CN208251111U - The Double-row Piles Support system of the local soft soil property of foundation pit can be overcome - Google Patents

The Double-row Piles Support system of the local soft soil property of foundation pit can be overcome Download PDF

Info

Publication number
CN208251111U
CN208251111U CN201820363950.4U CN201820363950U CN208251111U CN 208251111 U CN208251111 U CN 208251111U CN 201820363950 U CN201820363950 U CN 201820363950U CN 208251111 U CN208251111 U CN 208251111U
Authority
CN
China
Prior art keywords
campshed
double
behind
front side
rear side
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820363950.4U
Other languages
Chinese (zh)
Inventor
张敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Third Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd
Original Assignee
Third Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Third Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd filed Critical Third Engineering Co Ltd of China Railway 19th Bureau Group Co Ltd
Priority to CN201820363950.4U priority Critical patent/CN208251111U/en
Application granted granted Critical
Publication of CN208251111U publication Critical patent/CN208251111U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses the Double-row Piles Support systems that one kind can overcome the local soft soil property of foundation pit, it solves to the double triangle Double-row Piles Support partial alteration for having selected and having implemented into other support forms, the support form of existing partial alteration is not perfect with the connection that double triangle supporting construction is completed, and easily causes the non-uniform problem of local pressure.Rear side attachment beam (6) is provided between campshed after rear side (10) and preceding campshed (1), intermediate attachment beam (7) are provided between campshed behind centre (9) and preceding campshed, front side attachment beam (8) is provided between campshed behind front side (2) and preceding campshed, crown beam (5) are being provided between campshed after campshed behind campshed after rear side (10), centre and front side, high inclination-angle rotary churning pile (3) are being provided with after preceding campshed and centre between campshed, inserted with precast concrete beam (4) in high inclination-angle rotary churning pile.Design strength is met, and does not change the overall structure of design of its support.

Description

The Double-row Piles Support system of the local soft soil property of foundation pit can be overcome
Technical field
The present invention relates to a kind of buildings of system of deep foundation pit support, in particular to a kind of to be directed to deep basal pit and substrate part soil Layer relatively soft double-row pile mechanism and its construction method.
Background technique
Deep basal pit Double-row Piles Support has been developed in recent years a kind of novel supporting construction, with other supporting construction bodies System compares, and Double-row Piles Support form has good lateral rigidity, can effectively limit the lateral deformation of supporting construction.Double-row pile Support design method and construction have that convenient, lateral fulcrum, soil-baffling structure stress condition is good, it is steady to be able to maintain foundation pit without being arranged Calmly, it the advantages that construction safety, is widely used in engineering.The Double-row Piles Support of double triangle is suitable for soil layer mechanism phase To solid deep basal pit, have the characteristics that filling stake quantity is few, supporting intensity is high, project cost is lower, easy for construction.But specific In construction, when local soil property soft situation relatively occurs in somewhere in deep basal pit, the intensity of double triangle supporting construction will drop It is low, it is not able to satisfy design requirement, the prior art is to the double triangle Double-row Piles Support partial alteration for having selected and having implemented at it Its support form, it is not perfect with connection that double triangle supporting construction is completed that there are the support forms of partial alteration, is easy to draw Local discontinuity is played, the intensity of integer support is influenced.
Summary of the invention
The present invention provides Double-row Piles Support systems and construction method that one kind can overcome the local soft soil property of foundation pit, solve To the double triangle Double-row Piles Support partial alteration that has selected and implemented at other support forms, existing partial alteration Support form is not perfect with the connection that double triangle supporting construction is completed, and easily causes the non-uniform technology of local pressure and asks Topic.
The present invention is to solve the above technical problem by the following technical programs:
A kind of Double-row Piles Support system overcoming the local soft soil property of foundation pit, after at foundation pit locally soft soil property Campshed behind side, it is intermediate after campshed and preceding campshed behind campshed, front side, rear side connection is provided between campshed after rear side and preceding campshed Beam, is provided with intermediate attachment beam between campshed behind centre and preceding campshed, before being provided between campshed behind front side and preceding campshed Side attachment beam is being provided with crown beam between campshed after campshed behind campshed, centre after rear side and front side, in preceding campshed and intermediate heel row It is provided with high inclination-angle rotary churning pile between stake, inserted with precast concrete beam in high inclination-angle rotary churning pile.
Angle between high inclination-angle rotary churning pile and intermediate attachment beam is 50-75 degree.
A kind of construction method overcoming the local Double-row Piles Support system of soft soil property of foundation pit, comprising the following steps:
The first step, construct campshed after rear side, it is intermediate after campshed behind campshed and front side, method particularly includes: remove rear side heel row Stake stake holes, it is intermediate after residue behind campshed stake holes and front side in campshed stake holes;Respective steel reinforcement cage is transferred into respective stake holes Bottom hole, then respective concrete steel conduit is transferred, carry out second of borehole cleaning, then, continuous pouring underwater concrete, until stake holes Until slurry is returned in aperture, after the completion of perfusion, conduit, campshed after formation are dismantled;
Second step, after campshed concrete final set stablize after, from the stake top platform inner side of preceding campshed to centre after The direction of campshed performs high inclination-angle rotary churning pile, and high inclination-angle rotary churning pile takes segmentation rotary-spraying construction, and construction angle is 50-75 degree, greatly Inclination angle rotary churning pile links together preceding campshed and campshed behind centre, after high inclination-angle jet grouting pile construction, at its concrete end It coagulates before stablizing, precast concrete pile is inserted into high inclination-angle rotary churning pile;
Third step constructs preceding campshed, and the upper end of precast concrete pile and the steel reinforcement cage of preceding campshed are linked together;
After the concrete final set of 4th step, current campshed is stablized, rear side attachment beam, intermediate attachment beam, front side connection are carried out Beam and constructing for crown beam perform, and complete constructing for double triangle Double-row Piles Support systems.
It can be directed in work progress the purpose of the present invention is to provide a kind of, exploration before soil layer part practical structures and design Soil layer construction existing for deviation when, the construction method of local stiffening is carried out to the supporting construction that has designed;It is strong to meet design Degree, and do not change the overall structure of design of its support.
Detailed description of the invention
Fig. 1 is structural schematic diagram of the invention.
Specific embodiment
The present invention is described in detail with reference to the accompanying drawing:
A kind of Double-row Piles Support system overcoming the local soft soil property of foundation pit, after at foundation pit locally soft soil property Campshed 10 behind side, it is intermediate after campshed 2 and preceding campshed 1 behind campshed 9, front side, be provided between campshed 10 and preceding campshed 1 after rear side Rear side attachment beam 6 is being provided with intermediate attachment beam 7 between campshed 9 and preceding campshed 1 behind centre, campshed 2 and preceding campshed behind front side It is provided with front side attachment beam 8 between 1, is being provided with crown beam between campshed 2 after campshed 9 behind campshed 10, centre after rear side and front side 5, it is being provided with high inclination-angle rotary churning pile 3 between campshed 9 after preceding campshed 1 and centre, inserted with prefabricated mixed in high inclination-angle rotary churning pile 3 Solidifying soil beam 4.
Angle between high inclination-angle rotary churning pile 3 and intermediate attachment beam 7 is 50-75 degree.
A kind of construction method overcoming the local Double-row Piles Support system of soft soil property of foundation pit, comprising the following steps:
The first step, construct campshed 10 after rear side, it is intermediate after campshed 2 behind campshed 9 and front side, method particularly includes: remove rear side Afterwards campshed stake holes, it is intermediate after residue behind campshed stake holes and front side in campshed stake holes;Respective steel reinforcement cage is transferred to respective Stake holes bottom hole, then respective concrete steel conduit is transferred, second of borehole cleaning is carried out, then, continuous pouring underwater concrete, until Until slurry is returned in stake holes aperture, after the completion of perfusion, conduit, campshed after formation are dismantled;
Second step, after campshed concrete final set stablize after, from the stake top platform inner side of preceding campshed 1 to centre after The direction of campshed 9 performs high inclination-angle rotary churning pile 3, and high inclination-angle rotary churning pile 3 takes segmentation rotary-spraying construction, and construction angle is 50-75 Degree, high inclination-angle rotary churning pile 3 links together preceding campshed 1 and campshed 9 behind centre, after high inclination-angle rotary churning pile 3 is constructed, at it Before concrete final set is stablized, precast concrete pile 4 is inserted into high inclination-angle rotary churning pile 3;
Third step constructs preceding campshed 1, and the upper end of precast concrete pile 4 and the steel reinforcement cage of preceding campshed 1 are linked together;
After the concrete final set of 4th step, current campshed 1 is stablized, progress rear side attachment beam 6, intermediate attachment beam 7, front side connect It connects beam 8 and constructing for crown beam 5 performs, complete constructing for double triangle Double-row Piles Support systems.
The present invention be directed to the construction methods of Double-row Piles Support local strengthening, in double triangle Double-row Piles Support, this hair The bright double triangle Double-row-piles Structure for being provided with concrete-cored rotary churning pile, by preceding campshed 1, rear campshed, high inclination-angle rotary churning pile 3, prefabricated mixed Solidifying soil stake 4, crown beam 5 and three linking beam compositions.Construction method are as follows: the residue after removing in campshed, then to rear campshed Hole depth, hole location, hole shape, aperture etc. are checked, natural mud are injected in aperture using slush pump and conduit, repeated flushing, Sediment is finally cleared up in device to hole, and injects air toward bottom hole using air compressor machine, the water generated in hole with mud mixing using it Pressure, simultaneously develops sand setting and sediment, whole hole bottom hole sediment thickness will be met the requirements.The steel reinforcement cage of campshed is down toward bottom hole afterwards Afterwards, then lower concrete steel conduit;DN125 concrete steel conduit uses screwed connection, in order to guarantee conduit in casting and compacting of concrete Pipe can be mentioned after the completion, in final section catheter tail one U type hanging ring of reinforcement welding, connect the wirerope in tripping in hole Onto hanging ring.After steel reinforcement cage and conduit tripping in, that is, carrying out second of borehole cleaning, it is desirable that borehole cleaning to bottom hole sediment is not more than 50 millimeters, Borehole cleaning to mud balance, which reaches design requirement, to be stopped.Perfusion Underwater Concrete will be carried out continuously, and must not be interrupted, and guarantee concrete piles quality, directly Slurry is returned to aperture, to guarantee concrete piles quality.After the completion of perfusion, conduit is dismantled, and notices that stake top is protected.It is steady to heel row quality of pile After fixed, high inclination-angle rotary churning pile 3, rotary churning pile 3 are performed from the stake top platform inner side of preceding campshed 1 to the direction of campshed 9 behind centre Segmentation rotary-spraying construction is taken, construction angle is 50-75 degree, and terminal position is minimum position, rotary churning pile at a distance from rear campshed After 3 constructions, before its quality is stablized, precast concrete pile 4 is inserted.After band whirl spraying quality of pile is stablized, preceding campshed 1 It constructs, specific method is identical as rear campshed, and 4 upper end of precast concrete pile links together with preceding 1 steel reinforcement cage of campshed.To preceding After 1 mass of campshed is stablized, the construction of crown beam and linking beam is carried out.

Claims (2)

1. one kind can overcome the Double-row Piles Support system of the local soft soil property of foundation pit, including the rear side at foundation pit locally soft soil property Afterwards campshed (10), it is intermediate after campshed (2) and preceding campshed (1) behind campshed (9), front side, which is characterized in that campshed (10) after rear side It is provided with rear side attachment beam (6) between preceding campshed (1), is provided with centre between campshed behind centre (9) and preceding campshed (1) and connects Connect beam (7), be provided between campshed behind front side (2) and preceding campshed (1) front side attachment beam (8), after rear side campshed (10), in Between after be provided with crown beam (5) between campshed (2) behind campshed (9) and front side, set between campshed (9) after preceding campshed (1) and centre High inclination-angle rotary churning pile (3) are equipped with, inserted with precast concrete beam (4) in high inclination-angle rotary churning pile (3).
2. one kind according to claim 1 can overcome the Double-row Piles Support system of the local soft soil property of foundation pit, feature exists In the angle between high inclination-angle rotary churning pile (3) and intermediate attachment beam (7) is 50-75 degree.
CN201820363950.4U 2018-03-18 2018-03-18 The Double-row Piles Support system of the local soft soil property of foundation pit can be overcome Active CN208251111U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820363950.4U CN208251111U (en) 2018-03-18 2018-03-18 The Double-row Piles Support system of the local soft soil property of foundation pit can be overcome

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820363950.4U CN208251111U (en) 2018-03-18 2018-03-18 The Double-row Piles Support system of the local soft soil property of foundation pit can be overcome

Publications (1)

Publication Number Publication Date
CN208251111U true CN208251111U (en) 2018-12-18

Family

ID=64609419

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820363950.4U Active CN208251111U (en) 2018-03-18 2018-03-18 The Double-row Piles Support system of the local soft soil property of foundation pit can be overcome

Country Status (1)

Country Link
CN (1) CN208251111U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113605398A (en) * 2021-07-14 2021-11-05 广州市设计院集团有限公司 Foundation pit supporting mechanism

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113605398A (en) * 2021-07-14 2021-11-05 广州市设计院集团有限公司 Foundation pit supporting mechanism

Similar Documents

Publication Publication Date Title
CN108533272B (en) Exit construction method for tunnel with extremely small clear distance
CN106968256B (en) Foundation pit assembled steel trestle construction method
CN103696784B (en) Large-diameter long pipe curtain construction method for shallowly-buried large-span under-tunnel-passing architectural structure
CN104533446A (en) Construction method and structure of two-layer preliminary support for preventing geological disaster of large-section weak surrounding rock tunnel
CN105544575B (en) A kind of bottom concrete construction method under water of use steel truss reinforcement
CN109024651B (en) Steel pipe concrete mixed pile foundation and construction method
CN103741657A (en) Construction method of large multifunctional over-water construction platform
CN101696578A (en) Construction method for pouring foundations of main pylon piers of bridge on deep water inclined runway
CN105672337B (en) The construction method of cast-in-place open caisson formwork system
CN206319886U (en) Tunnel lining structure
CN108547641A (en) The bottom stab ilization system and its construction method in rich water soft stratum heavy haul railway tunnel
CN103953355A (en) Method of acceptance construction in slurry shield tunnel
CN105113514B (en) Foundation pit enclosure system with underground continuous wall as vertical cantilever fulcrum and construction method
CN110777802A (en) Deep foundation pit high-low span supporting structure and construction method thereof
CN206467667U (en) Suspended net shotcrete building enclosure between a kind of stake of use expansion type fixation reinforced mesh
CN208251111U (en) The Double-row Piles Support system of the local soft soil property of foundation pit can be overcome
CN103603357B (en) A kind of multi-platform without inner support self waterproofing foundation pit enclosure structure and constructional method thereof
CN101498133B (en) Method and supporting construction for enlarging basement top-down method earth excavation space
CN107355008A (en) A kind of prefabricated attachment structure and method of newly-increased steel core concrete column and existing structure
CN204436407U (en) The structure that the pre-Geological disaster prevention of the double-deck preliminary bracing of a kind of big cross section Support System in Soft Rock Tunnels occurs
CN111350187A (en) Template system suitable for large-diameter manual hole digging annular foundation pile and construction method
CN109779640A (en) A kind of shield launching portal breaking construction method
CN109826224A (en) A kind of sinking well protection wall digging foundation and its construction method for desert region iron tower of power transmission line
CN101492918B (en) Beam column node for base pit engineering of topdown construction method
CN108301419A (en) The Double-row Piles Support system and construction method of the local soft soil property of foundation pit can be overcome

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP02 Change in the address of a patent holder
CP02 Change in the address of a patent holder

Address after: 110136 No. 36 Shenbei Road, Shenyang New District, Shenyang City, Liaoning Province

Patentee after: China Railway 19th Bureau No.3 Engineering Co., Ltd.

Address before: 110136 No. 36 Shenbei Road, Shenbei New District, Liaoyang City, Liaoning Province

Patentee before: China Railway 19th Bureau No.3 Engineering Co., Ltd.