CN208535969U - A kind of circulating fluidized bed boiler installation bed material device - Google Patents

A kind of circulating fluidized bed boiler installation bed material device Download PDF

Info

Publication number
CN208535969U
CN208535969U CN201821148374.8U CN201821148374U CN208535969U CN 208535969 U CN208535969 U CN 208535969U CN 201821148374 U CN201821148374 U CN 201821148374U CN 208535969 U CN208535969 U CN 208535969U
Authority
CN
China
Prior art keywords
circulating fluidized
pipe
fluidized bed
boiler
bed material
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201821148374.8U
Other languages
Chinese (zh)
Inventor
陈东阳
张晋轩
郭伟
丛丹
张帅
于帅
郭军
刘海斌
申红波
睢晓峰
李志强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201821148374.8U priority Critical patent/CN208535969U/en
Application granted granted Critical
Publication of CN208535969U publication Critical patent/CN208535969U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Fluidized-Bed Combustion And Resonant Combustion (AREA)

Abstract

The utility model discloses a kind of circulating fluidized bed boiler to install bed material device additional, is related to the auxiliary equipment of fluidized-bed combustion boiler;Including circulating fluidized bed boiler, bucket elevator, conveyer and slag library, the feeding inlet of circulating fluidized bed boiler is connected by first pipe with the outlet of bucket elevator, the outlet of bucket elevator is connected by second pipe with the slag library, gate valve is respectively arranged in first pipe and second pipe, the bottom of bucket elevator is connected with conveyer;The utility model will be combined into one for circulating fluidized bed boiler extra bed material with to boiler slag removal, realize the purpose for quickly installing bed material additional;The present apparatus saves boiler and installs the bed material time additional, reduces bed material and installs expense additional, improves economic benefit.

Description

A kind of circulating fluidized bed boiler installation bed material device
Technical field
The utility model relates to the auxiliary equipment of fluidized-bed combustion boiler more particularly to a kind of circulating fluidized bed boiler to install bed material additional Device.
Background technique
Circulating fluidized bed boiler is the highest clean coal combustion technology of industrialization degree.Circulating fluidized bed boiler uses fluidised form Change burning, primary structure includes combustion chamber (including emulsion zone and dilute-phase zone) and circulation melt down (including high-temperature gas-solid separator with Revert system) two large divisions.Maximum difference with bubbling fluidized bed combustion technology is operating air velocity height, enhances burning and desulfurization Etc. heterogeneous reactions process, boiler capacity can be expanded to power industry acceptable large capacity (600MW or ratings above) Currently, circulating fluidized bed boiler underlying issues and expansion, abrasion, the overtemperature such as very good solution calorifics, mechanics, materialogy Equal engineering problems become fire retardant solid fuel (such as gangue, oil shale, municipal refuse, mud and other wastes) energy benefit Advanced technology.
Circulating fluidized bed boiler need to install a certain amount of bottom ash additional as igniting starting bed material when starting, and original bed material installs additional Mode is that artificial installation is shakeout after the bed material being sieved is transported to operating layer by being manually transported to burner hearth by boiler manhole door, I takes around the side's 70-80 bed material at company 480t/h circulating fluidized bed boiler one-shot bed material, and artificial install additional needs 2-3 days, Bed material installs overlong time, serious shadow to unit starting time additional.
Utility model content
The utility model has saved boiler and has installed bed material additional by providing a kind of circulating fluidized bed boiler installation bed material device Time realizes boiler feeding and deslagging using set of device simultaneously.The utility model is achieved by the following technical solution.
A kind of circulating fluidized bed boiler installation bed material device, including circulating fluidized bed boiler, further include bucket elevator, defeated Machine and slag library are sent, the feeding inlet of circulating fluidized bed boiler is connected by first pipe with the outlet of bucket elevator, described The outlet of bucket elevator is connected by second pipe with the slag library, is set respectively on the first pipe and second pipe It is equipped with gate valve, the bottom of the bucket elevator is connected with conveyer.
Further, the conveyer is bucket chain conveyor.
Further, the outlet of the bucket elevator is connected with first pipe and second pipe respectively by threeway It is logical.
Further, the side wall of circulating fluidized bed boiler is arranged in the feeding inlet of the circulating fluidized bed boiler.
The utility model is generated compared with the existing technology to be had the beneficial effect that.
The utility model will be combined into one with to boiler slag removal for circulating fluidized bed boiler extra bed material, realize quick feeding and The purpose of discharge.The present apparatus saves boiler and installs the bed material time additional, and the previous artificial bed material that installs additional needs 2-3 days, installs bed additional after improvement Material needs 4-5 hour, and each unit maintenance is complete after improvement can shift to an earlier date starting in 1.5-2.5 days more in the past, every time can multiple electric 4,000,000 KWh increases by 1,320,000 yuan of operating income.Secondly, reducing bed material installs expense additional, therefore expense can be saved by once installing bed material additional after improving With 1.08 ten thousand yuan, it can be saved bed material by unit starting 10 times calculating, whole year and be installed additional 10.8 ten thousand yuan of expense within 1 year.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the utility model.
Wherein, 1 is circulating fluidized bed boiler, and 2 be bucket elevator, and 3 be conveyer, and 4 be slag library, and 5 be first pipe, 6 It is gate valve for second pipe, 7.
Specific embodiment
In order to which technical problem to be solved in the utility model, technical solution and beneficial effect is more clearly understood, tie Embodiment and attached drawing are closed, the present invention will be further described in detail.It should be appreciated that specific embodiment described herein It is only used to explain the utility model, is not used to limit the utility model.This is described in detail below with reference to examples and drawings The technical solution of utility model, but the scope of protection is not limited by this.
As shown in Figure 1, a kind of circulating fluidized bed boiler installs bed material device, including circulating fluidized bed boiler 1 additional, it further include bucket The feeding inlet in formula elevator 2, conveyer 3 and slag library 4, circulating fluidized bed boiler 1 passes through first pipe 5 and bucket elevator 2 Outlet is connected, and the outlet of bucket elevator 2 is connected by second pipe 6 with slag library 4, in first pipe 5 and second pipe 6 It is respectively arranged with gate valve 7, the bottom of bucket elevator 2 is connected with conveyer 3.Conveyer 3 is bucket chain conveyor.
The outlet of bucket elevator 2 is connected with first pipe 5 and second pipe 6 respectively by threeway.
The side wall of circulating fluidized bed boiler 1 is arranged in the feeding inlet of circulating fluidized bed boiler 1.
Specific embodiment are as follows: one threeway is set in 2 top exit pipeline of bucket elevator, the threeway is by bucket lifting 2 outlet conduit of machine is divided into two-way, is connected to slag library 4 all the way, another way is connected to the pipeline of circulating fluidized bed boiler 1 into burner hearth. When installing bed material additional, the gate valve 7 on second pipe 6 is closed, opens the gate valve 7 of first pipe 5, while starting air-introduced machine, First air Machine.The bed material being manually sieved is added by 3 top feed opening of bucket chain conveyor, is promoted to through bucket chain conveyor 3, bucket elevator 2 Top enters burner hearth, the tune of air quantity through bucket elevator 2 to first pipe 5, then by 1 side wall tapping of circulating fluidized bed boiler It is whole to be adjusted according to the speed for installing speed additional, guarantee that bed material when installing additional in furnace is smooth.
Bed material installation finishes, and closes the gate valve 7 of first pipe 5, opens the gate valve 7 on second pipe 6, simultaneously closes off chain bucket 3 top feed opening of conveyer, boiler can normal deslagginves.
The above content is the further descriptions done in conjunction with specific preferred embodiment to the utility model, cannot Assert that specific embodiment of the present utility model is only limitted to this, for the utility model person of an ordinary skill in the technical field For, under the premise of not departing from the utility model, several simple deduction or replace can also be made, all shall be regarded as belonging to The utility model determines scope of patent protection by the claims submitted.

Claims (4)

1. a kind of circulating fluidized bed boiler installs bed material device, including circulating fluidized bed boiler (1) additional, which is characterized in that further include Bucket elevator (2), conveyer (3) and slag library (4), the feeding inlet of the circulating fluidized bed boiler (1) pass through first pipe (5) be connected with the outlet of bucket elevator (2), the outlet of the bucket elevator (2) by second pipe (6) with it is described Slag library (4) is connected, and is respectively arranged with gate valve (7) on the first pipe (5) and second pipe (6), the bucket type mentions The bottom for rising machine (2) is connected with conveyer (3).
2. a kind of circulating fluidized bed boiler according to claim 1 installs bed material device additional, which is characterized in that the conveying Machine (3) is bucket chain conveyor.
3. a kind of circulating fluidized bed boiler according to claim 1 installs bed material device additional, which is characterized in that the bucket type The outlet of elevator (2) is connected with first pipe (5) and second pipe (6) respectively by threeway.
4. a kind of circulating fluidized bed boiler according to claim 1 installs bed material device additional, which is characterized in that the circulation Side wall of the feeding inlet setting of fluidized-bed combustion boiler (1) in circulating fluidized bed boiler (1).
CN201821148374.8U 2018-07-19 2018-07-19 A kind of circulating fluidized bed boiler installation bed material device Expired - Fee Related CN208535969U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821148374.8U CN208535969U (en) 2018-07-19 2018-07-19 A kind of circulating fluidized bed boiler installation bed material device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821148374.8U CN208535969U (en) 2018-07-19 2018-07-19 A kind of circulating fluidized bed boiler installation bed material device

Publications (1)

Publication Number Publication Date
CN208535969U true CN208535969U (en) 2019-02-22

Family

ID=65387010

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821148374.8U Expired - Fee Related CN208535969U (en) 2018-07-19 2018-07-19 A kind of circulating fluidized bed boiler installation bed material device

Country Status (1)

Country Link
CN (1) CN208535969U (en)

Similar Documents

Publication Publication Date Title
CN101124434B (en) Cyclone bypass for a circulating fluidized bed reactor
CN107191925A (en) A kind of CFBB and its abnormal method of adjustment of returning charge
CN103436703B (en) Total-oxygen side-blown reduction smelting converter
CN103604121B (en) Adopt the oil shale semi-coke fluidized bed combustion syste of triple channel flow-dividing control material returning device
CN103884013A (en) Combustion method and device of coupled environment-friendly fluidized bed boiler
CN103123111B (en) A kind of power station boiler burner based on coal dust classification pre-burning-pyrolysis
CN208535969U (en) A kind of circulating fluidized bed boiler installation bed material device
CN109340742B (en) Novel fluidized bed flue gas furnace
CN107384482B (en) Energy-saving environment-friendly gasification furnace for collective fuel gas supply
CN101349511A (en) Flue gas waste heat recovery method and apparatus for ferroalloy cluster electric stove
CN204739601U (en) Combustor secondary wind box ash exhauster
CN105753348B (en) A kind of production technology of Indonesia's bituminous rock tailing particles nsp kiln
CN205223092U (en) Coke oven heating infeeds structure with air segmentation
CN209801470U (en) low-nitrogen combustion system of circulating fluidized bed boiler
CN105570908B (en) Method and system for recycling and treating waste
CN204063016U (en) A kind of electrostatic field takes off the fluidized system that sodium prevents boiler heating surface from staiing
CN207298917U (en) A kind of sunken bed ballast group fluid bed for using super-low calorific value fuel
CN209763052U (en) Circulating fluidized bed boiler return ash conveying structure
CN108167824B (en) Circulating fluidized bed power station boiler system
Maysyuk Measures to prevent emissions of pollutants when burning coals in small-capacity boilers in the central ecological area of the Baikal natural territory
CN103557518B (en) The organic working medium boiler of slime burning
CN216347870U (en) Lepidolite bakes burning furnace waste heat recovery and utilizes system over a slow fire
CN218864157U (en) Fly ash recycling device for replenishing fluidized bed boiler bed material
CN108278596A (en) A kind of CFB boiler system and its operation method using garbage derivatived fuel
CN221376338U (en) Direct reduction rotary kiln flue gas treatment device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant