which is aggregated on 1, is provided with injection centrifugal pump C1, y-type filter Y and clear water flow meter FM, clear water flow meter
FM can show the flow of clear water, according to the clear water flow of display, can adjust uninterrupted according to design requirement, mix mud
It is more uniform.
Measuring tank includes the room A and the room B, and the room A and the room B can realize independent metering, can also two Room intercommunications, pass through discharge butterfly valve row
Empty raffinate, discharge butterfly valve are pneumatic control, and strainer is arranged in the tank bottom exit of measuring tank.Measuring tank can be with the discharge capacity of metering liquid
With mixing water capacity, it can also be used to investment and batch mixed chemical addition agent.
Mud line manifold assembly 3 includes circular centrifugal pump C2 and perfusion centrifugal pump C3, and circular centrifugal pump C2 is inhaled from slurry mixing tank
Enter cement slurry, C2 outlet, circulation manifold 2, high energy mixers D3 are then pumped by circular centrifugal, it is in diffusion chamber D2 and dry
Ash and water carry out secondary mixing, then cement slurry is discharged to completion secondary cycle slurry in slurry mixing tank, make cement slurry mixed effect more
It is good, guarantee that cement slurry density is uniform;And centrifugal pump C3 is perfused and is delivered in diffusion chamber D2 later by density control system E, benefit
Actual density of the cement slurry by manifold is tested with the sensor on density control system E, measuring numerical value can directly touch
Screen display can also directly display on secondary meter.
Water pipe is aggregated into 1 from measuring tank or external source sucking clear water, and the centrifugal pump that water pipe is aggregated into is two sets only
Clear water is delivered in high energy mixers D3 by vertical injection centrifugal pump C1, water pipe after being aggregated into 1 pressurization, and from upper grey manifold
Assembly 4 enter dry ash tentatively mixed, but also with circulation manifold 2 in mud progress it is secondary mix, so as to more
Add and is sufficiently mixed mud.The clear water flow that can be measured using clear water flow meter FM, can directly display on the touchscreen, according to
The data obtained is tested, rotational handle adjusts clear water flow to suitable size, keeps mud mixing more uniform.Spray centrifugal pump
C1 also provides the water source of certain pressure simultaneously for the post-job cleaning of vehicle, meets the needs of cleaning.
It is to provide the pipeline of solid carbon dioxide plaster, including connecting tube for the hybrid system of efficient well cementing operation that upper ash pipe, which is aggregated into 4,
Line, upper grey sebific duct and centering type ash discharging valve D1.The solid carbon dioxide plaster of ash can is connected to centering type ash valve D1, high energy by connecting pipeline
The water flow of mixer D3 high speed injection forms vacuum suck solid carbon dioxide plaster and mixes with fluid.Mixed cement slurry is in cement stock tank
In agitated blade further mix, circular centrifugal pump C2 realize cement slurry secondary and multiple mixing.Cement slurry density meter will
The real density of cement slurry feeds back to computer.Flowmeter is installed in injection line, it feeds back to the flow signal of water
Computer.Computer automatically controls the injection of solid carbon dioxide plaster and clear water according to the cement slurry density and clear water flow collected
Amount, to reach the cement slurry density value of setting.
High energy mixers D3 is by the clear water for being aggregated into 1 entrance by water pipe and the centering type ash discharging valve being aggregated by upper ash pipe
The concrete grey and mixed together by the cement slurry that circulation manifold 2 recycles that D1 enters.High energy mixers D3 is entire mixed
The core component in system synthesis is starched, is the main component for carrying out mud mixture.
The above is only the preferred embodiment of the utility model, not does limit in any form to the utility model
System, as expansion, needs for high energy mixers to be designed as 2 or more according to field operation, centrifugal pump is made accordingly as needed
Simple designs, equivalent variations or density control system are using multiple, and each road manifold carries out simple modification and equivalents are fallen
Enter within the protection scope of the utility model.
Claims (9)
1. a kind of hybrid system of efficient well cementing operation, including measuring tank, water pipe are aggregated into, upper ash pipe is aggregated into, high energy is mixed
Clutch, slurry mixing tank and mud line manifold assembly, which is characterized in that the slurry mixing tank is at least connected with there are two high energy mixers, institute
The inlet for the slurry mixing tank stated is connect with diffusion chamber, and the diffusion chamber is connect with high energy mixers, the high energy mixers
Discharging is directed into slurry mixing tank by diffusion chamber, at least one diffusion chamber is connect with density control system.
2. the hybrid system of efficient well cementing operation according to claim 1, which is characterized in that the diffusion chamber is at least
One.
3. the hybrid system of efficient well cementing operation according to claim 1, which is characterized in that the water pipe is aggregated into
On be provided with injection centrifugal pump, y-type filter, purge valve and clear water flow meter, clear water flow meter can show the flow of clear water,
According to the clear water flow of display, uninterrupted can be adjusted according to design requirement, keep mud mixing more uniform.
4. the hybrid system of efficient well cementing operation according to claim 1, which is characterized in that the measuring tank includes A
Room and the room B, the room A and the room B can realize independent metering, can also two Room intercommunications, pass through discharge butterfly valve empty raffinate, the discharge butterfly
Valve is pneumatic control, and strainer is arranged in the tank bottom exit of the measuring tank.
5. the hybrid system of efficient well cementing operation according to claim 1, which is characterized in that the mud line manifold assembly
Centrifugal pump is pumped and is perfused including circular centrifugal, and the circular centrifugal pump sucks cement slurry from slurry mixing tank, then passes through circulation
Be centrifuged pump discharge, circulation manifold, high energy mixers, carry out in diffusion chamber with dry ash and water it is secondary mix, then by cement slurry
It is discharged to completion secondary cycle slurry in slurry mixing tank, and centrifugal pump is perfused and is delivered in diffusion chamber later by density control system,
Actual density of the cement slurry by manifold is tested using the sensor on density control system.
6. the according to claim 1, hybrid system of efficient well cementing operation described in any one of 3 or 5, which is characterized in that described
Water pipe be aggregated into from measuring tank or external source sucking clear water, clear water is delivered in high energy mixers after pressurization, with from
The dry ash that upper ash pipe is aggregated into entrance is tentatively mixed, but also carries out secondary mix with the mud in circulation manifold.
7. the hybrid system of efficient well cementing operation according to claim 1, which is characterized in that the upper ash pipe is aggregated into
It is to provide the pipeline of solid carbon dioxide plaster, including connecting pipeline, upper grey sebific duct and ash discharging valve for the hybrid system of efficient well cementing operation.
8. the hybrid system of efficient well cementing operation according to claim 1 or claim 7, which is characterized in that the high energy mixing
Device is by the clear water for being aggregated into entrance by water pipe and the concrete grey entered by the ash discharging valve that upper ash pipe is aggregated into and by recycling
The cement slurry of manifold circulation is mixed together.
9. the hybrid system of efficient well cementing operation according to claim 1-5, which is characterized in that water pipe summarizes
At purge valve, the ash discharging valve that is aggregated into of upper ash pipe be all made of bivariate and automatically control, slurry mixing tank liquid level is using automatically controlling.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820667334.8U CN208576026U (en) | 2018-05-07 | 2018-05-07 | A kind of hybrid system of efficient well cementing operation |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820667334.8U CN208576026U (en) | 2018-05-07 | 2018-05-07 | A kind of hybrid system of efficient well cementing operation |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208576026U true CN208576026U (en) | 2019-03-05 |
Family
ID=65506749
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820667334.8U Active CN208576026U (en) | 2018-05-07 | 2018-05-07 | A kind of hybrid system of efficient well cementing operation |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208576026U (en) |
Cited By (35)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108687954A (en) * | 2018-05-07 | 2018-10-23 | 烟台杰瑞石油装备技术有限公司 | A kind of hybrid system of efficient well cementing operation |
CN110159225A (en) * | 2019-05-25 | 2019-08-23 | 烟台杰瑞石油装备技术有限公司 | A method of complete control of automatically cementing the well |
US10895202B1 (en) | 2019-09-13 | 2021-01-19 | Bj Energy Solutions, Llc | Direct drive unit removal system and associated methods |
US10907459B1 (en) | 2019-09-13 | 2021-02-02 | Bj Energy Solutions, Llc | Methods and systems for operating a fleet of pumps |
US10954770B1 (en) | 2020-06-09 | 2021-03-23 | Bj Energy Solutions, Llc | Systems and methods for exchanging fracturing components of a hydraulic fracturing unit |
US10961908B1 (en) | 2020-06-05 | 2021-03-30 | Bj Energy Solutions, Llc | Systems and methods to enhance intake air flow to a gas turbine engine of a hydraulic fracturing unit |
US10968837B1 (en) | 2020-05-14 | 2021-04-06 | Bj Energy Solutions, Llc | Systems and methods utilizing turbine compressor discharge for hydrostatic manifold purge |
US10989180B2 (en) | 2019-09-13 | 2021-04-27 | Bj Energy Solutions, Llc | Power sources and transmission networks for auxiliary equipment onboard hydraulic fracturing units and associated methods |
US11002189B2 (en) | 2019-09-13 | 2021-05-11 | Bj Energy Solutions, Llc | Mobile gas turbine inlet air conditioning system and associated methods |
US11015594B2 (en) | 2019-09-13 | 2021-05-25 | Bj Energy Solutions, Llc | Systems and method for use of single mass flywheel alongside torsional vibration damper assembly for single acting reciprocating pump |
US11015536B2 (en) | 2019-09-13 | 2021-05-25 | Bj Energy Solutions, Llc | Methods and systems for supplying fuel to gas turbine engines |
US11022526B1 (en) | 2020-06-09 | 2021-06-01 | Bj Energy Solutions, Llc | Systems and methods for monitoring a condition of a fracturing component section of a hydraulic fracturing unit |
US11028677B1 (en) | 2020-06-22 | 2021-06-08 | Bj Energy Solutions, Llc | Stage profiles for operations of hydraulic systems and associated methods |
US11066915B1 (en) | 2020-06-09 | 2021-07-20 | Bj Energy Solutions, Llc | Methods for detection and mitigation of well screen out |
US11109508B1 (en) | 2020-06-05 | 2021-08-31 | Bj Energy Solutions, Llc | Enclosure assembly for enhanced cooling of direct drive unit and related methods |
US11125066B1 (en) | 2020-06-22 | 2021-09-21 | Bj Energy Solutions, Llc | Systems and methods to operate a dual-shaft gas turbine engine for hydraulic fracturing |
US11149533B1 (en) | 2020-06-24 | 2021-10-19 | Bj Energy Solutions, Llc | Systems to monitor, detect, and/or intervene relative to cavitation and pulsation events during a hydraulic fracturing operation |
US11193361B1 (en) | 2020-07-17 | 2021-12-07 | Bj Energy Solutions, Llc | Methods, systems, and devices to enhance fracturing fluid delivery to subsurface formations during high-pressure fracturing operations |
US11208880B2 (en) | 2020-05-28 | 2021-12-28 | Bj Energy Solutions, Llc | Bi-fuel reciprocating engine to power direct drive turbine fracturing pumps onboard auxiliary systems and related methods |
US11208953B1 (en) | 2020-06-05 | 2021-12-28 | Bj Energy Solutions, Llc | Systems and methods to enhance intake air flow to a gas turbine engine of a hydraulic fracturing unit |
US11220895B1 (en) | 2020-06-24 | 2022-01-11 | Bj Energy Solutions, Llc | Automated diagnostics of electronic instrumentation in a system for fracturing a well and associated methods |
US11236739B2 (en) | 2019-09-13 | 2022-02-01 | Bj Energy Solutions, Llc | Power sources and transmission networks for auxiliary equipment onboard hydraulic fracturing units and associated methods |
US11268346B2 (en) | 2019-09-13 | 2022-03-08 | Bj Energy Solutions, Llc | Fuel, communications, and power connection systems |
US11408794B2 (en) | 2019-09-13 | 2022-08-09 | Bj Energy Solutions, Llc | Fuel, communications, and power connection systems and related methods |
US11415125B2 (en) | 2020-06-23 | 2022-08-16 | Bj Energy Solutions, Llc | Systems for utilization of a hydraulic fracturing unit profile to operate hydraulic fracturing units |
US11428165B2 (en) | 2020-05-15 | 2022-08-30 | Bj Energy Solutions, Llc | Onboard heater of auxiliary systems using exhaust gases and associated methods |
US11473413B2 (en) | 2020-06-23 | 2022-10-18 | Bj Energy Solutions, Llc | Systems and methods to autonomously operate hydraulic fracturing units |
US11560845B2 (en) | 2019-05-15 | 2023-01-24 | Bj Energy Solutions, Llc | Mobile gas turbine inlet air conditioning system and associated methods |
US11624326B2 (en) | 2017-05-21 | 2023-04-11 | Bj Energy Solutions, Llc | Methods and systems for supplying fuel to gas turbine engines |
US11635074B2 (en) | 2020-05-12 | 2023-04-25 | Bj Energy Solutions, Llc | Cover for fluid systems and related methods |
US11639654B2 (en) | 2021-05-24 | 2023-05-02 | Bj Energy Solutions, Llc | Hydraulic fracturing pumps to enhance flow of fracturing fluid into wellheads and related methods |
US11867118B2 (en) | 2019-09-13 | 2024-01-09 | Bj Energy Solutions, Llc | Methods and systems for supplying fuel to gas turbine engines |
US11933153B2 (en) | 2020-06-22 | 2024-03-19 | Bj Energy Solutions, Llc | Systems and methods to operate hydraulic fracturing units using automatic flow rate and/or pressure control |
US11939853B2 (en) | 2020-06-22 | 2024-03-26 | Bj Energy Solutions, Llc | Systems and methods providing a configurable staged rate increase function to operate hydraulic fracturing units |
US12065968B2 (en) | 2019-09-13 | 2024-08-20 | BJ Energy Solutions, Inc. | Systems and methods for hydraulic fracturing |
-
2018
- 2018-05-07 CN CN201820667334.8U patent/CN208576026U/en active Active
Cited By (136)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US11624326B2 (en) | 2017-05-21 | 2023-04-11 | Bj Energy Solutions, Llc | Methods and systems for supplying fuel to gas turbine engines |
CN108687954A (en) * | 2018-05-07 | 2018-10-23 | 烟台杰瑞石油装备技术有限公司 | A kind of hybrid system of efficient well cementing operation |
US11560845B2 (en) | 2019-05-15 | 2023-01-24 | Bj Energy Solutions, Llc | Mobile gas turbine inlet air conditioning system and associated methods |
CN110159225A (en) * | 2019-05-25 | 2019-08-23 | 烟台杰瑞石油装备技术有限公司 | A method of complete control of automatically cementing the well |
US11719234B2 (en) | 2019-09-13 | 2023-08-08 | Bj Energy Solutions, Llc | Systems and method for use of single mass flywheel alongside torsional vibration damper assembly for single acting reciprocating pump |
