CN208235499U CN201820400438.2U CN201820400438U CN208235499U CN 208235499 U CN208235499 U CN 208235499U CN 201820400438 U CN201820400438 U CN 201820400438U CN 208235499 U CN208235499 U CN 208235499U
Authority
CN
China
Prior art keywords
lattice column
short lattice
pile crown
static test
steel plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820400438.2U
Other languages
Chinese (zh)
Inventor
柴艳飞
刘智勇
徐利
任富芝
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Sixth Engineering Division Co Ltd
Original Assignee
China Construction Sixth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Sixth Engineering Division Co Ltd filed Critical China Construction Sixth Engineering Division Co Ltd
Priority to CN201820400438.2U priority Critical patent/CN208235499U/en
Application granted granted Critical
Publication of CN208235499U publication Critical patent/CN208235499U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Piles And Underground Anchors (AREA)

Abstract

The utility model discloses a kind of pile crown structures convenient for Rapid Implementation static test, including the short lattice column being inserted at the top of steel reinforcement cage, multiple spaced apart connecting rods are equipped between the short lattice column and the steel reinforcement cage, the top of the short lattice column is protruded on the steel reinforcement cage, is connected with Horizontal load-bearing steel plate at the top of the short lattice column;The filling concrete height of pile crown is higher by the high 0.5~1m of top mark of the short lattice column.The structure that the utility model welds load-bearing steel plate by using short lattice column pre-buried in the top of steel reinforcement cage and on short lattice column replaces traditional reinforced mesh, it eliminates and cast-in-place builds concrete construction process, to save the strong time such as pile crown of static test, the construction speed at scene is accelerated.

Description

A kind of pile crown structure convenient for Rapid Implementation static test
Technical field
The utility model relates to a kind of pile crown structure, especially a kind of pile crown structure convenient for Rapid Implementation static test.
Background technique
Static test is widely used in railway traffic engineering vehicle as one of the important method for determining bearing capacity of borehole bored concrete pile Stand or the deep-foundation pit engineering of house construction engineering in, the general preloading of static test is larger, needs to carry out the pile crown of cast-in-situ bored pile Processing increases cast-in-place concrete after reinforced mesh, and the strong time such as scene is longer, seriously affects the construction speed at scene, therefore compel It is essential and wants a kind of pile crown structure convenient for Rapid Implementation static test.
Summary of the invention
The utility model is to solve technical problem present in well-known technique and provide a kind of convenient for the examination of Rapid Implementation static load The pile crown structure tested.
The utility model is adopted the technical scheme that solve technical problem present in well-known technique: one kind is convenient for fast Speed implements the pile crown structure of static test, including the short lattice column being inserted at the top of steel reinforcement cage, in the short lattice column and institute State between steel reinforcement cage be equipped with multiple spaced apart connecting rods, the short lattice column top protrusion the steel reinforcement cage it On, Horizontal load-bearing steel plate is connected at the top of the short lattice column;The filling concrete height of pile crown is higher by the short lattice High 0.5~the 1m of the top mark of column.
The top mark height of the short lattice column is higher by 20~30cm than the design stake top absolute altitude of cast-in-situ bored pile.
The short lattice column be made of steel plate, the steel plate with a thickness of 16~25mm.
The connecting rod is made of any one in reinforcing bar, steel plate or fashioned iron.
The Horizontal load-bearing steel plate uses square structure, and side length is more than or equal to the diameter of cast-in-situ bored pile, with a thickness of 2~ 4cm。
The utility model has the advantages and positive effects of: by using short lattice column pre-buried in the top of steel reinforcement cage And weld the structure of load-bearing steel plate on short lattice column and replace traditional reinforced mesh, it eliminates and cast-in-place builds concrete construction Sequence accelerates the construction speed at scene to save the strong time such as pile crown of static test.
Detailed description of the invention
Fig. 1 is the sectional side elevation of the utility model;
Fig. 2 is the top view of Fig. 1 (removing Horizontal load-bearing steel plate).
In figure: 1, steel reinforcement cage;2, short lattice column;3, Horizontal load-bearing steel plate;4, connecting rod;5, the concrete of pile crown.
Specific embodiment
For the invention, features and effects that can further appreciate that the utility model, the following examples are hereby given, and cooperates Detailed description are as follows for attached drawing:
Fig. 1 and Fig. 2, a kind of pile crown structure convenient for Rapid Implementation static test are please referred to, including is inserted into the top of steel reinforcement cage 1 Short lattice column 2 in portion is equipped with multiple spaced apart connecting rods 4 between the short lattice column 2 and the steel reinforcement cage 1, The top of the short lattice column 2 is protruded on the steel reinforcement cage 1, is connected with Horizontal load-bearing at the top of the short lattice column 2 Steel plate 3;5 influx height of concrete of pile crown is higher by the high 0.5~1m of top mark of the short lattice column 2.
In the present embodiment, the top mark height of the short lattice column 2 be higher by 20 than the design stake top absolute altitude of cast-in-situ bored pile~ 30cm.The short lattice column 2 be made of steel plate, the steel plate with a thickness of 16~25mm.The connecting rod 4 is by steel Made of any one in muscle, steel plate or fashioned iron.The Horizontal load-bearing steel plate 3 uses square structure, and side length is more than or equal to The diameter of cast-in-situ bored pile, with a thickness of 2~4cm.
The construction procedure of the utility model are as follows:
1) during construction drill filling pile cage of reinforcement, short lattice column and steel reinforcement cage are connected with prefabricated connecting rod It connects securely;
2) it transfers in steel reinforcement cage to the hole being drilled, and casting concrete;
3) concrete of hole pouring pile to be drilled reaches design strength, cuts the concrete dross of cast-in-situ bored pile stake top, makes Expose at the top of short lattice column;
4) by Horizontal load-bearing steel plate and short lattice column firm welding.
Although being described above in conjunction with preferred embodiment of the attached drawing to the utility model, the utility model is not It is confined to above-mentioned specific embodiment, the above mentioned embodiment is only schematical, is not restrictive, ability The those of ordinary skill in domain is not departing from the utility model aims and claimed under the enlightenment of the utility model In the case where range, many forms can also be made, these are belonged within the protection scope of the utility model.

Claims (5)

1. a kind of pile crown structure convenient for Rapid Implementation static test, which is characterized in that in being inserted at the top of steel reinforcement cage Short lattice column is equipped with multiple spaced apart connecting rods, the short lattice between the short lattice column and the steel reinforcement cage The top of column is protruded on the steel reinforcement cage, is connected with Horizontal load-bearing steel plate at the top of the short lattice column;Pile crown mixes Solidifying soil influx height is higher by the high 0.5~1m of top mark of the short lattice column.
2. the pile crown structure according to claim 1 convenient for Rapid Implementation static test, which is characterized in that the short lattice The top mark height of column is higher by 20~30cm than the design stake top absolute altitude of cast-in-situ bored pile.
3. the pile crown structure according to claim 1 convenient for Rapid Implementation static test, which is characterized in that the short lattice Column be made of steel plate, the steel plate with a thickness of 16~25mm.
4. the pile crown structure according to claim 1 convenient for Rapid Implementation static test, which is characterized in that the connecting rod Part is made of any one in reinforcing bar, steel plate or fashioned iron.
5. the pile crown structure according to claim 1 convenient for Rapid Implementation static test, which is characterized in that the level is held Weight steel plate uses square structure, and side length is more than or equal to the diameter of cast-in-situ bored pile, with a thickness of 2~4cm.
CN201820400438.2U 2018-03-22 2018-03-22 A kind of pile crown structure convenient for Rapid Implementation static test Expired - Fee Related CN208235499U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820400438.2U CN208235499U (en) 2018-03-22 2018-03-22 A kind of pile crown structure convenient for Rapid Implementation static test

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820400438.2U CN208235499U (en) 2018-03-22 2018-03-22 A kind of pile crown structure convenient for Rapid Implementation static test

Publications (1)

Publication Number Publication Date
CN208235499U true CN208235499U (en) 2018-12-14

Family

ID=64589251

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820400438.2U Expired - Fee Related CN208235499U (en) 2018-03-22 2018-03-22 A kind of pile crown structure convenient for Rapid Implementation static test

Country Status (1)

Country Link
CN (1) CN208235499U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112323877A (en) * 2020-11-06 2021-02-05 江西省地质工程(集团)公司 One-time pouring construction method for static pressure test pile head of cast-in-situ bored pile

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112323877A (en) * 2020-11-06 2021-02-05 江西省地质工程(集团)公司 One-time pouring construction method for static pressure test pile head of cast-in-situ bored pile

Similar Documents

Publication Publication Date Title
CN109024651B (en) Steel pipe concrete mixed pile foundation and construction method
CN106759442A (en) A kind of single-pile elevated bearing-platform and anchor cable tower-crane foundation structure and its construction method
CN101240550A (en) Construction method for lattice type steel column tower crane pedestal
CN206467667U (en) Suspended net shotcrete building enclosure between a kind of stake of use expansion type fixation reinforced mesh
EP2698476B1 (en) Method for the construction of an offshore structure and foundation for an offshore structure
CN102864781A (en) Foundation pit supporting method utilizing inclined piles
CN210713897U (en) Pile foundation hole opening protection device
CN106759281A (en) A kind of anchoring for preventing cast-in-place concrete pile rising of steel cage is pitched
CN110387879A (en) A kind of concrete filling pile construction method of hydraulic vibration hammer hidden pipe
CN101942830B (en) Construction method of combined concrete soil pile with core pile
CN208235499U (en) A kind of pile crown structure convenient for Rapid Implementation static test
JP6413469B2 (en) Pile foundation and pile foundation construction method
CN113737776B (en) Ultra-long steel pipe pile under condition of marine-facies deep mucky soil and construction method thereof
CN208088311U (en) Back-pressure de-bowed type pile slab supporting structure after stake
CN201144425Y (en) Mini pile tower foundation
CN211735555U (en) Long spiral bored concrete pile overlength steel reinforcement cage back insertion construction verticality control assembly
CN103741690A (en) Soil plug compensating pipe pile pulling out method and soil plug compensating pipe pile pulling device using same
CN109339044A (en) A kind of concrete pipe pile construction equipment
Bhardwaj et al. Pullout capacity of model micropiles under oblique loads
CN108330986A (en) Back-pressure de-bowed type pile slab supporting structure and construction method after stake
CN105040828B (en) A kind of round steel pipe binding type steel concrete column and steel beam joint structure
CN204825924U (en) Square steel tube concrete waist rail
Zhussupbekov et al. The Results of Dynamic (Pile Driving Analysis) and Traditional Static Piling Tests in Capital of Kazakhstan
CN106284331A (en) Large-diameter and rock-socketed filling piles improves the method for vertical bearing capacity
CN207405615U (en) A kind of supporting construction of canal formula cutting cement soil continuous wall combination work shape prefabricated pile

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee