CN208566729U - A kind of smoke cooling tower with flue dust collecting function - Google Patents

A kind of smoke cooling tower with flue dust collecting function Download PDF

Info

Publication number
CN208566729U
CN208566729U CN201820870674.0U CN201820870674U CN208566729U CN 208566729 U CN208566729 U CN 208566729U CN 201820870674 U CN201820870674 U CN 201820870674U CN 208566729 U CN208566729 U CN 208566729U
Authority
CN
China
Prior art keywords
cooling chamber
condenser
cooling
fixedly connected
flue dust
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820870674.0U
Other languages
Chinese (zh)
Inventor
阮帅
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Aosua Refrigeration Co Ltd
Original Assignee
Zhejiang Aosua Refrigeration Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Aosua Refrigeration Co Ltd filed Critical Zhejiang Aosua Refrigeration Co Ltd
Priority to CN201820870674.0U priority Critical patent/CN208566729U/en
Application granted granted Critical
Publication of CN208566729U publication Critical patent/CN208566729U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Heat-Exchange Devices With Radiators And Conduit Assemblies (AREA)

Abstract

The utility model relates to industrial cooling tower technical fields, and disclose a kind of smoke cooling tower with flue dust collecting function, including tower body, admission line is fixedly connected at the top of the tower body, the tower body is internally provided with the first cooling chamber, the two sides inner wall of first cooling chamber is fixedly connected to the first condenser, the side of first condenser is fixedly connected with the first condenser pipe, first condenser pipe runs through the first cooling chamber and extends to the outside of tower body, exhaust fan is fixedly connected at the top of first cooling chamber, the intake stack of the exhaust fan runs through and extends to the inside of the first cooling chamber.The smoke cooling tower with flue dust collecting function, flue dust inside cooling chamber can be collected, then flue dust is adsorbed by water, to reach the effect to flue dust collecting, secondary cooling, to increase the cooling effect of the cooling tower, to increase the working efficiency of people, the cost of people's post-processing is reduced.

Description

A kind of smoke cooling tower with flue dust collecting function
Technical field
The utility model relates to industrial cooling tower technical field, specially a kind of flue gas with flue dust collecting function is cooling Tower.
Background technique
Cooling tower be thermal power plant, nuclear power station secondary cycle water gravity-flow ventilation cooling system a kind of important building.Cigarette Air cooling tower is a kind of relatively conventional industrial equipment, is widely used, and cooling is by the cold of conveying coolant liquid in the prior art But pipe carries out contacting realization cooling with flue gas.But it since the high-temp solid impurity in flue gas directly contacts cooling tube, easily corrodes Cooling tube and the abrasion for causing cooling tube, and cooling efficiency is not high, the solid impurity temperature of usual exhaust outlet is still preferable, can not Reach discharge standard, cause when next stage being filtered processing, is easy to cause fire, cause damages, so needing to cigarette Dust in gas is handled, and can be only achieved discharge standard, in flue gas dust processing after, how to collect dust again at The a great problem of people, people are typically all to pass through water to adsorb flue dust, are then discharged out, although can arrange to a certain extent in this way Certain dust out, if but dust be adhered in cooling tower, will lead to cooling tower working efficiency reduce, influence people's Normal use.
Utility model content
(1) the technical issues of solving
In view of the deficiencies of the prior art, the utility model provides a kind of smoke cooling tower with flue dust collecting function, If solving dust to be adhered in cooling tower, the working efficiency that will lead to cooling tower is reduced, and influences asking for people's normal use Topic.
(2) technical solution
To achieve the above object, the utility model provides the following technical solutions: a kind of flue gas with flue dust collecting function Cooling tower, including tower body, are fixedly connected with admission line at the top of the tower body, the tower body to be internally provided with first cooling Room, the two sides inner wall of first cooling chamber are fixedly connected to the first condenser, and the side of first condenser is fixed to be connected It is connected to the first condenser pipe, first condenser pipe runs through the first cooling chamber and extends to the outside of tower body, first cooling chamber Top be fixedly connected with exhaust fan, the intake stack of the exhaust fan runs through and extends to the inside of the first cooling chamber, described The wind pipe of exhaust fan is fixedly connected with water storage box, and the side of the water storage box is fixedly connected sequentially has water inlet pipe from top to bottom Road and outlet conduit, the other side of the water storage box are fixedly connected with outlet pipe, and the bottom of first cooling chamber is fixed to be connected It is connected to the second cooling chamber, the two sides inner wall of second cooling chamber is fixedly connected to the second condenser, second condenser Side be fixedly connected with the second condenser pipe, second condenser pipe is through the second cooling chamber and extends to the outside of tower body, institute Outlet pipe is stated through tower body and extends to the inside of the second cooling chamber, the side of second cooling chamber is fixedly connected with exhaust Pipeline.
Preferably, the junction of the admission line, outlet pipe and exhaust pipe and tower body is provided with sealing ring, institute Stating sealing ring is rubber seal.
Preferably, the quantity of first condenser is four, and the first condenser of every two is one group, and two group first cold Condenser is symmetricly set on the inside of the first cooling chamber.
Preferably, the quantity of second condenser is four, and the second condenser of every two is one group, and two group second cold Condenser is symmetricly set on the inside of the second cooling chamber.
Preferably, it is provided with valve on the water inlet line and outlet conduit, and valve is high pressure valve.
Preferably, the shape of first cooling chamber and the second cooling chamber is mutually matched, and the first cooling chamber and second cold But the volume of room is identical.
Preferably, the inner sidewall of the wind pipe of the intake stack and exhaust fan of the exhaust fan is fixedly connected to protection Film, the protecting film are plastic protection film.
(3) beneficial effect
Compared with prior art, the utility model provides a kind of smoke cooling tower with flue dust collecting function, has Below the utility model has the advantages that
1, the smoke cooling tower with flue dust collecting function passes through the first cooling chamber of setting, the first condenser and One condenser pipe effectively can carry out cooling treatment to the air entered inside the first cooling chamber, by the exhaust fan of setting, store Flue dust inside first cooling chamber can be collected, then be inhaled flue dust by water by water tank, inlet and outlet pipes It is attached, to achieve the effect that flue dust collecting.
2, the smoke cooling tower with flue dust collecting function passes through the second cooling chamber of setting, the second condenser and Two condenser pipes can carry out secondary cooling to the air entered inside the second cooling chamber, to increase the cooling of the cooling tower Effect reduces the cost of people's post-processing to increase the working efficiency of people.
Detailed description of the invention
FIG. 1 is a schematic structural view of the utility model;
Fig. 2 is the utility model protecting film structure schematic diagram.
In figure: 1 tower body, 2 admission lines, 3 first cooling chambers, 4 first condensers, 5 first condenser pipes, 6 exhaust fans, 7 store Water tank, 8 water inlet lines, 9 outlet pipes, 10 second cooling chambers, 11 second condensers, 12 second condenser pipes, 13 valves, 14 exhausts Pipeline, 15 sealing rings, 16 outlet conduits, 17 protecting films.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work Every other embodiment obtained, fall within the protection scope of the utility model.
The top of a kind of smoke cooling tower with flue dust collecting function referring to FIG. 1-2, including tower body 1, tower body 1 is solid Surely it is connected with admission line 2, tower body 1 is internally provided with the first cooling chamber 3, and the two sides inner wall of the first cooling chamber 3 is fixed to be connected It is connected to the first condenser 4, the quantity of the first condenser 4 is four, and the first condenser of every two 4 is one group, and two group first cold Condenser 4 is symmetricly set on the inside of the first cooling chamber 3, and the side of the first condenser 4 is fixedly connected with the first condenser pipe 5, and first Condenser pipe 5 runs through the first cooling chamber 3 and extends to the outside of tower body 1, passes through the first cooling chamber 3 of setting, the first condenser 4 With the first condenser pipe 5, cooling treatment effectively can be carried out to the air entered inside the first cooling chamber 3, the first cooling chamber 3 Top is fixedly connected with exhaust fan 6, and the intake stack of exhaust fan 6 runs through and extends to the inside of the first cooling chamber 3, exhaust fan 6 Intake stack and the inner sidewall of wind pipe of exhaust fan 6 be fixedly connected to protecting film 17, protecting film 17 is plastic protection Film, the wind pipe of exhaust fan 6 are fixedly connected with water storage box 7, and the side of water storage box 7 is fixedly connected sequentially from top to bottom to be had into water Valve 13 is provided on pipeline 8 and outlet conduit 16, water inlet line 8 and outlet conduit 16, and valve 13 is high pressure valve, is led to Exhaust fan 6, water storage box 7, water inlet line 8 and the outlet conduit 16 for crossing setting, can carry out the flue dust inside the first cooling chamber 3 It collects, is then adsorbed flue dust by water, to achieve the effect that, to flue dust collecting, the other side of water storage box 7 is fixedly connected with Outlet pipe 9, the bottom of the first cooling chamber 3 are fixedly connected with the second cooling chamber 10, the first cooling chamber 3 and the second cooling chamber 10 Shape is mutually matched, and the first cooling chamber 3 is identical as the volume of the second cooling chamber 10, and the two sides inner wall of the second cooling chamber 10 is solid Surely it is connected with the second condenser 11, the quantity of the second condenser 11 is four, and the second condenser of every two 11 is one group, two The second condenser 11 of group is symmetricly set on the inside of the second cooling chamber 10, and it is cold that the side of the second condenser 11 is fixedly connected with second Solidifying pipe 12, the second condenser pipe 12 run through the second cooling chamber 10 and extend to the outside of tower body 1, pass through the second cooling chamber of setting 10, the second condenser 11 and the second condenser pipe 12 can carry out secondary cooling to the air entered inside the second cooling chamber 10, from And the cooling effect of the cooling tower is increased, to increase the working efficiency of people, the cost of people's post-processing is reduced, Outlet pipe 9 runs through tower body 1 and extends to the inside of the second cooling chamber 10, and the side of the second cooling chamber 10 is fixedly connected with exhaust The junction of pipeline 14, admission line 2, outlet pipe 9 and exhaust pipe 14 and tower body 1 is provided with sealing ring 15, sealing ring 15 be rubber seal.
The electric elements occurred in this article are electrically connected with extraneous main controller and 220V alternating current, and main controller can be meter Calculation machine etc. plays the conventionally known equipment of control.
In conclusion this has the smoke cooling tower of flue dust collecting function, it is cold by the first cooling chamber 3, first of setting Condenser 4 and the first condenser pipe 5 effectively can carry out cooling treatment to the air entered inside the first cooling chamber 3, pass through setting Exhaust fan 6, water storage box 7, water inlet line 8 and outlet conduit 16, the flue dust inside the first cooling chamber 3 can be collected, Then flue dust is adsorbed by water, to achieve the effect that condense flue dust collecting by the second cooling chamber 10, second of setting Device 11 and the second condenser pipe 12 can carry out secondary cooling to the air entered inside the second cooling chamber 10, to increase this The cooling effect of cooling tower reduces the cost of people's post-processing to increase the working efficiency of people.
It should be noted that, in this document, relational terms such as first and second and the like are used merely to a reality Body or operation are distinguished with another entity or operation, are deposited without necessarily requiring or implying between these entities or operation In any actual relationship or order or sequence.Moreover, the terms "include", "comprise" or its any other variant are intended to Non-exclusive inclusion, so that the process, method, article or equipment including a series of elements is not only wanted including those Element, but also including other elements that are not explicitly listed, or further include for this process, method, article or equipment Intrinsic element.
While there has been shown and described that the embodiments of the present invention, for the ordinary skill in the art, It is understood that these embodiments can be carried out with a variety of variations in the case where not departing from the principles of the present invention and spirit, repaired Change, replacement and variant, the scope of the utility model is defined by the appended claims and the equivalents thereof.

Claims (7)

1. a kind of smoke cooling tower with flue dust collecting function, including tower body (1), it is characterised in that: the top of the tower body (1) Portion is fixedly connected with admission line (2), and the tower body (1) is internally provided with the first cooling chamber (3), first cooling chamber (3) two sides inner wall is fixedly connected to the first condenser (4), and the side of first condenser (4) is fixedly connected with first Condenser pipe (5), first condenser pipe (5) run through the first cooling chamber (3) and extend to the outside of tower body (1), and described first is cold But it is fixedly connected with exhaust fan (6) at the top of room (3), the intake stack of the exhaust fan (6) runs through and extends to the first cooling The wind pipe of the inside of room (3), the exhaust fan (6) is fixedly connected with water storage box (7), the side of the water storage box (7) from Top to bottm, which is fixedly connected sequentially, water inlet line (8) and outlet conduit (16), and the other side of the water storage box (7) is fixedly connected with The bottom of outlet pipe (9), first cooling chamber (3) is fixedly connected with the second cooling chamber (10), second cooling chamber (10) two sides inner wall is fixedly connected to the second condenser (11), and the side of second condenser (11) is fixedly connected with Two condenser pipes (12), second condenser pipe (12) is through the second cooling chamber (10) and extends to the outside of tower body (1), it is described go out Feed channel (9) runs through tower body (1) and extends to the inside of the second cooling chamber (10), and the side of second cooling chamber (10) is fixed It is connected with exhaust pipe (14).
2. a kind of smoke cooling tower with flue dust collecting function according to claim 1, it is characterised in that: the air inlet The junction of pipeline (2), outlet pipe (9) and exhaust pipe (14) and tower body (1) is provided with sealing ring (15), the sealing Enclosing (15) is rubber seal.
3. a kind of smoke cooling tower with flue dust collecting function according to claim 1, it is characterised in that: described first The quantity of condenser (4) is four, and the first condenser of every two (4) is one group, and two group of first condenser (4) is symmetricly set on The inside of first cooling chamber (3).
4. a kind of smoke cooling tower with flue dust collecting function according to claim 1, it is characterised in that: described second The quantity of condenser (11) is four, and the second condenser of every two (11) is one group, and two group of second condenser (11) symmetrically sets Set the inside in the second cooling chamber (10).
5. a kind of smoke cooling tower with flue dust collecting function according to claim 1, it is characterised in that: the water inlet It is provided with valve (13) on pipeline (8) and outlet conduit (16), and valve (13) is high pressure valve.
6. a kind of smoke cooling tower with flue dust collecting function according to claim 1, it is characterised in that: described first Cooling chamber (3) and the shape of the second cooling chamber (10) are mutually matched, and the volume of the first cooling chamber (3) and the second cooling chamber (10) It is identical.
7. a kind of smoke cooling tower with flue dust collecting function according to claim 1, it is characterised in that: the exhausting The inner sidewall of the wind pipe of the intake stack and exhaust fan (6) of machine (6) is fixedly connected to protecting film (17), the protecting film It (17) is plastic protection film.
CN201820870674.0U 2018-06-06 2018-06-06 A kind of smoke cooling tower with flue dust collecting function Expired - Fee Related CN208566729U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820870674.0U CN208566729U (en) 2018-06-06 2018-06-06 A kind of smoke cooling tower with flue dust collecting function

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820870674.0U CN208566729U (en) 2018-06-06 2018-06-06 A kind of smoke cooling tower with flue dust collecting function

Publications (1)

Publication Number Publication Date
CN208566729U true CN208566729U (en) 2019-03-01

Family

ID=65485402

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820870674.0U Expired - Fee Related CN208566729U (en) 2018-06-06 2018-06-06 A kind of smoke cooling tower with flue dust collecting function

Country Status (1)

Country Link
CN (1) CN208566729U (en)

Similar Documents

Publication Publication Date Title
CN107907454A (en) One kind is used for indoor air quality detecting device
CN204403675U (en) For the waste gas pipeline of environmental protection equipment
CN208566729U (en) A kind of smoke cooling tower with flue dust collecting function
CN202778121U (en) Bag type dust collector with heat recovery device
CN112502976A (en) Vacuum system for high-end photovoltaic module production and vacuumizing process thereof
CN204080086U (en) Strip steel Zn-plating residual heat using device
CN201187933Y (en) Compressed air purifier
CN205505820U (en) Waste gas waste heat recovery device of boiler
CN205505046U (en) Thermal power residual heat from flue gas system
CN114757025A (en) Multipoint coupling energy-saving design method for electrolytic aluminum smoke-discharging purification system
CN205424884U (en) Residual heat from flue gas of firepower factory device
CN208269181U (en) A kind of smoke cooling tower with cleaning function
CN208567571U (en) A kind of large cooling column with multiple heat dissipation function
CN203657503U (en) Exhaust gas processing system of kiln
CN208075596U (en) A kind of cooler for mineral hot furnace flue gas cleaning system
CN209011492U (en) A kind of exhaust pipe with rainproof function
CN206069361U (en) Hydrogen cooled generator group hydrogen cleaning purifying plant
CN207913437U (en) The cooling down of a kind of dust-removing waste gas cools down and utilizes device
CN109569159A (en) Electrostatic Water Membrane Dedusting method
CN107906996B (en) A kind of waste-heat recovery device of high abrasion casting
CN208269686U (en) A kind of smoke cooling tower with water circulatory function
CN205579844U (en) Industrial central air conditioning
CN220802475U (en) Impurity removal system for compressed air pipeline of clean room
CN210021506U (en) Waste gas purification conveyer pipe
CN212458009U (en) Condensing device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190301

Termination date: 20200606

CF01 Termination of patent right due to non-payment of annual fee