US10989180B2 (en) | 2019-09-13 | 2021-04-27 | Bj Energy Solutions, Llc | Power sources and transmission networks for auxiliary equipment onboard hydraulic fracturing units and associated methods |
US11655763B1 (en) | 2019-09-13 | 2023-05-23 | Bj Energy Solutions, Llc | Direct drive unit removal system and associated methods |
US10982596B1 (en) | 2019-09-13 | 2021-04-20 | Bj Energy Solutions, Llc | Direct drive unit removal system and associated methods |
US11649766B1 (en) | 2019-09-13 | 2023-05-16 | Bj Energy Solutions, Llc | Mobile gas turbine inlet air conditioning system and associated methods |
US11002189B2 (en) | 2019-09-13 | 2021-05-11 | Bj Energy Solutions, Llc | Mobile gas turbine inlet air conditioning system and associated methods |
US12049808B2 (en) | 2019-09-13 | 2024-07-30 | Bj Energy Solutions, Llc | Methods and systems for operating a fleet of pumps |
US11015594B2 (en) | 2019-09-13 | 2021-05-25 | Bj Energy Solutions, Llc | Systems and method for use of single mass flywheel alongside torsional vibration damper assembly for single acting reciprocating pump |
US11015536B2 (en) | 2019-09-13 | 2021-05-25 | Bj Energy Solutions, Llc | Methods and systems for supplying fuel to gas turbine engines |
US11971028B2 (en) | 2019-09-13 | 2024-04-30 | Bj Energy Solutions, Llc | Systems and method for use of single mass flywheel alongside torsional vibration damper assembly for single acting reciprocating pump |
US11401865B1 (en) | 2019-09-13 | 2022-08-02 | Bj Energy Solutions, Llc | Direct drive unit removal system and associated methods |
US11060455B1 (en) | 2019-09-13 | 2021-07-13 | Bj Energy Solutions, Llc | Mobile gas turbine inlet air conditioning system and associated methods |
US11867118B2 (en) | 2019-09-13 | 2024-01-09 | Bj Energy Solutions, Llc | Methods and systems for supplying fuel to gas turbine engines |
US11859482B2 (en) | 2019-09-13 | 2024-01-02 | Bj Energy Solutions, Llc | Power sources and transmission networks for auxiliary equipment onboard hydraulic fracturing units and associated methods |
US11092152B2 (en) | 2019-09-13 | 2021-08-17 | Bj Energy Solutions, Llc | Systems and method for use of single mass flywheel alongside torsional vibration damper assembly for single acting reciprocating pump |
US11460368B2 (en) | 2019-09-13 | 2022-10-04 | Bj Energy Solutions, Llc | Fuel, communications, and power connection systems and related methods |
US11767791B2 (en) | 2019-09-13 | 2023-09-26 | Bj Energy Solutions, Llc | Mobile gas turbine inlet air conditioning system and associated methods |
US11761846B2 (en) | 2019-09-13 | 2023-09-19 | Bj Energy Solutions, Llc | Fuel, communications, and power connection systems and related methods |
US11149726B1 (en) | 2019-09-13 | 2021-10-19 | Bj Energy Solutions, Llc | Systems and method for use of single mass flywheel alongside torsional vibration damper assembly for single acting reciprocating pump |
US11725583B2 (en) | 2019-09-13 | 2023-08-15 | Bj Energy Solutions, Llc | Mobile gas turbine inlet air conditioning system and associated methods |
US11156159B1 (en) | 2019-09-13 | 2021-10-26 | Bj Energy Solutions, Llc | Mobile gas turbine inlet air conditioning system and associated methods |
US11408794B2 (en) | 2019-09-13 | 2022-08-09 | Bj Energy Solutions, Llc | Fuel, communications, and power connection systems and related methods |
US11473997B2 (en) | 2019-09-13 | 2022-10-18 | Bj Energy Solutions, Llc | Fuel, communications, and power connection systems and related methods |
US12092100B2 (en) | 2019-09-13 | 2024-09-17 | Bj Energy Solutions, Llc | Systems and method for use of single mass flywheel alongside torsional vibration damper assembly for single acting reciprocating pump |
US11473503B1 (en) | 2019-09-13 | 2022-10-18 | Bj Energy Solutions, Llc | Direct drive unit removal system and associated methods |
US12065968B2 (en) | 2019-09-13 | 2024-08-20 | BJ Energy Solutions, Inc. | Systems and methods for hydraulic fracturing |
US11852001B2 (en) | 2019-09-13 | 2023-12-26 | Bj Energy Solutions, Llc | Methods and systems for operating a fleet of pumps |
US11629584B2 (en) | 2019-09-13 | 2023-04-18 | Bj Energy Solutions, Llc | Power sources and transmission networks for auxiliary equipment onboard hydraulic fracturing units and associated methods |
US11236739B2 (en) | 2019-09-13 | 2022-02-01 | Bj Energy Solutions, Llc | Power sources and transmission networks for auxiliary equipment onboard hydraulic fracturing units and associated methods |
US10907459B1 (en) | 2019-09-13 | 2021-02-02 | Bj Energy Solutions, Llc | Methods and systems for operating a fleet of pumps |
US11619122B2 (en) | 2019-09-13 | 2023-04-04 | Bj Energy Solutions, Llc | Methods and systems for operating a fleet of pumps |
US11613980B2 (en) | 2019-09-13 | 2023-03-28 | Bj Energy Solutions, Llc | Methods and systems for operating a fleet of pumps |
US11608725B2 (en) | 2019-09-13 | 2023-03-21 | Bj Energy Solutions, Llc | Methods and systems for operating a fleet of pumps |
US11268346B2 (en) | 2019-09-13 | 2022-03-08 | Bj Energy Solutions, Llc | Fuel, communications, and power connection systems |
US11604113B2 (en) | 2019-09-13 | 2023-03-14 | Bj Energy Solutions, Llc | Fuel, communications, and power connection systems and related methods |
US11280331B2 (en) | 2019-09-13 | 2022-03-22 | Bj Energy Solutions, Llc | Systems and method for use of single mass flywheel alongside torsional vibration damper assembly for single acting reciprocating pump |
US11280266B2 (en) | 2019-09-13 | 2022-03-22 | Bj Energy Solutions, Llc | Mobile gas turbine inlet air conditioning system and associated methods |
US11287350B2 (en) | 2019-09-13 | 2022-03-29 | Bj Energy Solutions, Llc | Fuel, communications, and power connection methods |
US11598263B2 (en) | 2019-09-13 | 2023-03-07 | Bj Energy Solutions, Llc | Mobile gas turbine inlet air conditioning system and associated methods |
US11578660B1 (en) | 2019-09-13 | 2023-02-14 | Bj Energy Solutions, Llc | Direct drive unit removal system and associated methods |
US10895202B1 (en) | 2019-09-13 | 2021-01-19 | Bj Energy Solutions, Llc | Direct drive unit removal system and associated methods |
US11555756B2 (en) | 2019-09-13 | 2023-01-17 | Bj Energy Solutions, Llc | Fuel, communications, and power connection systems and related methods |
US11319878B2 (en) | 2019-09-13 | 2022-05-03 | Bj Energy Solutions, Llc | Direct drive unit removal system and associated methods |
US11530602B2 (en) | 2019-09-13 | 2022-12-20 | Bj Energy Solutions, Llc | Power sources and transmission networks for auxiliary equipment onboard hydraulic fracturing units and associated methods |
US11346280B1 (en) | 2019-09-13 | 2022-05-31 | Bj Energy Solutions, Llc | Direct drive unit removal system and associated methods |
US11512642B1 (en) | 2019-09-13 | 2022-11-29 | Bj Energy Solutions, Llc | Direct drive unit removal system and associated methods |
US11708829B2 (en) | 2020-05-12 | 2023-07-25 | Bj Energy Solutions, Llc | Cover for fluid systems and related methods |
US11635074B2 (en) | 2020-05-12 | 2023-04-25 | Bj Energy Solutions, Llc | Cover for fluid systems and related methods |
US10968837B1 (en) | 2020-05-14 | 2021-04-06 | Bj Energy Solutions, Llc | Systems and methods utilizing turbine compressor discharge for hydrostatic manifold purge |
US11898504B2 (en) | 2020-05-14 | 2024-02-13 | Bj Energy Solutions, Llc | Systems and methods utilizing turbine compressor discharge for hydrostatic manifold purge |
US11698028B2 (en) | 2020-05-15 | 2023-07-11 | Bj Energy Solutions, Llc | Onboard heater of auxiliary systems using exhaust gases and associated methods |
US11542868B2 (en) | 2020-05-15 | 2023-01-03 | Bj Energy Solutions, Llc | Onboard heater of auxiliary systems using exhaust gases and associated methods |
US11624321B2 (en) | 2020-05-15 | 2023-04-11 | Bj Energy Solutions, Llc | Onboard heater of auxiliary systems using exhaust gases and associated methods |
US11428165B2 (en) | 2020-05-15 | 2022-08-30 | Bj Energy Solutions, Llc | Onboard heater of auxiliary systems using exhaust gases and associated methods |
US11434820B2 (en) | 2020-05-15 | 2022-09-06 | Bj Energy Solutions, Llc | Onboard heater of auxiliary systems using exhaust gases and associated methods |
US11959419B2 (en) | 2020-05-15 | 2024-04-16 | Bj Energy Solutions, Llc | Onboard heater of auxiliary systems using exhaust gases and associated methods |
US11208880B2 (en) | 2020-05-28 | 2021-12-28 | Bj Energy Solutions, Llc | Bi-fuel reciprocating engine to power direct drive turbine fracturing pumps onboard auxiliary systems and related methods |
US11603745B2 (en) | 2020-05-28 | 2023-03-14 | Bj Energy Solutions, Llc | Bi-fuel reciprocating engine to power direct drive turbine fracturing pumps onboard auxiliary systems and related methods |
US11814940B2 (en) | 2020-05-28 | 2023-11-14 | Bj Energy Solutions Llc | Bi-fuel reciprocating engine to power direct drive turbine fracturing pumps onboard auxiliary systems and related methods |
US11313213B2 (en) | 2020-05-28 | 2022-04-26 | Bj Energy Solutions, Llc | Bi-fuel reciprocating engine to power direct drive turbine fracturing pumps onboard auxiliary systems and related methods |
US11365616B1 (en) | 2020-05-28 | 2022-06-21 | Bj Energy Solutions, Llc | Bi-fuel reciprocating engine to power direct drive turbine fracturing pumps onboard auxiliary systems and related methods |
US11129295B1 (en) | 2020-06-05 | 2021-09-21 | Bj Energy Solutions, Llc | Enclosure assembly for enhanced cooling of direct drive unit and related methods |
US11109508B1 (en) | 2020-06-05 | 2021-08-31 | Bj Energy Solutions, Llc | Enclosure assembly for enhanced cooling of direct drive unit and related methods |
US11627683B2 (en) | 2020-06-05 | 2023-04-11 | Bj Energy Solutions, Llc | Enclosure assembly for enhanced cooling of direct drive unit and related methods |
US11208953B1 (en) | 2020-06-05 | 2021-12-28 | Bj Energy Solutions, Llc | Systems and methods to enhance intake air flow to a gas turbine engine of a hydraulic fracturing unit |
US10961908B1 (en) | 2020-06-05 | 2021-03-30 | Bj Energy Solutions, Llc | Systems and methods to enhance intake air flow to a gas turbine engine of a hydraulic fracturing unit |
US11723171B2 (en) | 2020-06-05 | 2023-08-08 | Bj Energy Solutions, Llc | Enclosure assembly for enhanced cooling of direct drive unit and related methods |
US11746698B2 (en) | 2020-06-05 | 2023-09-05 | Bj Energy Solutions, Llc | Systems and methods to enhance intake air flow to a gas turbine engine of a hydraulic fracturing unit |
US11598264B2 (en) | 2020-06-05 | 2023-03-07 | Bj Energy Solutions, Llc | Systems and methods to enhance intake air flow to a gas turbine engine of a hydraulic fracturing unit |
US11378008B2 (en) | 2020-06-05 | 2022-07-05 | Bj Energy Solutions, Llc | Systems and methods to enhance intake air flow to a gas turbine engine of a hydraulic fracturing unit |
US11891952B2 (en) | 2020-06-05 | 2024-02-06 | Bj Energy Solutions, Llc | Systems and methods to enhance intake air flow to a gas turbine engine of a hydraulic fracturing unit |
US11300050B2 (en) | 2020-06-05 | 2022-04-12 | Bj Energy Solutions, Llc | Systems and methods to enhance intake air flow to a gas turbine engine of a hydraulic fracturing unit |
US11022526B1 (en) | 2020-06-09 | 2021-06-01 | Bj Energy Solutions, Llc | Systems and methods for monitoring a condition of a fracturing component section of a hydraulic fracturing unit |
US11939854B2 (en) | 2020-06-09 | 2024-03-26 | Bj Energy Solutions, Llc | Methods for detection and mitigation of well screen out |
US11566506B2 (en) | 2020-06-09 | 2023-01-31 | Bj Energy Solutions, Llc | Methods for detection and mitigation of well screen out |
US11629583B2 (en) | 2020-06-09 | 2023-04-18 | Bj Energy Solutions, Llc | Systems and methods for exchanging fracturing components of a hydraulic fracturing unit |
US11319791B2 (en) | 2020-06-09 | 2022-05-03 | Bj Energy Solutions, Llc | Methods and systems for detection and mitigation of well screen out |
US11066915B1 (en) | 2020-06-09 | 2021-07-20 | Bj Energy Solutions, Llc | Methods for detection and mitigation of well screen out |
US11015423B1 (en) | 2020-06-09 | 2021-05-25 | Bj Energy Solutions, Llc | Systems and methods for exchanging fracturing components of a hydraulic fracturing unit |
US11085281B1 (en) | 2020-06-09 | 2021-08-10 | Bj Energy Solutions, Llc | Systems and methods for exchanging fracturing components of a hydraulic fracturing unit |
US11261717B2 (en) | 2020-06-09 | 2022-03-01 | Bj Energy Solutions, Llc | Systems and methods for exchanging fracturing components of a hydraulic fracturing unit |
US11339638B1 (en) | 2020-06-09 | 2022-05-24 | Bj Energy Solutions, Llc | Systems and methods for exchanging fracturing components of a hydraulic fracturing unit |
US11208881B1 (en) | 2020-06-09 | 2021-12-28 | Bj Energy Solutions, Llc | Methods and systems for detection and mitigation of well screen out |
US11512570B2 (en) | 2020-06-09 | 2022-11-29 | Bj Energy Solutions, Llc | Systems and methods for exchanging fracturing components of a hydraulic fracturing unit |
US11867046B2 (en) | 2020-06-09 | 2024-01-09 | Bj Energy Solutions, Llc | Systems and methods for exchanging fracturing components of a hydraulic fracturing unit |
US10954770B1 (en) | 2020-06-09 | 2021-03-23 | Bj Energy Solutions, Llc | Systems and methods for exchanging fracturing components of a hydraulic fracturing unit |
US11572774B2 (en) | 2020-06-22 | 2023-02-07 | Bj Energy Solutions, Llc | Systems and methods to operate a dual-shaft gas turbine engine for hydraulic fracturing |
US11933153B2 (en) | 2020-06-22 | 2024-03-19 | Bj Energy Solutions, Llc | Systems and methods to operate hydraulic fracturing units using automatic flow rate and/or pressure control |
US11236598B1 (en) | 2020-06-22 | 2022-02-01 | Bj Energy Solutions, Llc | Stage profiles for operations of hydraulic systems and associated methods |
US11952878B2 (en) | 2020-06-22 | 2024-04-09 | Bj Energy Solutions, Llc | Stage profiles for operations of hydraulic systems and associated methods |
US11939853B2 (en) | 2020-06-22 | 2024-03-26 | Bj Energy Solutions, Llc | Systems and methods providing a configurable staged rate increase function to operate hydraulic fracturing units |
US11639655B2 (en) | 2020-06-22 | 2023-05-02 | Bj Energy Solutions, Llc | Systems and methods to operate a dual-shaft gas turbine engine for hydraulic fracturing |
US11028677B1 (en) | 2020-06-22 | 2021-06-08 | Bj Energy Solutions, Llc | Stage profiles for operations of hydraulic systems and associated methods |
US11208879B1 (en) | 2020-06-22 | 2021-12-28 | Bj Energy Solutions, Llc | Stage profiles for operations of hydraulic systems and associated methods |
US11898429B2 (en) | 2020-06-22 | 2024-02-13 | Bj Energy Solutions, Llc | Systems and methods to operate a dual-shaft gas turbine engine for hydraulic fracturing |
US11408263B2 (en) | 2020-06-22 | 2022-08-09 | Bj Energy Solutions, Llc | Systems and methods to operate a dual-shaft gas turbine engine for hydraulic fracturing |
US11598188B2 (en) | 2020-06-22 | 2023-03-07 | Bj Energy Solutions, Llc | Stage profiles for operations of hydraulic systems and associated methods |
US11125066B1 (en) | 2020-06-22 | 2021-09-21 | Bj Energy Solutions, Llc | Systems and methods to operate a dual-shaft gas turbine engine for hydraulic fracturing |
US11732565B2 (en) | 2020-06-22 | 2023-08-22 | Bj Energy Solutions, Llc | Systems and methods to operate a dual-shaft gas turbine engine for hydraulic fracturing |
US11661832B2 (en) | 2020-06-23 | 2023-05-30 | Bj Energy Solutions, Llc | Systems and methods to autonomously operate hydraulic fracturing units |
US11415125B2 (en) | 2020-06-23 | 2022-08-16 | Bj Energy Solutions, Llc | Systems for utilization of a hydraulic fracturing unit profile to operate hydraulic fracturing units |
US11719085B1 (en) | 2020-06-23 | 2023-08-08 | Bj Energy Solutions, Llc | Systems and methods to autonomously operate hydraulic fracturing units |
US12065917B2 (en) | 2020-06-23 | 2024-08-20 | Bj Energy Solutions, Llc | Systems and methods to autonomously operate hydraulic fracturing units |
US11428218B2 (en) | 2020-06-23 | 2022-08-30 | Bj Energy Solutions, Llc | Systems and methods of utilization of a hydraulic fracturing unit profile to operate hydraulic fracturing units |
US11466680B2 (en) | 2020-06-23 | 2022-10-11 | Bj Energy Solutions, Llc | Systems and methods of utilization of a hydraulic fracturing unit profile to operate hydraulic fracturing units |
US11473413B2 (en) | 2020-06-23 | 2022-10-18 | Bj Energy Solutions, Llc | Systems and methods to autonomously operate hydraulic fracturing units |
US11939974B2 (en) | 2020-06-23 | 2024-03-26 | Bj Energy Solutions, Llc | Systems and methods of utilization of a hydraulic fracturing unit profile to operate hydraulic fracturing units |
US11649820B2 (en) | 2020-06-23 | 2023-05-16 | Bj Energy Solutions, Llc | Systems and methods of utilization of a hydraulic fracturing unit profile to operate hydraulic fracturing units |
US11566505B2 (en) | 2020-06-23 | 2023-01-31 | Bj Energy Solutions, Llc | Systems and methods to autonomously operate hydraulic fracturing units |
US11274537B2 (en) | 2020-06-24 | 2022-03-15 | Bj Energy Solutions, Llc | Method to detect and intervene relative to cavitation and pulsation events during a hydraulic fracturing operation |
US11506040B2 (en) | 2020-06-24 | 2022-11-22 | Bj Energy Solutions, Llc | Automated diagnostics of electronic instrumentation in a system for fracturing a well and associated methods |
US11668175B2 (en) | 2020-06-24 | 2023-06-06 | Bj Energy Solutions, Llc | Automated diagnostics of electronic instrumentation in a system for fracturing a well and associated methods |
US11692422B2 (en) | 2020-06-24 | 2023-07-04 | Bj Energy Solutions, Llc | System to monitor cavitation or pulsation events during a hydraulic fracturing operation |
US11149533B1 (en) | 2020-06-24 | 2021-10-19 | Bj Energy Solutions, Llc | Systems to monitor, detect, and/or intervene relative to cavitation and pulsation events during a hydraulic fracturing operation |
US11542802B2 (en) | 2020-06-24 | 2023-01-03 | Bj Energy Solutions, Llc | Hydraulic fracturing control assembly to detect pump cavitation or pulsation |
US11299971B2 (en) | 2020-06-24 | 2022-04-12 | Bj Energy Solutions, Llc | System of controlling a hydraulic fracturing pump or blender using cavitation or pulsation detection |
US11512571B2 (en) | 2020-06-24 | 2022-11-29 | Bj Energy Solutions, Llc | Automated diagnostics of electronic instrumentation in a system for fracturing a well and associated methods |
US11391137B2 (en) | 2020-06-24 | 2022-07-19 | Bj Energy Solutions, Llc | Systems and methods to monitor, detect, and/or intervene relative to cavitation and pulsation events during a hydraulic fracturing operation |
US11255174B2 (en) | 2020-06-24 | 2022-02-22 | Bj Energy Solutions, Llc | Automated diagnostics of electronic instrumentation in a system for fracturing a well and associated methods |
US11746638B2 (en) | 2020-06-24 | 2023-09-05 | Bj Energy Solutions, Llc | Automated diagnostics of electronic instrumentation in a system for fracturing a well and associated methods |
US11220895B1 (en) | 2020-06-24 | 2022-01-11 | Bj Energy Solutions, Llc | Automated diagnostics of electronic instrumentation in a system for fracturing a well and associated methods |
US11365615B2 (en) | 2020-07-17 | 2022-06-21 | Bj Energy Solutions, Llc | Methods, systems, and devices to enhance fracturing fluid delivery to subsurface formations during high-pressure fracturing operations |
US11920450B2 (en) | 2020-07-17 | 2024-03-05 | Bj Energy Solutions, Llc | Methods, systems, and devices to enhance fracturing fluid delivery to subsurface formations during high-pressure fracturing operations |
US11193360B1 (en) | 2020-07-17 | 2021-12-07 | Bj Energy Solutions, Llc | Methods, systems, and devices to enhance fracturing fluid delivery to subsurface formations during high-pressure fracturing operations |
US11608727B2 (en) | 2020-07-17 | 2023-03-21 | Bj Energy Solutions, Llc | Methods, systems, and devices to enhance fracturing fluid delivery to subsurface formations during high-pressure fracturing operations |
US11994014B2 (en) | 2020-07-17 | 2024-05-28 | Bj Energy Solutions, Llc | Methods, systems, and devices to enhance fracturing fluid delivery to subsurface formations during high-pressure fracturing operations |
US11255175B1 (en) | 2020-07-17 | 2022-02-22 | Bj Energy Solutions, Llc | Methods, systems, and devices to enhance fracturing fluid delivery to subsurface formations during high-pressure fracturing operations |
US11193361B1 (en) | 2020-07-17 | 2021-12-07 | Bj Energy Solutions, Llc | Methods, systems, and devices to enhance fracturing fluid delivery to subsurface formations during high-pressure fracturing operations |
US11603744B2 (en) | 2020-07-17 | 2023-03-14 | Bj Energy Solutions, Llc | Methods, systems, and devices to enhance fracturing fluid delivery to subsurface formations during high-pressure fracturing operations |
US11639654B2 (en) | 2021-05-24 | 2023-05-02 | Bj Energy Solutions, Llc | Hydraulic fracturing pumps to enhance flow of fracturing fluid into wellheads and related methods |
US11732563B2 (en) | 2021-05-24 | 2023-08-22 | Bj Energy Solutions, Llc | Hydraulic fracturing pumps to enhance flow of fracturing fluid into wellheads and related methods |
US11867045B2 (en) | 2021-05-24 | 2024-01-09 | Bj Energy Solutions, Llc | Hydraulic fracturing pumps to enhance flow of fracturing fluid into wellheads and related methods |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN208576026U (en) | A kind of hybrid system of efficient well cementing operation | |
CN108687954A (en) | A kind of hybrid system of efficient well cementing operation | |
RU2400296C1 (en) | Method of continuous cement mortar batch mixing | |
CN210948703U (en) | Double-liquid mixed grouting preparation system | |
CN203990481U (en) | Polymer negative pressure suction dispersal device | |
CN110671130A (en) | Operation method of double-liquid mixed grouting preparation system | |
US20190233275A1 (en) | Method and apparatus for metering flow during centralized well treatment | |
CN206937600U (en) | The double mixing type fluid delivery systems of one kind well cementation pump sledge | |
CN102345454B (en) | Fracturing fluid jet mixer | |
CN108593522A (en) | Automatic online labeling water purification filter element test line and labeling method | |
CN209724309U (en) | A kind of online filling apparatus of slippery water powder drag reducer | |
CN111831015A (en) | Skid-mounted liquid additive accurate adding device and method | |
CN208777312U (en) | It is a kind of to handle backstage for starching and returning slurry automatically | |
CN103939743B (en) | The Slurry Pipeline Transportation system of a kind of low abrasion and carrying method | |
CN207169441U (en) | Polymer dissolving device | |
CN106337678B (en) | The electronic mulling sled of double pump | |
CN216870286U (en) | Test device for testing shield construction double-slurry initial setting time | |
CN109379962A (en) | A kind of preceding fertilizer apparatus of water-fertilizer integral pump | |
CN202133915U (en) | Fully-automatic self-operated solution blending device | |
CN208493854U (en) | It is a kind of to use negative pressure of vacuum principle mixing cleaning solution, the device of water and air | |
CN210868737U (en) | Fertilizer applying device | |
CN212433636U (en) | Skid-mounted liquid additive accurate adding device | |
CN109306858A (en) | Polymer injection well online concentration device and method | |
CN209727670U (en) | A kind of system for simulating downhole erosion environment | |
CN209596951U (en) | One kind quickly mixing new device for oil field equipment siccative |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |