- CN208236001U CN208236001U CN201820635874.8U CN201820635874U CN208236001U CN 208236001 U CN208236001 U CN 208236001U CN 201820635874 U CN201820635874 U CN 201820635874U CN 208236001 U CN208236001 U CN 208236001U
- Authority
- CN
- China
- Prior art keywords
- support
- top plate
- plate
- hoistable platform
- supporting beam
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Working Measures On Existing Buildindgs (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
The utility model discloses the hoistable platforms dismantled for foundation pit supporting beam comprising lifting device, support device and jacking apparatus;The lifting device includes that bottom plate, top plate and the hydraulic lifting frame being supported between top plate and bottom plate, hydraulic lifting frame can push top plate to be raised and lowered;Support device includes backing plate and at least two support rods, lifting device is arranged on the backing plate of support device, support rod is arranged around lifting device, the bottom end of support rod is removably mounted on backing plate, after the top plate of lifting device is jacked up by hydraulic lifting frame to setting position, the top of support rod is removably mounted on top plate;Jacking apparatus can elongate or shorten, and jacking apparatus is mounted on the upside of top plate.Using the hoistable platform, the efficiency of construction can be effectively improved.
Description
Technical field
Auxiliary device when the utility model relates to be dismantled to the supporting beam being mounted in foundation pit, and in particular to be used for
The hoistable platform of foundation pit supporting beam disassembly.
Background technique
The chief component of support system one of of the supporting beam as foundation pit, support in the dismounting second layer and more on the lower
Liang Shi, it is general using cutting or on the spot decomposing supporting beam by building block, then again by building block using artificial auxiliary
Mechanical mode is helped to transport foundation pit.For the supporting beam of top layer, since operating space is larger, generally for the less base of width
Hole is usually arranged crane at the edge of foundation pit, is segmented supporting beam using crane and hangs foundation pit, and base biggish for width
Hole, since the limitation of length of boom and the support strength of margin of foundation pit are limited, crane can only be to supporting beam close to margin of foundation pit
Part hung, and supporting beam can not be hung apart from the farther away part of margin of foundation pit, for this of supporting beam
Part-structure is removed by the way of carrying out supporting beam to be decomposed into components at present, and this method for dismounting not only needs
Consuming is a large amount of artificial, and operating efficiency is lower, affects the progress of whole building construction.
Utility model content
The purpose of the utility model is to overcome drawbacks described above, provide a kind of lifting that supporting beam dismounting speed can be improved
Platform, to improve the efficiency of construction, specific technical solution is as follows:
For the hoistable platform of foundation pit supporting beam disassembly, the supporting beam is arranged horizontally on the column in foundation pit, the liter
Drop machine is characterised by comprising lifting device, support device and jacking apparatus;The lifting device includes bottom plate, top plate and branch
The hydraulic lifting frame between top plate and bottom plate is supportted, hydraulic lifting frame can push top when elongating or shortening along the vertical direction
Plate is raised and lowered;The support device includes backing plate and at least two support rods, lifting device are arranged in the pad of support device
On plate, at least two support rods arrange that the bottom end of support rod is removably mounted on backing plate around lifting device, work as liter
The top plate of falling unit is jacked up by hydraulic lifting frame to after setting position, and the top of support rod is removably mounted on top plate;Top
Rising device can elongate or shorten, and jacking apparatus is mounted on the upside of top plate.Preferably, the jacking apparatus is jack.
Currently, hydraulic lifting frame comparative maturity, model is relatively abundanter, it can satisfy the needs of the application, according to this
The different loads of hoistable platform in application can select the hydraulic lifting frame without model, naturally it is also possible to be customized or from
System.
When dismantling the top layer supporting beam in the supporting beam or Multi-layer supporting beam of single layer setting using the utility model, press first
Supporting beam is divided into several disassembly sections according to the arrangement of column, when needing to remove supporting beam, first by the hoistable platform
It is arranged in the lower section for needing the disassembly section dismantled, then jacking apparatus is extended, jacking apparatus is made to be resisted against disassembly from bottom to top
The downside of section, then separates at the both ends for dismantling section with the other parts of supporting beam, after completing separation, starts jacking apparatus, makes
Jacking apparatus extends upwards, and disassembly section is pushed away original position, then installs temporary track in the lower section of disassembly section, completes interim
After the installation of track, be again started up jacking apparatus, shorten jacking apparatus, will disassembly section transfer on transfer device, using turn
The disassembly section removed is transported to storage area by shipping unit.After the utility model, when dismantling supporting beam, it is no longer necessary to will prop up
Support beam is decomposed into components, but supporting beam is split as several disassembly sections, and disassembly section is disposably transported as a whole
Foundation pit out, compare the prior art, can effectively save the take-down time and shipping time of a large amount of supporting beam, can be effectively
Improve the construction efficiency of building.
It further, further include counter weight device, which includes idler wheel, connecting rope and counterweight, and the idler wheel is rotationally
It is mounted on top plate, one end of connecting rope is fixed on top plate, and the other end of connecting rope after idler wheel up around extending downwardly simultaneously
Connect the counterweight.The decrease speed that can accelerate lifting device using counter weight device improves the removal efficiency of hoistable platform.When
When needing to remove hoistable platform, support rod is removed first, then under by hydraulic lifting frame, rely on hydraulic lifting frame itself merely
Weight and, the retraction speed of hydraulic lifting frame is slower, and after counter weight device be arranged, the retraction for increasing hydraulic lifting frame is fast
Degree, can accelerate the service speed to hoistable platform.
Further, the lifting device further includes bearing plate, which is laid on the upper surface of top plate, the jacking dress
It sets and is mounted on bearing plate.Undertake biggish load since jacking apparatus can generate at work, these load long terms in
When on the top plate of hydraulic lifting frame, top plate can be made to generate a degree of deformation, bearing plate is set, load can be transmitted to hold first
Weight plate, since the deformation that load acts on and generates can also primarily occur on bearing plate, when there is serious deformation in bearing plate,
Bearing plate can be replaced, so that the maintenance to the top plate of hydraulic lifting frame is reduced, to extend the use longevity of entire hoistable platform
Life.
Preferably, for convenience of the transport of support rod and installation, the support rod divides bar removably by the support of at least two sections
It is formed by connecting.After support rod is divided into more piece, the weight of single component can be mitigated, be easily installed the operation of personnel.
Further, bridging is provided between two adjacent support rods.After bridging is set, each support rod can be made
One entirety mutually relied on is formed by state independent, is passed through by the load that jacking apparatus is transmitted on single support rod
Bridging is transmitted to other support rods, the load for passing over all support rod shareds by jacking apparatus.
Detailed description of the invention:
Fig. 1 is the structure diagram of the first embodiment of the utility model.
Fig. 2 is a usage state diagram of the utility model.
Fig. 3 is an arrangement schematic diagram of jacking apparatus.
Fig. 4 is another arrangement schematic diagram of jacking apparatus.
Specific embodiment:
Embodiment 1:
Refering to fig. 1 and Fig. 2, the hoistable platform 100 for the disassembly of foundation pit supporting beam, supporting beam 200 are arranged horizontally in foundation pit
On interior column, which includes lifting device 10, support device 20 and jacking apparatus 30.Lifting device 10 includes bottom plate
11, top plate 17 and the hydraulic lifting frame 12 being supported between top plate 17 and bottom plate 11, the hydraulic lifting frame 12 have hydraulic jack
Top 18, under the action of hydraulic jack 18, hydraulic lifting frame 12 can be raised and lowered, and hydraulic lifting frame is along vertical side
To when elongating or shortening, top plate 17 can be pushed to be raised and lowered.Bottom plate 11 and top plate 17 are in rectangle.
Support device 20 includes backing plate 21 and support rod 22, and lifting device 10 is arranged on the backing plate 21 of support device 20,
The bottom end of support rod 22 is removably mounted on the upper surface of backing plate 21, when the top plate 17 of lifting device 10 is by hydraulic lifting frame top
After playing setting position, the top of support rod 22 is removably mounted on top plate 17.Jacking apparatus can elongate or shorten, top
Rise the upside that device is mounted on top plate 17.Specifically in the present embodiment, jacking apparatus uses jack 30.
For convenience of transport, in the present embodiment, lifting device 10 further includes bearing plate 13, which is laid on top plate
17 upper surface, supporting beam 200 of the hoistable platform 100 for disassembly in the present embodiment have two girders disposed in parallel
201, it is provided with the connection support 202 being evenly arranged, between two girders 201 for preferably to the portion to be dismantled in supporting beam
Divide and form stable support, there are four the settings of jack 30, and four jack 30 are arranged and are all mounted in two column, two row and hold
The upper surface of weight plate 13, every two jack 30 correspond to a connection support 202.
In the present embodiment, backing plate 21 is in rectangle, and opposite with about 17 top plate, and support rod 22 is provided with four, four branch
Strut is arranged on four angles of backing plate 21.For convenience of installing and transporting, support rod is divided 221,222 groups of bar by the support of two sections
At the support of, two sections divide bar 221,222 through flanged joint together.The top and bottom end of support rod 22 are all made of flange and are separately connected
In top plate 17 on backing plate 21.It is understood that in other embodiments, support rod 22 can also divide bar by three sections or the support of four sections
It is formed by connecting.It is appreciated that different according to required support strength, the quantity of support rod can also only be set as two, or
It is set as five, the six roots of sensation and more roots.
To guarantee that the support strength of entire hoistable platform is set between two adjacent support rods 22 in the present embodiment
It is equipped with bridging 23.
To enable hoistable platform successfully to decline, in the present embodiment, it is also provided with counter weight device, the counter weight device packet
Idler wheel 14, connecting rope 15 and counterweight 16 are included, straight-bar 19 is installed on bearing plate 13, straight-bar 19 is vertically arranged in bearing plate 13
Upper surface, idler wheel 14 is rotatably mounted at the top of straight-bar 19, and one end of connecting rope 15 is fixed on bearing plate 13, connecting rope
The other end up around being extended downwardly after idler wheel 14 and connect the counterweight 16.
It is appreciated that bearing plate 13 can be cancelled, after cancelling bearing plate 13, straight-bar 19 can be directly connected to connecting rope
On top plate 17.
In hoistable platform 100 in use, first by hoistable platform 100 under the disassembly section that supporting beam 200 needs to dismantle
Side installs, and when installing hoistable platform, backing plate 21 is laid in selected location first, support device 20 is then arranged in pad
On plate 21, hydraulic lifting frame 12 is increased to setting height, then support rod 22 and bridging 23 are installed.Complete above-mentioned work
After work, bearing plate 13 is laid on top plate, counter weight device is installed, is finally installed in place jack, hoistable platform installation
It completes.After hoistable platform is installed, start jack, the piston rod 31 of jack is resisted against to the lower flank of connection support 202
On edge 203, then the other parts for dismantling section and supporting beam are disconnected, is completed after disconnecting work, is again started up jack, makes four
The piston rod 31 of a jack synchronizes upward jacking, moves up the disassembly section of supporting beam, after reaching setting position, stops tearing open
The movement of section is unloaded, hold mode after the installation for completing conveying track, then opens then in the lower section installation and transportation track of disassembly section
Dynamic jack, makes the piston rod of jack bounce back, the disassembly section of supporting beam is placed on conveying track, then will dismantle section edge
Conveying track is dragged away.Hoistable platform next disassembly section is moved to again to work.
In the present embodiment, two jack can also be only arranged, ask in other embodiments by being provided with four jack
Refering to Fig. 3, two jack 42 in Fig. 3 are supported on the upside of bearing plate 41, extension of two jack 42 along connection support 202
Direction is arranged, and two jack 42 in Fig. 3 are for being resisted against same root connection support.
Referring to Fig. 4, two jack 44 are arranged on bearing plate 43 in the Fig. 4, and two jack 44 are along support
The extending direction of beam extends, and in hoistable platform work, two jack 44 are respectively resisted against in a connection support.
Claims (6)
1. the supporting beam is arranged horizontally on the column in foundation pit, the lifting for the hoistable platform of foundation pit supporting beam disassembly
Machine is characterised by comprising lifting device, support device and jacking apparatus;The lifting device includes bottom plate, top plate and support
Hydraulic lifting frame between top plate and bottom plate, hydraulic lifting frame can push top plate when elongating or shortening along the vertical direction
It is raised and lowered;The support device includes backing plate and at least two support rods, lifting device are arranged in the backing plate of support device
On, at least two support rods arrange that the bottom end of support rod is removably mounted on backing plate around lifting device, work as lifting
The top plate of device is jacked up by hydraulic lifting frame to after setting position, and the top of support rod is removably mounted on top plate;Jacking
Device is mounted on the upside of top plate.
2. hoistable platform according to claim 1, which is characterized in that further include counter weight device, which includes rolling
Wheel, connecting rope and counterweight, the idler wheel are rotatably mounted on top plate, and one end of connecting rope is fixed on top plate, connecting rope
The other end after idler wheel up around extending downwardly and connect the counterweight.
3. hoistable platform according to claim 2, which is characterized in that the lifting device further includes bearing plate, the load-bearing
Plate is laid on the upper surface of top plate, and the jacking apparatus is mounted on bearing plate.
4. hoistable platform according to claim 1, which is characterized in that the jacking apparatus is jack.
5. hoistable platform according to claim 1, which is characterized in that the support rod divides bar removable by the support of at least two sections
It is formed by connecting with unloading.
6. hoistable platform according to claim 1, which is characterized in that be provided with scissors between two adjacent support rods
Support.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820635874.8U CN208236001U (en) | 2018-04-28 | 2018-04-28 | Hoistable platform for the disassembly of foundation pit supporting beam |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820635874.8U CN208236001U (en) | 2018-04-28 | 2018-04-28 | Hoistable platform for the disassembly of foundation pit supporting beam |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208236001U true CN208236001U (en) | 2018-12-14 |
Family
ID=64581755
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820635874.8U Active CN208236001U (en) | 2018-04-28 | 2018-04-28 | Hoistable platform for the disassembly of foundation pit supporting beam |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208236001U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110185248A (en) * | 2019-05-31 | 2019-08-30 | 王玉瑶 | One kind is for article support device hanging in building |
CN111677525A (en) * | 2020-05-27 | 2020-09-18 | 浙江新中源建设有限公司 | Inner supporting beam and dismantling method thereof |
-
2018
- 2018-04-28 CN CN201820635874.8U patent/CN208236001U/en active Active
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110185248A (en) * | 2019-05-31 | 2019-08-30 | 王玉瑶 | One kind is for article support device hanging in building |
CN111677525A (en) * | 2020-05-27 | 2020-09-18 | 浙江新中源建设有限公司 | Inner supporting beam and dismantling method thereof |
CN111677525B (en) * | 2020-05-27 | 2022-01-18 | 浙江新中源建设有限公司 | Inner supporting beam and dismantling method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN208236001U (en) | Hoistable platform for the disassembly of foundation pit supporting beam | |
CN101210418A (en) | Non-floor-bracket construction method for suspension bridge tower frame cross beam | |
CN111254840A (en) | Integral beam falling structure and beam falling method for steel box girder bridge | |
CN108411922A (en) | The method for dismounting of bracing members | |
CN101693509A (en) | Large tonnage reactor truck loading jacking technique | |
CN202369333U (en) | Wall mounting elevator | |
JP4796411B2 (en) | Bridge removal method | |
CN210827131U (en) | Pier device for adjusting front-rear height difference of lower guide beam of bridge girder erection machine | |
CN102926330B (en) | Installation method of hanging basket suitable for bridge construction | |
CN101660660B (en) | Novel installing method of gas cabinet | |
CN111058609A (en) | Construction and protection integrated portable operation platform and method | |
CN106115546B (en) | A kind of cargo elevator structure and freight moving equipment | |
JP2016142097A (en) | Portable hoist unit and horizontal member dismantling method | |
CN106671262B (en) | Rail mounted concrete distributing device rectangle and its distributing method | |
CN202429882U (en) | Movable lifting frame | |
CN112647976B (en) | Lining trolley for dovetail type large-section tunnel and construction method thereof | |
CN212866926U (en) | Movable supporting beam dismounting device | |
CN110371852B (en) | Sintering machine head star wheel and bin installation method | |
CN202689494U (en) | Elevator shaft template support | |
CN101709344B (en) | Method for hoisting terrace for furnace top raw gas pipeline | |
CN206692229U (en) | A kind of gate-type lifting device for thermal insulation coatings construction work high above the ground | |
CN219100775U (en) | Lifting type unloading platform | |
CN205531262U (en) | Steel construction construction platform can rise automatically | |
CN204299144U (en) | Elevator internal mold operating platform | |
CN213199698U (en) | Exempt from to hoist convenient dismantlement and treat support of repairing vehicle car hopper |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |