- Publication number
- CN208440128U CN208440128U CN201821028602.8U CN201821028602U CN208440128U CN 208440128 U CN208440128 U CN 208440128U CN 201821028602 U CN201821028602 U CN 201821028602U CN 208440128 U CN208440128 U CN 208440128U
- Authority
- CN
- China
- Prior art keywords
- elevator
- support rod
- support bar
- hoistway
- connector
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 230000003014 reinforcing effect Effects 0.000 title claims abstract description 11
- 229910000831 Steel Inorganic materials 0.000 claims description 8
- 239000010959 steel Substances 0.000 claims description 8
- 238000004078 waterproofing Methods 0.000 claims 2
- 238000011282 treatment Methods 0.000 claims 1
- 238000010276 construction Methods 0.000 abstract description 7
- 230000002787 reinforcement Effects 0.000 abstract description 4
- 238000009418 renovation Methods 0.000 abstract description 2
- 230000032683 aging Effects 0.000 description 3
- 230000018109 developmental process Effects 0.000 description 3
- 230000009286 beneficial effect Effects 0.000 description 2
- 238000005260 corrosion Methods 0.000 description 2
- 230000007797 corrosion Effects 0.000 description 2
- 230000005611 electricity Effects 0.000 description 2
- 238000009434 installation Methods 0.000 description 2
- 239000000463 material Substances 0.000 description 2
- 238000000034 method Methods 0.000 description 2
- 230000009471 action Effects 0.000 description 1
- 238000005265 energy consumption Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 230000008569 process Effects 0.000 description 1
- 238000010008 shearing Methods 0.000 description 1
- 230000000087 stabilizing effect Effects 0.000 description 1
- 230000009466 transformation Effects 0.000 description 1
Landscapes
- Lift-Guide Devices, And Elevator Ropes And Cables (AREA)
Abstract
The utility model relates to hoistways and attachment beam stiffening device that a kind of existing building installs elevator additional, belong to building renovation reinforcement measure field.It mainly include elevator, hoistway column, attachment beam, first support bar, second support bar, the first connector, the second connector, rubber block, planar spring, billet.The position lower part that elevator is connect with attachment beam is provided with hoistway column;Between left and right sides side hoistway column and attachment beam, it is tiltedly equipped with first support bar and second support bar;Two first support bars and second support bar are connected with hoistway column by the first connector respectively;The top of rubber block is provided with planar spring, and rubber block is connected with second support bar by the second connector;The planar spring on left and right sides second support bar top passes through the second connector respectively and is connected with elevator and attachment beam;The utility model structure is simple, and cost is relatively low, construction quickly, it is practical, it is easy to spread and have well reinforce reinforcing effect, bring guarantee to the safety of people.
Description
Technical field
The utility model belongs to building renovation reinforcement measure field, installs the well of elevator additional more particularly to a kind of existing building
Road and attachment beam stiffening device.
Background technique
With the quickening of Urbanization in China, Building Trade in China development is very fast, at present whole nation existing building area
Nearly 50,000,000,000 square metres are amounted to, a large amount of existing buildings have been unable to meet modern development since building function is backward and safety is insufficient
It needs, is especially built in the nineteen ninety pervious anti-seismic performance requirement that current specifications is mostly not achieved, while a large amount of existing buildings
For non-energy saving building, it would be highly desirable to carry out reducing energy consumption, it is quite huge that these, which all show that existing building needs the project amount being transformed,
's.
The dwelling construction in China is progressed into from the economical of the phase early 1980s to 21st century
Fairly well-off level, improving existing living quality becomes the primary demand of resident.Due to historical reasons, China still has
Many six, seven layers even higher than seven layers of house is fitted without elevator, and with the arriving of aging society, existing apartment installs electricity additional
The concern for the middle and old age residents that ladder increasingly causes the common people especially to live in walk-up building, become one it is anxious to be resolved
Social concern.
Nowadays earth resource is nervous, and many countries have all entered the ranks of aging, and the development in city has many old
City, we are transformed also in progress like a raging fire existing building.For many existing buildings electricity is not installed
Ladder, this can not meet the needs of people's lives, especially with the propulsion of aging of population, in the old room of not elevator
In son, the inconvenience of the action of the elderly extremely, China is also carrying out the transformation that old house installs elevator additional.So how to guarantee
How the safety for installing elevator additional guarantees the safety of people when nature or artificial disaster occurs, then designing one kind both
Building installs the hoistway of elevator additional and attachment beam stiffening device is necessary.
Utility model content
In order to solve above-mentioned technical problem, the utility model provide a kind of existing building install additional the hoistway of elevator with
Attachment beam stiffening device, simple mainly for developing a kind of structure, cost is relatively low, construction quickly, it is practical, it is easy to spread and
There is the device for reinforcing reinforcing effect well, it is more safe firm between elevator and attachment beam to make, to solve to install elevator additional
The problems such as insecure with attachment beam.
The technical solution adopted in the utility model is as follows:
The utility model is the hoistway and attachment beam stiffening device of a kind of existing building installation elevator, including elevator, hoistway
Column, attachment beam, first support bar, second support bar, the first connector, the second connector, rubber block, planar spring, billet;
Attachment beam is connected on the right side of elevator;The position lower part that elevator is connect with attachment beam is provided with hoistway column;Left side hoistway column and company
It connects between beam, is tiltedly equipped with first support bar, it is same between right side hoistway column and attachment beam to be tiltedly equipped with first support bar, two first
Support rod is arranged in up-side down triangle;The position of first support bar middle and upper part is horizontally disposed second support bar;First support bar
Both ends are provided with billet;Two first support bars are connected with hoistway column by the first connector, and left side first support bar passes through
First connector is connected with elevator, and right side first support bar is connected by the first connector with attachment beam;Second support bar is same
It is connected by the first connector with hoistway column;The top of second support bar is provided with rubber block, and the top of rubber block is provided with flat
Flat spring, rubber block are connected with second support bar by the second connector;The planar spring on left side second support bar top passes through
Second connector is connected with elevator, and the planar spring on right side second support bar top is connected by the second connector with attachment beam;
Further, the first support bar, second support bar, the first connector, the second connector, rubber block, plate
Spring and billet carry out waterproof and corrosion-resistant is handled.
Further, the first support bar, second support bar and billet are light weight type steel.
Further, the first support bar, second support bar, the first connector, the second connector, rubber block, plate
Device composed by spring and billet is prefabricated components.
Further, the cross section of the first support bar and the formed figure of second support bar is the shape of falling A.
Further, described by prefabricated component, the lower part of first support bar and second support bar are connected by first
Fitting is connected with hoistway column;The top of first support bar is connected by the first connector with elevator and attachment beam;By plate bullet
Spring is connected by the second connector with attachment beam and elevator;Finally carry out the processing such as subsequent waterproof.
The utility model has the beneficial effects that
The utility model has the beneficial effects that the construction is simple of the utility model, construction cost are low.Industrialization is split very
It is convenient and easy to produce, it is easily installed, is prefabricated component, be conducive to push process of industrialization.Structure is simple, is all very often
The cost of the material seen, construction cost and material is relatively low, and construction quickly, does not influence the normal life needs of people, practicability
By force, easy to spread.After installing elevator additional for existing building, elevator shaft using particularly significant, bearing capacity needs very high
It is required that the requirement of stabilizing power is also very high, the position that elevator shaft is connected with attachment beam is relatively very weak place, is easiest to
It destroys, is threatened to the safety belt of people.The use of the present apparatus can reinforce reinforcement, elevator shaft and attachment beam well
Between connection, improve the intensity of junction, the performances such as tension shearing resistance have and reinforce reinforcing effect well, to the trip of people
Safety belt ensures.
Detailed description of the invention
Fig. 1 is the hoistway and attachment beam stiffening device diagrammatic cross-section that existing building installs elevator additional.
In figure, 1 is elevator;2 be hoistway column;3 be attachment beam;4 be first support bar;5 be second support bar;6 be first
Connector;7 be the second connector;8 be rubber block;9 be planar spring;10 be billet.
Specific embodiment
The utility model is described in detail with reference to the accompanying drawings and embodiments:
Embodiment: as shown in Figure 1, the utility model is the hoistway and attachment beam reinforcement dress of a kind of existing building installation elevator
Set, including elevator 1, hoistway column 2, attachment beam 3, first support bar 4, second support bar 5, the first connector 6, the second connector 7,
Rubber block 8, planar spring 9, billet 10;The right side of elevator 1 is connected with attachment beam 3;The position that elevator 1 is connect with attachment beam 3
Lower part is provided with hoistway column 2;Between left side hoistway column 2 and attachment beam 3, it is tiltedly equipped with first support bar 4, right side hoistway column 2 and company
It connects and is equally tiltedly equipped with first support bar 4 between beam 3, two first support bars 4 are arranged in up-side down triangle;On in first support bar 4
The position in portion is horizontally disposed second support bar 5;The both ends of first support bar 4 are provided with billet 10;Two first support bars 4
Be connected with hoistway column 2 by the first connector 6, left side first support bar 4 passes through the first connector 6 and is connected with elevator 1, right side the
One support rod 4 is connected by the first connector 6 with attachment beam 3;Second support bar 5 equally passes through the first connector 6 and hoistway column 2
It is connected;The top of second support bar 5 is provided with rubber block 8, and the top of rubber block 8 is provided with planar spring 9, rubber block 8 and
Two support rods 5 are connected by the second connector 7;The planar spring 9 on 5 top of left side second support bar by the second connector 7 with
Elevator 1 is connected, and the planar spring 9 on 5 top of right side second support bar is connected by the second connector 7 with attachment beam 3;
As shown in Figure 1, the first support bar 4, second support bar 5, the first connector 6, the second connector 7, rubber block
8, planar spring 9 and billet 10 carry out waterproof and corrosion-resistant is handled.
As shown in Figure 1, the first support bar 4, second support bar 5 and billet 10 are light weight type steel.
As shown in Figure 1, the first support bar 4, second support bar 5, the first connector 6, the second connector 7, rubber block
8, device composed by planar spring 9 and billet 10 is prefabricated components.
As shown in Figure 1, the cross section of the first support bar 4 and the formed figure of second support bar 5 is the shape of falling A.
As shown in Figure 1, it is described by prefabricated component, the lower part of first support bar 4 and second support bar 5 are passed through first
Connector 6 is connected with hoistway column 2;The top of first support bar 4 is connected by the first connector 6 with elevator 1 and attachment beam 3;
Planar spring 9 is connected by the second connector 7 with attachment beam 3 and elevator 1;Finally carry out the processing such as subsequent waterproof.
The above is only the preferred embodiment of the utility model, it is noted that for the common skill of the art
For art personnel, without departing from the principle of this utility model, several improvements and modifications can also be made, these improve and
Retouching also should be regarded as the protection scope of the utility model.
Claims (6)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201821028602.8U CN208440128U (en) | 2018-07-01 | 2018-07-01 | Reinforcing device for hoistway and connecting beam of elevator installed in existing building |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201821028602.8U CN208440128U (en) | 2018-07-01 | 2018-07-01 | Reinforcing device for hoistway and connecting beam of elevator installed in existing building |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN208440128U true CN208440128U (en) | 2019-01-29 |
Family
ID=65087702
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201821028602.8U Expired - Fee Related CN208440128U (en) | 2018-07-01 | 2018-07-01 | Reinforcing device for hoistway and connecting beam of elevator installed in existing building |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN208440128U (en) |
Cited By (1)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN113338440A (en) * | 2021-06-29 | 2021-09-03 | 福建宏之升钢结构工程有限公司 | Steel beam supporting structure with multi-layer steel structure |
-
2018
- 2018-07-01 CN CN201821028602.8U patent/CN208440128U/en not_active Expired - Fee Related
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN113338440A (en) * | 2021-06-29 | 2021-09-03 | 福建宏之升钢结构工程有限公司 | Steel beam supporting structure with multi-layer steel structure |
| CN113338440B (en) * | 2021-06-29 | 2022-06-21 | 福建宏之升钢结构工程有限公司 | Steel beam supporting structure with multi-layer steel structure |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN203247867U (en) | Building structure for installing elevator for old building | |
| CN103437423A (en) | Controllable quantitative release connection method and structure for steel truss | |
| CN101892706B (en) | Current building renovation external energy-saving balcony structure system | |
| CN208440128U (en) | Reinforcing device for hoistway and connecting beam of elevator installed in existing building | |
| CN205894274U (en) | Assembly type structure structure | |
| CN106006308A (en) | Elevator device special for old building reconstruction | |
| CN208884556U (en) | A kind of reinforcement device for adding elevator foundation and shaft | |
| CN108979194A (en) | A kind of existing building installs elevator flexible connection node and its construction method additional | |
| CN205838261U (en) | The special lift device that the transformation of a kind of old buildings uses | |
| CN208440133U (en) | A reinforced connecting beam device for adding elevators to existing buildings | |
| CN208777761U (en) | An elevator flexible connection node installed in an existing building | |
| CN208440127U (en) | Anti-pulling device for elevators installed in existing buildings | |
| CN208440126U (en) | Install elevator and existing building collision buffer device | |
| CN208441507U (en) | A kind of existing building installs the stiffening device of elevator additional | |
| CN207974241U (en) | A kind of combined box-shaped building formed steel construction system | |
| CN208441506U (en) | A kind of existing building installation earthquake resistance of elevator attachment device | |
| CN108657900A (en) | Install elevator and existing building buffer device for collision additional | |
| CN207988562U (en) | A kind of Fire lift floor | |
| CN206091502U (en) | Use concrete frame antidetonation reinforced structure of steel sheet net | |
| JP2013044187A (en) | Building | |
| CN105088980B (en) | A kind of helistop | |
| CN108675087A (en) | A kind of existing building installs the reinforcement connecting beam apparatus of elevator additional | |
| CN108545571A (en) | Existing building installs elevator drawing-resisting device additional | |
| CN207404653U (en) | A kind of light elevator | |
| CN209369027U (en) | Prefabricated concrete upper and lower column and beam connection nodes |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| GR01 | Patent grant | ||
| GR01 | Patent grant | ||
| CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20190129 Termination date: 20210701 |
|
| CF01 | Termination of patent right due to non-payment of annual fee |