CN208279200U - A kind of parallel change rail mechanism - Google Patents
A kind of parallel change rail mechanism Download PDFInfo
- Publication number
- CN208279200U CN208279200U CN201820745861.6U CN201820745861U CN208279200U CN 208279200 U CN208279200 U CN 208279200U CN 201820745861 U CN201820745861 U CN 201820745861U CN 208279200 U CN208279200 U CN 208279200U
- Authority
- CN
- China
- Prior art keywords
- track
- trolley
- portal frame
- frame slideway
- skeleton
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Abstract
The utility model discloses a kind of parallel change rail mechanisms, including portal frame slideway, trolley skeleton and track lifting appliance, spray room track is connected on the right side of the lower end of the portal frame slideway, and idler wheel is distributed in the upper end of portal frame slideway, the inside middle portion of the idler wheel, which runs through, main shaft, and fixing seat is installed on the downside of main the tip of the axis, the trolley skeleton is fixed on the end of fixing seat, the bottom of the trolley skeleton is inlaid with trolley track, and the two sides of the bottom of trolley track are provided with pulley blocks, the track lifting appliance is connected to the bottom of pulley blocks.The parallel change rail mechanism is provided with portal frame slideway, it is respectively in parallel shape structure between portal frame slideway and spray room track and trapped orbit, it can guarantee intersect between portal frame slideway and spray room track, to avoid occurring spray room in use clashing with curing oven use aspects, workpiece is caused to pause between spraying and solidification, so that workpiece effectively can not be sprayed and be solidified.
Description
Technical field
The utility model relates to become rail mechanism technical field, specially a kind of parallel change rail mechanism.
Background technique
Many spray rooms exist with curing oven use aspects and conflict at this stage, and when product solidifies in curing oven, spray room is necessary
It stops work, otherwise movable hanger can not have enough to meet the need, and the parallel rail mechanism that becomes can improve spray room and curing oven use aspects problem, mention
High efficiency.
When change rail mechanism spray room in use and curing oven in the market works at the same time, movable hanger can not have enough to meet the need, and cause
Suspender effectively can not be sprayed and be solidified, and reduce suspender spraying and solidification production efficiency, and become rail mechanism and do not have in use
There is good fixed structure, lead to be likely to occur trolley in use falling from portal frame slideway upper end, leads to hanging for small car
Tool damage, brings unnecessary loss to using, for this purpose, it is proposed that a kind of parallel change rail mechanism.
Utility model content
The purpose of this utility model is to provide a kind of parallel change rail mechanisms, to solve city mentioned above in the background art
When change rail mechanism spray room in use and curing oven on field work at the same time, movable hanger can not have enough to meet the need, and cause suspender that can not have
Effect is sprayed and is solidified, and suspender spraying and solidification production efficiency are reduced, and becomes rail mechanism in use without solid well
Determine structure, lead to be likely to occur trolley in use falling from portal frame slideway upper end, the suspender of small car is caused to damage, to making
The problem of with unnecessary loss is brought.
To achieve the above object, the utility model provides the following technical solutions: a kind of parallel change rail mechanism, including portal frame
Slideway, trolley skeleton and track lifting appliance, are connected with spray room track on the right side of the lower end of the portal frame slideway, and portal frame slideway
Idler wheel is distributed in upper end, and the inside middle portion of the idler wheel, which runs through, main shaft, and is equipped with fixing seat on the downside of main the tip of the axis, described
Trolley skeleton is fixed on the end of fixing seat, and the bottom of the trolley skeleton is inlaid with trolley track, and the bottom of trolley track
Two sides are provided with pulley blocks, and the track lifting appliance is connected to the bottom of pulley blocks, and the inside surrounding of pulley blocks is inlaid with hexagonal
The rear end downside of screw, the trolley skeleton is equipped with push bracket, and anti-slip layer is distributed on the inside of push bracket, the track lifting appliance
Lower end is fixed with fixed column, and the lower end of fixed column is provided with hanging ring, and the top two sides of the fixing seat are connected with limited bolt, institute
It states and trapped orbit is installed on the left of the lower end of portal frame slideway.
It preferably, is in disjoint well shape structure between the portal frame slideway and spray room track and trapped orbit, and
It is respectively in parallel shape structure between portal frame slideway and spray room track and trapped orbit.
Preferably, the trolley skeleton is connected by idler wheel with portal frame slideway, and trolley skeleton and portal frame slideway
Between to be slidably connected, and idler wheel is distributed along the surrounding of trolley skeleton.
Preferably, the equidistant lower end for being evenly distributed on trolley skeleton of the trolley track, and trolley track is provided with 4
It is a, and be parallel construction between trolley track and trolley track.
Preferably, it is welding between the pulley blocks and track lifting appliance, and is liftable between pulley blocks and trolley track
Structure.
Preferably, the L-shape distribution of the push bracket, and be bonded to each other between push bracket and anti-slip layer.
Compared with prior art, the utility model has the beneficial effects that the parallel change rail mechanism is provided with portal frame slideway,
It is in respectively parallel shape structure between portal frame slideway and spray room track and trapped orbit, can guarantees portal frame slideway and spray room rail
Will not intersect between road, prevent from occurring spray room in use to clash with curing oven use aspects, cause workpiece spraying with
It pauses, so that workpiece effectively can not be sprayed and be solidified, makes troubles to user, trolley skeleton is fixed between solidification
In the end of fixing seat, trolley skeleton is connected by idler wheel with portal frame slideway, when user needs trolley skeleton to two
When side is moved, trolley skeleton can be suitably positioned by idler wheel in use, while idler wheel is distributed along surrounding, energy
The stability for enough guaranteeing trolley skeleton on the move prevents occurring the fixed shakiness of trolley skeleton in use, leads to trolley skeleton
It jolts in movement, workpiece is caused to fall off, the two sides of the bottom of trolley track are provided with pulley blocks, and trolley track is equidistant
It is evenly distributed on the lower end of trolley skeleton, and is parallel construction between trolley track and trolley track, when user puts workpiece
Certain suitable distance is had when setting track lifting appliance lower end, between workpiece and workpiece, prevents work occur in spraying and solidification
It is touched between part and workpiece, causes workpiece effectively not sprayed and be solidified, make troubles to user, while making
It can guarantee the perpendicular shape distribution of workpiece in.
Detailed description of the invention
Fig. 1 is the utility model three dimensional structure diagram;
Fig. 2 is the utility model side structure schematic view;
Fig. 3 is the utility model overlooking structure diagram.
In figure: 1, portal frame slideway, 2, spray room track, 3, idler wheel, 4, main shaft, 5, fixing seat, 6, trolley skeleton, 7, trolley
Track, 8, pulley blocks, 9, track lifting appliance, 10, push bracket, 11, anti-slip layer, 12, hex screw, 13, fixed column, 14, hanging ring, 15,
Limited bolt, 16, solidification track.
Specific embodiment
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model
Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole
Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work
Every other embodiment obtained, fall within the protection scope of the utility model.
Please refer to Fig. 1-3, the utility model provides a kind of technical solution: a kind of parallel change rail mechanism, including portal frame are sliding
Road 1, spray room track 2, idler wheel 3, main shaft 4, fixing seat 5, trolley skeleton 6, trolley track 7, pulley blocks 8, track lifting appliance 9, push bracket
10, anti-slip layer 11, hex screw 12, fixed column 13, hanging ring 14, limited bolt 15 and trapped orbit 16, the lower end of portal frame slideway 1
Right side is connected with spray room track 2, and the upper end of portal frame slideway 1 is distributed with idler wheel 3, portal frame slideway 1 and spray room track 2 and consolidates
It is in disjoint well shape structure between orbit determination road 16, and between portal frame slideway 1 and spray room track 2 and trapped orbit 16 respectively
In parallel shape structure, it can guarantee intersect between portal frame slideway 1 and spray room track 2, prevent occurring spray room in use
Clashed with curing oven use aspects, workpiece caused to pause between spraying and solidification so that workpiece can not effectively into
Row spraying and solidification, make troubles to user, and the inside middle portion of idler wheel 3, which runs through, main shaft 4, and peace on the downside of the end of main shaft 4
Equipped with fixing seat 5, trolley skeleton 6 is fixed on the end of fixing seat 5, and trolley skeleton 6 is connected by idler wheel 3 with portal frame slideway 1
It connects, and to be slidably connected between trolley skeleton 6 and portal frame slideway 1, and idler wheel 3 is distributed along the surrounding of trolley skeleton 6, when making
When user needs to move trolley skeleton 6 to two sides, trolley skeleton 6 can be placed into properly by idler wheel 3 in use
Position, while idler wheel 3 is distributed along surrounding, can be guaranteed the stability of trolley skeleton 6 on the move, be prevented from occurring in use small
Vehicle skeleton 6 is fixed unstable, causes to jolt in the movement of trolley skeleton 6, causes workpiece to fall off, the bottom of trolley skeleton 6
It is inlaid with trolley track 7, and the two sides of the bottom of trolley track 7 are provided with pulley blocks 8, trolley track 7 is equidistant to be evenly distributed on
The lower end of trolley skeleton 6, and trolley track 7 is provided with 4, and is parallel construction between trolley track 7 and trolley track 7,
When workpiece is placed into 9 lower end of track lifting appliance by user, certain suitable distance is had between workpiece and workpiece, prevents from spraying
It applies and occurs touching between workpiece and workpiece in solidifying, cause workpiece effectively not sprayed and be solidified, give user
It making troubles, while can guarantee the perpendicular shape distribution of workpiece in use, track lifting appliance 9 is connected to the bottom of pulley blocks 8, and
The inside surrounding of pulley blocks 8 is inlaid with hex screw 12, between pulley blocks 8 and track lifting appliance 9 for welding, and pulley blocks 8 with it is small
It is liftable structure between track road 7, pulley blocks 8 and track lifting appliance 9 are with good stability, prevent pulley blocks in use
8 when slinging heavier object, cause it is fixed unstable between pulley blocks 8 and track lifting appliance 9, cause pulley blocks 8 and track lifting appliance 9 it
Between be broken, cause track lifting appliance 9 to be dropped from 8 lower end of pulley blocks, so that the workpiece damage in track lifting appliance 9, give user
Bring unnecessary economic loss, push bracket 10 be installed on the downside of the rear end of trolley skeleton 6, and the inside of push bracket 10 be distributed with it is anti-skidding
Layer 11, the L-shape distribution of push bracket 10, and be bonded to each other between push bracket 10 and anti-slip layer 11, when user needs to push trolley skeleton 6
When being moved, trolley skeleton 6 can be pushed to be moved, anti-slip layer 11 can be held as user by push bracket 10 in use
Firmly when handle in push bracket 10, prevent from skidding between hand and handle, while user more saves when pushing push bracket 10
Power, user-friendly, the lower end of track lifting appliance 9 is fixed with fixed column 13, and the lower end of fixed column 13 is provided with hanging ring 14,
The top two sides of fixing seat 5 are connected with limited bolt 15, are equipped with trapped orbit 16 on the left of the lower end of portal frame slideway 1.
Working principle: passing through hanging ring 14 for this kind of parallel change rail mechanism first, workpiece be linked into 14 bottom end of hanging ring, this
When user by pulley blocks 8, track lifting appliance 9 is moved up, when the workpiece on wherein two sets track lifting appliances 9 is from spray room spraying
After be pushed into curing oven and solidify by spray room track 2, trolley track 7, the curing oven track 16 of connection, at this time by small
Push bracket 10 on vehicle skeleton 6, propelling sheave 3 is mobile on portal frame slideway 1 to drive trolley skeleton 6 to move integrally, two other
Trolley track corresponds to spray room and curing oven, then sprays other two pieces track lifting appliance 9 with spraying in suspension workpiece push-in spray room
After workpiece is moved out on trolley track 7, then return to original position for trolley skeleton 6 is whole, open curing oven at this time
Remove on workpiece to original trolley track 7, last moving trolley skeleton 6 will need cured workpiece to move into furnace, removal it is complete
At workpiece undercarriage, the entire parallel use process for becoming rail mechanism is completed like this.
While there has been shown and described that the embodiments of the present invention, for the ordinary skill in the art,
It is understood that these embodiments can be carried out with a variety of variations in the case where not departing from the principles of the present invention and spirit, repaired
Change, replacement and variant, the scope of the utility model is defined by the appended claims and the equivalents thereof.
Claims (6)
1. a kind of parallel change rail mechanism, including portal frame slideway (1), trolley skeleton (6) and track lifting appliance (9), it is characterised in that:
It is connected with spray room track (2) on the right side of the lower end of the portal frame slideway (1), and idler wheel is distributed in the upper end of portal frame slideway (1)
(3), the inside middle portion of the idler wheel (3) runs through and has main shaft (4), and is equipped with fixing seat (5), institute on the downside of the end of main shaft (4)
The end that trolley skeleton (6) is fixed on fixing seat (5) is stated, the bottom of the trolley skeleton (6) is inlaid with trolley track (7), and
The two sides of the bottom of trolley track (7) are provided with pulley blocks (8), and the track lifting appliance (9) is connected to the bottom of pulley blocks (8), and
The inside surrounding of pulley blocks (8) is inlaid with hex screw (12), is equipped with push bracket on the downside of the rear end of the trolley skeleton (6)
(10), it and on the inside of push bracket (10) being distributed with anti-slip layer (11), the lower end of the track lifting appliance (9) is fixed with fixed column (13),
And the lower end of fixed column (13) is provided with hanging ring (14), the top two sides of the fixing seat (5) are connected with limited bolt (15), described
Trapped orbit (16) are installed on the left of the lower end of portal frame slideway (1).
2. a kind of parallel change rail mechanism according to claim 1, it is characterised in that: the portal frame slideway (1) and spray room
Be in disjoint well shape structure between track (2) and trapped orbit (16), and portal frame slideway (1) and spray room track (2) and
It is respectively in parallel shape structure between trapped orbit (16).
3. a kind of parallel change rail mechanism according to claim 1, it is characterised in that: the trolley skeleton (6) passes through idler wheel
(3) it is connected with portal frame slideway (1), and to be slidably connected between trolley skeleton (6) and portal frame slideway (1), and idler wheel
(3) it is distributed along the surrounding of trolley skeleton (6).
4. a kind of parallel change rail mechanism according to claim 1, it is characterised in that: the trolley track (7) is equidistant
The even lower end for being distributed in trolley skeleton (6), and trolley track (7) is provided with 4, and trolley track (7) and trolley track (7)
Between be parallel construction.
5. a kind of parallel change rail mechanism according to claim 1, it is characterised in that: the pulley blocks (8) and track lifting appliance
(9) it is welding between, and is liftable structure between pulley blocks (8) and trolley track (7).
6. a kind of parallel change rail mechanism according to claim 1, it is characterised in that: the L-shape distribution of the push bracket (10), and
It is bonded to each other between push bracket (10) and anti-slip layer (11).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820745861.6U CN208279200U (en) | 2018-05-18 | 2018-05-18 | A kind of parallel change rail mechanism |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820745861.6U CN208279200U (en) | 2018-05-18 | 2018-05-18 | A kind of parallel change rail mechanism |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208279200U true CN208279200U (en) | 2018-12-25 |
Family
ID=64730576
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820745861.6U Active CN208279200U (en) | 2018-05-18 | 2018-05-18 | A kind of parallel change rail mechanism |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208279200U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112944892A (en) * | 2021-02-22 | 2021-06-11 | 湖南人文科技学院 | Method for eliminating kiln car fault in high-temperature tunnel kiln |
-
2018
- 2018-05-18 CN CN201820745861.6U patent/CN208279200U/en active Active
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112944892A (en) * | 2021-02-22 | 2021-06-11 | 湖南人文科技学院 | Method for eliminating kiln car fault in high-temperature tunnel kiln |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204602495U (en) | A kind of aluminium alloy wheel hub of vehicle spray equipment of environmental protection | |
CN208279200U (en) | A kind of parallel change rail mechanism | |
CN201864264U (en) | Rolling-disk self-unloading scrap-iron vehicle | |
CN202193546U (en) | Crane end beam structure with rail sweeping device | |
CN205009259U (en) | Screw drive's spraying manipulator's stand mechanism adopts | |
CN205009258U (en) | Chain drive's spraying manipulator's stand mechanism adopts | |
CN202357261U (en) | Full-automatic blank powder wiping machine | |
CN204250214U (en) | A kind of motor bike automatic lifting main support | |
CN201321467Y (en) | Steel-smelting spray gun lifting device | |
CN209424724U (en) | A kind of gantry welding assembly unit | |
CN209427705U (en) | Automatic blanking device is used in pipe processing in one kind | |
CN204817283U (en) | Car body dust collecting equipment | |
CN205306893U (en) | Industrial dust remover | |
CN207844358U (en) | A kind of steering cross traveling trolley | |
CN204866866U (en) | Rack and pinion drawbench | |
CN209480562U (en) | A kind of chain push-and-pull type injection molding machine mould replacing trolley | |
CN208589302U (en) | A kind of mobile hydraulic frame type stranding machine wiring vehicle | |
CN209367032U (en) | A kind of high-level shelf | |
CN206069314U (en) | A kind of steel rope trailer | |
CN202847722U (en) | Mine car not prone to falling off track | |
CN108297838B (en) | A kind of car detailing automobile side limitation profile automatic cleaning equipment | |
CN104875102A (en) | Mechanical polishing equipment with waste residue recycling device | |
CN206662230U (en) | Servo link rod spraying machine | |
CN203199503U (en) | Hub lifting frame for drying | |
CN213749682U (en) | Door and window fire resistance test frame translation dolly |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |