CN208437430U - A kind of steel pipe's production cooling device - Google Patents

A kind of steel pipe's production cooling device Download PDF

Info

Publication number
CN208437430U
CN208437430U CN201821716078.3U CN201821716078U CN208437430U CN 208437430 U CN208437430 U CN 208437430U CN 201821716078 U CN201821716078 U CN 201821716078U CN 208437430 U CN208437430 U CN 208437430U
Authority
CN
China
Prior art keywords
cooling
steel pipe
cooler bin
bay
salvaging
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201821716078.3U
Other languages
Chinese (zh)
Inventor
朱小敏
吕镕昊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Wuxi Xinding Metal Products Co Ltd
Original Assignee
Wuxi Xinding Metal Products Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Wuxi Xinding Metal Products Co Ltd filed Critical Wuxi Xinding Metal Products Co Ltd
Priority to CN201821716078.3U priority Critical patent/CN208437430U/en
Application granted granted Critical
Publication of CN208437430U publication Critical patent/CN208437430U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model relates to steel pipe's production fields, specifically a kind of steel pipe's production cooling device, including substrate, cooling component, spray assemblies, limit assembly, salvage cooling bay and recirculation assembly, the cooling component, limit assembly and recirculation assembly are installed in the top of substrate, spray assemblies are mounted on the top of cooling component, and the top of spray assemblies is located at the underface of one end of limit assembly, the other end of limit assembly is located at the top for salvaging cooling bay, the both ends of recirculation assembly are connected with salvaging cooling bay and cooling component respectively, it was equipped with for the first communicating pipe between salvaging cooling bay and the cooling component, the both ends of first communicating pipe are connected with salvaging cooling bay and cooling component respectively.The utility model structure is simple, improves the cooling efficiency and production efficiency of steel pipe, reduces the use of water flow, and practicability is stronger.

Description

A kind of steel pipe's production cooling device
Technical field
The utility model relates to steel pipe's production field, specifically a kind of steel pipe's production cooling device.
Background technique
Steel pipe is applied not only to trandfer fluid and powdery solid, exchange thermal energy, manufacture machine components and container, it is still a kind of Economic steel.Building structure rack, pillar and machinery mount are manufactured with steel pipe, weight can be mitigated, saves metal 20~40%, And it can realize batch production mechanized construction.Steel can be saved, simplify construction by manufacturing highway bridge not only with steel pipe, and can be big The big area for reducing stopping off, investment reduction and maintenance cost, are widely used afterwards in every field.
The production of steel pipe at present be by plug successively by hot melt, perforation and cooling process be process, to plug into Steel pipe is formed after eleven punch 11 process, needs to cool down it, traditional mode, which is used, carries out water cooling in cooling bay for steel pipe, After cooling to a certain number of steel pipes, need to replace in the water in cooling bay, this mode is not only to the cooling of steel pipe Speed is slower, and larger to the output of manual labor, influences the production efficiency of steel pipe.
Utility model content
The purpose of this utility model is to provide a kind of steel pipe's production cooling devices, to solve to mention in above-mentioned background technique Out the problem of.
The technical solution of the utility model is: including substrate, cooling component, spray assemblies, limit assembly, salvaging cooling bay And recirculation assembly, the cooling component, limit assembly and recirculation assembly are installed in the top of substrate, spray assemblies are mounted on cold But the top of component, and the top of spray assemblies is located at the underface of one end of limit assembly, the other end position of limit assembly In the top for salvaging cooling bay, the both ends of recirculation assembly are connected with salvaging cooling bay and cooling component respectively, and the salvaging is cold But be equipped with for the first communicating pipe between pond and cooling component, the both ends of the first communicating pipe respectively with salvage cooling bay and cooling component phase Connection.
In one preferred embodiment of the utility model, the cooling component includes cooler bin, cooling tube and suction pump, described Cooling tube is mounted in cooler bin, and the output end of suction pump is connected with spray assemblies, input terminal and the cooler bin phase of suction pump Connection.
In one preferred embodiment of the utility model, the spray assemblies include shell, the second communicating pipe, three spray heads With three pipeline fixers, shell inside in rectangular configuration and with cooler bin is connected, three spray heads in vertical and Equidistantly it is mounted in shell, the both ends of the second communicating pipe are connected with the output end of three spray heads and suction pump respectively, and three A pipeline fixer is corresponded with three spray heads and is fixedly connected with the inner wall of shell.
In one preferred embodiment of the utility model, the limit assembly includes support frame, shaft, driving motor, carrying Frame, several limit shafts and it is several lead batter post, several batter posts of leading equally are arranged, and support frame is fixed with all bottoms for leading batter post It connects, is fixedly connected at the top of the bottom of support frame and substrate, carrier is in the top for being vertically installed at cooler bin, driving motor In the top for being horizontally arranged at carrier and its output end is fixedly connected with one end of shaft, if the other end of shaft sequentially passes through Dry to lead batter post, several limit shafts are equidistantly fixed in shaft.
In one preferred embodiment of the utility model, the recirculation assembly includes water circulating pump, third connecting pipe and the 4th Communicating pipe, the water circulating pump are mounted on the top of substrate, the both ends of third connecting pipe respectively with salvage cooling bay and recirculated water The input terminal of pump is connected, and the both ends of the 4th communicating pipe are connected with the output end of water circulating pump and cooler bin respectively.
It is described to salvage the catheterization table for being equipped with and being inclined to set in cooling bay in one preferred embodiment of the utility model.
The utility model provides a kind of steel pipe's production cooling device herein and has compared with prior art by improving Following improvement and advantage:
(1) it is docked by several batter posts of leading with the punching machine of steel pipe, is slid after plug is completed to perforate to several and led tiltedly On column, several limited posts limit steel pipe, are driven using suction pump the water in cooler bin flowing to three from the second communicating pipe In a spray head, steel pipe is cooled down for the first time, the rotation of driving motor drive shaft, several limit shafts in drive shaft are therewith Rotation slides steel pipe to salvaging in cooling bay according to self gravity, realizes the secondary cooling to steel pipe, the utility model structure Simply, the cooling efficiency and production efficiency of steel pipe are improved.
(2) it is driven by water circulating pump and the water salvaged in cooling bay is successively passed through into third connecting pipe and the 4th communicating pipe stream To cooler bin, the water in cooler bin is rapidly cooled using cooling tube, the first communicating pipe drained into the water in cooler bin It salvages in cooling bay, realizes the quick-replaceable of water;And be connected using shell with cooler bin, it can be realized to three spray heads Water is recycled, and the use of water flow is reduced, to reduce production cost, practicability is stronger.
Detailed description of the invention
The utility model is further explained with reference to the accompanying drawings and examples:
Fig. 1 is the schematic perspective view of the utility model;
Fig. 2 is the top view of the utility model;
Fig. 3 is the cross-sectional view in Fig. 2 along line A-A;
Fig. 4 is the cross-sectional view in Fig. 2 along line B-B;
Description of symbols:
Substrate 1, cooling component 2, cooler bin 2a, cooling tube 2b, suction pump 2c, spray assemblies 3, shell 3a, the second connection Pipe 3b, spray head 3c, pipeline fixer 3d, limit assembly 4, support frame 4a, shaft 4b, driving motor 4c, carrier 4d, limit Axis 4e, leads batter post 4f, salvages cooling bay 5, recirculation assembly 6, water circulating pump 6a, third connecting pipe 6b, the 4th communicating pipe 6c, and first Communicating pipe 7, catheterization table 8.
Specific embodiment
The utility model is described in detail below in conjunction with attached Fig. 1 to Fig. 4, to the skill in the utility model embodiment Art scheme is clearly and completely described, it is clear that and the described embodiments are only a part of the embodiments of the utility model, and The embodiment being not all of.Based on the embodiments of the present invention, those of ordinary skill in the art are not making creativeness Every other embodiment obtained, fall within the protection scope of the utility model under the premise of labour.
The utility model provides a kind of steel pipe's production cooling device by improving herein, as Figure 1-Figure 4, including base Plate 1, spray assemblies 3, limit assembly 4, salvages cooling bay 5 and recirculation assembly 6, the cooling component 2, limit group at cooling component 2 Part 4 and recirculation assembly 6 are installed in the top of substrate 1, and spray assemblies 3 are mounted on the top of cooling component 2, and spray assemblies 3 top is located at the underface of one end of limit assembly 4, and the other end of limit assembly 4 is located at the top for salvaging cooling bay 5, follows The both ends of ring assemblies 6 respectively with salvage cooling bay 5 and cooling component 2 and be connected, the salvaging cooling bay 5 and cooling component 2 it Between be equipped with for the first communicating pipe 7, the both ends of the first communicating pipe 7 respectively with salvage cooling bay 5 and cooling component 2 and be connected.
The cooling component 2 includes that cooler bin 2a, cooling tube 2b and suction pump 2c, the cooling tube 2b are mounted on cooler bin In 2a, the output end of suction pump 2c is connected with spray assemblies 3, and the input terminal of suction pump 2c is connected with cooler bin 2a, utilizes Cooling tube 2b cools down the water in cooler bin 2a, and suction pump 2c driving can will flow to nozzle component in cooler bin 2a, To realize the first cooling of steel pipe.
The spray assemblies 3 include shell 3a, the second communicating pipe 3b, three spray head 3c and three pipeline fixer 3d, The shell 3a is in rectangular configuration and is connected with the inside of cooler bin 2a, and three spray head 3c are in vertical and are equidistantly mounted on In shell 3a, the both ends of the second communicating pipe 3b are connected with the output end of three spray head 3c and suction pump 2c respectively, three pipes Road fixing piece 3d is corresponded with three spray head 3c and is fixedly connected with the inner wall of shell 3a, and being driven by suction pump 2c will Water in cooler bin 2a is flow in three spray head 3c from the second communicating pipe 3b, realizes the first cooling to steel pipe, it is cold to improve its But efficiency.
If the limit assembly 4 include support frame 4a, shaft 4b, driving motor 4c, carrier 4d, several limit shaft 4e and Dry to lead batter post 4f, several batter post 4f that lead equally are arranged, and support frame 4a is fixedly connected with all bottoms for leading batter post 4f, support The bottom of frame 4a is fixedly connected with the top of substrate 1, and carrier 4d is in the top for being vertically installed at cooler bin 2a, driving motor 4c In the top for being horizontally arranged at carrier 4d and its output end is fixedly connected with one end of shaft 4b, and the other end of shaft 4b is successively Batter post 4f is led through several, several limit shaft 4e are equidistantly fixed on shaft 4b, several to being located at by several limit shaft 4e The steel pipe led on batter post 4f is limited, when spray assemblies 3 to steel pipe by for the first time cool down after, driving motor 4c drive shaft 4b It is rotated synchronously with several limit shaft 4e, steel pipe slides according to self gravity to cooling bay 5 is salvaged, and completes secondary cooling.
The recirculation assembly 6 includes water circulating pump 6a, third connecting pipe 6b and the 4th communicating pipe 6c, the water circulating pump 6a It is mounted on the top of substrate 1, the both ends of third connecting pipe 6b are connected with the input terminal for salvaging cooling bay 5 and water circulating pump 6a respectively Logical, the both ends of the 4th communicating pipe 6c are connected with the output end of water circulating pump 6a and cooler bin 2a respectively, pass through water circulating pump 6a The water salvaged in cooling bay 5 can be flow to cooling in cooler bin 2a from third connecting pipe 6b and the 4th communicating pipe 6c by driving, when It after cooling, salvages in cooling bay 5, is completed to the quick-replaceable for salvaging cooling bay 5 from flowing to the first communicating pipe 7.
It is described to salvage the catheterization table 8 for being equipped with and being inclined to set in cooling bay 5, fishing is carried out to steel pipe convenient for postorder.
Working principle: being led batter post 4f and docked with the punching machine of steel pipe by several, slid after plug completes perforation to Several to lead on batter post 4f, several limited posts limit steel pipe, using suction pump 2c driving by the water in cooler bin 2a from the Two communicating pipes 3b flow in three spray head 3c, were cooled down for the first time to steel pipe, and driving motor 4c drive shaft 4b rotation drives Several limit shaft 4e on shaft 4b are rotated with it, and are slid steel pipe to salvaging in cooling bay 5 according to self gravity, are realized to steel The secondary cooling of pipe;The water salvaged in cooling bay 5 is successively passed through into third connecting pipe 6b and the 4th by water circulating pump 6a driving Communicating pipe 6c flow in cooler bin 2a, is rapidly cooled using cooling tube 2b to the water in cooler bin 2a, and the first communicating pipe 7 will Water in cooler bin 2a, which drains into, to be salvaged in cooling bay 5, realizes the quick-replaceable of water;And it is connected using shell 3a with cooler bin 2a It is logical, it can be realized and the water of three spray head 3c is recycled, reduce the use of water flow.
The foregoing description of the disclosed embodiments can be realized professional and technical personnel in the field or using originally practical new Type.Various modifications to these embodiments will be readily apparent to those skilled in the art, and determine herein The General Principle of justice can be realized in other embodiments without departing from the spirit or scope of the present utility model.Cause This, the present invention will not be limited to the embodiments shown herein, and is to fit to and principles disclosed herein The widest scope consistent with features of novelty.

Claims (6)

1. a kind of steel pipe's production cooling device, it is characterised in that: including substrate (1), cooling component (2), spray assemblies (3), Limit assembly (4) salvages cooling bay (5) and recirculation assembly (6), the cooling component (2), limit assembly (4) and recirculation assembly (6) it is installed in the top of substrate (1), spray assemblies (3) are mounted on the top of cooling component (2), and spray assemblies (3) Top is located at the underface of one end of limit assembly (4), and the other end of limit assembly (4) is located at the top for salvaging cooling bay (5), The both ends of recirculation assembly (6) respectively with salvage cooling bay (5) and cooling component (2) and be connected, the salvaging cooling bay (5) and cold But between component (2) be equipped with the first communicating pipe (7), the both ends of the first communicating pipe (7) respectively with salvage cooling bay (5) and cool down group Part (2) is connected.
2. steel pipe's production cooling device according to claim 1, it is characterised in that: the cooling component (2) includes cold But case (2a), cooling tube (2b) and suction pump (2c), the cooling tube (2b) are mounted in cooler bin (2a), suction pump (2c) Output end is connected with spray assemblies (3), and the input terminal of suction pump (2c) is connected with cooler bin (2a).
3. steel pipe's production cooling device according to claim 2, it is characterised in that: the spray assemblies (3) include shell Body (3a), the second communicating pipe (3b), three spray heads (3c) and three pipeline fixers (3d), the shell (3a) are in rectangle knot Structure and it is connected with the inside of cooler bin (2a), three spray heads (3c) are in vertical and be equidistantly mounted in shell (3a), and the The both ends of two communicating pipes (3b) are connected with the output end of three spray heads (3c) and suction pump (2c) respectively, and three pipelines are fixed Part (3d) is corresponded with three spray heads (3c) and is fixedly connected with the inner wall of shell (3a).
4. steel pipe's production cooling device according to claim 3, it is characterised in that: the limit assembly (4) includes branch Support (4a), shaft (4b), driving motor (4c), carrier (4d), several limit shafts (4e) and it is several lead batter post (4f), it is several It leads batter post (4f) to be equally arranged, support frame (4a) is fixedly connected with all bottoms for leading batter post (4f), support frame (4a) It is fixedly connected at the top of bottom and substrate (1), carrier (4d) is in the top for being vertically installed at cooler bin (2a), driving motor (4c) is in the top for being horizontally arranged at carrier (4d) and its output end is fixedly connected with one end of shaft (4b), shaft (4b) The other end sequentially pass through it is several lead batter post (4f), several limit shafts (4e) are equidistantly fixed on shaft (4b).
5. steel pipe's production cooling device according to claim 2, it is characterised in that: the recirculation assembly (6) includes following Ring water pump (6a), third connecting pipe (6b) and the 4th communicating pipe (6c), the water circulating pump (6a) are mounted on the top of substrate (1) Portion, the both ends of third connecting pipe (6b) are connected with the input terminal for salvaging cooling bay (5) and water circulating pump (6a) respectively, and the 4th connects The both ends of siphunculus (6c) are connected with the output end of water circulating pump (6a) and cooler bin (2a) respectively.
6. steel pipe's production cooling device according to claim 1, it is characterised in that: set in the salvaging cooling bay (5) There is the catheterization table (8) being inclined to set.
CN201821716078.3U 2018-10-22 2018-10-22 A kind of steel pipe's production cooling device Active CN208437430U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201821716078.3U CN208437430U (en) 2018-10-22 2018-10-22 A kind of steel pipe's production cooling device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201821716078.3U CN208437430U (en) 2018-10-22 2018-10-22 A kind of steel pipe's production cooling device

Publications (1)

Publication Number Publication Date
CN208437430U true CN208437430U (en) 2019-01-29

Family

ID=65086370

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201821716078.3U Active CN208437430U (en) 2018-10-22 2018-10-22 A kind of steel pipe's production cooling device

Country Status (1)

Country Link
CN (1) CN208437430U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111069319A (en) * 2019-11-26 2020-04-28 湖州吴兴珀莱机械厂 Quick cooling device is used in steel pipe production
CN111774424A (en) * 2020-06-23 2020-10-16 江苏联峰实业有限公司 Process for controlled cold rolling of deformed steel bar

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111069319A (en) * 2019-11-26 2020-04-28 湖州吴兴珀莱机械厂 Quick cooling device is used in steel pipe production
CN111069319B (en) * 2019-11-26 2022-06-03 东莞市必富模具钢材有限公司 Quick cooling device is used in steel pipe production
CN111774424A (en) * 2020-06-23 2020-10-16 江苏联峰实业有限公司 Process for controlled cold rolling of deformed steel bar

Similar Documents

Publication Publication Date Title
CN205324379U (en) Aluminium prduct process uses high -efficient cooling device
CN208437430U (en) A kind of steel pipe's production cooling device
CN108273922A (en) A kind of multi-functional cooling device being applied to production Hardware fitting
CN207806597U (en) A kind of novel metal casting is cooled with circulating water device
CN210718337U (en) Cooling device used after mold is used
CN217961363U (en) Cooling crystallizer
CN203534308U (en) Cooling device for circulating water
CN214981032U (en) Automatic emptying robot that gets of assembly line
CN212071288U (en) Cuttings and cooling liquid recovery processing device of numerically controlled fraise machine
CN200965244Y (en) Circulated cooling high-temperature resistant furnace door
CN210664039U (en) Spiral tube type cooler
CN206944743U (en) Full bolt connection cooling tower
CN208105967U (en) A kind of good intelligent communication base station of moisture-proof dust-proof effect convenient for ventilation
CN208833029U (en) The cooling cast welding cooling-water cooling device of economic benefits and social benefits
CN220597558U (en) Metal heat treatment cooling device
CN110538985A (en) heat abstractor of non ferrous metal casting manufacturing usefulness
CN221537661U (en) Wire drawing oil cooling mechanism
CN206823626U (en) A kind of annular heat exchange type chemical industry feed liquid cooling and stirring tank
CN208223219U (en) The energy saving and environment friendly spray filled cooling tower of Blower-free
CN205482057U (en) Circulation condensing equipment
CN216245118U (en) Flexible and simple scaling powder cooling device
CN214501882U (en) Effective energy-conserving steel wire cooling arrangement
CN217715627U (en) Cooling device is used in production of environment-friendly aluminum alloy ornamental strip
CN215724532U (en) Pipe cap production cooling device
CN216540800U (en) Molten iron cooling device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant