CN208297142U - For the turbine power plant static test system of retrofiting that navigates - Google Patents
For the turbine power plant static test system of retrofiting that navigates Download PDFInfo
- Publication number
- CN208297142U CN208297142U CN201820774067.4U CN201820774067U CN208297142U CN 208297142 U CN208297142 U CN 208297142U CN 201820774067 U CN201820774067 U CN 201820774067U CN 208297142 U CN208297142 U CN 208297142U
- Authority
- CN
- China
- Prior art keywords
- navigates
- power plant
- remodeling
- turbine power
- test system
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Testing And Monitoring For Control Systems (AREA)
Abstract
The utility model provides a kind of for the remodeling turbine power plant static test system that navigates, comprising: shell is equipped with signal generating assembly, output precision and control assembly on the housing;Operating circuit, the operating circuit are arranged in the shell, and the operating circuit is communicated with the signal generating assembly, the output precision and the control assembly;Wherein the operating circuit includes: logic controller, the control assembly and the logic controller communication;Signal generator, the signal generating assembly pass through the signal generator and the logic controller communication;Display module, the output precision pass through the display module and the logic controller communication.Compared with prior art, the utility model has the advantage that on the basis of keeping original test request for the remodeling turbine power plant static test system that navigates, a set of test platform is designed, by test plan prepared in advance, diagnosed, tested and is recorded on platform.
Description
Technical field
The utility model relates to one kind for the remodeling turbine power plant static test system that navigates.
Background technique
Boat retrofits Gas Turbine Generating Units after finalization of the manufacture at present, gas turbine, generator, activation system, lubrication
System, cleaning system, control system, vibroseis, fire-fighting system, distribution system, synchronization system, direct current system, AC system
Carry out connection electrically and mechanically, between system or independent prizing body itself to carry out functional test, electrical installation test etc. quiet
State test, and these tests are all that independent test, record are carried out by various instruments, instrument, cannot concentrate and be tested, be taken
It is thing, laborious, it is not easy to carry out centralized recording, system decision problem reason.
Utility model content
For the defects in the prior art, the utility model aim is to provide a kind of being used for for solution above-mentioned technical problem
Boat remodeling turbine power plant static test system.
In order to solve the above technical problems, the utility model provides a kind of remodeling turbine power plant static test system that is used to navigate
System, comprising: shell is equipped with signal generating assembly, output precision and control assembly on the housing;Operating circuit, the work
Make circuit to be arranged in the shell, the operating circuit and the signal generating assembly, the output precision and the control
Assembly communication;Wherein the operating circuit includes: logic controller, the control assembly and the logic controller communication;Letter
Number generator, the signal generating assembly pass through the signal generator and the logic controller communication;Display module, it is described
Output precision passes through the display module and the logic controller communication.
Preferably, the signal generator includes: that layer occurs for signal, and layer occurs for the signal and the logic controller is logical
Letter;Power station subsystem element and station control unit, the signal generating assembly pass through the power station subsystem element and described
Station control unit occurs layer with the signal and communicates.
Preferably, the signal generating assembly includes simulation instrument signal generator, RTD/TC signal generator, switch letter
Number generator and voltage/current source generator.
Preferably, the control assembly includes test subsystems selection key, test human-computer interaction interface and emergent stopping
Button.
Preferably, the output precision includes feedback states display and Pressure/Temperature display.
Preferably, the operating circuit further includes alarm output module, the alarm output module and the logic control
Device communication.
Preferably, it is equipped with alarm assemblies on the housing, the alarm assemblies are communicated with the alarm output module;Its
Described in alarm assemblies include alarm/shutdown status indicator and buzzer.
Preferably, the logic controller is PLC.
Compared with prior art, the utility model has following excellent for the remodeling turbine power plant static test system that navigates
Point: on the basis of keeping original test request, a set of test platform is designed, by test plan prepared in advance, in platform
On diagnosed, tested and recorded.
Detailed description of the invention
Upon reading the detailed description of non-limiting embodiments with reference to the following drawings, other spies of the utility model
Sign objects and advantages will become more apparent upon.
Fig. 1 is the utility model for the remodeling turbine power plant static test system structural schematic diagram that navigates;
Fig. 2 is the utility model for the remodeling turbine power plant static test system operating circuit schematic diagram that navigates.
In figure:
1- simulates instrument signal generator 2-RTD/TC signal generator 3- switch signal generator
4- voltage/current source generator 5- alarm/shutdown status indicator 6- feedback states display
7- buzzer 8- Pressure/Temperature display 9- test subsystems selection key
10- emergency stop button 11- tests human-computer interaction interface 12- shell
Specific embodiment
The utility model is described in detail combined with specific embodiments below.Following embodiment will be helpful to this field
Technical staff further understands the utility model, but does not limit the utility model in any form.It should be pointed out that ability
For the those of ordinary skill in domain, without departing from the concept of the premise utility, several changes and improvements can also be made.
The utility model for navigate remodeling turbine power plant static test system by various voltmeters, signal generator,
Alarm, analog signal, the functions such as switching signal, display instruction, which are integrated on moveable test platform, to be designed for uniformity,
And is classified and arranged according to certain rule or test request and signals security.
As shown in Figure 1 and Figure 2, a kind of remodeling turbine power plant static test system that is used to navigate provided by the utility model,
Include: shell 12, be equipped with signal generating assembly, output precision, control assembly and alarm assemblies on housing 12, operating circuit is set
It sets in shell 12, operating circuit is communicated with signal generating assembly, output precision control assembly and alarm assemblies.
Operating circuit specifically includes that logic controller (the present embodiment uses PLC), signal generator, display module and report
Alert output module.
Signal generator includes: that layer occurs for signal, and layer occurs for signal and logic controller (the present embodiment uses PLC) is logical
Letter;Power station subsystem element and station control unit, signal generating assembly pass through power station subsystem element and station control unit
Layer occurs with signal to communicate.
Signal generating assembly includes simulation instrument signal generator 1, RTD/TC signal generator 2, switch signal generator 3
And voltage/current source generator 4.
Control assembly includes test subsystems selection key 9, test human-computer interaction interface 11 and emergency stop button 10.
Output precision includes feedback states display 6 and Pressure/Temperature display 8.
It is equipped with alarm assemblies on housing 12, alarm assemblies are communicated with alarm output module;Wherein alarm assemblies include report
Police/shutdown status indicator 5 and buzzer 7.
1) power station static test is broadly divided into power station subsystem element and station control unit two parts, according to test request
System under test (SUT) may be selected in control assembly.
2) when power station subsystem element is measured body, the electric signal of generation is sent to signal, layer, signal hair occurs
The signal of acquisition is input to logic controller (the present embodiment uses PLC) and passes through display module display module by generating layer, is read
Real time data.PLC is according to logic judgment simultaneously, if reaches alarm or shutdown value sends signal alarm output module.
3) when station control unit be measured body when, by signal occur layer output voltage, electric current, pressure, flow, RTD,
TC, on-off model test its internal board, electric linkage function.
4) concentrations such as indicator light, alarm lamp, buzzer are connected to alarm output module, accurately and reliably judge testing number
According to.
5) it will start switch, signaling switch, emergent stopping, logic control etc. are arranged in control assembly, logic controller (this
Embodiment uses PLC), improve the safety of whole system.
By this comprehensive test platform device, each subsystem stationary singnal in power station is simulated, power station control system is carried out
Functional test, while data record and report output are carried out by built-in record PAD.
By this comprehensive test platform device, individual control signal and correlation signal are sent to a subsystem, checks each son
Working state of system, and form relative recording and report.
Specific embodiment of the utility model is described above.It is to be appreciated that the utility model not office
It is limited to above-mentioned particular implementation, those skilled in the art can make a variety of changes or modify within the scope of the claims,
This has no effect on the substantive content of the utility model.In the absence of conflict, the spy in embodiments herein and embodiment
Sign can be arbitrarily combined with each other.
Claims (8)
1. one kind is for the remodeling turbine power plant static test system that navigates characterized by comprising
Shell is equipped with signal generating assembly, output precision and control assembly on the housing;
Operating circuit, the operating circuit are arranged in the shell, the operating circuit and the signal generating assembly, described
Output precision and control assembly communication;Wherein
The operating circuit includes:
Logic controller, the control assembly and the logic controller communication;
Signal generator, the signal generating assembly pass through the signal generator and the logic controller communication;
Display module, the output precision pass through the display module and the logic controller communication.
2. according to claim 1 for the remodeling turbine power plant static test system that navigates, which is characterized in that the letter
Number generator includes:
Layer occurs for signal, and layer and the logic controller communication occur for the signal;
Power station subsystem element and station control unit, the signal generating assembly pass through the power station subsystem element and described
Station control unit occurs layer with the signal and communicates.
3. according to claim 2 for the remodeling turbine power plant static test system that navigates, which is characterized in that the letter
Number generating assembly includes simulation instrument signal generator, RTD/TC signal generator, switch signal generator and voltage/current source
Generator.
4. according to claim 2 for the remodeling turbine power plant static test system that navigates, which is characterized in that the control
Component processed includes test subsystems selection key, test human-computer interaction interface and emergency stop button.
5. according to claim 1 for the remodeling turbine power plant static test system that navigates, which is characterized in that described defeated
Component includes feedback states display and Pressure/Temperature display out.
6. according to claim 5 for the remodeling turbine power plant static test system that navigates, which is characterized in that the work
It further include alarm output module as circuit, the alarm output module and the logic controller communication.
7. according to claim 6 for the remodeling turbine power plant static test system that navigates, which is characterized in that described
Shell is equipped with alarm assemblies, and the alarm assemblies are communicated with the alarm output module;Wherein
The alarm assemblies include alarm/shutdown status indicator and buzzer.
8. according to claim 1 for the remodeling turbine power plant static test system that navigates, which is characterized in that described to patrol
Collecting controller is PLC.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820774067.4U CN208297142U (en) | 2018-05-23 | 2018-05-23 | For the turbine power plant static test system of retrofiting that navigates |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820774067.4U CN208297142U (en) | 2018-05-23 | 2018-05-23 | For the turbine power plant static test system of retrofiting that navigates |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208297142U true CN208297142U (en) | 2018-12-28 |
Family
ID=64726915
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820774067.4U Active CN208297142U (en) | 2018-05-23 | 2018-05-23 | For the turbine power plant static test system of retrofiting that navigates |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208297142U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114115167A (en) * | 2020-08-27 | 2022-03-01 | 郑州深澜动力科技有限公司 | Battery pack fire extinguishing test system |
-
2018
- 2018-05-23 CN CN201820774067.4U patent/CN208297142U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114115167A (en) * | 2020-08-27 | 2022-03-01 | 郑州深澜动力科技有限公司 | Battery pack fire extinguishing test system |
CN114115167B (en) * | 2020-08-27 | 2024-03-26 | 郑州深澜动力科技有限公司 | Battery pack fire extinguishing test system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN201336157Y (en) | Novel test device for reactor protection systematic procedure instrument testing | |
CN208297142U (en) | For the turbine power plant static test system of retrofiting that navigates | |
CN102798759A (en) | Insulation resistance test system | |
CN104020376A (en) | Three-remote automatic testing method for power distribution terminal | |
CN205620509U (en) | Difunctional circuit maintenance tester | |
CN209215493U (en) | A kind of railway signal measuring device | |
CN106019123A (en) | RF circuit off-location detecting system of communication and navigation system | |
CN112485577B (en) | Low-voltage testing device for power electronic equipment | |
GB1355142A (en) | Computer-based installation for the functional checking of a vehicle electrical system | |
CN104391255A (en) | Switching power supply fault simulator | |
CN103995207A (en) | Three-remote automatic test device for power distribution terminal | |
CN209044027U (en) | NEW ADAPTIVE tripping outlet logic tester | |
CN104407254A (en) | Circuit board tester | |
CN203981790U (en) | A kind of combined type backup auto-activating device tester | |
CN103207342B (en) | A kind of checking experiment grounding intelligent prior-warning device | |
CN206021071U (en) | A kind of diesel engine side monitoring box test system | |
CN203522711U (en) | Signal converter electrical aging detection apparatus | |
CN205193187U (en) | Extra -high voltage TDC direct current protection verifying attachment | |
CN209731272U (en) | A kind of test platform of High Speed Train Operation Control system | |
CN209471144U (en) | A kind of hydroelectric power plant's generating unit speed node calibration equipment | |
CN105606988A (en) | Circuit tester | |
CN203101536U (en) | Switch cabinet test table | |
CN111308235A (en) | Relay protection contact action tester based on wireless transmission | |
CN221378137U (en) | Test bench of BOX equipment | |
CN108226730A (en) | A kind of multichannel insulation pressure resistance automatic testing equipment and method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |