CN208225258U - A kind of power construction safety pre-warning system based on Internet of Things - Google Patents
A kind of power construction safety pre-warning system based on Internet of Things Download PDFInfo
- Publication number
- CN208225258U CN208225258U CN201820820923.5U CN201820820923U CN208225258U CN 208225258 U CN208225258 U CN 208225258U CN 201820820923 U CN201820820923 U CN 201820820923U CN 208225258 U CN208225258 U CN 208225258U
- Authority
- CN
- China
- Prior art keywords
- management host
- internet
- system based
- warning system
- construction management
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Alarm Systems (AREA)
Abstract
The utility model discloses a kind of power construction safety pre-warning system based on Internet of Things, including construction management host and subsystem of registering, subsystem of registering is connected with construction management host, it further include more temporary grounding sticks, temporary grounding stick includes location hook, location hook includes coupler body, and barred body is internally provided with earth lead, earth lead and coupler body phase;The outer wall of barred body is provided with support plate, the positioning screw rod with support plate thread cooperation is provided in support plate, aperture location hole directed downwardly is provided on coupler body, the bottom of location hole is provided with pressure sensor, and location hole is internally provided with spring, the upper end of positioning screw rod is inserted into location hole and compressed spring;Pressure sensor is connected with control chip, and control chip is connected with construction management host.This system can monitor the case where each temporary grounding stick in real time, can handle in time after temporary grounding stick Joint failure, can reduce the probability of happening of accident, enhance the safety of construction.
Description
Technical field
The utility model belongs to technical field of electric power construction, especially a kind of power construction safe early warning based on Internet of Things
System.
Background technique
During power construction, the installation of temporary grounding stick be it is highly important, it can be to avoid induced electricity and mistake
Casualty accident caused by power on operation, it is necessary to guarantee temporary earthing device mounting stability, prevents it from falling off, meanwhile, electric power
After the completion of construction, therefore, to assure that all temporary grounding sticks are all removed, and cause grid short circuit to avoid when powering again.In order to protect
Card temporary grounding dress stick is effectively installed, and needs to be monitored it.
In addition, in power construction, it is also necessary to the registering of construction personnel, come off duty, construction management etc. is monitored, apply
Number for 201810006047.7 patent of invention, to disclose a kind of electric power construction field based on wireless sensor network information-based
Supervision system realizes real-time acquisition, monitoring and record to electric power construction field information, facilitates supervisors at different levels and at different levels
Leader judges rapidly working site situation, ensure that the timeliness and accuracy of the transmission of electric power construction field information, mentions
High informatization security management level.But there is no the open monitoring to temporary grounding stick, administrative staff to know for the system
Whether in place temporary grounding fills stick installation.
Utility model content
The purpose of this utility model is to provide it is a kind of be able to detect temporary grounding stick installation whether in place based on Internet of Things
The power construction safety pre-warning system of net.
Purpose of the utility model is realized as follows: a kind of power construction safety pre-warning system based on Internet of Things, packet
Including construction management host and subsystem of registering, module is connected the subsystem of registering with construction management host by wireless communication,
It further include more temporary grounding sticks, the temporary grounding stick includes barred body, and the upper end of the barred body, which is provided with, to be used for
Temporary grounding dress stick is articulated in the location hook on power transmission line, the location hook includes conductive coupler body, the inside setting of barred body
There is earth lead, the earth lead is connected with coupler body;The outer wall of the barred body is provided with support plate, is arranged in the support plate
There is the positioning screw rod with support plate thread cooperation, is provided with aperture location hole directed downwardly on coupler body, the bottom of the location hole is set
It is equipped with pressure sensor, and location hole is internally provided with spring, the spring and pressure sensor contacts, the positioning screw rod
Upper end is inserted into location hole and compressed spring, and the positioning screw rod can enclose closed positioning chamber with coupler body;
The pressure sensor is connected with control chip, the control chip module and construction management master by wireless communication
Machine is connected.
Further, the subsystem of registering includes personal identification card, RFID identification module and processor, the processor
Built-in wireless communication module, the RFID identification module are electrically connected with processor, the processor by wireless communication module with
Construction management host is connected.
Further, the processor is arm processor.
Further, the control chip is installed on barred body outer wall.
Further, the control chip is single-chip microcontroller.
Further, the construction management host and control chip are respectively connected with display screen.
Further, the construction management host is connected with alarm.
The beneficial effects of the utility model are: improved by the structure to temporary grounding stick, can real-time monitoring face
When grounding rod installation whether consolidate, when temporary grounding stick falls off, control chip can be by information module by wireless communication
It is sent to construction management host, administrative staff deal in time, prevent the generation of safety accident.In addition, by temporary grounding stick
Monitoring and personnel the case where registering etc. and to be integrated into an entirety, administrative staff is facilitated to grasp entire construction site, violation is grasped
It alarms, more efficiently avoids the generation of safety accident.
Detailed description of the invention
Fig. 1 is the system schematic of the utility model.
Fig. 2 is the temporary grounding dress stick schematic diagram of the utility model.
Appended drawing reference: 1-barred body;2-coupler bodies;3-support plates;4-positioning screw rods;5-location holes;6-pressure sensings
Device;7-springs;8-positioning chambers;9-earth leads;10-control chips;11-display screens;12-alarms;100-constructions
Managing main frame;110-register subsystem;111-personal identification cards;112-RFID identification modules;113-processors.
Specific embodiment
The present invention will be further described with reference to the accompanying drawings and examples.
As depicted in figs. 1 and 2, a kind of power construction safety pre-warning system based on Internet of Things of the utility model, including
Construction management host 100 and subsystem 110 of registering, register subsystem 110 module and the construction management master by wireless communication
Machine 100 is connected.Construction management host 100 is used to collect the information of registering of employee, and module transmits information by wireless communication
To construction management host 100, various information are summarized, are recorded by construction management host 100, attendance record are generated, in order to working hour
Statistics, the convenient management to employee.General computer can be used in construction management host 100.
It further include more temporary groundings dress sticks, the temporary grounding stick includes barred body 1, and barred body 1 be the cylinder to insulate, can be with
It is plastic cylinder, it is hand-held in order to facilitate construction personnel, handle can be set in the outer wall of barred body 1.The upper end of the barred body 1 is provided with
For temporary grounding stick to be articulated in the location hook on power transmission line, the location hook includes conductive coupler body 2, the inside of barred body 1
It is provided with earth lead 9, the earth lead 9 is connected with coupler body 2, and when construction, earth lead 9 is embedded in underground, if
There are also remaining electricity on power transmission line, the fax on power transmission line can be directed at ground by coupler body 2 and earth lead 9, prevent electricity defeated
It is transmitted in electric wire and causes safety accident.The outer wall of the barred body 1 is provided with support plate 3, is provided with and props up in the support plate 3
The positioning screw rod 4 that fagging 3 is threadedly engaged, positioning screw rod 4 can be used the higher plastic bar of intensity, be provided with aperture court on coupler body 2
Under location hole 5, the bottom of the location hole 5 is provided with pressure sensor 6, and pressure sensor 6 can convert pressure signal
For electric signal, the sensor of PT124G-210 model specifically can be used.Location hole 5 is internally provided with spring 7, the spring 7 with
Pressure sensor 6 contacts, and the upper end of the positioning screw rod 4 is inserted into location hole 5 and compressed spring 7, and the positioning screw rod 4
Closed positioning chamber 8 can be enclosed with coupler body 2.
The pressure sensor 6 is connected with control chip 10, the control chip 10 module and construction by wireless communication
Managing main frame 100 is connected.When temporary grounding stick is installed, transmission line is hooked using coupler body 2, rotational positioning screw rod 4 makes positioning screw rod
4 are moved upward in location hole 5,4 compressed spring 7 of positioning screw rod, and pressure is transmitted to pressure sensor 6 by spring 7, and pressure passes
Sensor 6, which detects, converts electric signal for pressure signal after pressure signal, and by the electric signal transmission to control chip 10, control
Module transmits a signal to construction management host 100 to chip 10 by wireless communication again, construction management host 100 to the information into
Row judgement, if spring 7 reaches standard value to the pressure of pressure sensor 6, temporary grounding stick is installed in place, if spring 7
Standard value is less than to the pressure of pressure sensor 6, then installs not in place, construction management host 100 notifies administrative staff in time, with
Make reply in time convenient for administrative staff.After temporary grounding stick installs, if being detached from transmission line again during construction,
Pressure sensor 6 is also able to detect that the variation of pressure and transmits a signal to control chip 10, controls chip 10 again by signal
It is transmitted to construction management host 100, administrative staff can quickly deal with.It controls chip 10 and uses general single-chip microcontroller,
Such as 51 single-chip microcontrollers, MSP430 single-chip microcontroller.
After this system, the case where each temporary grounding stick can be monitored in real time, after temporary grounding stick Joint failure
It can handle in time, the probability of happening of accident can be reduced, enhance the safety of construction.
The subsystem 110 of registering includes personal identification card 111, RFID identification module 112 and processor 113, the place
Wireless communication module built in device 113 is managed, the RFID identification module 112 is electrically connected with processor 113, and the processor 113 is logical
Wireless communication module is crossed to be connected with construction management host 100.Each one personal identification card 111 of employee setup, personal identification card 111
The information of employee is inside stored, RFID identification module 112 can be read out the information in personal identification card 111, and will letter
Breath is transmitted to processor 113, and processor 113 transmits information to construction management host 100 again, and construction management host 100 will be every
The information of a personnel summarizes storage, and in order to count working hour, administrative staff can be preferably managed employee.
Wireless transport module includes wireless sending module and wireless receiving module, and wireless sending module setting is in control chip
10 and processor 113 on, for sending radio signal, wireless receiving module is arranged on construction management host 100, for connecing
Radio signal is received, wireless sending module and wireless receiving module cooperate, and can be realized the wireless transmission of information.Wireless hair
Send module and wireless receiving module using existing common technology.
Processor 113 can also be using single-chip microcontroller etc., in the utility model, and processor 113 uses arm processor.
The control chip 10 is installed on 1 outer wall of barred body, specifically, installation box body can be arranged in 1 outer wall of barred body, will control
Chip 10 is mounted in box body, and in order to water proof and dust proof, battery can also be arranged in box body, can be to control chip 10 and pressure
Force snesor 6 provides electric energy.
The construction management host 100, processor 113 and control chip 10 are respectively connected with display screen 11, can be to various
Data are shown, administrative staff can more quickly, various situations are well understood.
The construction management host 100 is connected with alarm 12.Alarm 12 can be combined aural and visual alarm, when some is interim
When ground connection dress stick occurs abnormal, construction management host 100 controls alarm 12 and sounds an alarm, and administrative staff can know at once.
The above descriptions are merely preferred embodiments of the present invention, is not intended to limit the utility model, for this
For the technical staff in field, various modifications and changes may be made to the present invention.It is all in the spirit and principles of the utility model
Within, any modification, equivalent replacement, improvement and so on should be included within the scope of protection of this utility model.
Claims (7)
1. a kind of power construction safety pre-warning system based on Internet of Things, including construction management host (100) and subsystem of registering
(110), module is connected the subsystem of registering (110) with construction management host (100) by wireless communication, it is characterised in that:
It further include more temporary grounding sticks, the temporary grounding stick includes barred body (1), and the upper end of the barred body (1) is provided with for inciting somebody to action
Temporary grounding stick is articulated in the location hook on power transmission line, and the location hook includes conductive coupler body (2), and the inside of barred body (1) is set
It is equipped with earth lead (9), the earth lead (9) is connected with coupler body (2);The outer wall of the barred body (1) is provided with support plate
(3), the positioning screw rod (4) being threadedly engaged with support plate (3) is provided on the support plate (3), coupler body is provided with aperture on (2)
The bottom of location hole (5) directed downwardly, the location hole (5) is provided with pressure sensor (6), and location hole (5) is internally provided with
Spring (7), the spring (7) contact with pressure sensor (6), and the upper end of the positioning screw rod (4) is inserted into location hole (5)
And compressed spring (7), and the positioning screw rod (4) can enclose closed positioning chamber (8) with coupler body (2);The pressure sensor
(6) control chip (10), the control chip (10) module and construction management host (100) phase by wireless communication are connected with
Even.
2. a kind of power construction safety pre-warning system based on Internet of Things according to claim 1, it is characterised in that: described
Subsystem (110) of registering includes personal identification card (111), RFID identification module (112) and processor (113), the processor
(113) wireless communication module built in, the RFID identification module (112) are electrically connected with processor (113), the processor
(113) module is connected with construction management host (100) by wireless communication.
3. a kind of power construction safety pre-warning system based on Internet of Things according to claim 2, it is characterised in that: described
Processor (113) is arm processor.
4. a kind of power construction safety pre-warning system based on Internet of Things according to claim 1, it is characterised in that: described
Control chip (10) is installed on barred body (1) outer wall.
5. a kind of power construction safety pre-warning system based on Internet of Things according to claim 1, it is characterised in that: described
Controlling chip (10) is single-chip microcontroller.
6. a kind of power construction safety pre-warning system based on Internet of Things according to claim 1, it is characterised in that: described
Construction management host (100) and control chip (10) are respectively connected with display screen (11).
7. a kind of power construction safety pre-warning system based on Internet of Things according to claim 1, it is characterised in that: described
Construction management host (100) is connected with alarm (12).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820820923.5U CN208225258U (en) | 2018-05-30 | 2018-05-30 | A kind of power construction safety pre-warning system based on Internet of Things |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820820923.5U CN208225258U (en) | 2018-05-30 | 2018-05-30 | A kind of power construction safety pre-warning system based on Internet of Things |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208225258U true CN208225258U (en) | 2018-12-11 |
Family
ID=64506821
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820820923.5U Expired - Fee Related CN208225258U (en) | 2018-05-30 | 2018-05-30 | A kind of power construction safety pre-warning system based on Internet of Things |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208225258U (en) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109887235A (en) * | 2019-03-28 | 2019-06-14 | 广西桂海高速公路有限公司 | A kind of work zone safety alarm device |
CN109946557A (en) * | 2019-03-26 | 2019-06-28 | 国网江苏省电力有限公司扬州供电分公司 | A kind of electronics ground connection hook |
CN117057617A (en) * | 2023-10-11 | 2023-11-14 | 湖北华中电力科技开发有限责任公司 | Electric power construction site safety monitoring and early warning system based on Internet of things |
-
2018
- 2018-05-30 CN CN201820820923.5U patent/CN208225258U/en not_active Expired - Fee Related
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109946557A (en) * | 2019-03-26 | 2019-06-28 | 国网江苏省电力有限公司扬州供电分公司 | A kind of electronics ground connection hook |
CN109946557B (en) * | 2019-03-26 | 2024-04-26 | 国网江苏省电力有限公司扬州供电分公司 | Electronic grounding hook |
CN109887235A (en) * | 2019-03-28 | 2019-06-14 | 广西桂海高速公路有限公司 | A kind of work zone safety alarm device |
CN117057617A (en) * | 2023-10-11 | 2023-11-14 | 湖北华中电力科技开发有限责任公司 | Electric power construction site safety monitoring and early warning system based on Internet of things |
CN117057617B (en) * | 2023-10-11 | 2023-12-08 | 湖北华中电力科技开发有限责任公司 | Electric power construction site safety monitoring and early warning system based on Internet of things |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN208225258U (en) | A kind of power construction safety pre-warning system based on Internet of Things | |
CN109638966A (en) | A kind of monitoring of arrester intelligent online, data remote visualization cloud platform system | |
CN207650323U (en) | A kind of electric fire monitoring system | |
CN106768135A (en) | A kind of intelligent telemetering water meter based on MSP430 | |
CN104266681A (en) | Electric cable well state safety monitoring system based on Internet of Things and GIS | |
CN111681381A (en) | Intelligent recognition system for preventing external damage of power transmission line | |
CN208207842U (en) | Power distribution room safety management system | |
CN205643445U (en) | Anti -electricity -theft ammeter case mounting structure | |
CN201691639U (en) | Remote wirelessly managed intelligent pillar box | |
CN205450633U (en) | Two accuse devices of remote intelligent well electricity | |
CN206020991U (en) | Water resource well electricity dual control management system | |
CN214041180U (en) | A plant diseases and insect pests quarantine check out test set for crops | |
CN106570998A (en) | Intelligent single door and window drawer movement monitoring device | |
CN206179152U (en) | Antitheft warning device of transformer | |
CN205829307U (en) | A kind of intelligent and safe distributing monitoring system | |
CN204330009U (en) | Based on the cable shaft status safety monitoring system of Internet of Things and GIS | |
CN207458114U (en) | A kind of substation wirelessly wire management system | |
CN207559282U (en) | Power distribution equipment and distribution system | |
CN201191740Y (en) | Power-line tower synthetic protection system | |
CN206312353U (en) | A kind of intelligent meter data recording system data concentrator | |
CN106448100A (en) | 230M-LTE wireless collector | |
CN208386804U (en) | A kind of monitoring box state on_line monitoring system | |
CN220105818U (en) | Device for preventing inclination of door leaf of protective door | |
CN218157842U (en) | Testing arrangement of monitoring well hydrogeological parameter | |
CN210322022U (en) | Medium-voltage power distribution cabinet temperature measurement visiting system |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20181211 |