CN208440127U - Existing building installs elevator drawing-resisting device additional - Google Patents
Existing building installs elevator drawing-resisting device additional Download PDFInfo
- Publication number
- CN208440127U CN208440127U CN201821027033.5U CN201821027033U CN208440127U CN 208440127 U CN208440127 U CN 208440127U CN 201821027033 U CN201821027033 U CN 201821027033U CN 208440127 U CN208440127 U CN 208440127U
- Authority
- CN
- China
- Prior art keywords
- spring
- billet
- existing building
- high strong
- rubber body
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Abstract
The utility model relates to a kind of existing buildings to install elevator drawing-resisting device additional, belong to building renovation earthquake resistant construction field.It mainly include existing building, bolt, billet, compressed spring, high strong spring, attachment beam, yielding rubber body, steel bracket, planar spring.It is mutually fixed between billet and existing building by bolt, billet is provided with compressed spring and high strong spring far from the side of existing building;Billet is connected with compressed spring, and the another side of compressed spring is connected with attachment beam;Billet is equally connected with high strong spring, and the another side of high strong spring is connected with yielding rubber body;Yielding rubber body is mutually fixed by bolt with attachment beam;The other side of the yielding rubber body far from high strong spring, is provided with steel bracket, planar spring is provided in the middle part of steel bracket.The utility model construction is simple, construction cost are low.Industrialization fractionation is very convenient and easy to produce, is easily installed, and is prefabricated component, is conducive to push process of industrialization.
Description
Technical field
The utility model belongs to building renovation earthquake resistant construction field, installs elevator tension additional more particularly to a kind of existing building
Pulling device.
Background technique
With the quickening of Urbanization in China, Building Trade in China development is very fast, at present whole nation existing building area
Nearly 50,000,000,000 square metres are amounted to, a large amount of existing buildings have been unable to meet modern development since building function is backward and safety is insufficient
It needs, is especially built in the nineteen ninety pervious anti-seismic performance requirement that current specifications is mostly not achieved, while a large amount of existing buildings
For non-energy saving building, it would be highly desirable to carry out reducing energy consumption, it is quite huge that these, which all show that existing building needs the project amount being transformed,
's.
The dwelling construction in China is progressed into from the economical of the phase early 1980s to 21st century
Fairly well-off level, improving existing living quality becomes the primary demand of resident.Due to historical reasons, China still has
Many six, seven layers even higher than seven layers of house is fitted without elevator, and with the arriving of aging society, existing apartment installs electricity additional
The concern for the middle and old age residents that ladder increasingly causes the common people especially to live in walk-up building, become one it is anxious to be resolved
Social concern.
Nowadays earth resource is nervous, and many countries have all entered the ranks of aging, and the development in city has many old
City, we are transformed also in progress like a raging fire existing building.For many existing buildings electricity is not installed
Ladder, this can not meet the needs of people's lives, especially with the propulsion of aging of population, in the old room of not elevator
In son, the inconvenience of the action of the elderly extremely, China is also carrying out the transformation that old house installs elevator additional.So how to guarantee
How the safety for installing elevator additional guarantees the safety of people when nature or artificial disaster occurs, then designing one kind both
It is necessary that building, which installs elevator drawing-resisting device additional,.
Utility model content
In order to solve above-mentioned technical problem, the utility model provides a kind of existing building installation elevator anti-pulling dress
It sets, construction is simple, construction cost is low.Industrialization fractionation is very convenient and easy to produce, is easily installed, and is prefabricated component, has
Conducive to process of industrialization is pushed, mainly for solving to generate the harm of drawing when an earthquake occurs.
The technical solution adopted in the utility model is as follows:
The utility model is that a kind of existing building installs elevator drawing-resisting device additional, including existing building, bolt, billet,
Compressed spring, high strong spring, attachment beam, yielding rubber body, steel bracket (8), planar spring;Lead between billet and existing building
Bolt is crossed mutually to fix;Billet is provided with compressed spring and high strong spring far from the side of existing building;Billet is connected with pressure
The another side of contracting spring, compressed spring is connected with attachment beam;Billet is equally connected with high strong spring, the another side of high strong spring
It is connected with yielding rubber body;Yielding rubber body is mutually fixed by bolt with attachment beam;Yielding rubber body is another far from high strong spring
Side is provided with steel bracket, is provided with planar spring in the middle part of steel bracket (8).
Further, the existing building, bolt, billet, compressed spring, high strong spring, attachment beam, yielding rubber
Body, steel bracket and planar spring carry out waterproof and corrosion-resistant is handled.
Further, the steel bracket and billet are light weight type steel.
Further, the billet, compressed spring, high strong spring, yielding rubber body, steel bracket and planar spring six
Device composed by point is prefabricated components.
Further, the attachment beam uses square steel.
Further, the fixed steel bracket in the inside in attachment beam and planar spring, then fix yielding rubber body
In the other side of steel bracket;It carries out the connection of several high strong springs and carries out the connection of compressed spring.
Further, the construction method of the present apparatus are as follows: by the compressed spring for the device made and high strong spring into
The capable connection with billet, finally passes through bolt for billet) carry out fixation with existing building.
The utility model has the beneficial effects that
The utility model has the beneficial effects that the construction is simple of the utility model, construction cost are low.Industrialization is split very
It is convenient and easy to produce, it is easily installed, is prefabricated component, be conducive to push process of industrialization.Structure is simple, is all very often
The cost of the material seen, construction cost and material is relatively low, and construction quickly, does not influence the normal life needs of people, practicability
By force, easy to spread.When earthquake occurs, installs additional and be good at occurring very much drawing destruction between elevator and existing building, then
The present apparatus can protect existing building well and install the process of the drawing generated between elevator additional, provide one to the process of drawing
A good buffering, and rebound process, can guarantee existing building and install additional elevator will not because of drawing destruction and generate
Danger, provide guarantee for the life security of people.
Detailed description of the invention
Fig. 1 is that the utility model existing building installs elevator drawing-resisting device diagrammatic cross-section additional.
In figure, 1 is existing building;2 be bolt;3 be billet;4 be compressed spring;5 be high strong spring;6 be attachment beam;
7 be yielding rubber body;8 be steel bracket;9 be planar spring.
Specific embodiment:
The utility model is described in detail with reference to the accompanying drawings and embodiments:
Embodiment: as shown in Figure 1, the utility model include existing building 1, it is bolt 2, billet 3, compressed spring 4, high-strength
Spring 5, attachment beam 6, yielding rubber body 7, steel bracket 8, planar spring 9;Pass through 2 phase of bolt between billet 3 and existing building 1
It is fixed;Billet 3 is provided with compressed spring 4 and high strong spring 5 far from the side of existing building 1;Billet 3 is connected with compression bullet
Spring 4, the another side of compressed spring 4 are connected with attachment beam 6;Billet 3 is equally connected with high strong spring 5, high strong spring 5 it is another
While being connected with yielding rubber body 7;Yielding rubber body 7 is fixed by bolt 2 and 6 phase of attachment beam, and attachment beam 6 uses square steel;It is slow
The other side of the rubber bodies 7 far from high strong spring 5 is rushed, steel bracket 8 is provided with, the middle part of steel bracket 8 is provided with planar spring 9.
The existing building 1, bolt 2, billet 3, compressed spring 4, high strong spring 5, attachment beam 6, yielding rubber body 7,
Steel bracket 8 and planar spring 9 carry out waterproof and corrosion-resistant is handled.
The steel bracket 8 and billet 3 are light weight type steel.
The billet 3, compressed spring 4, high strong spring 5,9 six part of yielding rubber body 7, steel bracket 8 and planar spring
Composed device is prefabricated components.
Yielding rubber body 7, is then fixed on steel branch by the fixed steel bracket 8 in the inside in attachment beam 6 and planar spring 9
The other side of frame 8;It carries out the connection of several high strong springs 5 and carries out the connection of compressed spring 4.
The construction method is the compressed spring 4 for the device that will be made and high strong spring 5 carries out and the company of billet 3
It connects, billet 3 is finally carried out to the fixation with existing building 1 by bolt 2.
The above is only the preferred embodiment of the utility model, it is noted that for the common skill of the art
For art personnel, without departing from the principle of this utility model, several improvements and modifications can also be made, these improve and
Retouching also should be regarded as the protection scope of the utility model.
Claims (7)
1. existing building installs elevator drawing-resisting device additional, it is characterised in that: including existing building (1), bolt (2), billet
(3), compressed spring (4), high strong spring (5), attachment beam (6), yielding rubber body (7), steel bracket (8), planar spring (9);Steel
It is mutually fixed between backing plate (3) and existing building (1) by bolt (2);Billet (3) is arranged far from the side of existing building (1)
There are compressed spring (4) and high strong spring (5);Billet (3) is connected with compressed spring (4), the another side connection of compressed spring (4)
There are attachment beam (6);Billet (3) is equally connected with high strong spring (5), and the another side of high strong spring (5) is connected with yielding rubber
Body (7);Yielding rubber body (7) is mutually fixed by bolt (2) with attachment beam (6);Yielding rubber body (7) is far from high strong spring (5)
The other side, be provided with steel bracket (8), planar spring (9) be provided in the middle part of steel bracket (8).
2. existing building as described in claim 1 installs elevator drawing-resisting device additional, it is characterised in that: existing building (1), bolt
(2), billet (3), compressed spring (4), high strong spring (5), attachment beam (6), yielding rubber body (7), steel bracket (8) and plate
Spring (9) carries out waterproof and corrosion-resistant is handled.
3. existing building as described in claim 1 installs elevator drawing-resisting device additional, it is characterised in that: steel bracket (8) and billet
It (3) is light weight type steel.
4. existing building as described in claim 1 installs elevator drawing-resisting device additional, it is characterised in that: billet (3), compressed spring
(4), high strong spring (5), device composed by (9) six part of yielding rubber body (7), steel bracket (8) and planar spring are prefabricated
Component.
5. existing building as described in claim 1 installs elevator drawing-resisting device additional, it is characterised in that: attachment beam (6) uses square
Steel.
6. existing building as described in claim 1 installs elevator drawing-resisting device additional, it is characterised in that: in the inside of attachment beam (6)
Fixed steel bracket (8) and planar spring (9), are then fixed on yielding rubber body (7) other side of steel bracket (8);It is counted
The connection of the high strong spring of root (5) and the connection for carrying out compressed spring (4).
7. existing building as described in claim 1 installs elevator drawing-resisting device additional, it is characterised in that: by the pressure for the device made
Contracting spring (4) and high strong spring (5) carry out the connection with billet (3), finally by billet (3) by bolt (2) carry out with
The fixation of existing building (1).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821027033.5U CN208440127U (en) | 2018-07-01 | 2018-07-01 | Existing building installs elevator drawing-resisting device additional |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201821027033.5U CN208440127U (en) | 2018-07-01 | 2018-07-01 | Existing building installs elevator drawing-resisting device additional |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208440127U true CN208440127U (en) | 2019-01-29 |
Family
ID=65086944
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201821027033.5U Expired - Fee Related CN208440127U (en) | 2018-07-01 | 2018-07-01 | Existing building installs elevator drawing-resisting device additional |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208440127U (en) |
-
2018
- 2018-07-01 CN CN201821027033.5U patent/CN208440127U/en not_active Expired - Fee Related
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108824841A (en) | A kind of installation elevator basis anti-sedimentation apparatus and its construction method | |
CN108979194A (en) | A kind of existing building installs elevator flexible connection node and its construction method additional | |
CN201543150U (en) | High-rise industrial building fire-fighting water supply system configuration structure | |
CN208440127U (en) | Existing building installs elevator drawing-resisting device additional | |
CN108545571A (en) | Existing building installs elevator drawing-resisting device additional | |
CN208440128U (en) | Existing building installs the hoistway and attachment beam stiffening device of elevator additional | |
CN108657900A (en) | Install elevator and existing building buffer device for collision additional | |
CN205838261U (en) | The special lift device that the transformation of a kind of old buildings uses | |
CN208440126U (en) | Install elevator and existing building buffer device for collision additional | |
CN203722553U (en) | Automatic wind-shielding overload protection photovoltaic support | |
CN208441508U (en) | Existing building installs elevator shearing resistance cutting apparatus additional | |
CN208777761U (en) | A kind of existing building installation elevator flexible connection node | |
CN208441506U (en) | A kind of existing building installation earthquake resistance of elevator attachment device | |
CN208884556U (en) | A kind of installation elevator basis and hoistway reinforce bracing means | |
CN207529763U (en) | A kind of structure for reducing dry-type transformer operation noise | |
CN106006308A (en) | Elevator device special for old building reconstruction | |
CN108797624A (en) | A kind of installation elevator basis reinforce bracing means with hoistway | |
CN208441507U (en) | A kind of existing building installs the stiffening device of elevator additional | |
CN207988562U (en) | A kind of Fire lift floor | |
CN208440131U (en) | Anti- installation elevator and existing building crash device | |
CN108571182A (en) | A kind of existing building installs the stiffening device of elevator additional | |
CN108678414A (en) | A kind of existing building installation earthquake resistance of elevator attachment device | |
CN108678413A (en) | Existing building installs elevator shearing resistance cutting apparatus additional | |
CN108675087A (en) | A kind of existing building installs the reinforcement connecting beam apparatus of elevator additional | |
CN108545572A (en) | Existing building installs the hoistway and tie-beam stiffening device of elevator additional |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190129 Termination date: 20210701 |
|