CN208384000U - A kind of power distribution automation aviation plug formula primary equipment simulation terminal system - Google Patents

A kind of power distribution automation aviation plug formula primary equipment simulation terminal system Download PDF

Info

Publication number
CN208384000U
CN208384000U CN201820328817.5U CN201820328817U CN208384000U CN 208384000 U CN208384000 U CN 208384000U CN 201820328817 U CN201820328817 U CN 201820328817U CN 208384000 U CN208384000 U CN 208384000U
Authority
CN
China
Prior art keywords
unit
aviation plug
primary equipment
electric current
power distribution
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820328817.5U
Other languages
Chinese (zh)
Inventor
张丹阳
楼伟杰
程辉阳
叶加炜
徐亮
王光增
姜奕
董勇腾
孟子辰
张锐
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JINHUA TRANSMISSION ENGINEERING Co Ltd
State Grid Corp of China SGCC
Jinhua Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Original Assignee
JINHUA TRANSMISSION ENGINEERING Co Ltd
State Grid Corp of China SGCC
Jinhua Power Supply Co of State Grid Zhejiang Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JINHUA TRANSMISSION ENGINEERING Co Ltd, State Grid Corp of China SGCC, Jinhua Power Supply Co of State Grid Zhejiang Electric Power Co Ltd filed Critical JINHUA TRANSMISSION ENGINEERING Co Ltd
Priority to CN201820328817.5U priority Critical patent/CN208384000U/en
Application granted granted Critical
Publication of CN208384000U publication Critical patent/CN208384000U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Supply And Distribution Of Alternating Current (AREA)

Abstract

The utility model relates to one kind can be with analog remote signaling, remote control, the power distribution automation aviation plug formula primary equipment of telemetering experiment simulates terminal system, solution is not able to satisfy distribution power automation terminal remote control in the prior art, remote signalling, the problem of demand of the analog quantitys such as telemetering test, a kind of power distribution automation aviation plug formula primary equipment simulation terminal system, including remote signalling output unit, voltage input unit, electric current input unit, control signal aviation plug unit, electric current inputs aviation plug unit, power supply aviation plug unit, control unit, simulate terminal unit, simulation terminal unit is connected with remote signalling output unit, test voltage is short-circuit during the test of aviation plug formula distribution power automation terminal can effectively be reduced, the risks such as current open, lifting test wiring efficiency, meet distribution power automation terminal with remote signalling contact output engineering Remote signalling, telemetering, the requirement for being remotely controlled test simulation amount, can substitute completely primary equipment and be tested.

Description

A kind of power distribution automation aviation plug formula primary equipment simulation terminal system
Technical field
The utility model relates to a kind of distribution automation fields, can be with analog remote signaling, remote control, telemetering more particularly, to one kind The power distribution automation aviation plug formula primary equipment of experiment simulates terminal system.
Background technique
During Distribution Automation Construction and O&M, it can all be related to the test to distribution power automation terminal, primary In the case that equipment is not connect with distribution power automation terminal or primary equipment charges, the test of distribution power automation terminal needs to rely on Primary equipment simulates terminal to simulate the experiment work that primary equipment completes distribution power automation terminal associated loop, and the current country is answered The most access way of distribution power automation terminal is to be connected by aviation plug, and when test carries out wiring dosage to it, Under conventional method, need first by the progress wiring work respectively again corresponding with signal location of plug pointer, due to aviation plug Contact pin gap is smaller, leads to test connection low efficiency, and be also easy to produce test voltage short circuit, current open the problems such as, influence to test Job schedule jeopardizes experimental facilities safety, though there is the simulation of traditional analog breaker once to set in the test of existing power distribution automation It is standby, but when being tested using traditional mimic-disconnecting switch device, it needs to be attached by terminal row wiring and device, grasp Make process complexity, efficiency is lower, traditional mimic-disconnecting switch can only mimic-disconnecting switch control loop, do not have telemetering, remote signalling connects Mouthful, there is biggish limitation in use, be not able to satisfy the analog quantitys such as distribution power automation terminal remote control, remote signalling, telemetering The demand of test.
Summary of the invention
The utility model mainly solves not being able to satisfy distribution power automation terminal remote control, remote signalling, telemetering etc. in the prior art The problem of demand of analog quantity test, provide that a kind of to have remote signalling, remote control, a kind of distribution of telemetering simulated experiment demand automatic Change aviation plug formula primary equipment and simulates terminal system.
Above technical problems of the utility model are mainly solved by the following technical scheme: a kind of distribution is automatic Change aviation plug formula primary equipment simulate terminal system, including remote signalling output unit, voltage input unit, electric current input unit, Control signal aviation plug unit, electric current input aviation plug unit, power supply aviation plug unit, control unit, simulation terminal Unit, described control unit, voltage input unit, electric current input unit, control signal aviation plug unit, electric current input aviation Plug unit, power supply aviation plug unit are connected with simulation terminal unit respectively, and the simulation terminal unit and remote signalling output are single Member is connected, and there are six pins, respectively AB line voltage TV secondary side voltage, CB line electricity for power input and voltage aviation plug Press TV secondary side voltage, AB line voltage TV secondary side voltage, CB line voltage TV secondary side voltage, zero sequence TV secondary side just Pole, zero sequence TV secondary side cathode, cable specification are RVVP1.5mm2;Electric current inputs aviation plug, and there are six pins, respectively phase Electric current A, phase current B, phase current C, phase current common end, zero-sequence current, zero-sequence current common end, cable specification are RVVP2.5mm²;It is respectively coincidence, quartile, energy storage CN-, energy storage CN+, non-energy storage that control, signal aviation plug, which have 10 pins, Position, remote signalling common end, close a floodgate output-, close a floodgate output+, separating brake output-, separating brake output+, cable specification RVVP1.5mm2.
As a preferred embodiment, further include separating brake unit, combined floodgate unit, the combined floodgate unit, separating brake unit respectively with It simulates terminal unit to be connected, combined floodgate separating brake unit can be motor-operted switch or electric knife gate.
It as a preferred embodiment, further include integrated current interface unit, indicator unit, voltage tester line interface list Member, testing current line interface unit, the integrated current interface unit, indicator unit, voltage tester line interface unit, electric current P-wire interface unit is respectively connected with simulation terminal unit respectively, and indicator unit is for observing Control experiment.
As a preferred embodiment, divide on the power distribution automation aviation plug formula primary equipment simulation terminal box body left side It is not provided with power input and voltage aviation plug, electric current input aviation plug, control signal aviation plug, the electric current input In power input and voltage aviation plug lower part, the control signal aviation plug setting is inputted in electric current navigates for aviation plug setting Blind plug lower part.
As a preferred embodiment, it is set respectively on the power distribution automation aviation plug formula primary equipment simulation terminal box body It is equipped with electric current input jack, voltage input jack, the voltage input jack is arranged in electric current input jack lower part, the distribution Position of the switch indicator light, opening button, combined floodgate are provided on the upside of automation aviation plug formula primary equipment simulation terminal box body Button, remote signalling export button, and the position of the switch indicator light is arranged on the left of opening button, and the switch knob is arranged in separating brake On the right side of button, the remote signalling output button is arranged in opening button lower part.
Therefore, the utility model has the advantages that: the utility model be suitable for distribution power automation terminal test, can also be used as Mimic-disconnecting switch is applied in the debugging process of protective relaying device, has filled up and has simulated by the primary equipment of interface of aviation plug The blank of terminal, plug and play are greatly shortened compared to traditional analog breaker terminals row's secondary connection time, can be effective Risks, the lifting test such as test voltage short circuit, current open during aviation plug formula distribution power automation terminal is tested is reduced to connect Line efficiency, the utility model have the instruction of analog switch divide-shut brake, the functions such as control;Integrated current, voltage tester line interface;Tool There is remote signalling contact output engineering to meet distribution power automation terminal remote signalling, telemetering, the requirement for being remotely controlled test simulation amount, can substitute completely Primary equipment is tested.
Detailed description of the invention
Attached drawing 1 is the front view structure of power distribution automation aviation plug formula primary equipment simulation terminal box body in the utility model Schematic diagram;
Attached drawing 2 is the plan structure of power distribution automation aviation plug formula primary equipment simulation terminal box body in the utility model Schematic diagram;
Attached drawing 3 is the side view structure of power distribution automation aviation plug formula primary equipment simulation terminal box body in the utility model Schematic diagram;
Attached drawing 4 is the structure frame figure of the utility model;
1. simulating 2. control unit of terminal unit, 3. integrated current interface unit
4. 5. testing current line interface unit of indicator unit, 6. voltage tester line interface unit
7. 8. separating brake unit of combined floodgate unit, 9. electric current inputs aviation plug unit
10. power supply aviation plug unit 11. controls signal aviation plug unit
12. 13. voltage input unit of electric current input unit, 14. remote signalling output unit
15. 16. electric current input jack of power input and voltage aviation plug
17. 18. electric current of voltage input jack inputs aviation plug 19. and controls signal aviation plug
20. 21. opening button of position of the switch indicator light, 22. switch knob
23. remote signalling exports button.
Specific embodiment
A kind of power distribution automation aviation plug formula primary equipment of the present embodiment simulates terminal system, including remote signalling output unit 14, voltage input unit 13, electric current input unit 12, control signal aviation plug unit 11, electric current input aviation plug unit 9, power supply aviation plug unit 10, control unit 2, simulation terminal unit 1, control unit, voltage input unit, electric current input are single Member, control signal aviation plug unit, electric current input aviation plug unit, power supply aviation plug unit respectively with simulation terminal list Member is connected, and simulation terminal unit is connected with remote signalling output unit, and there are six pins for power input and voltage aviation plug, respectively AB line voltage TV secondary side voltage, CB line voltage TV secondary side voltage, AB line voltage TV secondary side voltage, CB line electricity TV secondary side voltage, zero sequence TV secondary side anode, zero sequence TV secondary side cathode are pressed, cable specification is RVVP1.5mm2;Electric current Inputting aviation plug, there are six pin, respectively phase current A, phase current B, phase current C, phase current common end, zero-sequence currents, zero Sequence electric current common end, cable specification are RVVP2.5mm2;Control, signal aviation plug have 10 pins be respectively coincidence, quartile, Energy storage CN-, energy storage CN+, non-energy storage position, remote signalling common end, close a floodgate output-, close a floodgate output+, separating brake output-, separating brake output+, Cable specification RVVP1.5mm2.
It further include that integrated current interface unit 3, indicator unit 4, voltage tester line interface unit 6, testing current line connect Mouth unit 5, integrated current interface unit, indicator unit, voltage tester line interface unit, testing current line interface unit difference It is respectively connected with simulation terminal unit, indicator unit is for observing Control experiment.
It further include separating brake unit 8, combined floodgate unit 7, combined floodgate unit, separating brake unit are connected with simulation terminal unit respectively, close Lock separating brake unit can be motor-operted switch or electric knife gate.
Electric current input jack 16, electricity are respectively arranged on power distribution automation aviation plug formula primary equipment simulation terminal box body Input jack 17 is pressed, voltage input jack is arranged in electric current input jack lower part, power distribution automation aviation plug formula primary equipment Position of the switch indicator light 20, opening button 21, switch knob 22, remote signalling output button are provided on the upside of simulation terminal box body 23, position of the switch indicator light is arranged on the left of opening button, and switch knob is arranged on the right side of opening button, and remote signalling output button is set It sets in opening button lower part, it is corresponding that power distribution automation aviation plug formula primary equipment simulates the electric current input jack on terminal box body Electric current input unit, power distribution automation aviation plug formula primary equipment simulate the voltage input jack corresponding voltage on terminal box body Input unit, opening button correspond to separating brake unit, and switch knob, which corresponds to combined floodgate unit remote signalling output unit and corresponds to remote signalling output, to be pressed Button.
Power input and electricity are respectively arranged on the left of power distribution automation aviation plug formula primary equipment simulation terminal box body Aviation plug 15, electric current input aviation plug 18, control signal aviation plug 19 are pressed, electric current inputs aviation plug and is arranged in power supply Input and voltage aviation plug lower part, control signal aviation plug setting electric current input aviation plug lower part, power input and The input of voltage aviation plug corresponding power and voltage aviation plug unit, electric current input aviation plug unit corresponding current input boat Blind plug controls signal aviation plug corresponding control signal aviation plug unit.
Meet distribution power automation terminal remote signalling, telemetering, the requirement for being remotely controlled test simulation amount with remote signalling contact output engineering, Primary equipment can be substituted completely to be tested.
The specific embodiments described herein are merely examples of the spirit of the present invention.The utility model institute Belonging to those skilled in the art can make various modifications or additions to the described embodiments or using similar Mode substitute, but without departing from the spirit of the present application or beyond the scope of the appended claims.
Although electric current input aviation plug is used more herein, opening button, switch knob, position of the switch instruction The terms such as lamp, remote signalling output button, but it does not exclude the possibility of using other terms.The use of these items is only for more Easily describe and explain the essence of the utility model;It is practical new with this for being construed as any additional limitation all Type spirit is disagreed.

Claims (5)

1. a kind of power distribution automation aviation plug formula primary equipment simulates terminal system, it is characterised in that: exported including remote signalling single First (14), voltage input unit (13), electric current input unit (12), control signal aviation plug unit (11), electric current input boat Blind plug unit (9), power supply aviation plug unit (10), control unit (2), simulation terminal unit (1), described control unit, Voltage input unit, electric current input unit, control signal aviation plug unit, electric current input aviation plug unit, power supply aviation Plug unit is connected with simulation terminal unit respectively, and the simulation terminal unit is connected with remote signalling output unit.
2. a kind of power distribution automation aviation plug formula primary equipment according to claim 1 simulates terminal system, feature Being further includes separating brake unit (8), combined floodgate unit (7), and the combined floodgate unit, separating brake unit are connected with simulation terminal unit respectively.
3. a kind of power distribution automation aviation plug formula primary equipment according to claim 1 simulates terminal system, feature Being further includes that integrated current interface unit (3), indicator unit (4), voltage tester line interface unit (6), testing current line connect Mouth unit (5), the integrated current interface unit, indicator unit, voltage tester line interface unit, testing current line interface list Member is respectively connected with simulation terminal unit respectively.
4. a kind of power distribution automation aviation plug formula primary equipment according to claim 1 simulates terminal system, feature It is to be respectively arranged with power input and voltage aviation on power distribution automation aviation plug formula primary equipment simulation terminal box body left side Plug (15), electric current input aviation plug (18), control signal aviation plug (19), the electric current input aviation plug setting exist Power input and voltage aviation plug lower part, the control signal aviation plug setting input aviation plug lower part in electric current.
5. a kind of power distribution automation aviation plug formula primary equipment according to claim 1-4 simulates terminal system System, it is characterized in that being respectively arranged with electric current input jack on power distribution automation aviation plug formula primary equipment simulation terminal box body (16), voltage input jack (17), the voltage input jack setting is in electric current input jack lower part, the power distribution automation boat It is provided with position of the switch indicator light (20) on the upside of blind plug formula primary equipment simulation terminal box body, opening button (21), closes a floodgate Button (22), remote signalling output button (23), the position of the switch indicator light are arranged on the left of opening button, and the switch knob is set It sets on the right side of opening button, the remote signalling output button is arranged in opening button lower part.
CN201820328817.5U 2018-03-09 2018-03-09 A kind of power distribution automation aviation plug formula primary equipment simulation terminal system Active CN208384000U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820328817.5U CN208384000U (en) 2018-03-09 2018-03-09 A kind of power distribution automation aviation plug formula primary equipment simulation terminal system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820328817.5U CN208384000U (en) 2018-03-09 2018-03-09 A kind of power distribution automation aviation plug formula primary equipment simulation terminal system

Publications (1)

Publication Number Publication Date
CN208384000U true CN208384000U (en) 2019-01-15

Family

ID=64974275

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820328817.5U Active CN208384000U (en) 2018-03-09 2018-03-09 A kind of power distribution automation aviation plug formula primary equipment simulation terminal system

Country Status (1)

Country Link
CN (1) CN208384000U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109470941A (en) * 2018-03-09 2019-03-15 金华送变电工程有限公司 A kind of power distribution automation aviation plug formula primary equipment simulation terminal system and method
CN110749796A (en) * 2019-11-22 2020-02-04 国网四川省电力公司检修公司 Remote signaling test multiplexing device and operation method for electric power integrated automation system of transformer substation

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109470941A (en) * 2018-03-09 2019-03-15 金华送变电工程有限公司 A kind of power distribution automation aviation plug formula primary equipment simulation terminal system and method
CN110749796A (en) * 2019-11-22 2020-02-04 国网四川省电力公司检修公司 Remote signaling test multiplexing device and operation method for electric power integrated automation system of transformer substation

Similar Documents

Publication Publication Date Title
CN108919002A (en) A kind of test macro of direct-current charging post
CN105761569B (en) 10Kv distribution transformer analogue simulation systems
CN208384000U (en) A kind of power distribution automation aviation plug formula primary equipment simulation terminal system
CN107976596A (en) A kind of distribution power automation terminal experimental rig and its method of work
CN109444542A (en) A kind of fully automatic secondary insulating resistance of cable auxiliary test unit and its test method
CN211826183U (en) Novel simple simulation circuit breaker
CN113990132B (en) Power transformation and distribution operation and maintenance integrated training system and training method
CN107450019A (en) Handcart type breaker low-voltage motion test instrument
CN209311574U (en) Fully automatic secondary insulating resistance of cable auxiliary test unit
CN208384025U (en) A kind of test macro of direct-current charging post
CN201374500Y (en) Intelligent power distribution cabinet
CN109470941A (en) A kind of power distribution automation aviation plug formula primary equipment simulation terminal system and method
CN107202928B (en) Automatic switching-on device analog circuit breaker of standby power supply
CN207036969U (en) A kind of prepared auto restart action logic test accessory
CN103136999B (en) Simulation demonstrator used for training remote electric load control function
CN202976623U (en) Simulation demonstration device used for training remote electrical load control
CN218727677U (en) Nuclear power station nuclear island low-voltage alternating-current distribution board test device
CN207541171U (en) Miniature simulation circuit breaker
CN203927005U (en) Electric valve control circuit and the electric operated valve instrument that comprises this circuit
CN206292365U (en) Relay protection operation case actuating of relay characteristic tester and its automatic wire-changing device
CN216211624U (en) Real standard system of power transformation and distribution operation and maintenance integration
CN204516201U (en) Comprehensive cable distribution Simulated training device is installed in interior lines
CN103915004A (en) Aircraft station simulation training practical operation system
CN209514909U (en) Metering device wiring judges training and examination device
CN209894928U (en) Device for simulating 10kV high-voltage vacuum permanent magnet circuit breaker