CN208486947U - A kind of combustion steaming united fuel system of bavin - Google Patents

A kind of combustion steaming united fuel system of bavin Download PDF

Info

Publication number
CN208486947U
CN208486947U CN201820858055.XU CN201820858055U CN208486947U CN 208486947 U CN208486947 U CN 208486947U CN 201820858055 U CN201820858055 U CN 201820858055U CN 208486947 U CN208486947 U CN 208486947U
Authority
CN
China
Prior art keywords
lng
heat exchanger
bog
diesel engine
steam turbine
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820858055.XU
Other languages
Chinese (zh)
Inventor
张晓荣
张运秋
李博洋
李卉阳
于成龙
韩淑洁
姚文龙
杨桑宇
黄兴旺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
QINGDAO OCEAN SHIPPING MARINERS COLLEGE
Original Assignee
QINGDAO OCEAN SHIPPING MARINERS COLLEGE
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by QINGDAO OCEAN SHIPPING MARINERS COLLEGE filed Critical QINGDAO OCEAN SHIPPING MARINERS COLLEGE
Priority to CN201820858055.XU priority Critical patent/CN208486947U/en
Application granted granted Critical
Publication of CN208486947U publication Critical patent/CN208486947U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Engine Equipment That Uses Special Cycles (AREA)
  • Filling Or Discharging Of Gas Storage Vessels (AREA)

Abstract

The utility model provides a kind of combustion steaming united fuel system of bavin, and system includes fuel system, refrigeration storage system, gas turbine generating system, diesel power generation system and steam turbine power generating.LNG and BOG comes out from LNG cargo hold, BOG is liquefied as LNG using the LNG in LNG condenser, then gas turbine, diesel engine and donkey boiler are conveyed to together with LNG in LNG condenser, heat exchanger is gasified LNG heating for BOG using the jacket-cooling water or steam turbine high-temp waste gas of diesel engine during conveying, cold energy is wherein used for when LNG heats up and gasifies the refrigeration of freezer, and BOG is used to generate electricity by gas turbine and diesel engine, water in boiler is heated as superheated steam using BOG by donkey boiler, then is transported to steam turbine and is generated electricity.The advantages of the utility model: the requirement based on system dynamic equipment to fuel pressure is different, BOG and LNG is rationally utilized, while realizing the utilization of LNG cold energy again.

Description

A kind of combustion steaming united fuel system of bavin
Technical field
Bavin, which is steamed, the utility model relates to fuel supply field more particularly to a kind of combustion for LNG cargo ship combines fuel Supply system.
Background technique
In recent years, international regulations constantly propose new demand to ship Air Pollutant Emission, so that the LNG fuel of low pollution Increasingly by the favor of shipowner, and the increase of the LNG quantum of international trade is so that the quantity of LNG ships that transport sharply increases.According to mesh Preceding oil price and LNG price level saves fuel cost using diesel oil using LNG clean energy resource ratio, together under identical navigation condition When in environmental protection, the discharge of nitrogen dioxide, carbon dioxide, sulfur dioxide and particulate matter can be effectively reduced using LNG fuel Amount.
LNG cargo ship generallys use single LNG as main energy sources at present, and other merchant ships mostly use double fuel to send out greatly Motivation, most LNG cargo ship is all made of steam turbine power plant, but the whole thermal efficiency of steam turbine is lower.? During LNG cargo ship cargo transport, a large amount of BOG as propellant can be generated, therefore it is united to steam bavin using combustion Fuel system improves the thermal efficiency of system.
It is exactly to use three kinds of gas turbine, diesel engine and steam turbine power devices that bavin association system is steamed in so-called combustion, so The power supply that above-mentioned three kinds of power devices are generated afterwards realizes that joint promotes to marine propuision system.Combustion is steamed bavin and is fired in combination Material supply system is exactly the system for carrying out fuel supply to gas turbine, diesel engine and steam turbine respectively.It is dynamic due to what is used Power device increases three, can not provide using only the BOG in LNG cargo hold for gas turbine, diesel engine and steam turbine Sufficient fuel, therefore while using BOG, it is also necessary to using the LNG in LNG cargo hold come for gas turbine, diesel engine and Steam turbine provides fuel.Operating condition and pressure requirements difference based on gas turbine, diesel engine and steam turbine, transport LNG Design is optimized in the application of the fuel system of ship.
Summary of the invention
The utility model is to provide a kind of combustion steaming bavin joint combustion using LNG and BOG in LNG cargo hold for LNG cargo ship Expect supply system.The system realizes LNG and BOG to gas turbine, diesel engine and donkey boiler (to steam turbine steam supply) Supply, while realizing and LNG cold energy is used for freezer refrigerating in LNG gasification.
The technical solution of the utility model.
A kind of combustion steaming united fuel system of bavin, including fuel system, refrigeration storage system, gas turbine power generation system System, diesel power generation system and steam turbine power generating, wherein fuel system pumps (1,2,3,4), LNG cargo hold by transportation by lighter (5,6,7,8), BOG compressor (9), LNG condenser (10), the first automatic valve (11), force (forcing) pump (12), First Heat Exchanger (20) It is formed with third heat exchanger (25), wherein transportation by lighter pump (1,2,3,4) is respectively placed in the bottom of LNG cargo hold (5,6,7,8), transportation by lighter pump The LNG conveyance conduit of (1,2,3,4) is connected after merging with LNG condenser (10), and LNG cargo hold (5,6,7,8) is located at the BOG at top Conveyance conduit is connected after merging with BOG compressor (9), and then BOG compressor (9) is connected with LNG condenser (10), and first is automatic Valve (11) is connected with the BOG delivery pipe at the top of LNG condenser (10), then again with the BOG delivery pipe before BOG compressor (9) Road be connected, it is in parallel with third heat exchanger (25) after force (forcing) pump (12) is connected with First Heat Exchanger (20), then with LNG condenser (10) the LNG delivery pipe positioned at bottom is connected, and in First Heat Exchanger (20) LNG from tube side flow through and refrigerant from shell side stream Cross, LNG stream crosses tube side in third heat exchanger (25) and heat medium flows through shell side, heat medium be the first diesel engine (28) and The jacket-cooling water of second diesel engine (30) or the high-temp waste gas of steam turbine (35).
Refrigeration storage system is by circulating pump (13), flow control valve (14,16,18), freezer heat exchanger (15,17,19) and first Heat exchanger (20) forms, wherein the series pipe of first flow regulating valve (14) and the first freezer heat exchanger (15), second flow The series pipe and third flow control valve (18) and third freezer heat exchanger of regulating valve (16) and the second freezer heat exchanger (17) (19) it is connect with circulating pump (13) and First Heat Exchanger (20) by placed in series after series pipe is in parallel, wherein being changed first Refrigerant selects R22 in hot device (20).
Gas turbine generating system is by the second heat exchanger (21), the first surge tank (22), gas turbine (23) and the first hair Motor (24) composition, wherein the second heat exchanger (21), the first surge tank (22) and gas turbine (23) pass sequentially through placed in series Connection, gas turbine (23) is connected with the first generator (24) by shaft coupling, wherein LNG is walked in the second heat exchanger (21) Tube side and what heat medium was walked is shell side, heat medium is the jacket-cooling water of the first diesel engine (28) and the second diesel engine (30) Or the high-temp waste gas of steam turbine (35).
Diesel power generation system is successively by the second automatic valve (26), the second surge tank (27), the first diesel engine (28), second Diesel engine (30), the second generator (29) and third generator (31) composition, wherein the second automatic valve (26) and the second surge tank (27) it is connected by placed in series, the admission line of the first diesel engine (28) and the second diesel engine (30) buffers after merging with second Tank (27) is connected by placed in series, and the first diesel engine (28) is connected with the second generator (29) by shaft coupling, the second bavin Oil machine (30) is connected with third generator (31) by shaft coupling.
Steam turbine power generating is successively by third automatic valve (32), third surge tank (33), donkey boiler (34), steam Turbine (35) and the 4th generator (36) composition, wherein third automatic valve (32), third surge tank (33), donkey boiler (34) and Steam turbine (35) passes sequentially through placed in series connection, and steam turbine (35) is connected with the 4th generator (36) by shaft coupling It connects.
The admission line of second automatic valve (26) and third automatic valve (32) is connected after merging with third heat exchanger (25).
Detailed description of the invention
Fig. 1 is that the united fuel system diagram of bavin is steamed in the combustion.
In figure: 1, first the 2, second transportation by lighter of transportation by lighter pump pump 3, the 4, the 4th transportation by lighter pump of third transportation by lighter pump
5, the first LNG cargo hold 6, the 2nd LNG cargo hold 7, the 3rd LNG cargo hold 8, the 4th LNG cargo hold
9, BOG compressor 10, LNG condenser 11, the first automatic valve 12, force (forcing) pump 13, circulating pump
14, first flow regulating valve 15, the first freezer heat exchanger 16, second flow regulating valve
17, the second freezer heat exchanger 18, third flow control valve 19, third freezer heat exchanger 20, first exchange heat Device 21, the second heat exchanger 22, the first surge tank 23, gas turbine 24, the first generator
25, third heat exchanger 26, the second automatic valve 27, the second surge tank 28, the first diesel engine
29, the second generator 30, the second diesel engine 31, third generator 32, third automatic valve
33, third surge tank 34, donkey boiler 35, steam turbine 36, the 4th generator
Specific embodiment
Specific embodiment of the present utility model is described with reference to the accompanying drawing, to more fully understand that this is practical new Type.
For entire fuel system, BOG admission pressure needed for gas turbine (23) 2.8MPa ~ 3MPa it Between, BOG admission pressure needed for the first diesel engine (28) and the second diesel engine (30) is between 0.5 ~ 0.8MPa, and donkey boiler (34) the BOG admission pressure needed for is between 0.1 ~ 0.2MPa, and the BOG pressure as needed for each power device is different, so can To carry out branch supply to each power device.
The main working process of system is.
The LNG of LNG cargo hold (5,6,7,8) bottom enters in LNG condenser (10) after transportation by lighter pump (1,2,3,4) pressurization, And the BOG come out at the top of LNG enters after BOG compressor (9) compression in LNG condenser (10), using the cooling capacity of LNG by BOG Condensation liquefaction is LNG, wherein, since the condensing capacity of LNG condenser (10) is insufficient, leading to part BOG in BOG condensation process It can not liquefy, this part BOG can be such that the pressure of LNG condenser (10) increases.Accident occurs in order to prevent, can be in LNG condenser (10) a BOG delivery pipe is connect at the top of.First automatic valve (11) is by the pressure in measurement LNG condenser (10) come control valve The aperture of door, BOG extra in LNG condenser (10) is transported in BOG pipeline by BOG delivery pipe, is compressed again through BOG After machine (9) compression, into condensation in LNG condenser (10), to guarantee that the interior pressure of LNG condenser (10) is stablized, to guarantee the The admission pressure demand of one diesel engine (28), the second diesel engine (30) and donkey boiler (34), transportation by lighter pump (1,2,3,4) with LNG and BOG can be compressed to 1MPa by BOG compressor (9).
LNG points come out from LNG condenser (10) are two-way, enter the first heat exchange after pressurized pump (12) pressurization all the way In device (20), the refrigerant in refrigeration storage system is allowed to absorb cold energy, then LNG enters in the second heat exchanger (21), utilizes the first diesel oil LNG gasification is BOG, BOG by the heat of the jacket-cooling water or steam turbine (35) exhaust gas of machine (28) and the second diesel engine (30) Enter gas turbine (23) after the first surge tank (22) to burn, gas turbine (23) drives the first generator by shaft coupling (24) it generates electricity, for the admission pressure demand for meeting gas turbine (23), while in view of passing through First Heat Exchanger (20) With pressure loss when the second heat exchanger (21), LNG can be compressed to 3MPa with force (forcing) pump (12).
In refrigeration storage system, the refrigerant for obtaining cold energy comes out from First Heat Exchanger (20), is divided into after circulating pump (13) Three tunnels, it is right into released cold quantity in the first freezer heat exchanger (15) all the way after the flow of first flow regulating valve (14) is adjusted First freezer freezes;Another way enters the second freezer heat exchanger (17) after the flow of second flow regulating valve (16) is adjusted Middle released cold quantity freezes to the second freezer;Finally enter the after the flow of third flow control valve (18) is adjusted all the way Released cold quantity in three freezer heat exchangers (19), freezes to third freezer, wherein the optional R22 of refrigerant used in refrigeration storage system.
Another way LNG enters in third heat exchanger (25), utilizes the cylinder of the first diesel engine (28) and the second diesel engine (30) LNG gasification is BOG by the heat of jacket water or steam turbine (35) exhaust gas, and then BOG points are two-way, automatic through second all the way The pressure of valve (26) is adjusted with after the second surge tank (27), and two-way is divided to respectively enter the first diesel engine (28) and the second diesel engine (30) it burns, the first diesel engine (28) and the second diesel engine (30) pass through shaft coupling and drive the second generator (29) and third respectively Generator (31) generates electricity;Another way adjusts through the pressure of third automatic valve (32) and enters auxiliary after third surge tank (33) Water in boiler (34) is heated into overheat and steamed by boiler (34) burning, the heat that donkey boiler (34) is generated when being burnt using BOG Vapour supplies it to steam turbine (35), and steam turbine (35) drives the 4th generator (36) to generate electricity by shaft coupling, In the second automatic valve (26) by the pressure of BOG in measurement diesel power generation system pipeline come the aperture of control valve so that pipe The pressure of BOG is consistent with the inlet pressure of the first diesel engine (28) and the second diesel engine (30) in road, and third automatic valve (32) is logical Cross in measurement donkey boiler heating system that the pressure of BOG carrys out the aperture of control valve in pipeline so that in pipeline the pressure of BOG with The inlet pressure of donkey boiler (34) is consistent.
When LNG cargo ship is suspended, LNG, which stops supply, leads to the BOG pressure suddenly change of system pipeline, gas turbine hair Extra BOG is conducive to keep pipe in the surge tank (22,27,33) of electric system, diesel power generation system and steam turbine system The stabilization of gas pressure in road.

Claims (1)

1. the united fuel system of bavin is steamed in a kind of combustion, it is characterised in that: including fuel system, refrigeration storage system, combustion gas Turbine electricity generation system, diesel power generation system and steam turbine power generating, wherein fuel system by transportation by lighter pump (1,2,3, 4), LNG cargo hold (5,6,7,8), BOG compressor (9), LNG condenser (10), the first automatic valve (11), force (forcing) pump (12), first Heat exchanger (20) and third heat exchanger (25) composition, wherein transportation by lighter pump (1,2,3,4) is respectively placed in LNG cargo hold (5,6,7,8) Bottom, the LNG conveyance conduit of transportation by lighter pump (1,2,3,4) are connected after merging with LNG condenser (10), LNG cargo hold (5,6,7,8) position It is connected after the BOG conveyance conduit at top merges with BOG compressor (9), then BOG compressor (9) and LNG condenser (10) phase Even, the first automatic valve (11) is connected with the BOG delivery pipe at the top of LNG condenser (10), then again and before BOG compressor (9) BOG conveyance conduit be connected, it is in parallel with third heat exchanger (25) after force (forcing) pump (12) is connected with First Heat Exchanger (20), then with The LNG delivery pipe that LNG condenser (10) is located at bottom is connected, and LNG flows through and refrigerant from tube side in First Heat Exchanger (20) It is flowed through from shell side, LNG stream crosses tube side in third heat exchanger (25) and heat medium flows through shell side, and heat medium is the first diesel oil The high-temp waste gas of the jacket-cooling water or steam turbine (35) of machine (28) and the second diesel engine (30);
Refrigeration storage system is by circulating pump (13), flow control valve (14,16,18), freezer heat exchanger (15,17,19) and the first heat exchange Device (20) composition, wherein the series pipe of first flow regulating valve (14) and the first freezer heat exchanger (15), second flow are adjusted The series pipe and third flow control valve (18) and third freezer heat exchanger (19) of valve (16) and the second freezer heat exchanger (17) Series pipe it is in parallel after connect with circulating pump (13) and First Heat Exchanger (20) by placed in series, wherein in First Heat Exchanger (20) refrigerant selects R22 in;
Gas turbine generating system is by the second heat exchanger (21), the first surge tank (22), gas turbine (23) and the first generator (24) it forms, wherein the second heat exchanger (21), the first surge tank (22) pass sequentially through placed in series with gas turbine (23) and connect, Gas turbine (23) is connected with the first generator (24) by shaft coupling, wherein LNG walks tube side in the second heat exchanger (21) And what heat medium was walked is shell side, heat medium is jacket-cooling water or the steaming of the first diesel engine (28) and the second diesel engine (30) The high-temp waste gas of steam turbine (35);
Diesel power generation system is successively by the second automatic valve (26), the second surge tank (27), the first diesel engine (28), the second diesel oil Machine (30), the second generator (29) and third generator (31) composition, wherein the second automatic valve (26) and the second surge tank (27) Connected by placed in series, the admission line of the first diesel engine (28) and the second diesel engine (30) merge after with the second surge tank (27) it is connected by placed in series, the first diesel engine (28) is connected with the second generator (29) by shaft coupling, the second diesel oil Machine (30) is connected with third generator (31) by shaft coupling;
Steam turbine power generating is successively by third automatic valve (32), third surge tank (33), donkey boiler (34), steam turbine (35) it is formed with the 4th generator (36), wherein third automatic valve (32), third surge tank (33), donkey boiler (34) and steam Turbine (35) passes sequentially through placed in series connection, and steam turbine (35) is connected with the 4th generator (36) by shaft coupling;
The admission line of second automatic valve (26) and third automatic valve (32) is connected after merging with third heat exchanger (25).
CN201820858055.XU 2018-06-05 2018-06-05 A kind of combustion steaming united fuel system of bavin Expired - Fee Related CN208486947U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820858055.XU CN208486947U (en) 2018-06-05 2018-06-05 A kind of combustion steaming united fuel system of bavin

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820858055.XU CN208486947U (en) 2018-06-05 2018-06-05 A kind of combustion steaming united fuel system of bavin

Publications (1)

Publication Number Publication Date
CN208486947U true CN208486947U (en) 2019-02-12

Family

ID=65250746

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820858055.XU Expired - Fee Related CN208486947U (en) 2018-06-05 2018-06-05 A kind of combustion steaming united fuel system of bavin

Country Status (1)

Country Link
CN (1) CN208486947U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112648530A (en) * 2021-01-06 2021-04-13 青岛科技大学 BOG processing system of LNG transport ship
CN113701043A (en) * 2021-08-27 2021-11-26 广东海洋大学 Comprehensive system for preparing, storing and burning hydrogen on LNG ship

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112648530A (en) * 2021-01-06 2021-04-13 青岛科技大学 BOG processing system of LNG transport ship
CN112648530B (en) * 2021-01-06 2022-04-26 青岛科技大学 BOG processing system of LNG transport ship
CN113701043A (en) * 2021-08-27 2021-11-26 广东海洋大学 Comprehensive system for preparing, storing and burning hydrogen on LNG ship

Similar Documents

Publication Publication Date Title
CN102084114B (en) Gas supply systems for gas engines
RU2627323C2 (en) Method and device for gas-fuel supply in internal combustion engine
US7287389B2 (en) Feeding energy to a gas terminal from a ship for transporting liquefied gas
CN109386316B (en) LNG cold energy and BOG combustion energy combined utilization system and method
JP2015500759A (en) Hybrid fuel supply system and method for marine engine
CN112963732A (en) BOG comprehensive utilization system of LNG receiving station
CN208486947U (en) A kind of combustion steaming united fuel system of bavin
JP2015127510A (en) Vessel fuel supply system
KR101232311B1 (en) Waster heat recovery system with the exhaust gas from the gas combustion unit
JP6214252B2 (en) Boiler system
CN108367800A (en) Steamer including engine
KR101614605B1 (en) Supercritical Carbon Dioxide Power Generation System and Ship having the same
CN109723555A (en) Utilize the compound electricity generation system of differential pressure power generation
CN103382930B (en) System utilizing normal temperature compressor to process low temperature gas
US9097208B2 (en) Cryogenic pump system for converting fuel
KR101271188B1 (en) Waste heat recycling system for ship
JP6214253B2 (en) Boiler system
KR102002951B1 (en) LNG Fuel Gas Supply System
KR20160073349A (en) Supercritical Carbon Dioxide Power Generation System and Ship having the same
KR102035891B1 (en) Supercritical Carbon Dioxide Power Generation System and Ship having the same
KR20160017740A (en) Supercritical Carbon Dioxide Power Generation System and Ship having the same
KR101839643B1 (en) Supercritical Carbon Dioxide Power Generation System having Steam Supplying Function and Ship having the same
KR101928138B1 (en) Ship installed Supercritical Carbon Dioxide Power Generation System
KR20160017741A (en) Supercritical Carbon Dioxide Power Generation System and Ship having the same
CN114109658B (en) LNG power ship host machine waste heat and LNG vaporization cold energy integrated utilization system

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190212