CN208235499U - A kind of pile crown structure convenient for Rapid Implementation static test - Google Patents
A kind of pile crown structure convenient for Rapid Implementation static test Download PDFInfo
- Publication number
- CN208235499U CN208235499U CN201820400438.2U CN201820400438U CN208235499U CN 208235499 U CN208235499 U CN 208235499U CN 201820400438 U CN201820400438 U CN 201820400438U CN 208235499 U CN208235499 U CN 208235499U
- Authority
- CN
- China
- Prior art keywords
- lattice column
- short lattice
- pile crown
- static test
- steel plate
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
- 230000003068 static effect Effects 0.000 title claims abstract description 17
- 238000012360 testing method Methods 0.000 title claims abstract description 16
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 39
- 239000010959 steel Substances 0.000 claims abstract description 39
- 230000002787 reinforcement Effects 0.000 claims abstract description 18
- 238000011065 in-situ storage Methods 0.000 claims description 8
- XEEYBQQBJWHFJM-UHFFFAOYSA-N Iron Chemical compound [Fe] XEEYBQQBJWHFJM-UHFFFAOYSA-N 0.000 claims description 6
- 238000013461 design Methods 0.000 claims description 4
- 229910052742 iron Inorganic materials 0.000 claims description 3
- 230000004941 influx Effects 0.000 claims description 2
- 230000003014 reinforcing effect Effects 0.000 claims description 2
- 239000002689 soil Substances 0.000 claims 1
- 238000010276 construction Methods 0.000 abstract description 8
- 238000000034 method Methods 0.000 abstract description 6
- 238000005266 casting Methods 0.000 description 1
- 230000000694 effects Effects 0.000 description 1
- 210000003205 muscle Anatomy 0.000 description 1
- 230000008092 positive effect Effects 0.000 description 1
- 238000012545 processing Methods 0.000 description 1
- 238000003466 welding Methods 0.000 description 1
Landscapes
- Piles And Underground Anchors (AREA)
Abstract
The utility model discloses a kind of pile crown structures convenient for Rapid Implementation static test, including the short lattice column being inserted at the top of steel reinforcement cage, multiple spaced apart connecting rods are equipped between the short lattice column and the steel reinforcement cage, the top of the short lattice column is protruded on the steel reinforcement cage, is connected with Horizontal load-bearing steel plate at the top of the short lattice column;The filling concrete height of pile crown is higher by the high 0.5~1m of top mark of the short lattice column.The structure that the utility model welds load-bearing steel plate by using short lattice column pre-buried in the top of steel reinforcement cage and on short lattice column replaces traditional reinforced mesh, it eliminates and cast-in-place builds concrete construction process, to save the strong time such as pile crown of static test, the construction speed at scene is accelerated.
Description
Technical field
The utility model relates to a kind of pile crown structure, especially a kind of pile crown structure convenient for Rapid Implementation static test.
Background technique
Static test is widely used in railway traffic engineering vehicle as one of the important method for determining bearing capacity of borehole bored concrete pile
Stand or the deep-foundation pit engineering of house construction engineering in, the general preloading of static test is larger, needs to carry out the pile crown of cast-in-situ bored pile
Processing increases cast-in-place concrete after reinforced mesh, and the strong time such as scene is longer, seriously affects the construction speed at scene, therefore compel
It is essential and wants a kind of pile crown structure convenient for Rapid Implementation static test.
Summary of the invention
The utility model is to solve technical problem present in well-known technique and provide a kind of convenient for the examination of Rapid Implementation static load
The pile crown structure tested.
The utility model is adopted the technical scheme that solve technical problem present in well-known technique: one kind is convenient for fast
Speed implements the pile crown structure of static test, including the short lattice column being inserted at the top of steel reinforcement cage, in the short lattice column and institute
State between steel reinforcement cage be equipped with multiple spaced apart connecting rods, the short lattice column top protrusion the steel reinforcement cage it
On, Horizontal load-bearing steel plate is connected at the top of the short lattice column;The filling concrete height of pile crown is higher by the short lattice
High 0.5~the 1m of the top mark of column.
The top mark height of the short lattice column is higher by 20~30cm than the design stake top absolute altitude of cast-in-situ bored pile.
The short lattice column be made of steel plate, the steel plate with a thickness of 16~25mm.
The connecting rod is made of any one in reinforcing bar, steel plate or fashioned iron.
The Horizontal load-bearing steel plate uses square structure, and side length is more than or equal to the diameter of cast-in-situ bored pile, with a thickness of 2~
4cm。
The utility model has the advantages and positive effects of: by using short lattice column pre-buried in the top of steel reinforcement cage
And weld the structure of load-bearing steel plate on short lattice column and replace traditional reinforced mesh, it eliminates and cast-in-place builds concrete construction
Sequence accelerates the construction speed at scene to save the strong time such as pile crown of static test.
Detailed description of the invention
Fig. 1 is the sectional side elevation of the utility model;
Fig. 2 is the top view of Fig. 1 (removing Horizontal load-bearing steel plate).
In figure: 1, steel reinforcement cage;2, short lattice column;3, Horizontal load-bearing steel plate;4, connecting rod;5, the concrete of pile crown.
Specific embodiment
For the invention, features and effects that can further appreciate that the utility model, the following examples are hereby given, and cooperates
Detailed description are as follows for attached drawing:
Fig. 1 and Fig. 2, a kind of pile crown structure convenient for Rapid Implementation static test are please referred to, including is inserted into the top of steel reinforcement cage 1
Short lattice column 2 in portion is equipped with multiple spaced apart connecting rods 4 between the short lattice column 2 and the steel reinforcement cage 1,
The top of the short lattice column 2 is protruded on the steel reinforcement cage 1, is connected with Horizontal load-bearing at the top of the short lattice column 2
Steel plate 3;5 influx height of concrete of pile crown is higher by the high 0.5~1m of top mark of the short lattice column 2.
In the present embodiment, the top mark height of the short lattice column 2 be higher by 20 than the design stake top absolute altitude of cast-in-situ bored pile~
30cm.The short lattice column 2 be made of steel plate, the steel plate with a thickness of 16~25mm.The connecting rod 4 is by steel
Made of any one in muscle, steel plate or fashioned iron.The Horizontal load-bearing steel plate 3 uses square structure, and side length is more than or equal to
The diameter of cast-in-situ bored pile, with a thickness of 2~4cm.
The construction procedure of the utility model are as follows:
1) during construction drill filling pile cage of reinforcement, short lattice column and steel reinforcement cage are connected with prefabricated connecting rod
It connects securely;
2) it transfers in steel reinforcement cage to the hole being drilled, and casting concrete;
3) concrete of hole pouring pile to be drilled reaches design strength, cuts the concrete dross of cast-in-situ bored pile stake top, makes
Expose at the top of short lattice column;
4) by Horizontal load-bearing steel plate and short lattice column firm welding.
Although being described above in conjunction with preferred embodiment of the attached drawing to the utility model, the utility model is not
It is confined to above-mentioned specific embodiment, the above mentioned embodiment is only schematical, is not restrictive, ability
The those of ordinary skill in domain is not departing from the utility model aims and claimed under the enlightenment of the utility model
In the case where range, many forms can also be made, these are belonged within the protection scope of the utility model.
Claims (5)
1. a kind of pile crown structure convenient for Rapid Implementation static test, which is characterized in that in being inserted at the top of steel reinforcement cage
Short lattice column is equipped with multiple spaced apart connecting rods, the short lattice between the short lattice column and the steel reinforcement cage
The top of column is protruded on the steel reinforcement cage, is connected with Horizontal load-bearing steel plate at the top of the short lattice column;Pile crown mixes
Solidifying soil influx height is higher by the high 0.5~1m of top mark of the short lattice column.
2. the pile crown structure according to claim 1 convenient for Rapid Implementation static test, which is characterized in that the short lattice
The top mark height of column is higher by 20~30cm than the design stake top absolute altitude of cast-in-situ bored pile.
3. the pile crown structure according to claim 1 convenient for Rapid Implementation static test, which is characterized in that the short lattice
Column be made of steel plate, the steel plate with a thickness of 16~25mm.
4. the pile crown structure according to claim 1 convenient for Rapid Implementation static test, which is characterized in that the connecting rod
Part is made of any one in reinforcing bar, steel plate or fashioned iron.
5. the pile crown structure according to claim 1 convenient for Rapid Implementation static test, which is characterized in that the level is held
Weight steel plate uses square structure, and side length is more than or equal to the diameter of cast-in-situ bored pile, with a thickness of 2~4cm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820400438.2U CN208235499U (en) | 2018-03-22 | 2018-03-22 | A kind of pile crown structure convenient for Rapid Implementation static test |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820400438.2U CN208235499U (en) | 2018-03-22 | 2018-03-22 | A kind of pile crown structure convenient for Rapid Implementation static test |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208235499U true CN208235499U (en) | 2018-12-14 |
Family
ID=64589251
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820400438.2U Expired - Fee Related CN208235499U (en) | 2018-03-22 | 2018-03-22 | A kind of pile crown structure convenient for Rapid Implementation static test |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208235499U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112323877A (en) * | 2020-11-06 | 2021-02-05 | 江西省地质工程(集团)公司 | One-time pouring construction method for static pressure test pile head of cast-in-situ bored pile |
-
2018
- 2018-03-22 CN CN201820400438.2U patent/CN208235499U/en not_active Expired - Fee Related
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112323877A (en) * | 2020-11-06 | 2021-02-05 | 江西省地质工程(集团)公司 | One-time pouring construction method for static pressure test pile head of cast-in-situ bored pile |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109024651B (en) | Steel pipe concrete mixed pile foundation and construction method | |
CN106759442A (en) | A kind of single-pile elevated bearing-platform and anchor cable tower-crane foundation structure and its construction method | |
CN101240550A (en) | Construction method for lattice type steel column tower crane pedestal | |
CN206467667U (en) | Suspended net shotcrete building enclosure between a kind of stake of use expansion type fixation reinforced mesh | |
EP2698476B1 (en) | Method for the construction of an offshore structure and foundation for an offshore structure | |
CN102864781A (en) | Foundation pit supporting method utilizing inclined piles | |
CN210713897U (en) | Pile foundation hole opening protection device | |
CN106759281A (en) | A kind of anchoring for preventing cast-in-place concrete pile rising of steel cage is pitched | |
CN110387879A (en) | A kind of concrete filling pile construction method of hydraulic vibration hammer hidden pipe | |
CN101942830B (en) | Construction method of combined concrete soil pile with core pile | |
CN208235499U (en) | A kind of pile crown structure convenient for Rapid Implementation static test | |
JP6413469B2 (en) | Pile foundation and pile foundation construction method | |
CN113737776B (en) | Ultra-long steel pipe pile under condition of marine-facies deep mucky soil and construction method thereof | |
CN208088311U (en) | Back-pressure de-bowed type pile slab supporting structure after stake | |
CN201144425Y (en) | Mini pile tower foundation | |
CN211735555U (en) | Long spiral bored concrete pile overlength steel reinforcement cage back insertion construction verticality control assembly | |
CN103741690A (en) | Soil plug compensating pipe pile pulling out method and soil plug compensating pipe pile pulling device using same | |
CN109339044A (en) | A kind of concrete pipe pile construction equipment | |
Bhardwaj et al. | Pullout capacity of model micropiles under oblique loads | |
CN108330986A (en) | Back-pressure de-bowed type pile slab supporting structure and construction method after stake | |
CN105040828B (en) | A kind of round steel pipe binding type steel concrete column and steel beam joint structure | |
CN204825924U (en) | Square steel tube concrete waist rail | |
Zhussupbekov et al. | The Results of Dynamic (Pile Driving Analysis) and Traditional Static Piling Tests in Capital of Kazakhstan | |
CN106284331A (en) | Large-diameter and rock-socketed filling piles improves the method for vertical bearing capacity | |
CN207405615U (en) | A kind of supporting construction of canal formula cutting cement soil continuous wall combination work shape prefabricated pile |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20181214 |
|
CF01 | Termination of patent right due to non-payment of annual fee |