CN208501416U - A kind of sponge urban water-through road structure - Google Patents

A kind of sponge urban water-through road structure Download PDF

Info

Publication number
CN208501416U
CN208501416U CN201820990506.5U CN201820990506U CN208501416U CN 208501416 U CN208501416 U CN 208501416U CN 201820990506 U CN201820990506 U CN 201820990506U CN 208501416 U CN208501416 U CN 208501416U
Authority
CN
China
Prior art keywords
permeable
underlayment
base
lane
drainage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820990506.5U
Other languages
Chinese (zh)
Inventor
程生平
何天钦
魏晋
贾睿
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
North China Municipal Engineering Design and Research Institute Co Ltd
CSCEC Aecom Consultant Co Ltd
Original Assignee
North China Municipal Engineering Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by North China Municipal Engineering Design and Research Institute Co Ltd filed Critical North China Municipal Engineering Design and Research Institute Co Ltd
Priority to CN201820990506.5U priority Critical patent/CN208501416U/en
Application granted granted Critical
Publication of CN208501416U publication Critical patent/CN208501416U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

A kind of sponge urban water-through road structure, including car lane, non-motorized lane, greenbelt, roadbed, kerbstone and kerb cushion block;Car lane is from top to bottom successively including surface layer, Drainage Base, semi-rigid type base and draining underlayment in drainage surface layer, draining.Sealing is provided between Drainage Base and semi-rigid type base.Non-motorized lane successively includes permeable surface layer, porous base course and permeable underlayment from top to bottom.Impervious barrier layer is provided between the permeable underlayment and roadbed of non-motorized lane.Greenbelt includes planting soil, and planting soil is embedded with drainpipe, and drainpipe periphery is equipped with rubble filter layer, and rubble filter layer periphery is equipped with permeable anti-filter geotextiles.Car lane uses semi-transparent water channel line structure, and road surface gathered water can quickly, effectively be discharged by road surface vertical drainage, avoid rainwater from entering semi-rigid type base, underlayment and roadbed and cause to soften, improve pavement strength and durability;Road traffic safety is improved, urban waterlogging is reduced.

Description

A kind of sponge urban water-through road structure
Technical field
The utility model relates to urban road engineering technical fields, and in particular to a kind of sponge urban water-through road structure.
Background technique
Traditional urban road surfaces are generally made of impermeable materials such as asphalt or cement concretes, road surface row Water is realized by crown slope.However, the rainwater within the scope of rainy day road surface cannot be laterally rejected to outside the range of road surface in time, make At surface gathered water;Lead to skid resistance of pavement seriously and reduce, vehicle driving is easily drifted about, and traffic safety is influenced, be easy to cause friendship The generation of interpreter's event.In addition, making waterproof pavement changes the original hydrology ecological environment in city, municipal drainage system is increased The pressure of system easily causes the generation of urban waterlogging in the case of heavy rain.
Road surface is the important carrier of city space, and solves the problems, such as an important ring for urban waterlogging.With ground surface material Continuous development, porous pavement for solve urban waterlogging provide feasibility.Porous pavement is mixed using the biggish pitch of voidage Material or cement concrete are closed, road surface has preferable permeability, can reduce road table ponding with vertical drainage;Simultaneously by Lu Biaoyu Water is discharged into sub-surface or roadbed, and city cavernous body storage road table water serves as in roadbed or base, and the Urban Natural hydrology is promoted to follow Ring mitigates the pressure of sewerage system.
Porous pavement can effective solution urban waterlogging, adjust urban heat land effect, it has also become construction sponge city weight Want approach.Current porous pavement is directed to pavement or non-motorized lane mostly, and the load of effect is smaller.Friendship on car lane Logical load is larger, and porous pavement will not only meet drainage requirement, it is also necessary to have enough bearing strengths.If car lane using Road table rainwater is discharged into roadbed by full porous pavement, is be easy to cause roadbed softening intensity insufficient, is led to pavement destruction.Such as patent A kind of permeable road structure based on sponge the idea of the city that CN 207176431U is announced, although can be realized road surface drainage storage Water function, but roadbed is easy to happen the use on harm influence road surface.Thus.Design it is a kind of can Quick drainage, water storage it is motor-driven Lane line structure, while roadbed, pavement strength can not also be influenced, for solving urban waterlogging, realizing that sponge city is very necessary.
Summary of the invention
The purpose of this utility model is to provide a kind of sponge urban water-through road structure, which can be in not shadow The rainwater within the scope of road surface is effectively excluded in the case where ringing motor vehicle road surface bearing strength, reduces urban waterlogging, promotes city certainly Right Hydrology circulation.
The purpose of this utility model is realized through the following technical scheme.A kind of sponge urban water-through road structure, Including car lane, non-motorized lane, greenbelt, roadbed, kerbstone and kerb cushion block;It is characterized by: car lane is from upper Successively including surface layer, Drainage Base, semi-rigid type base and underlayment in drainage surface layer, draining under and;Drainage Base and semi-rigid Sealing is provided between property base.
Non-motorized lane successively includes permeable surface layer, porous base course and permeable underlayment from top to bottom.Non-motorized lane Impervious barrier layer is provided between permeable underlayment and roadbed.
Greenbelt includes planting soil, and planting soil is embedded with drainpipe, and drainpipe periphery is equipped with rubble filter layer, rubble mistake Filtering layer periphery is equipped with permeable anti-filter geotextiles;It drains tube wall and is equipped with large number of inlet opening, drainpipe and existing draining System connectivity.The drainpipe being arranged in greenbelt is PVC drain pipe, so that road has enough drainabilities, works as greening Water level with interior rainwater no longer rises when reaching the permeable base layer height of non-motorized lane, but is discharged into draining system by drainpipe In system.The metalling of making and permeable anti-filter geotextiles around PVC drain pipe, preventing planting soil from entering PVC drain pipe causes to arrange Water is not smooth.
Be equipped with fine sand layer between the semi-rigid type base of planting soil and car lane, draining underlayment, planting soil and roadbed it Between be equipped with fine sand layer, above fine sand layer and planting soil bottom is equipped with anti-seepage geotextile.The anti-seepage geotextile of setting, for preventing The rainwater being only stored in greenbelt, which enters roadbed, influences subgrade strength.The fine sand layer of making below geotextiles avoids applying The rupture of work process anti-seepage geotextile.
Kerbstone and kerb cushion block are made of water-permeable cement concrete, and voidage is greater than 20%.Car lane with it is non-maneuver Rainwater in lane is discharged into greenbelt by permeable road kerb, permeable kerb cushion block, and greenbelt undertakes road surface as reservoir Water storage function mitigates sewerage system pressure.
Sponge urban water-through road provided by the utility model, can be in the case where not influencing road surface bearing strength effectively The rainwater within the scope of road surface is excluded, the traffic safety on car lane road surface and non-motor vehicle road surface is improved, effectively solution city Waterlogging problem promotes Urban Natural Hydrology circulation.
The water discharge technology principle of the utility model is sketched: car lane uses half permeable pavement structure, drainage surface thickness Spend 40mm, voidage 15~20%, surface thickness 80mm, voidage 18~25% in draining, Drainage Base thickness 100mm, gap Rate 20~25%;The moisture storage capacity on car lane road surface are as follows: 4 × 15%+8 × 20%+10 × 25%=47mm.Non-motorized lane is using complete Permeable pavement structure, permeable surface thickness 180mm, voidage 10~15%, porous base course thickness 200mm, voidage 20~30%, Underlayment 150mm, voidage 30~40%, non-motor vehicle road surface moisture storage capacity are as follows: 180 × 10%+200 × 20%+150 × 30%= 103mm.As it can be seen that car lane and non-motorized lane have enough water spaces, rapid discharge path table rainwater during having heavy rain Ability.The sealing being arranged between car lane porous base course and semi-rigid underlayment, avoid rainwater penetrate into semi-rigid type base and The intensity for reducing car lane underlayment and roadbed, ensure that the intensity and durability on road surface.
Compared with existing porous pavement, the utility model have it is following the utility model has the advantages that the utility model car lane Using semi-transparent water channel line structure, road surface gathered water can quickly, be effectively discharged by road surface vertical drainage, rainwater is avoided to enter half Rigid base, underlayment and roadbed cause to soften, and improve pavement strength and durability;Greenbelt is as reservoir, in not shadow Rainwater is collected in the case where ringing subgrade strength, the rainwater within the scope of road surface is discharged into greenbelt, is reducing sewerage system pressure Urban ecology water circulation is promoted while power.The ponding within the scope of road surface effectively can be quickly discharged in the utility model, improve Road traffic safety reduces urban waterlogging, promotes Urban Hydrologic system circulation.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the utility model.
Wherein: 1-car lane, 11-drainage surface layers, 12-draining in surface layer, 13-Drainage Bases, 14-semi-rigids Property base, 15-underlayments;2-non-motorized lanes, 21-permeable surface layers, 22-porous base courses, 23-permeable underlayments;3— Greenbelt, 31-planting soils, 32-permeable anti-filter geotextiles, 33-rubble filter layers, 34-drainpipes, 35-permeable cements are mixed Solidifying dirt road kerb, 36-water-permeable cement concrete kerb cushion blocks;4-sealings;5-impervious barrier layers;6-anti-seepage geotextiles;7— Fine sand layer, 8-roadbeds.
Specific embodiment
Illustrate to be described further the utility model with reference to the accompanying drawing.A kind of sponge urban water-through road as shown in Figure 1: Line structure, including car lane 1, non-motorized lane 2, greenbelt 3, roadbed 8, kerbstone 35 and kerb cushion block 36;Its feature exists In: car lane 1 is from top to bottom successively including surface layer 12, Drainage Base 13, semi-rigid type base 14 in drainage surface layer 11, draining With underlayment 15;Sealing 4 is provided between Drainage Base 13 and semi-rigid type base 14.
Non-motorized lane 2 successively includes permeable surface layer 21, porous base course 22 and permeable underlayment 23 from top to bottom.Permeable bottom Impervious barrier layer 5 is provided between base 23 and roadbed 8.
Greenbelt 3 includes planting soil 31, and planting soil 31 is embedded with drainpipe 34, and 34 periphery of drainpipe is equipped with rubble and filters Layer 33,33 periphery of rubble filter layer are equipped with permeable anti-filter geotextiles 32;34 tube wall of drainpipe is equipped with large number of inlet opening, row Water pipe 34 is connected to existing drainage system.
The drainage surface layer 11 of car lane asks OGFC-13 mixture to make using draining drip, and voidage 15% after compacting~ 20%, with a thickness of 4cm;Surface layer 12 asks mixture PAC-20 to make using permeable drip in draining, voidage 18%~25% after compacting, With a thickness of 8cm;Drainage Base 13 is made of ATPB-30 mixture, voidage 20%~25% after compacting, with a thickness of 10cm;Half Rigid base 14 is made of cement stabilized macadam, thickness 20cm;It drains underlayment 15 and uses cement Stability Gravel, thickness 20cm。
The permeable surface layer 21 of non-motorized lane 2 use compacting after voidage for 10%~15% C30 water-permeable cement concrete Production, thickness 18cm;Porous base course 22 use compacting after voidage for 20%~30% porous cement treated macadam, thickness 20cm;Permeable underlayment 23 use compacting after voidage for 30%~40% graded broken stone, thickness 15cm.
The depth of planting soil 31 is 1m, and drainpipe 34 is the PVC floral tube that diameter is 100mm, longitudinally disposed along road, draining The same elevation in 23 bottom of permeable underlayment of 34 tube bottom position of pipe and non-motorized lane.Every 20m is along road laterally one draining of setting Conduit, to connect longitudinal P VC floral tube and sewerage system.
In order to guarantee the anti-seepage effect of anti-seepage geotextile, planting soil 31 and roadbed 8, semi-rigid type base 14, draining when construction Fine sand layer 7 is first set between underlayment 15, is repaved on fine sand layer 7 equipped with anti-seepage geotextile 6.Kerbstone 35 and kerb cushion block 36 is prefabricated using water-permeable cement concrete.
36 bottom of kerb cushion block of car lane 1 is located at the upper surface of sealing 4,36 bottom of kerb cushion block of non-motorized lane 2 Portion is located at the upper surface of permeable underlayment 23.

Claims (8)

1. a kind of sponge urban water-through road structure, including car lane, non-motorized lane, greenbelt, roadbed, kerbstone and edge Stone cushion block;It is characterized by: car lane (1) is from top to bottom successively including surface layer (12), row in drainage surface layer (11), draining Water-base (13), semi-rigid type base (14) and underlayment (15);It is provided between Drainage Base (13) and semi-rigid type base (14) Sealing (4).
2. a kind of sponge urban water-through road structure as described in claim 1, it is characterised in that: non-motorized lane (2) is from upper It successively include permeable surface layer (21), porous base course (22) and permeable underlayment (23) under and;Permeable underlayment (23) and roadbed (8) Between be provided with impervious barrier layer (5).
3. a kind of sponge urban water-through road structure as claimed in claim 2, it is characterised in that: greenbelt (3) includes plantation Native (31), planting soil (31) are embedded with drainpipe (34), and drainpipe (34) periphery is equipped with rubble filter layer (33), rubble filtering Layer (33) periphery is equipped with permeable anti-filter geotextiles (32);Drainpipe (34) tube wall is equipped with large number of inlet opening, drainpipe (34) it is connected to existing drainage system.
4. a kind of sponge urban water-through road structure as claimed in claim 3, it is characterised in that: the drainage surface of car lane Layer (11) asks OGFC-13 mixture to make using draining drip, voidage 15%~20% after compacting, with a thickness of 4cm;Surface layer in draining (12) mixture PAC-20 is asked to make using permeable drip, voidage 18%~25% after compacting, with a thickness of 8cm;Drainage Base (13) It is made of ATPB-30 mixture, voidage 20%~25% after compacting, with a thickness of 10cm;Semi-rigid type base (14) uses cement Stabilization gravel production, thickness 20cm;It drains underlayment (15) and uses cement Stability Gravel, thickness 20cm.
5. a kind of sponge urban water-through road structure as claimed in claim 4, it is characterised in that: non-motorized lane (2) it is saturating Water surface layer (21) use compacting after voidage for 10%~15% C30 water-permeable cement concrete, thickness 18cm;Porous base course (22) Use voidage after compacting for 20%~30% porous cement treated macadam, thickness 20cm;Permeable underlayment (23) is using compacting The graded broken stone that voidage is 30%~40% afterwards, thickness 15cm.
6. a kind of sponge urban water-through road structure as claimed in claim 5, it is characterised in that: the depth of planting soil (31) is 1m, drainpipe (34) are the PVC floral tube that diameter is 100mm, the permeable base of drainpipe (34) tube bottom position and non-motorized lane The same elevation in layer (23) bottom.
7. a kind of sponge urban water-through road structure as described in claim 1 to 6 any one, it is characterised in that: motor vehicle Kerb cushion block (36) bottom in road (1) is located at the upper surface of sealing (4).
8. a kind of sponge urban water-through road structure as claimed in claim 7, it is characterised in that: the edge of non-motorized lane (2) Stone cushion block (36) bottom is located at the upper surface of permeable underlayment (23).
CN201820990506.5U 2018-06-26 2018-06-26 A kind of sponge urban water-through road structure Active CN208501416U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820990506.5U CN208501416U (en) 2018-06-26 2018-06-26 A kind of sponge urban water-through road structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820990506.5U CN208501416U (en) 2018-06-26 2018-06-26 A kind of sponge urban water-through road structure

Publications (1)

Publication Number Publication Date
CN208501416U true CN208501416U (en) 2019-02-15

Family

ID=65286672

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820990506.5U Active CN208501416U (en) 2018-06-26 2018-06-26 A kind of sponge urban water-through road structure

Country Status (1)

Country Link
CN (1) CN208501416U (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110042723A (en) * 2019-04-29 2019-07-23 杭州悦为科技有限公司 The construction method of the permeable road of full precast splice type
CN110241673A (en) * 2019-06-26 2019-09-17 温岭名森园林市政工程有限公司 A kind of town road structure and its construction method
CN111926735A (en) * 2020-07-29 2020-11-13 杨通兰 Road greening isolation belt for sponge city and construction method thereof
CN111945513A (en) * 2020-08-12 2020-11-17 鹏程建设集团有限公司 Municipal road and construction method thereof
CN113308960A (en) * 2021-05-27 2021-08-27 中国五冶集团有限公司 High-turnover assembly type curb cushion block and mold and construction method thereof

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110042723A (en) * 2019-04-29 2019-07-23 杭州悦为科技有限公司 The construction method of the permeable road of full precast splice type
CN110241673A (en) * 2019-06-26 2019-09-17 温岭名森园林市政工程有限公司 A kind of town road structure and its construction method
CN111926735A (en) * 2020-07-29 2020-11-13 杨通兰 Road greening isolation belt for sponge city and construction method thereof
CN111926735B (en) * 2020-07-29 2021-05-07 深圳市八骏环境景观有限公司 Road greening isolation belt for sponge city and construction method thereof
CN111945513A (en) * 2020-08-12 2020-11-17 鹏程建设集团有限公司 Municipal road and construction method thereof
CN111945513B (en) * 2020-08-12 2021-10-08 鹏程建设集团有限公司 Municipal road and construction method thereof
CN113308960A (en) * 2021-05-27 2021-08-27 中国五冶集团有限公司 High-turnover assembly type curb cushion block and mold and construction method thereof

Similar Documents

Publication Publication Date Title
CN208501416U (en) A kind of sponge urban water-through road structure
CN203160147U (en) Rainwater collection and drainage system for road
CN207793788U (en) A kind of porous pavement rain infiltration structure
CN205443840U (en) Car lane permeable pavement structure
CN2883464Y (en) Highway structure of realizing rainwater collection and reuse
CN105507112A (en) Pavement system for preventing waterlogging and supplying underground water
CN206219935U (en) A kind of permeable pavement structure of high intensity, high osmosis
CN104032793A (en) Garden type rainwater impact resistance system used for residential area road
CN208649827U (en) Self-purification drainage system for the strand highway construction of sponge city
CN205636407U (en) Road that permeates water drainage structures that catchments
CN101914882B (en) Low embankment structure in phreatic high slity soil region and construction method thereof
CN103981785A (en) Pervious concrete paving system with penetration and drainage guide tubes
CN207062672U (en) A kind of permeable pavement structure
CN206189240U (en) Permeate water, sidewalk face structure of retaining and drainage
CN2837360Y (en) Water permeable road and pavement structure
CN105544342A (en) Permeable pavement based urban road time-delay drainage structure
CN209024909U (en) A kind of sponge Multifunctional City pavement structure
CN207295367U (en) A kind of asphalt highway edge drainage structure
CN106087639A (en) A kind of highway, Irish bridge structure and Irish bridge construction method
CN111535098A (en) Rainwater drainage system for green belts and sidewalks of town roads and construction method
CN203160091U (en) A road pavement structure for preventing water from gathering on road surfaces
CN203160092U (en) A road rainwater collecting system for preventing water from gathering on road surfaces
CN105803888A (en) Sponge type road paving structure
CN213740415U (en) Porous permeable pavement system
CN214245208U (en) Permeable sidewalk pavement structure with drainage channel

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant