CN208310147U - A kind of site construction scaffold easy to carry - Google Patents

A kind of site construction scaffold easy to carry Download PDF

Info

Publication number
CN208310147U
CN208310147U CN201820725044.4U CN201820725044U CN208310147U CN 208310147 U CN208310147 U CN 208310147U CN 201820725044 U CN201820725044 U CN 201820725044U CN 208310147 U CN208310147 U CN 208310147U
Authority
CN
China
Prior art keywords
top plate
support frame
carry
site construction
sleeve
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820725044.4U
Other languages
Chinese (zh)
Inventor
王俊清
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201820725044.4U priority Critical patent/CN208310147U/en
Application granted granted Critical
Publication of CN208310147U publication Critical patent/CN208310147U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Ladders (AREA)

Abstract

The utility model discloses a kind of site construction scaffolds easy to carry, including lower support bar and castor, the lower support bar outer surface is respectively arranged with connector from top to bottom, clamp screw thread and supporting pad, sleeve is installed below the gripping sleeve, the trundle bracket left and right ends are respectively arranged with connecting hole and link block, the castor is mounted at left and right sides of trundle bracket lower end, the connector upper end is equipped with intermediate plate, the intermediate plate upper end is equipped with upper support frame, and upper support frame lower end is provided with lower connecting pin, securing plate is provided on the inside of the upper support frame, the upper support frame upper end is equipped with top plate, and top plate lower end offers top plate pin hole.The site construction scaffold easy to carry, facilitate worker to carry out storage placement to the foot support, saves space, and unpick and wash to the foot support convenient for worker, and it avoids preventing the foot support from sliding when worker is using the foot support and causing security risk to worker.

Description

A kind of site construction scaffold easy to carry
Technical field
The utility model relates to site construction technical field, specially a kind of site construction scaffold easy to carry.
Background technique
With the development of social science and technology, building trade is rapidly growing, advances each metropolitan fast development, building site Construction refers to that construction worker carries out building-up work in the construction area of planning, and the efficiency of site construction directly affects whole building The progress of engineering, so site construction technical field is increasingly valued by the people, common work of the scaffold as site construction Tool, substantially increases work task efficiency, still, most of foot support used in site construction field, not can be carried out at present Disassembly, and it is not easy to workers carry.
Utility model content
The purpose of this utility model is to provide a kind of site construction scaffolds easy to carry, to solve above-mentioned background Most of foot support used in the current site construction field proposed in technology, not can be carried out disassembly, and be not easy to workers carry The problem of.
To achieve the above object, the utility model provides the following technical solutions: a kind of site construction foot easy to carry Hand cradle, including lower support bar and castor, the lower support bar outer surface be respectively arranged with from top to bottom connector, clamp screw thread and Supporting pad, and clamp and gripping sleeve is installed on the outside of screw thread, sleeve is installed, and be connected with foot on the outside of sleeve below the gripping sleeve Wheel support, the trundle bracket left and right ends are respectively arranged with connecting hole and link block, and the castor is mounted under trundle bracket The end left and right sides, the connector upper end is equipped with intermediate plate, and intermediate staircase is connected on the left of intermediate plate, on the intermediate plate End is equipped with upper support frame, and upper support frame lower end is provided with lower connecting pin, is provided with securing plate on the inside of the upper support frame, and Upper support frame upper end is provided with connecting pin, and the upper support frame upper end is equipped with top plate, and top plate lower end offers top plate pin Hole, and top plate staircase is connected on the left of top plate.
Preferably, the lower support bar is threadedly coupled with supporting pad, and lower support bar and sleeve constitute rotational structure.
Preferably, the gripping sleeve upper end diameter is greater than its lower end diameter, and gripping sleeve is threadedly coupled with clamping.
Preferably, the intermediate plate and lower connecting pin constitute disassembly mounting structure, and lower connecting pin is torn open with connector composition Unload mounting structure.
Preferably, the top plate length is greater than upper support frame length, and the top plate pin hole of top plate lower end and upper connecting pin structure At disassembly mounting structure.
Preferably, the link block is rectangular configuration, and link block and trundle bracket constitute rotational structure.
Compared with prior art, the utility model has the beneficial effects that the site construction scaffold easy to carry,
1. lower support bar and upper support frame are disassembly mounting structure, worker is facilitated to carry out storage placement to the foot support, saved About space, and the foot support unpicked and washed convenient for worker;
2. the setting of supporting pad makes the scaffold fixing-stable, when worker uses the foot support, prevent the foot support sliding It moves and causes security risk to worker;
3. the setting of trundle bracket and castor is readily transported the foot support, when worker uses the foot support, folder is unscrewed It is fixed, rotate trundle bracket, and trundle bracket is fixed by connecting hole and link block interconnection, and then improves down The stability of support rod.
Detailed description of the invention
Fig. 1 is the utility model positive structure schematic;
Fig. 2 is the utility model left side structure schematic diagram;
Fig. 3 is the utility model trundle bracket structural schematic diagram.
In figure: 1, lower support bar;2, connector;3, screw thread is clamped;4, supporting pad;5, gripping sleeve;6, sleeve;7, castor branch Frame;8, connecting hole;9, castor;10, intermediate plate;11, upper support frame;12, lower connecting pin;13, securing plate;14, upper connecting pin; 15, top plate pin hole;16, top plate;17, top plate staircase;18, intermediate staircase;19, link block.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work Every other embodiment obtained, fall within the protection scope of the utility model.
Fig. 1-3 is please referred to, the utility model provides a kind of technical solution: a kind of site construction foot hand easy to carry Frame, including lower support bar 1, connector 2, clamping screw thread 3, supporting pad 4, gripping sleeve 5, sleeve 6, trundle bracket 7, connecting hole 8, foot Take turns 9, intermediate plate 10, upper support frame 11, lower connecting pin 12, securing plate 13, upper connecting pin 14, top plate pin hole 15, top plate 16, top plate Staircase 17, intermediate staircase 18 and link block 19,1 outer surface of lower support bar are respectively arranged with connector 2 from top to bottom, clamp screw thread 3 and supporting pad 4, and clamp and gripping sleeve 5 is installed on the outside of screw thread 3, lower support bar 1 is threadedly coupled with supporting pad 4, and lower support bar 1 constitutes rotational structure with sleeve 6, packs up trundle bracket 7 convenient for worker, and improves the stability in use of lower support bar 1, guarantees Safety of workers is constructed, and is equipped with sleeve 6 below gripping sleeve 5, and trundle bracket 7 is connected on the outside of sleeve 6,5 upper end of gripping sleeve is straight Diameter is greater than its lower end diameter, and gripping sleeve 5 is threadedly coupled with screw thread 3 is clamped, and in workers carry's foot support, passes through gripping sleeve 5 clamp trundle bracket 7, are convenient for workers carry's foot support, are providing a great convenience property of worker, trundle bracket 7 or so Both ends are respectively arranged with connecting hole 8 and link block 19, and link block 19 is rectangular configuration, and link block 19 and trundle bracket 7 are constituted Rotational structure, it is convenient for worker that trundle bracket 7 is fixed when being stored to trundle bracket 7, it is easy to operate, while giving worker It brings conveniently, castor 9 is mounted at left and right sides of 7 lower end of trundle bracket, and 2 upper end of connector is equipped with intermediate plate 10, and intermediate Intermediate staircase 18 is connected on the left of plate 10,10 upper end of intermediate plate is equipped with upper support frame 11, and 11 lower end of upper support frame is provided with Lower connecting pin 12, intermediate plate 10 and lower connecting pin 12 constitute disassembly mounting structure, and lower connecting pin 12 and connector 2 are constituted and dismantled The foot support is carried out disassembly, cleaning convenient for worker, while facilitating worker by tool when not using the foot support by mounting structure It is placed in 10 upper end of intermediate plate, securing plate 13 is provided on the inside of upper support frame 11, and 11 upper end of upper support frame is provided with connection Pin 14,11 upper end of upper support frame is equipped with top plate 16, and 16 lower end of top plate offers top plate pin hole 15, and connects on the left of top plate 16 It is connected to top plate staircase 17,16 length of top plate is greater than 11 length of upper support frame, and the top plate pin hole 15 of 16 lower end of top plate and upper connection Pin 14 constitutes disassembly mounting structure, disassembles top plate 16 convenient for worker and cleans, while being convenient for worker by the scaffold It is stored.
Working principle: when using the site construction scaffold easy to carry, first by the folder of 1 upper end of lower support bar Fixed 5 are screwed down along screw thread 3 is clamped, and make trundle bracket 7 by sleeve 6 along 1 slide downward of lower support bar, and by castor Bracket 7 is fixed on the lower end of lower support bar 1, and connecting hole 8 is aligned with link block 19 and is caught in, and is rotated further by the reinforcement of link block 19 Fixation to trundle bracket 7, then the foot support is moved to construction ground by the castor 9 that 7 lower end of trundle bracket is arranged by worker Point, by climbing intermediate staircase 18 and top plate staircase 17, climbs up the progress of top plate 16 when worker is constructed using the foot support Construction operation, and securing plate 13 improves the stability of upper support frame 11, at the same supporting pad 4 increase the scaffold grab ground Power improves the stability of the scaffold, has ensured the safety of worker, and construction tool can be placed in intermediate plate 10, has been Worker provides convenience, when not using the foot support, passes sequentially through connecting pin 14, top plate pin hole 15, connector 2 and lower connection Top plate 16, upper support frame 11 and intermediate plate 10 are disassembled, the foot support are cleaned and stored convenient for worker by pin 12, Increase whole practicability.
While there has been shown and described that the embodiments of the present invention, for the ordinary skill in the art, It is understood that these embodiments can be carried out with a variety of variations in the case where not departing from the principles of the present invention and spirit, repaired Change, replacement and variant, the scope of the utility model is defined by the appended claims and the equivalents thereof.

Claims (6)

1. a kind of site construction scaffold easy to carry, including lower support bar (1) and castor (9), it is characterised in that: described Lower support bar (1) outer surface is respectively arranged with connector (2) from top to bottom, clamps screw thread (3) and supporting pad (4), and clamps spiral shell It is equipped with gripping sleeve (5) on the outside of line (3), is equipped with sleeve (6) below the gripping sleeve (5), and be connected with foot on the outside of sleeve (6) Wheel support (7), trundle bracket (7) left and right ends are respectively arranged with connecting hole (8) and link block (19), the castor (9) It is mounted at left and right sides of trundle bracket (7) lower end, connector (2) upper end is equipped with intermediate plate (10), and intermediate plate (10) Left side is connected with intermediate staircase (18), and intermediate plate (10) upper end is equipped with upper support frame (11), and under upper support frame (11) End is provided with lower connecting pin (12), is provided with securing plate (13) on the inside of the upper support frame (11), and upper support frame (11) upper end It is provided with connecting pin (14), upper support frame (11) upper end is equipped with top plate (16), and top plate (16) lower end offers top Plate pin hole (15), and top plate staircase (17) are connected on the left of top plate (16).
2. one kind according to claim 1 site construction scaffold easy to carry, it is characterised in that: the lower support Bar (1) is threadedly coupled with supporting pad (4), and lower support bar (1) and sleeve (6) constitute rotational structure.
3. one kind according to claim 1 site construction scaffold easy to carry, it is characterised in that: the gripping sleeve (5) upper end diameter is greater than its lower end diameter, and gripping sleeve (5) is threadedly coupled with screw thread (3) are clamped.
4. one kind according to claim 1 site construction scaffold easy to carry, it is characterised in that: the intermediate plate (10) disassembly mounting structure is constituted with lower connecting pin (12), and lower connecting pin (12) and connector (2) constitute disassembly mounting structure.
5. one kind according to claim 1 site construction scaffold easy to carry, it is characterised in that: the top plate (16) length is greater than the length of upper support frame (11), and the top plate pin hole (15) of top plate (16) lower end and upper connecting pin (14) are constituted Dismantle mounting structure.
6. one kind according to claim 1 site construction scaffold easy to carry, it is characterised in that: the link block It (19) is rectangular configuration, and link block (19) and trundle bracket (7) constitute rotational structure.
CN201820725044.4U 2018-05-16 2018-05-16 A kind of site construction scaffold easy to carry Expired - Fee Related CN208310147U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820725044.4U CN208310147U (en) 2018-05-16 2018-05-16 A kind of site construction scaffold easy to carry

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820725044.4U CN208310147U (en) 2018-05-16 2018-05-16 A kind of site construction scaffold easy to carry

Publications (1)

Publication Number Publication Date
CN208310147U true CN208310147U (en) 2019-01-01

Family

ID=64711007

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820725044.4U Expired - Fee Related CN208310147U (en) 2018-05-16 2018-05-16 A kind of site construction scaffold easy to carry

Country Status (1)

Country Link
CN (1) CN208310147U (en)

Similar Documents

Publication Publication Date Title
CN206545475U (en) A kind of Portable multifunctional insulating ladder
CN210736137U (en) Mobile workbench for communication equipment maintenance
CN206331068U (en) A kind of distribution line failure positioner
CN103368104A (en) Insulating operating rod of ground potential operation non-bearing-strength consecutive wire clamp
CN208310147U (en) A kind of site construction scaffold easy to carry
CN207296360U (en) A kind of climbing frame falling proof mechanism and the climbing frame falling proof seat in the plane lock based on the mechanism
CN212154388U (en) Isolating device based on building construction
CN108374551A (en) A kind of site construction scaffold easy to carry
CN206144176U (en) Simple and easy building construction safety rail guard
CN209082961U (en) Novel hanging basket device for pitched roof transformation
CN104060939A (en) Ladder for maintaining large grab bucket
CN108453064A (en) A kind of machinery macrotype axes series cleaning device
CN106532557A (en) Crossing 10KV line construction platform tool apparatus
CN206091273U (en) Scaffold connecting device for civil engineering
CN206971693U (en) Adjustable type welds hanging basket
CN205777416U (en) Ladder scaffolding
CN205734923U (en) A kind of upper and lower transporting structure of catching robot
CN211369487U (en) Hanging basket for plastering exterior wall of building
CN210564331U (en) Steel structure escalator device
CN203961250U (en) A kind of multi-angle adjustable scaffold steel pipe and steel pipe scaffold
CN208122242U (en) A kind of shrinkable steel building platform device for high-altitude operation
CN215107240U (en) Safe springboard for building construction
CN206259651U (en) A kind of rural area fault maintenance activity device
CN212562591U (en) Novel space large-span building construction safety protection device
CN209382954U (en) A kind of construction site brick handling device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190101

Termination date: 20190516