CN208237487U CN201820734531.7U CN201820734531U CN208237487U CN 208237487 U CN208237487 U CN 208237487U CN 201820734531 U CN201820734531 U CN 201820734531U CN 208237487 U CN208237487 U CN 208237487U
Authority
CN
China
Prior art keywords
gas
connect
nitrogen
valve
pressure testing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820734531.7U
Other languages
Chinese (zh)
Inventor
解夫雷
张晓桂
徐来征
谢兆华
何贺
沈亚琴
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fives Stein Metallurgical Technology Shanghai Co Ltd
Original Assignee
Fives Stein Metallurgical Technology Shanghai Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fives Stein Metallurgical Technology Shanghai Co Ltd filed Critical Fives Stein Metallurgical Technology Shanghai Co Ltd
Priority to CN201820734531.7U priority Critical patent/CN208237487U/en
Application granted granted Critical
Publication of CN208237487U publication Critical patent/CN208237487U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Examining Or Testing Airtightness (AREA)

Abstract

Gas safety key with performing leak test includes: PLC control, gas pipeline, gas cutting device, nitrogen system and gas pressure testing element, PLC control is connect with gas cutting device, nitrogen system and gas pressure testing element, the connection of gas cutting device gas pipeline, nitrogen system is connect with the gas pipeline second half section, and gas pressure testing element is connect with gas pipeline.Wherein, gas cutting device includes: the first automatic cut-off valve for gas, the second automatic cut-off valve for gas, coal gas automatic relief stop valve and coal gas conveying bypass line.The utility model is compared with traditional technology, and test gas uses nitrogen in safety-key, substantially increases safety;By the chain dual monitoring of PLC software and hardware, the working condition of pressure instrumentation and automatic valve can be recorded with on-line real time monitoring;1 automatic stop valve is eliminated, power control cabinet is eliminated, is controlled using PLC, is saving cost, reduces failure rate, improves accuracy of leaking hunting.

Description

Gas safety key with performing leak test
Technical field
The utility model relates to steel production and processings, and in particular to the gas safety key with performing leak test.
Background technique
With coal gas in iron and steel domain as the more and more extensive of main fuel, recognize along with for environmental protection and safety With desired gradually height-regulating, the safety requirements of coal gas system is also stepped up.In coal gas system, the equipment of core is exactly Safety-key.Its effect is: realizing when detecting signal fault in process system and quick and precisely cuts off, prevents the hair of accident It is raw.
Traditional safety-key has the following problems by performing leak test, when automatic cut-off valve for gas is opened, inputs gas For coal gas, there are security risks;Time relay control there is response speeds poor, time of measuring length, low precision, maintainability be poor, The problems such as service life is short;Device valve is more, and coal gas automatic relief stop valve and automatic cut-off valve for gas leak simultaneously When, it can not judge, leak detection stability is poor, high failure rate;Gas pressure detecting element because can only feedback switch amount, can not react The case where when micro-leakage, need to test 5 minutes, and the testing time is long;Independent control cabinet of the control cabinet as safety-key, it is at high cost.
To solve the above-mentioned problems, we are made that a series of improvement.
Utility model content
The purpose of the utility model is to provide the gas safety keys with performing leak test, to overcome the prior art to be deposited Disadvantages mentioned above and deficiency.
Gas safety key with performing leak test includes: PLC control, gas pipeline, gas cutting device, nitrogen system System and gas pressure testing element, the PLC control connect with gas cutting device, nitrogen system and gas pressure testing element It connects, the gas cutting device is connect with gas pipeline, and the nitrogen system is connect with the gas pipeline second half section, institute Gas pressure testing element is stated to connect with gas pipeline;
Wherein, the gas cutting device includes: the first automatic cut-off valve for gas, the second automatic cut-off valve for gas, coal gas Automatic relief stop valve and coal gas convey bypass line, and first automatic cut-off valve for gas and gas pipeline front half section connect It connects, second automatic cut-off valve for gas is connect with the gas pipeline second half section, the coal gas conveying bypass line and coal gas Conveyance conduit connection, the coal gas automatic relief stop valve are connect with coal gas conveying bypass line.
Further, the nitrogen system includes: nitrogen gas delivery-line, nitrogen automatic stop valve and nitrogen check-valves, described Nitrogen gas delivery-line is connect with gas pipeline, is connect on the outside of the nitrogen automatic stop valve and nitrogen gas delivery-line, described It is connect on the inside of nitrogen check-valves and nitrogen gas delivery-line.
Further, the gas pressure testing element includes: that the first gas pressure testing element and the second gas pressure are surveyed Element is tried, the first gas pressure testing element is set on rear side of the first automatic cut-off valve for gas, and first gas pressure is surveyed Examination element is connect with gas pipeline, and the second gas pressure testing element is set on rear side of the second automatic cut-off valve for gas, The second gas pressure testing element is connect with gas pipeline.
The utility model has the beneficial effects that
The utility model is compared with traditional technology, and test gas uses nitrogen in safety-key, substantially increases safety;It is logical The chain dual monitoring of PLC software and hardware is crossed, the work of pressure instrumentation and automatic valve can be recorded with on-line real time monitoring Make state;1 automatic stop valve is eliminated, power control cabinet is eliminated, is controlled using PLC, reduced while saving cost Failure rate improves accuracy of leaking hunting, and the test a cycle time only has 2 minutes, shortens the testing time.
Detailed description of the invention:
Fig. 1 is the structure chart of the utility model.
Appended drawing reference:
PLC controls 100, gas pipeline 200, gas cutting device 300, the first automatic cut-off valve for gas 310, second Automatic cut-off valve for gas 320, coal gas automatic relief stop valve 330 and coal gas convey bypass line 340.
Nitrogen system 400, nitrogen gas delivery-line 410, nitrogen automatic stop valve 420 and nitrogen check-valves 430.
Gas pressure testing element 500, the first gas pressure testing element 510 and the second gas pressure testing element 520.
Specific embodiment
Below in conjunction with specific embodiment, progress explanation is made to the utility model.It should be understood that following embodiment is merely to illustrate The utility model is not for restriction the scope of the utility model.
Embodiment 1
Fig. 1 is the structure chart of the utility model.
As shown in Figure 1, the gas safety key with performing leak test includes: that PLC controls 100, gas pipeline 200, coal Gas disconnecting device 300, nitrogen system 400 and gas pressure testing element 500, PLC control 100 and gas cutting device 300, nitrogen Gas system 400 and gas pressure testing element 500 connect, and gas cutting device 300 is connect with gas pipeline 200, nitrogen System 400 is connect with 200 second half section of gas pipeline, and gas pressure testing element 500 is connect with gas pipeline 200.
Wherein, gas cutting device 300 include: the first automatic cut-off valve for gas 310, the second automatic cut-off valve for gas 320, Coal gas automatic relief stop valve 330 and coal gas convey bypass line 340, the first automatic cut-off valve for gas 310 and gas conveying tube The connection of 200 front half section of road, the second automatic cut-off valve for gas 320 are connect with 200 second half section of gas pipeline, and coal gas conveys branch Pipeline 340 is connect with gas pipeline 200, and coal gas automatic relief stop valve 330 is connect with coal gas conveying bypass line 340.
Nitrogen system 400 includes: nitrogen gas delivery-line 410, nitrogen automatic stop valve 420 and nitrogen check-valves 430, nitrogen Conveyance conduit 410 is connect with gas pipeline 200, is connected on the outside of nitrogen automatic stop valve 420 and nitrogen gas delivery-line 410, It is connected on the inside of nitrogen check-valves 430 and nitrogen gas delivery-line 410.
Gas pressure testing element 500 includes: the first gas pressure testing element 510 and the second gas pressure testing element 520, the first gas pressure testing element 510 is set to 310 rear side of the first automatic cut-off valve for gas, the first gas pressure testing element 510 connect with gas pipeline 200, after the second gas pressure testing element 520 is set to the second automatic cut-off valve for gas 320 Side, the second gas pressure testing element 520 are connect with gas pipeline 200.
Utility model works principle is integrated into all signal of interest by PLC control 100 using PLC control 100 During hardware is chain, using 100 all signal of interest of real time monitoring of PLC control, it can guarantee to pacify when any signal of interest occurs The quick cutting of full key board, realizes the duplicate protection of software and hardware.The hand before nitrogen check-valves 430 in nitrogen system 400 Valve changes nitrogen automatic stop valve 420 into, and low tension switch alarm has been changed to gas pressure detecting element 500, has eliminated a coal Gas automatic stop valve.Specific testing process, first the first automatic cut-off valve for gas 310, the second automatic cut-off valve for gas 320 and nitrogen Gas automatic stop valve 420 keeps off-position, and coal gas automatic relief stop valve 330 is opened, 510 numerical value of the first gas pressure testing element It is 0.
First gas pressure testing element 510 is closed, and gas pipeline 200 is sent before the first automatic cut-off valve for gas 310 Gas keeps pressure, and 500 numerical value of gas pressure testing element is 0, illustrates that the first automatic cut-off valve for gas 310 is not revealed;Nitrogen System 400 is opened, and is passed through nitrogen, real-time monitoring simultaneously makes pressure reach a numerical value and records.Close nitrogen system 400, record The pressure value of second gas pressure testing element 520 monitors the first gas pressure test member at the appointed time as requested The numerical value of part 510 and the second gas pressure testing element 520, meets performing leak test requirement compared with initial value, illustrates Two automatic cut-off valve for gas 320 and 330 performing leak test of coal gas automatic relief stop valve pass through.
The utility model is compared with traditional technology, and test gas uses nitrogen in safety-key, substantially increases safety;It is logical The chain dual monitoring of PLC software and hardware is crossed, the work of pressure instrumentation and automatic valve can be recorded with on-line real time monitoring Make state;1 automatic stop valve is eliminated, power control cabinet is eliminated, is controlled using PLC, reduced while saving cost Failure rate improves accuracy of leaking hunting, and the test a cycle time only has 2 minutes, shortens the testing time.
Specific embodiment of the present utility model is illustrated above, but the utility model is not limited thereto, only The objective of the utility model is not departed from, the utility model there can also be various change.

Claims (3)

1. the gas safety key with performing leak test characterized by comprising PLC controls (100), gas pipeline (200), gas cutting device (300), nitrogen system (400) and gas pressure testing element (500), the PLC control (100) It is connect with gas cutting device (300), nitrogen system (400) and gas pressure testing element (500), the gas cutting device (300) it being connect with gas pipeline (200), the nitrogen system (400) connect with gas pipeline (200) second half section, The gas pressure testing element (500) connect with gas pipeline (200);
Wherein, the gas cutting device (300) includes: the first automatic cut-off valve for gas (310), the second automatic cut-off valve for gas (320), coal gas automatic relief stop valve (330) and coal gas conveying bypass line (340), first automatic cut-off valve for gas (310) it is connect with gas pipeline (200) front half section, second automatic cut-off valve for gas (320) and gas pipeline (200) second half section connects, and coal gas conveying bypass line (340) connect with gas pipeline (200), and the coal gas is automatic Release stop valve (330) is connect with coal gas conveying bypass line (340).
2. the gas safety key according to claim 1 with performing leak test, it is characterised in that: the nitrogen system It (400) include: nitrogen gas delivery-line (410), nitrogen automatic stop valve (420) and nitrogen check-valves (430), the nitrogen conveying Pipeline (410) is connect with gas pipeline (200), and the nitrogen automatic stop valve (420) and nitrogen gas delivery-line (410) are outside It is connect on the inside of side connection, the nitrogen check-valves (430) and nitrogen gas delivery-line (410).
3. the gas safety key according to claim 1 with performing leak test, it is characterised in that: the gas pressure test Element (500) includes: the first gas pressure testing element (510) and the second gas pressure testing element (520), first coal Atmospheric pressure testing element (510) is set on rear side of the first automatic cut-off valve for gas (310), the first gas pressure testing element (510) it is connect with gas pipeline (200), the second gas pressure testing element (520) is set to the second coal gas and cuts automatically On rear side of disconnected valve (320), the second gas pressure testing element (520) connect with gas pipeline (200).
CN201820734531.7U 2018-05-17 2018-05-17 Gas safety key with performing leak test Active CN208237487U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820734531.7U CN208237487U (en) 2018-05-17 2018-05-17 Gas safety key with performing leak test

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820734531.7U CN208237487U (en) 2018-05-17 2018-05-17 Gas safety key with performing leak test

Publications (1)

Publication Number Publication Date
CN208237487U true CN208237487U (en) 2018-12-14

Family

ID=64579804

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820734531.7U Active CN208237487U (en) 2018-05-17 2018-05-17 Gas safety key with performing leak test

Country Status (1)

Country Link
CN (1) CN208237487U (en)

Similar Documents

Publication Publication Date Title
CN101324485A (en) Test device and method for detecting security of fuel battery passenger car hydrogen feed system
CN109883724B (en) Performance detection device and detection method for EBS (electronic brake system) double-channel bridge module
CN104949831A (en) Online checking device and methods for pilot valve and main valve of pilot operated safety valve
CN211780238U (en) Hydrogen-containing natural gas pipeline safety guarantee system based on hydrogen accumulation control
CN208237487U (en) Gas safety key with performing leak test
CN207865034U (en) A kind of gas pressure regulating system
CN111322521B (en) Hydrogen accumulation control-based hydrogen-containing natural gas pipeline safety guarantee system and method
CN204664860U (en) A kind of concentrated nitrogen gas supply system
CN207865038U (en) A kind of natural gas decompression transport system
CN102620145A (en) Automatic low-pressure protection system for coke oven gas pipeline
CN201944547U (en) System for compressed natural gas supply station
CN202220962U (en) Lubricating system with pipeline leakage detecting function
CN204731018U (en) Pilot valve and main valve on-line testing device in pilot operated safety valve
CN205191220U (en) Instrument air supply system
CN210514303U (en) Intelligent double-insurance carrier-gas-free online monitoring device for dissolved gas in oil
CN109856187B (en) Online real-time detection method for hydrocarbon dew point of gas pipeline
CN209927761U (en) Online real-time detection device for hydrocarbon dew point of gas pipeline
CN209841751U (en) Online real-time detection device for water dew point of gas pipeline
CN202583849U (en) Coke oven gas pipeline low-pressure automatic protection system
CN207485660U (en) For the decompression buffer unit of large reciprocating compressor enclosed performance test system
CN202469496U (en) Beam tube leak detector
CN217107299U (en) Brake control device
CN207239694U (en) The warning device that a kind of automatic detection rotary work-table angle deflects
CN204922521U (en) Gas valve automatic checkout device that leaks gas
CN213516326U (en) Valve off-line pressure test tool