CN208563589U - A kind of connection structure of assembled architecture wall and floor - Google Patents
A kind of connection structure of assembled architecture wall and floor Download PDFInfo
- Publication number
- CN208563589U CN208563589U CN201821012131.1U CN201821012131U CN208563589U CN 208563589 U CN208563589 U CN 208563589U CN 201821012131 U CN201821012131 U CN 201821012131U CN 208563589 U CN208563589 U CN 208563589U
- Authority
- CN
- China
- Prior art keywords
- floor
- wall
- connection structure
- assembled architecture
- head clamp
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The utility model provides the connection structure of a kind of assembled architecture wall and floor, including wall, upper layer floor and lower layer's floor, the wall upper and lower side passes through fixed structure and connect with upper layer floor and lower layer's floor, fixed structure includes the snap-gauge of " u "-shaped, the two sides of the bottom of snap-gauge are equipped with fixed otic placode, fixed otic placode is connect by anchoring screw with upper layer floor or lower layer's floor, snap-gauge inner wall is symmetrical arranged clamping structure, the clamping structure includes spring and head clamp, and wall is arranged between head clamp.The wallboard crack that the connection structure can prevent wall dislocation from generating.
Description
Technical field
The utility model belongs to assembled architecture field, in particular to the connection knot of a kind of assembled architecture wall and floor
Structure.
Background technique
Assembled architecture is some or all of will to build component to be prefabricated in the factory completion, and then transporting will to construction site
Component assembles the house built up by reliable connection type.It is set according to building size, partition wall scale metaplasia in factory
It produces and completes, be fixedly mounted between upper and lower floor as long as being transported to building construction scene, it is quickly succinct.
But in skyscraper, influenced by wind pressure, crustal movement etc., what wall usually was difficult to restore because of mobile generation
Crackle directly affects the intensity and incrustation of wall.
Summary of the invention
The technical problem to be solved by the utility model is to provide the connection structure of a kind of assembled architecture wall and floor,
The wallboard crack that can prevent wall dislocation from generating.
A kind of in order to solve the above technical problems, the technical scheme adopted by the utility model is: assembled architecture wall with
The connection structure of floor, including wall, upper layer floor and lower layer's floor, the wall upper and lower side pass through fixed structure and upper layer
Floor is connected with lower layer's floor, and fixed structure includes the snap-gauge of " u "-shaped, and the two sides of the bottom of snap-gauge are equipped with fixed otic placode, fixed ear
Plate is connect by anchoring screw with upper layer floor or lower layer's floor, and snap-gauge inner wall is symmetrical arranged clamping structure, the clamping structure
Including spring and head clamp, wall is arranged between head clamp.
In preferred scheme, the clamping structure further includes guide post, and spring pocket is in guide post, one end of guide post
Head clamp is connected, the other end of guide post passes through the through-hole being arranged on snap-gauge two sidewalls.
In further embodiment, the guide post is equipped with limit plate far from one end of head clamp.
In preferred scheme, the wall two sides are equipped with fixed groove, and head clamp is mounted in fixed groove.
In further embodiment, carriage, head clamp clamping carriage, clamping board foot are equipped in the fixed groove
It is very little to be less than fixed groove size.
In further scheme, the carriage is ball, and semi-circular groove is equipped in fixed groove, and ball rolls peace
In semi-circular groove.
In further scheme, the carriage is slide plate group, and slide plate group includes the plurality of steel plates being stacked with.
In scheme further, graphite linings are equipped between the steel plate.
The connection structure of a kind of assembled architecture wall and floor provided by the utility model, is not only able to achieve the fast of wall
Speed installation, and wall is made to can produce slight movement, it will not crack, be suitble to because of the dislocation between wall and floor
It is promoted in assembled architecture field.
Detailed description of the invention
The utility model is described in further detail with reference to the accompanying drawings and examples:
Fig. 1 is the overall structure diagram of the utility model.
Fig. 2 is the enlarged drawing in Fig. 1 at A.
Fig. 3 is the scheme of installation of another preferred carriage.
In figure: wall 1, upper layer floor 2, lower layer's floor 3, snap-gauge 4, fixed otic placode 5, anchoring screw 6, spring 7, head clamp
8, guide post 9, limit plate 10, fixed groove 11, ball 12, semi-circular groove 13, slide plate group 14, steel plate 15.
Specific embodiment
As shown in Figure 1, a kind of connection structure of assembled architecture wall and floor, including wall 1, upper layer floor 2 and under
Floor plate 3,1 upper and lower side of wall pass through fixed structure and connect with upper layer floor 2 and lower layer's floor 3, and fixed structure includes
The snap-gauge 4 of " u "-shaped, the two sides of the bottom of snap-gauge 4 are equipped with fixed otic placode 5, and fixed otic placode 5 is set as multiple groups, each group of fixed otic placode 5
4 two sides of snap-gauge are symmetricly set on, fixed otic placode 5 is connect by anchoring screw 6 with upper layer floor 2 or lower layer's floor 3, in snap-gauge 4
Wall is symmetrical arranged clamping structure, and the clamping structure includes spring 7 and head clamp 8, and wall 1 is arranged between head clamp 8.
7 both ends of spring are separately connected 4 two sides inner wall of head clamp 8 and snap-gauge, are clamped wall by spring 7 and head clamp 8
In snap-gauge 4, installation quickly, and due to the effect of spring 8, allows wall 1 is horizontal to be moved forward and backward, prevents wall 1 big
Effect of vibration under generate dislocation with upper layer floor 2 and lower layer's floor 3 and crack.
Preferably, the clamping structure further includes guide post 9, and spring 7 is sleeved in guide post 9, and one end of guide post 9 connects
Head clamp 8 is connect, the other end of guide post 9 passes through the through-hole being arranged on 4 two sidewalls of snap-gauge.
By mobile guide column 9, changes clamping plate 8 at a distance from 4 two sides inner wall of snap-gauge, facilitate the installation of wall 1.
The guide post 9 is equipped with limit plate 10 far from one end of head clamp 8.The limit plate 10 of setting prevents guide post 9 remote
One end from head clamp 8 is detached from snap-gauge 4 under the action of spring 7, and when preventing from not installing, fixed structure occurs components and loses.
1 two sides of wall are equipped with fixed groove 11, and head clamp 8 is mounted in fixed groove 11.
It is equipped with carriage in the fixed groove 11,8 clamping carriage of head clamp, 8 undersized of head clamp and solid
Determine 11 size of groove.
The carriage is ball 12, and semi-circular groove 13 is equipped in fixed groove 11, and the rolling of ball 12 is mounted on semicircle
In shape slot 13.
When biggish vibration occurs, ball 12 can be rolled along head clamp 8, allow wall up and down or horizontal left and right is moved
It is dynamic, it further prevents misplacing.
The alternative solution of the present embodiment in place, the carriage are slide plate group 14, and slide plate group 14 includes being stacked with
Plurality of steel plates 15.
When biggish vibration occurs, by sliding opposite between steel plate 15, allows wall up and down or horizontal left and right is moved
It is dynamic.To reduce the frictional force between slide plate group 14, graphite linings are equipped between steel plate 15.
Specific use process is as follows for the utility model: fixed structure is mounted on by wall 1 after the completion of prepared by precast plant
The upper and lower ends of wall are specifically mobile guide column 9, compressed spring 7, after fixed structure is mounted in snap-gauge 4, are unclamped
Guide post 9, head clamp 8 clamp wall 1, and the wall 1 for installing fixed structure is hoisted to installation floor, by fixed otic placode 5
It is mounted on upper floor version 2 or lower layer's floor 3 by anchoring screw 6, completes the installation of wall 1.
The above embodiments are only the optimal technical scheme of the utility model, and are not construed as the limit for the utility model
System, the technical solution that the protection scope of the utility model should be recorded with claim, the technical solution recorded including claim
The equivalents of middle technical characteristic are protection scope.Equivalent replacement i.e. within this range is improved, also in the utility model
Protection scope within.
Claims (8)
1. a kind of connection structure of assembled architecture wall and floor, including wall (1), upper layer floor (2) and lower layer's floor
(3), it is characterised in that: wall (1) upper and lower side passes through fixed structure and connect with upper layer floor (2) and lower layer's floor (3),
Fixed structure includes the snap-gauge (4) of " u "-shaped, and the two sides of the bottom of snap-gauge (4) are equipped with fixed otic placode (5), and fixed otic placode (5) pass through anchor
Gu screw (6) is connect with upper layer floor (2) or lower layer's floor (3), snap-gauge (4) inner wall is symmetrical arranged clamping structure, the clamping
Structure includes spring (7) and head clamp (8), and wall (1) is arranged between head clamp (8).
2. the connection structure of a kind of assembled architecture wall and floor according to claim 1, it is characterised in that: the folder
Locking structure further includes guide post (9), and spring (7) is sleeved on guide post (9), and one end of guide post (9) connects head clamp (8),
The other end of guide post (9) passes through the through-hole being arranged on snap-gauge (4) two sidewalls.
3. the connection structure of a kind of assembled architecture wall and floor according to claim 2, it is characterised in that: described to lead
Xiang Zhu (9) is equipped with limit plate (10) far from the one end of head clamp (8).
4. the connection structure of a kind of assembled architecture wall and floor according to claim 1, it is characterised in that: the wall
Body (1) two sides are equipped with fixed groove (11), and head clamp (8) is mounted in fixed groove (11).
5. the connection structure of a kind of assembled architecture wall and floor according to claim 4, it is characterised in that: described solid
Determine to be equipped with carriage in groove (11), head clamp (8) clamping carriage, head clamp (8) size is less than fixed groove (11)
Size.
6. the connection structure of a kind of assembled architecture wall and floor according to claim 5, it is characterised in that: the cunning
Dynamic device is ball (12), is equipped with semi-circular groove (13) in fixed groove (11), and ball (12) rolling is mounted on semi-circular groove
(13) in.
7. the connection structure of a kind of assembled architecture wall and floor according to claim 5, it is characterised in that: the cunning
Dynamic device is slide plate group (14), and slide plate group (14) includes the plurality of steel plates (15) being stacked with.
8. the connection structure of a kind of assembled architecture wall and floor according to claim 7, it is characterised in that: the steel
Graphite linings are equipped between plate (15).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821012131.1U CN208563589U (en) | 2018-06-28 | 2018-06-28 | A kind of connection structure of assembled architecture wall and floor |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821012131.1U CN208563589U (en) | 2018-06-28 | 2018-06-28 | A kind of connection structure of assembled architecture wall and floor |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208563589U true CN208563589U (en) | 2019-03-01 |
Family
ID=65488464
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821012131.1U Expired - Fee Related CN208563589U (en) | 2018-06-28 | 2018-06-28 | A kind of connection structure of assembled architecture wall and floor |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208563589U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111877542A (en) * | 2020-08-11 | 2020-11-03 | 滕信虎 | Energy-saving light steel structure |
CN113323486A (en) * | 2021-06-01 | 2021-08-31 | 台州学院 | Prefabricated concrete wallboard and floor slab connecting joint and construction method thereof |
-
2018
- 2018-06-28 CN CN201821012131.1U patent/CN208563589U/en not_active Expired - Fee Related
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111877542A (en) * | 2020-08-11 | 2020-11-03 | 滕信虎 | Energy-saving light steel structure |
CN113323486A (en) * | 2021-06-01 | 2021-08-31 | 台州学院 | Prefabricated concrete wallboard and floor slab connecting joint and construction method thereof |
CN113323486B (en) * | 2021-06-01 | 2022-05-24 | 台州学院 | Prefabricated concrete wallboard and floor slab connecting joint and construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN208563589U (en) | A kind of connection structure of assembled architecture wall and floor | |
CN103088943B (en) | Curtain wall three-dimensional adjusting type change over device | |
CN212534604U (en) | Assembled building damping device | |
CN214574887U (en) | Novel assembled shear wall structure power consumption device | |
CN213087044U (en) | Connecting structure of steel structure beam and steel structure column | |
CN204040236U (en) | A kind of Novel U-shaped steel plate energy consuming mechanism | |
CN105064551A (en) | Movable wallboard system | |
CN209874206U (en) | Mounting structure for environment-friendly ceiling | |
CN209891789U (en) | Novel wind mode frequency modulation mass damper that shakes | |
CN211735915U (en) | Shock-absorbing and shock-resistant assembled wall | |
CN207620365U (en) | Temporary support structure | |
CN216587440U (en) | Building energy-saving external wall heat-insulation decorative plate | |
CN202117170U (en) | Support structure capable of sliding freely | |
CN205116758U (en) | Steel truss is assembled and is supported adjusting device | |
CN207776227U (en) | A kind of assembled architecture reinforced concrete member | |
CN210659196U (en) | Prepackage type building outer wall scaffold frame | |
CN106836503A (en) | The antidetonation formed steel construction lightly constructed and simply equipped building being easily installed | |
CN203821882U (en) | Super high-rise prefabricated assembled type residential building | |
CN208235798U (en) | Column structure for prefabricated buildings | |
CN218970379U (en) | Curtain wall suspension type stand column and steel-concrete connecting mechanism | |
CN206267148U (en) | A kind of Static pressure pile driver being automatically positioned | |
CN205840002U (en) | A kind of power consumption steel-structure beam-column node of stiffness variable | |
CN204876206U (en) | Portable wallboard system | |
CN220058412U (en) | Building wallboard with shockproof structure | |
CN213709866U (en) | Steel structure column and connecting structure thereof |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190301 |
|
CF01 | Termination of patent right due to non-payment of annual fee |