CN208535381U - A kind of natural gas exploration conveyance conduit fast joint structure - Google Patents
A kind of natural gas exploration conveyance conduit fast joint structure Download PDFInfo
- Publication number
- CN208535381U CN208535381U CN201821093430.2U CN201821093430U CN208535381U CN 208535381 U CN208535381 U CN 208535381U CN 201821093430 U CN201821093430 U CN 201821093430U CN 208535381 U CN208535381 U CN 208535381U
- Authority
- CN
- China
- Prior art keywords
- pedestal
- bearing
- natural gas
- fixed
- main body
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Pipeline Systems (AREA)
Abstract
The utility model discloses a kind of natural gas exploration conveyance conduit fast joint structures, including pipe main body, gag lever post, first bearing and threaded hole, the bottom of the screw shell is provided with pedestal, and it is connected between pedestal and pedestal by fixed link, and the top of fixed link, which is run through, perforation, the perforation is internally provided with fixed fixture block, and the overhead surface of pedestal is arranged in fixed fixture block, the overhead surface of pedestal is additionally provided with scale, the top of the first bearing is fixedly connected with flange, and the inside of second bearing is arranged in the bottom of first bearing, the threaded hole is applied in the top of flange.The natural gas exploration is provided with gag lever post with conveyance conduit fast joint structure, it is possible thereby to be determined according to limit pole length to the position of lantern ring, and then collar footprint screw shell and threaded post is just made to can be very good to carry out the height of entire pipeline certain support work, facilitate the position of staff's line up to move.
Description
Technical field
The utility model relates to natural-gas transfer pipelines to install correlative technology field, and specially a kind of natural gas is surveyed with defeated
Send conduit fast connection structure.
Background technique
Natural gas exploration with conveying pipeline connection structure be it is a kind of by natural gas exploration the numerous pipelines of transmission process and pipe
Be attached between road, achieve the effect that facilitate and carry out long distance transportation, although the type of the connection structure on existing market with
It is large number of, but its still there is some problems, such as the pipeline configuration on existing market during being installed not
It is convenient accurately to be coincide at port, it can take a substantial amount of time and existing pipeline is in the mistake for being attached installation
It is to be installed by flange in journey, thus just makes entire connection structure flange base is very difficult work is fixed,
Difficulty is brought for the installment work of staff, therefore, we just propose that a kind of natural gas for facilitating solution problem above is surveyed
Survey conveying pipeline connection structure.
Utility model content
The purpose of this utility model is to provide a kind of natural gas exploration conveyance conduit fast joint structures, on solving
The exploration of natural gas currently on the market for stating background technique proposition cannot during being installed with conveying pipeline connection structure
Quickly mutually to coincide between two nozzles, the fixed very difficult problem of work of the bolt of later flange base.
To achieve the above object, the utility model provides the following technical solutions: a kind of natural gas exploration conveyance conduit is fast
Fast connection structure, including pipe main body, gag lever post, first bearing and threaded hole, the top of the pipe main body are fixedly installed with
Flange, and be connected between flange and flange by fastening bolt, the bottom of the gag lever post is fixedly installed with lantern ring, and lantern ring
Bottom be fixedly installed with screw shell, and threaded post is provided between screw shell and screw shell, the screw shell
Bottom be provided with pedestal, and be connected between pedestal and pedestal by fixed link, and the top of fixed link is through there is perforation,
The perforation is internally provided with fixed fixture block, and the overhead surface of pedestal, the overhead surface of pedestal is arranged in fixed fixture block
It is additionally provided with scale, the two sides top of the fixed link is respectively connected with fixed pointers, and the top of the first bearing is fixedly connected
There is flange, and the inside of second bearing is arranged in the bottom of first bearing, the threaded hole is applied in the top of flange.
Preferably, it is structure as a whole between the flange and first bearing, and the outer wall of first bearing and pipe main body
It is to be fitted and connected between inner wall.
Preferably, the connection type between the gag lever post and lantern ring is welds, and the perspective plane shape of gag lever post and lantern ring
Shape is L shape structure, and the connection type between lantern ring and pipe main body is to be connected together.
Preferably, the equal length of the length and fixed link of the pedestal, and the vertical central axes of pedestal and scale is perpendicular
Straight central axes overlap.
Preferably, the shape of the size for the shape that the top of the fixed link, which is run through, to be had perforation, and perforate and fixed fixture block
Size matches, and is structure as a whole between fixed fixture block and pedestal, while the horizontal median axis of fixed fixture block and pedestal
Horizontal median axis overlaps, and the top dead center position of fixed link is fixed with fixed pointers.
Preferably, the connection relationship between the second bearing and pipe main body inner wall is welds, and the wall of second bearing
Thickness is greater than the clearance distance between pipe main body and first bearing.
Compared with prior art, the utility model has the beneficial effects that the natural gas exploration is quickly connected with conveyance conduit
Structure setting has gag lever post, it is possible thereby to be determined according to limit pole length to the position of lantern ring, and then just makes lantern ring bottom
Portion's screw shell and threaded post can be very good to carry out the height of entire pipeline certain support work, facilitate staff couple
The position of nozzle is moved, meanwhile, the setting of scale, facilitates staff position according to indicated by fixed pointers above pedestal
It sets and the height between 2 pedestals is observed, the lifting work of matching thread sleeve and threaded post can reach well
2 nozzles are in the effect in same level, the position that will not expend a large amount of time line up of staff carries out really
Fixed, the setting of first bearing can make flange can be very good to be rotated during being installed, and facilitate bottom
Threads turn the fixed work of bolt, while the normal work of first bearing that guarantee is set of second bearing are carried out to it to top
It during work, also can be very good for first bearing and the gap inside pipe main body to be sealed, avoid natural gas
The problem of being revealed in gap inside one bearing and pipe main body.
Detailed description of the invention
Fig. 1 is the utility model schematic view of the front view;
Fig. 2 is enlarged structure schematic diagram at A in the utility model Fig. 1;
Fig. 3 is the utility model pipe main body top schematic cross-sectional view;
Fig. 4 is the utility model lantern ring schematic cross-sectional view;
Fig. 5 is the utility model flange side structure schematic view;
Fig. 6 is enlarged structure schematic diagram at B in the utility model Fig. 3.
In figure: 1, pipe main body;2, flange;3, fastening bolt;4, gag lever post;5, lantern ring;6, screw shell;7, screw thread
Column;8, pedestal;9, fixed link;10, it perforates;11, fixed fixture block;12, fixed pointers;13, scale;14, first bearing;15, spiral shell
Pit;16, second bearing.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model
Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole
Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work
Every other embodiment obtained, fall within the protection scope of the utility model.
Please refer to Fig. 1-6, the utility model provides a kind of technical solution: a kind of natural gas exploration conveyance conduit quickly connects
Binding structure, including it is pipe main body 1, flange 2, fastening bolt 3, gag lever post 4, lantern ring 5, screw shell 6, threaded post 7, pedestal 8, solid
Fixed pole 9, perforation 10, fixed fixture block 11, fixed pointers 12, scale 13, first bearing 14, threaded hole 15 and second bearing 16, pipe
The top of road main body 1 is fixedly installed with flange 2, and is connected between flange 2 and flange 2 by fastening bolt 3, flange 2 and the
It is structure as a whole between one bearing 14, and to be fitted and connected between the outer wall of first bearing 14 and the inner wall of pipe main body 1, it is convenient
Flange 2 is rotated under the action of first bearing 14, reaches what convenience was fastenedly connected the flange 2 of bottom
Effect, the bottom of gag lever post 4 are fixedly installed with lantern ring 5, and the bottom of lantern ring 5 is fixedly installed with screw shell 6, gag lever post 4 with
Connection type between lantern ring 5 is welding, and the perspective plane shape of gag lever post 4 and lantern ring 5 is L shape structure, and lantern ring 5 with
Connection type between pipe main body 1 is to be connected together, the convenient position made between 2 pedestals 8 under the action of gag lever post 4
It determines, achievees the effect that be determined its height under the action of fixed link 9, and screw shell 6 and screw shell 6
Between be provided with threaded post 7, the bottom of screw shell 6 is provided with pedestal 8, and between pedestal 8 and pedestal 8 pass through 9 phase of fixed link
Connection, the length of pedestal 8 and the equal length of fixed link 9, and the vertical central axes phase of the vertical central axes of pedestal 8 and scale 13
Mutually be overlapped, and the top of fixed link 9 is through there is perforation 10, perforate 10 the fixed fixture block 11 that is internally provided with, fixed link 9 it is upper
Side, which is run through, perforation 10, and the size of the shape of perforation 10 matches with the shape size of fixed fixture block 11, and fixed fixture block
It is structure as a whole between 11 and pedestal 8, while the horizontal median axis and the horizontal median axis phase mutual respect of pedestal 8 of fixed fixture block 11
It closes, the top dead center position of fixed link 9 is fixed with fixed pointers 12, convenient to carry out under the action of fixed link 9 between pedestal 8
It is fixed, also facilitate and the height between 2 pipe main bodies 1 is determined and is adjusted under the action of fixed pointers 12, and is solid
Determine the overhead surface that pedestal 8 is arranged in fixture block 11, the overhead surface of pedestal 8 is additionally provided with scale 13, the two sides top of fixed link 9
It is respectively connected with fixed pointers 12, the top of first bearing 14 is fixedly connected with flange 2, and the bottom setting of first bearing 14 is the
The inside of two bearings 16, the connection relationship between 1 inner wall of second bearing 16 and pipe main body are welding, and the wall of second bearing 16
Thickness is greater than the clearance distance between pipe main body 1 and first bearing 14, convenient to avoid natural gas under the action of second bearing 16
It is revealed in gap between pipe main body 1 and first bearing 14, threaded hole 15 is applied in the top of flange 2.
Working principle: when using natural gas exploration conveyance conduit fast joint structure, firstly, it is necessary to by first
1 side of being placed on the ground of pipe main body, then, position of the mobile lantern ring 5 on pipe main body 1, so that the limit of 5 top of lantern ring
Bar 4 is contacted with flange 2, later, first pipe main body 1 is placed on position to be installed under the action of pedestal 8, then, just
It needs to contact with each other between the flange 2 and first 1 upper flange 2 of pipe main body on second 1 top of pipe main body, then, then
By second pipe main body 1 under the action of pedestal 8 be fixed between ground, then, staff is first by fixed link 9
It is connected together between the perforation 10 of top and the fixation fixture block 11 of first 1 top of pipe main body, after the completion of connection, so that
The other end of fixed link 9 is directed at the pedestal 8 of second 1 bottom of pipe main body, so that the fixed pointers 12 on 9 top of fixed link are aligned
Scale 13 in second 1 bottom base 8 of pipe main body, when fixed pointers 12 are directed at the center of scale 13, at this point, 2
The nozzle of a pipe main body 1 is mutually identical, if not being in center, just needs to rotate screw shell 6, make
It obtains screw shell 6 and carries out rotation raising and lowering in the top of threaded post 7, the rotation to screw shell 6, so that second pipeline
The center of scale 13 of 1 bottom base of main body, 8 top and the fixed pointers 12 on 9 top of fixed link are in same horizontal line,
Just it ensure that the nozzle of 2 pipe main bodies, 1 top is mutually identical, later, flange 2 can be fastened, work people
Member carries out installment work by top of the fastening bolt 3 to flange 2, when the threaded hole 15 of 2 bottom of flange cannot carry out well
When installment work, staff can make the outside of first bearing 14 rotate in the inside of second bearing 16, first axle
The rotation of 14 drive flanges 2 is held, so that the threaded hole 15 of 2 bottom of flange is in the top of pipe main body 1, and then staff
To complete the installment work of entire pipe main body 1 well, simultaneously as the presence of second bearing 16, also can be very good
Guarantee that 1 inside natural gas of pipe main body will not be revealed from the inside of pipe main body 1 and the gap of first bearing 14, this specification
In the content that is not described in detail belong to the prior art well known to professional and technical personnel in the field.
Although the utility model is described in detail with reference to the foregoing embodiments, come for those skilled in the art
Say, it is still possible to modify the technical solutions described in the foregoing embodiments, or to part of technical characteristic into
Row equivalent replacement, within the spirit and principle of the utility model, any modification, equivalent replacement, improvement and so on should all
It is included within the scope of protection of this utility model.
Claims (6)
1. a kind of natural gas exploration conveyance conduit fast joint structure, including pipe main body (1), gag lever post (4), first bearing
(14) and threaded hole (15), it is characterised in that: the top of the pipe main body (1) is fixedly installed with flange (2), and flange (2)
It is connected between flange (2) by fastening bolt (3), the bottom of the gag lever post (4) is fixedly installed with lantern ring (5), and is covered
The bottom of ring (5) is fixedly installed with screw shell (6), and is provided with threaded post between screw shell (6) and screw shell (6)
(7), the bottom of the screw shell (6) is provided with pedestal (8), and passes through fixed link (9) phase between pedestal (8) and pedestal (8)
Connection, and the top of fixed link (9), through having perforation (10), the perforation (10) is internally provided with fixed fixture block (11),
And fixed fixture block (11) setting is additionally provided with scale (13), institute in the overhead surface of pedestal (8), the overhead surface of pedestal (8)
The two sides top for stating fixed link (9) is respectively connected with fixed pointers (12), and the top of the first bearing (14) is fixedly connected with method
Blue (2), and the bottom of first bearing (14) is arranged in the inside of second bearing (16), the threaded hole (15) is applied in flange
(2) top.
2. a kind of natural gas exploration conveyance conduit fast joint structure according to claim 1, it is characterised in that: described
Be structure as a whole between flange (2) and first bearing (14), and the inner wall of the outer wall of first bearing (14) and pipe main body (1) it
Between to be fitted and connected.
3. a kind of natural gas exploration conveyance conduit fast joint structure according to claim 1, it is characterised in that: described
Connection type between gag lever post (4) and lantern ring (5) is welding, and the perspective plane shape of gag lever post (4) and lantern ring (5) is " L "
Shape structure, and the connection type between lantern ring (5) and pipe main body (1) is to be connected together.
4. a kind of natural gas exploration conveyance conduit fast joint structure according to claim 1, it is characterised in that: described
The length of pedestal (8) and the equal length of fixed link (9), and the vertical axis of the vertical central axes of pedestal (8) and scale (13)
Line overlaps.
5. a kind of natural gas exploration conveyance conduit fast joint structure according to claim 1, it is characterised in that: described
The top of fixed link (9), which is run through, to be had perforation (10), and the shape size of the size of the shape of perforation (10) and fixed fixture block (11)
Match, and be structure as a whole between fixed fixture block (11) and pedestal (8), at the same the horizontal median axis of fixed fixture block (11) and
The horizontal median axis of pedestal (8) overlaps, and the top dead center position of fixed link (9) is fixed with fixed pointers (12).
6. a kind of natural gas exploration conveyance conduit fast joint structure according to claim 1, it is characterised in that: described
Connection relationship between second bearing (16) and pipe main body (1) inner wall is welding, and the wall thickness of second bearing (16) is greater than pipe
Clearance distance between road main body (1) and first bearing (14).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821093430.2U CN208535381U (en) | 2018-07-11 | 2018-07-11 | A kind of natural gas exploration conveyance conduit fast joint structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821093430.2U CN208535381U (en) | 2018-07-11 | 2018-07-11 | A kind of natural gas exploration conveyance conduit fast joint structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208535381U true CN208535381U (en) | 2019-02-22 |
Family
ID=65388597
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821093430.2U Expired - Fee Related CN208535381U (en) | 2018-07-11 | 2018-07-11 | A kind of natural gas exploration conveyance conduit fast joint structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208535381U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112337025A (en) * | 2020-11-05 | 2021-02-09 | 安徽飞达消防设备工程有限公司 | Conveying equipment for conveying fire-fighting foam liquid |
-
2018
- 2018-07-11 CN CN201821093430.2U patent/CN208535381U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112337025A (en) * | 2020-11-05 | 2021-02-09 | 安徽飞达消防设备工程有限公司 | Conveying equipment for conveying fire-fighting foam liquid |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206514066U (en) | A kind of compressed natural gas loading arm | |
CN208535381U (en) | A kind of natural gas exploration conveyance conduit fast joint structure | |
CN206174060U (en) | But pre -buried stagnant water adjustable joint's swirler | |
CN208034022U (en) | A kind of nozzle for Large Diameter Pipeline steel pipe and nozzle docking facilities | |
CN207761066U (en) | A kind of steel pipe column bolt splicing node | |
CN207618963U (en) | It is a kind of using fork truck at the top of basement pipe laying device | |
CN202576455U (en) | Opening device at tuyere of blast furnace hot air bustle pipe | |
CN103451338A (en) | Method for installing ascending tubes and five-way balls of blast furnace gas systems | |
CN209703408U (en) | A kind of civil engineering depositing dust spray equipment | |
CN203656365U (en) | Combination-type transition cable leading cage based on cable leading towards lower bridge surface | |
CN115417232A (en) | Multifunctional cable laying device | |
CN105347100B (en) | A kind of assembly type drag-line draw drum | |
CN205325016U (en) | Flange centering device | |
CN205169654U (en) | A simply turn to device for pressure steel pipe transportation | |
CN212897489U (en) | High-altitude steel pipe column concrete pouring operation platform | |
CN206220624U (en) | The helicopter servicing unit of extra-high voltage wine glass tower tower head | |
CN207608918U (en) | Basic transfer panel for communication iron tower | |
CN207077429U (en) | A kind of device of suitable different tube diameters tubing support | |
CN206320408U (en) | A kind of bag pillar suspension centre in nuclear power GB gallery lifting pipelines | |
CN207279140U (en) | A kind of modularization Work machine platform for pipe with small pipe diameter water supply line | |
CN206600042U (en) | A kind of inner suspended holding pole | |
CN205151362U (en) | Assembled cable drawing drum | |
CN206110364U (en) | Main couple and jack truss splicing joint structure | |
CN205368896U (en) | A built -in adjusting device for adjusting prefabricated track bed | |
CN208777705U (en) | A kind of pipe fitting direct-burried positioning device |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190222 Termination date: 20210711 |
|
CF01 | Termination of patent right due to non-payment of annual fee |