CN208293429U - The prestress hole path pressure grouting circulatory system in a kind of prestressed reinforced concrete construction - Google Patents

The prestress hole path pressure grouting circulatory system in a kind of prestressed reinforced concrete construction Download PDF

Info

Publication number
CN208293429U
CN208293429U CN201820442227.5U CN201820442227U CN208293429U CN 208293429 U CN208293429 U CN 208293429U CN 201820442227 U CN201820442227 U CN 201820442227U CN 208293429 U CN208293429 U CN 208293429U
Authority
CN
China
Prior art keywords
double
prestressed
circulatory system
pore passage
hole path
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820442227.5U
Other languages
Chinese (zh)
Inventor
胡进
刘欢
任若微
任军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China First Metallurgical Group Co Ltd
Original Assignee
China First Metallurgical Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China First Metallurgical Group Co Ltd filed Critical China First Metallurgical Group Co Ltd
Priority to CN201820442227.5U priority Critical patent/CN208293429U/en
Application granted granted Critical
Publication of CN208293429U publication Critical patent/CN208293429U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model discloses the prestress hole path pressure grouting circulatory systems in a kind of prestressed reinforced concrete construction, including blender, Double-layer filter type slurry can and pneumatic mortar machine, the filter device for being classified as upper and lower two segment spaces is equipped in the middle part of the Double-layer filter type slurry can, pneumatic mortar machine entrance is connected by madjack pipe with Double-layer filter type slurry can bottom, pneumatic mortar machine outlet is connected by inlet pipe with prestressed pore passage stock inlet, prestressed pore passage slurry output end at the top of pulp circulation loop pipeline and Double-layer filter type slurry can by being connected, the grout outlet and stock inlet of the prestressed pore passage are equipped with control valve and grout inspection instrument, blender is connected by pipeline with Double-layer filter type slurry can lower space, the utility model guarantees that hole path pressure grouting is closely knit with law of connected vessels and circulation loop system, it is stable to slurries index in prestressed pore passage and Grout outlet control valve, low in cost, good environmental protection, high financial profit are closed after grout inspection instrument detection in both ends is up to standard.

Description

The prestress hole path pressure grouting circulatory system in a kind of prestressed reinforced concrete construction
Technical field
The invention belongs to bridge concrete construction fields, are related to a kind of prestress hole path pressure grouting equipment, and in particular to a kind of The prestress hole path pressure grouting circulatory system in prestressed reinforced concrete construction.
Background technique
In prestressed reinforced concrete construction construction process, the main purpose of prestress hole path pressure grouting is:
(1) presstressed reinforcing steel is protected, prevents from corroding;
(2) bond presstressed reinforcing steel effectively with concrete members, with the development of control critical eigenvalue;
(3) and mitigate the load of beam-ends anchorage.
Therefore, prestress hole path pressure grouting construction is particularly important in prestressed reinforced concrete construction, and component on site construction method is at present After completing prestressing tendon tensioning, using the extra prestressing tendon of emery wheel cuts, the remaining length after presstressed reinforcing steel cuts off must not Less than 30mm.Presstressed reinforcing steel gap outside anchorage is clogged with cement slurry, so as not to grout and lose grouting pressure.It is reserved when sealing off and covering anchorage Gas vent.Pressure flush of water is used in duct before mud jacking, with sundries such as granulated slags in evacuation aperture, guarantees that duct is unimpeded.With sky after flushing Press blows away hole internal water accumulation, and compressed air will be without oil content.But it keeps duct to soak, makes being well combined for cement slurry and hole wall. Hole path pressure grouting uses Special grouting material, and water-cement ratio uses 0.26-0.28.Practical mixing water is added first in blender 80%-90% starts blender, is uniformly added into whole grouting materials, stirs while adding.Whole powder additions finish, then fastly Speed stirring 3min, is added the mixing water of remaining 10%-20%, continues to stir 2min.Grouting material is from stirring to indentation duct Perdurabgility, depending on temperature situation, generally within the scope of 30min~1h.When mud jacking, by inlet pipe slip casting, prestress pipe Grout outlet freely sprays slurries, closes grout outlet valve, mud jacking when grout outlet ejection slurries index is approximate with stock inlet consistent Machine holds pressure 3~5 minutes with 0.5MPa, closes prestressed pore passage stock inlet valve, and mud jacking terminates.
But at the scene in work progress, since process itself is existing insufficient, in mud jacking, duct grout outlet directly sprays Slurries are penetrated, so that: (1) due to the form that prestress pipe is symmetrical arc, especially large span continuous rigid frame bridge box beam, answer in advance The mud jacking mode of the larger therefore traditional grout outlet free-jetting slurries of power duct both ends vertical curve length is easy to cause hole to say The not firm problem of existing mud jacking, and the not firm prestressing tendon that will lead to of hole path pressure grouting corrodes, construction pre-stress is insufficient, and then influences engineering Quality;(2) slurries that grout outlet directly ejects seriously polluted mechanical equipment, the site environment of pier stud, ground storage, to clear Science and engineering brings bigger difficulty, and especially high pier stud cleaning is not only spent human and material resources, but also the personal safety of cleanup crew There is also hidden danger.(3) grout outlet free-jetting slurries waste material resources, have deviated from the developing policy of national energy-saving environmental protection.
Utility model content
The main purpose of the utility model is that live mud jacking process is instructed using a kind of prestress hole path pressure grouting circulatory system Construction, using law of connected vessels and the circulatory system, pore passage dense, environmental protection, saving material when achieving the purpose that mud jacking, simultaneously The structure for improving slurry can is Double-layer filter type, guarantees the quality of loop slurry.
In order to solve the above-mentioned technical problem, the technical solution adopted in the utility model is:
The prestress hole path pressure grouting circulatory system in a kind of prestressed reinforced concrete construction, it is characterised in that: including double medium filtration Formula slurry can and pneumatic mortar machine, the Double-layer filter type slurry can middle part are equipped with the filtering dress for being classified as upper and lower two segment spaces Set, the pneumatic mortar machine entrance is connected by madjack pipe with Double-layer filter type slurry can bottom, pneumatic mortar machine outlet pass through inlet pipe and Prestressed pore passage stock inlet is connected, and prestressed pore passage slurry output end passes through pulp circulation loop pipeline and Double-layer filter type slurry can top Portion is connected.
As an improvement, the grout outlet and stock inlet of the prestressed pore passage are equipped with control valve and grout inspection instrument.
As an improvement, further including blender, the blender passes through pipeline and Double-layer filter type slurry can lower space phase Even.
As an improvement, the inlet pipe and prestressed pore passage connecting pin are equipped with mud jacking mouth.
As an improvement, the filter device is telescopic filtering drawer.
As an improvement, the filter device is the filter screen being superimposed on two layers, the mesh of upper level filter net is greater than lower layer.
As an improvement, the inlet pipe and pulp circulation loop pipeline and prestressed pore passage are fixedly mounted by anchorage.
The utility model beneficial effect is:
This prestress hole path pressure grouting circulatory system mainly has the following characteristics that
(1) when this prestress hole path pressure grouting circulatory system is run, mainly by improved Double-layer filter type slurry can, mud jacking Machine, inlet pipe, prestressed pore passage and pulp circulation loop pipeline form a set of circulatory system, with law of connected vessels and follow Loop back path system guarantees that hole path pressure grouting is closely knit, reaches to slurries index stabilization in prestressed pore passage and in the detection of both ends grout inspection instrument Mark (i.e. both ends slurries index always) closes grout outlet control valve afterwards, holds pressure 3-5 minute with 0.5MPa by pneumatic mortar machine, closes in advance Stress duct stock inlet control valve, mud jacking process terminate.With such circulatory system construction quality is improved a lot, together When be greatly enhanced compared to more traditional mud-jacking technology efficiency;
(2) technical principle is easily understood, and this circulatory system controls equipment without high-grade, precision and advanced computer etc., applies convenient for scene Worker person understands and uses, and is suitble to promote;
(3) this circulatory system controls equipment without high-grade, precision and advanced computer etc., understands convenient for site operation personnel and operates, and protects It has demonstrate,proved construction site to manage the quality of critical process, system assembling and dismantling are convenient, and save the cost improves work efficiency simultaneously;
(4) improve slurry can structure: setting Double-layer filter type slurry can, loop slurry are entered on slurry can by return Layer flows into lower layer after slurry can filtering drawer filtering, improves the quality of loop slurry, while also ensuring construction quality;
(5) this circulatory system is simple, and construction cost investment is low, and engineering effort is good, remarkable in economical benefits;
(6) environment protecting is obvious, finds in previous construction: the slurries directly ejected by prestressed pore passage grout outlet are dirty Mechanical equipment, the site environment for having contaminated pier stud, ground storage, bring bigger difficulty to cleaning work, especially high pier stud is clear It is clean, it not only spends human and material resources, but also there is also hidden danger for the personal safety of cleanup crew.Pass through the application of this circulatory system, energy It effectively avoids pollution, while the serum recycle that grout outlet ejects utilizes, and saves material, reduces cost input.
(7) waste of material is avoided so that the slurries of duct grout outlet are recycled due to the presence of circulation loop And environmental pollution, technology is provided for construction " Civilization Worksite, green building site " and is guaranteed, social benefit is significant.
Detailed description of the invention
Fig. 1 is Continuous Rigid Box Beam mud jacking circulatory system schematic diagram.
Fig. 2 is prestressed concrete Precast T-Beam mud jacking circulatory system schematic diagram.
Fig. 3 is prestress hole path pressure grouting circulatory system partial enlargement diagram.
Fig. 4 is that the prestress hole path pressure grouting circulatory system recycles schematic diagram.
Appended drawing reference: 1- blender, 2- Double-layer filter type slurry can, 3- madjack pipe, 4- pneumatic mortar machine, 5- inlet pipe, 6- control Valve processed, 7- anchorage, 8- pulp circulation loop pipeline, 9- prestressed pore passage, 10- mud jacking mouth, 11- filter drawer, the inspection of 12- slurries Survey instrument, 13- bridge pier.
Specific embodiment
The utility model is illustrated with reference to the accompanying drawing
As shown in Figure 1 to Figure 3, a kind of to apply the prestressed pore passage in the prestressed reinforced concrete construction in continuous steel frame box beam The mud jacking circulatory system, including blender, Double-layer filter type slurry can and pneumatic mortar machine, the Double-layer filter type slurry can middle part are equipped with It is classified as the filter device of upper and lower two segment spaces, the pneumatic mortar machine entrance passes through madjack pipe and Double-layer filter type slurry can Bottom is connected, and pneumatic mortar machine outlet is connected by inlet pipe with prestressed pore passage stock inlet, and prestressed pore passage slurry output end passes through pulp It is connected at the top of circulation loop pipeline and Double-layer filter type slurry can, is equipped with control on the madjack pipe and pulp circulation loop pipeline Valve processed and grout inspection instrument, the blender is connected by pipeline with Double-layer filter type slurry can lower space, described into slurry Pipe is equipped with mud jacking mouth with prestressed pore passage connecting pin.The inlet pipe and pulp circulation loop pipeline pass through with prestressed pore passage Anchorage is fixedly mounted.
In the embodiment, the filter device is telescopic filtering drawer, as a kind of more preferably embodiment, the mistake Filter device is the filter screen being superimposed on two layers, and the mesh of upper level filter net is greater than lower layer, not only ensure that slurries by filter device The quality of circulation, and loop slurry can also take residual impurity in prestressed pore passage out of, and be filtered impurity by filter device It removes, greatly improves slurries compaction quality in prestressed pore passage, guarantee project progress.
As shown in figure 4, in this pre- prestressed reinforced concrete construction when the operation of the prestress hole path pressure grouting circulatory system, mainly by stirring It mixes machine, Double-layer filter type slurry can, pneumatic mortar machine, inlet pipe, prestressed pore passage and pulp circulation loop pipeline and forms a set of follow Control valve and grout inspection instrument is arranged in the stock inlet of prestressed pore passage by loop system, using inlet pipe by itself and pneumatic mortar machine Grout outlet connection, control valve and grout inspection instrument be set in prestress pipe grout outlet, then with pulp circulation loop pipe Road is connected to Double-layer filter type slurry can upper layer loop slurry filtering tank, and loop slurry flows into double medium filtration after filtering Lower layer's hole path pressure grouting slurry storage tank of formula slurry can, the outlet of slurries slurry can are connected to pneumatic mortar machine, complete the mud jacking circulatory system Foundation.After mud jacking starts, this circulatory system is allowed to be operated, when the slurries index and stock inlet one of prestressed pore passage grout outlet When cause, close prestress pipe grout outlet at control valve, and make pneumatic mortar machine to not less than 0.5Mpa pressure hold lotus 3~ 5min pressure maintaining closes stock inlet control valve after completing, and mud jacking terminates.(1) prestressed reinforced concrete construction mesoporous during this Road mud jacking utilizes law of connected vessels and the circulatory system, it is ensured that mud jacking is closely knit in prestress pipe, guarantees construction quality;(2) The slurries that grout outlet sprays will loop to Double-layer filter type slurry can impurity screening and (carry out to prestressed pore passage before mud jacking clear Simultaneously wind is washed, therefore slurries can recycle, furthermore loop slurry is filtered recycling by Double-layer filter type slurry can, Ensure that the quality of loop slurry), material is saved, and meet environmentally protective construction principle.
(1) system buildup
This prestress hole path pressure grouting circulatory system is related to blender, Double-layer filter type slurry can, pressure when being set up Pulp grinder, inlet pipe, prestressed pore passage pulp circulation loop pipeline, grout inspection instrument, control valve.Blender and Double-layer filter type The connection of slurry can lower layer slurry storage tank, the outlet of Double-layer filter type slurry can lower layer and pneumatic mortar machine are attached with madjack pipe, are pressed The grout outlet of pulp grinder and the stock inlet of prestress pipe are attached with inlet pipe, are examined in prestressed pore passage stock inlet setting slurries Instrument and control valve are surveyed, grout inspection instrument and control valve be set in prestressed pore passage grout outlet, then by prestressed pore passage Grout outlet be connected to Double-layer filter type slurry can upper layer loop slurry filtering tank with pulp circulation loop pipeline, loop slurry warp Lower layer's slurry storage tank is flowed into after filtering, so far, this prestress hole path pressure grouting circulatory system, which is set up, to be completed.
(2) mud jacking starts
Start to carry out hole path pressure grouting after completing prestressed pore passage cleaning and blowing away ponding with wind pressure machine, hole path pressure grouting uses Special grouting material, water-cement ratio use 0.26-0.28, carry out slurries stirring after feeding, and be stored in Double-layer filter type slurry can, Pass through inlet pipe, the slip casting into prestress pipe of pumping of prostressed duct mouth again.
(3) mud jacking terminates
When slurries are flowed out from prestressed pore passage grout outlet, slurries flow back to the double-deck mistake by pulp circulation loop pipeline circulation Filter formula slurry can measures pulp technical indicator, when slurry output end institute by being set to the grout inspection instrument of prestress pipe grout outlet When slurries technical indicator is consistent with stock inlet slurries technical indicator out, to hold lotus 3~5min pressure maintaining not less than 0.5Mpa pressure, really Slip casting is full in keeping road, closes prestress pipe stock inlet control valve, so far, mud jacking terminates.

Claims (7)

1. the prestress hole path pressure grouting circulatory system in a kind of prestressed reinforced concrete construction, it is characterised in that: including Double-layer filter type Slurry can and pneumatic mortar machine, the Double-layer filter type slurry can middle part are equipped with the filtering dress for being classified as upper and lower two segment spaces Set, the pneumatic mortar machine entrance is connected by madjack pipe with Double-layer filter type slurry can bottom, pneumatic mortar machine outlet pass through inlet pipe and Prestressed pore passage stock inlet is connected, and prestressed pore passage slurry output end passes through pulp circulation loop pipeline and Double-layer filter type slurry can top Portion is connected.
2. the prestress hole path pressure grouting circulatory system in a kind of prestressed reinforced concrete construction as described in claim 1, it is characterised in that: The grout outlet and stock inlet of the prestressed pore passage are equipped with control valve and grout inspection instrument.
3. the prestress hole path pressure grouting circulatory system in a kind of prestressed reinforced concrete construction as claimed in claim 2, it is characterised in that: It further include blender, the blender is connected by pipeline with Double-layer filter type slurry can lower space.
4. the prestress hole path pressure grouting circulatory system in a kind of prestressed reinforced concrete construction as claimed in claim 2, it is characterised in that: The inlet pipe and prestressed pore passage connecting pin are equipped with mud jacking mouth.
5. the prestress hole path pressure grouting circulatory system in a kind of prestressed reinforced concrete construction as claimed in claim 2, it is characterised in that: The filter device is telescopic filtering drawer.
6. the prestress hole path pressure grouting circulatory system in a kind of prestressed reinforced concrete construction as claimed in claim 2, it is characterised in that: The filter device is the filter screen being superimposed on two layers, and the mesh of upper level filter net is greater than lower layer.
7. the prestress hole path pressure grouting circulatory system in a kind of prestressed reinforced concrete construction as claimed in claim 2, it is characterised in that: The inlet pipe and pulp circulation loop pipeline and prestressed pore passage are fixedly mounted by anchorage.
CN201820442227.5U 2018-03-30 2018-03-30 The prestress hole path pressure grouting circulatory system in a kind of prestressed reinforced concrete construction Expired - Fee Related CN208293429U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820442227.5U CN208293429U (en) 2018-03-30 2018-03-30 The prestress hole path pressure grouting circulatory system in a kind of prestressed reinforced concrete construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820442227.5U CN208293429U (en) 2018-03-30 2018-03-30 The prestress hole path pressure grouting circulatory system in a kind of prestressed reinforced concrete construction

Publications (1)

Publication Number Publication Date
CN208293429U true CN208293429U (en) 2018-12-28

Family

ID=64694690

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820442227.5U Expired - Fee Related CN208293429U (en) 2018-03-30 2018-03-30 The prestress hole path pressure grouting circulatory system in a kind of prestressed reinforced concrete construction

Country Status (1)

Country Link
CN (1) CN208293429U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112227725A (en) * 2020-11-11 2021-01-15 中交第四公路工程局有限公司 Grouting structure of long pore passage of prestressed concrete stiffening beam and construction method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112227725A (en) * 2020-11-11 2021-01-15 中交第四公路工程局有限公司 Grouting structure of long pore passage of prestressed concrete stiffening beam and construction method thereof

Similar Documents

Publication Publication Date Title
CN104675141B (en) A kind of FRP pipe constraint cement-base composite material reinforces pillarwork
CN101424106A (en) Steel sheet regeneration mixed wall and construction method thereof
CN103570317A (en) Fair-faced concrete produced by using construction waste recycled aggregates
CN104846810A (en) Self-circulating posterior grouting bored pile construction method
CN105780976B (en) Compound concrete shear wall structure and its concreting method
CN110258848A (en) A kind of construction method of building energy conservation CL composite shear wall
CN104295002B (en) Inside set height strengthening regenerative mixed steel pipe concrete Column under Axial Load and the construction technology of local restriction
CN108999212A (en) The template construction method of underground concrete pool wall antiseep
CN101936170A (en) Cavern arch mould spraying concrete construction structure and process
CN112663774A (en) Construction method of unbonded prestressed large-diameter reinforced concrete thin-wall circular water tank
CN208293429U (en) The prestress hole path pressure grouting circulatory system in a kind of prestressed reinforced concrete construction
CN108894432A (en) A kind of very-high performance steel fiber concrete pipe constraint regeneration monolith column
CN108049395A (en) A kind of anti-collapse impact holing construction method in complex karst place
CN2921135Y (en) Special concrete crack induction strip for concrete construction joint
CN104060590B (en) The reinforcement leakage preventing structure of a kind of pressure diversion tunnel and construction method thereof
CN101451380B (en) Processing method of prefabricating common concrete outer plate recycled concrete core shear wall
CN215165624U (en) Grouting device behind cavity of hollow precast pile
CN104805864B (en) The cementing Waterproof Construction Technique that closes of basement top-down method exterior wall tongue and groove and sealing
CN212427210U (en) UHPC-RC combination coincide assembled utility tunnel structure
CN112663463A (en) Filling material, equipment and method for coring and hole testing of asphalt pavement
CN110042749A (en) UHPC steel tube concrete overlap-type lattice column structure and its construction method
CN104762961B (en) A kind of ultra-high performance concrete and ordinary concrete compound pile and construction method thereof
CN106759857B (en) Steel tube regeneration monolith assembling structure
CN109437803A (en) A kind of processing technology of energy conservation and environmental protection pervious concrete
CN106703196B (en) Interior ring type steel tube regeneration monolith assembling structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20181228