CN208212890U - Wet desulfuration tower - Google Patents

Wet desulfuration tower Download PDF

Info

Publication number
CN208212890U
CN208212890U CN201820575630.5U CN201820575630U CN208212890U CN 208212890 U CN208212890 U CN 208212890U CN 201820575630 U CN201820575630 U CN 201820575630U CN 208212890 U CN208212890 U CN 208212890U
Authority
CN
China
Prior art keywords
spray
support
supervisor
secondary beam
mounting portion
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820575630.5U
Other languages
Chinese (zh)
Inventor
曹善勇
李洪涛
马金刚
尤冲
王懿
沈振彬
陈良珍
黄均
林振国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Fidelity High Performance Flue Gas Purification System Engineering Co Ltd
Zouxian Huadian Power Co Ltd
Original Assignee
Zhejiang Fidelity High Performance Flue Gas Purification System Engineering Co Ltd
Zouxian Huadian Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Fidelity High Performance Flue Gas Purification System Engineering Co Ltd, Zouxian Huadian Power Co Ltd filed Critical Zhejiang Fidelity High Performance Flue Gas Purification System Engineering Co Ltd
Priority to CN201820575630.5U priority Critical patent/CN208212890U/en
Application granted granted Critical
Publication of CN208212890U publication Critical patent/CN208212890U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Treating Waste Gases (AREA)

Abstract

The utility model discloses wet desulfuration towers, including support girder and spray supervisor, support girder two are one group, support secondary beam is equipped between two support girders, spray supervisor is arranged in parallel with support girder, spray supervisor is equipped with slurries spray port, and spray supervisor is fixed on the lower section of support secondary beam by pipe collar, and the both ends of pipe collar are each attached on support secondary beam.The utility model has the advantages that: the setting support secondary beam between support girder, two support girders can be both fixed by support secondary beam and guarantee its stability, and setting spray supervisor slurries can be sprayed below support secondary beam, to prevent flue gas from escaping from support girder, recycle pipe collar that spray supervisor is suspended below support secondary beam, guarantee spray supervisor operation steady in a long-term, and the slurries sprayed will not be washed into support girder and secondary beam, improve the uniformly distributed property of flue gas flow field, improve desulfuration efficiency, extend the service life of spraying layer, improve the safe operation reliability of desulphurization system.

Description

Wet desulfuration tower
Technical field
The utility model relates to wet desulfuration towers.
Background technique
Coal fired boiler of power plant is the main row of the atmosphere pollutions such as flue dust, sulfur dioxide (SO2) and nitrogen oxides (NOX) Put one of source.To improve atmosphere quality, National Development and Reform Commission, Environmental Protection Department, National Energy Board combine the hair issued Change the energy [2014] 2093 about the notice for printing and distributing " coal electricity energy-saving and emission-reduction upgrading and transformation action plan (2014-2020) " Equal files, have worked out stringenter Air Pollutant Emission Index, it is desirable that eastern region creates the atmosphere pollution of coal unit Object concentration of emission basically reaches coal-fired turbine emission limit, and wherein SO2 concentration of emission requires to be not more than 35mg/Nm3.For dioxy Change sulphur emission reduction, usually wet desulphurization device is improved, realizes that desulfurization proposes effect, reach emission request.Spray tube is wet process The core component of desulfurizing tower, in wet desulfuration tower top spray-absorption area, close to the slurries of the nozzle ejection of spray tube supporting beam The supporting beam for easily washing away itself, when supporting beam is arranged below spray tube, region locating for supporting beam can not arrange downward spray Nozzle, such flue gas be easy from supporting beam escape and can not be reacted with sprayed slurry.
Utility model content
The purpose of this utility model is to provide wet desulfuration towers, can effectively solve the problem that and are supporting in existing wet desulfuration tower Liang Chu is easy to appear the problem of flue gas escape.
In order to solve the above-mentioned technical problem, the utility model is achieved through the following technical solutions: wet desulfuration tower, packet Support girder and spray supervisor are included, the support girder two are one group, support secondary beam is equipped between two support girders, The spray supervisor is arranged in parallel with support girder, and the spray supervisor is equipped with slurries spray port, and the spray supervisor passes through Pipe collar is fixed on the lower section of support secondary beam, and at U-shaped, the both ends of the pipe collar are each attached on support secondary beam the pipe collar.
Preferably, the spray supervisor is equipped with the spray looped pipeline vertical with support girder, also sets on the spray looped pipeline There is slurries spray port.
Preferably, the spray looped pipeline is fixed on spray supervisor by mounting shell, and the mounting shell includes the first installation Portion and the second mounting portion, first mounting portion is arc-shaped, and arc-shaped corresponding central angle is less than 180 degree, first peace Dress portion be fixed on spray supervisor outer circle wall on, second mounting portion be hollow cylinder, the inner hole of second mounting portion with The outer diameter for spraying looped pipeline is equal, is provided with through-hole on first mounting portion and communicates with the second mounting portion, the spray looped pipeline passes through Second mounting portion connects with spray supervisor.
Preferably, the spray looped pipeline is arranged in pairs, and symmetrical about spray supervisor's axis.
Preferably, every it is described spray looped pipeline on slurries spray port at least one be arranged in support girder just under Side.
Preferably, the spray supervisor gradually becomes smaller along sprayed slurry flow direction caliber.
Preferably, the cross section of the pipe collar is L shape.
Preferably, the spray angle of the slurries spray port is between 80~120 degree.
Preferably, the spacing between adjacent pipe collar is 1.6~2.0 meters.
Compared with prior art, the utility model has the advantages that: between support girder setting support secondary beam, pass through support Secondary beam, which can both be fixed two support girders, guarantees its stability, and can lead setting spray below support secondary beam Pipe sprays slurries, to prevent flue gas from escaping from support girder, recycles pipe collar that spray supervisor is suspended under support secondary beam Side guarantees spray supervisor operation steady in a long-term, and the slurries sprayed will not be washed into support girder and secondary beam, improve flue gas stream The uniformly distributed property of field improves desulfuration efficiency, extends the service life of spraying layer, improve the safe operation reliability of desulphurization system.
The spray supervisor is equipped with the spray looped pipeline vertical with support girder, and slurries spray also is provided on the spray looped pipeline Drench mouth.By spraying looped pipeline, further expansion sprays region, prevents flue gas from escaping.
The spray looped pipeline is fixed on spray supervisor by mounting shell, and the mounting shell includes the first mounting portion and second Mounting portion, first mounting portion is arc-shaped, and arc-shaped corresponding central angle is less than 180 degree, and first mounting portion is fixed On spray supervisor's outer circle wall, second mounting portion is hollow cylinder, the inner hole and spray looped pipeline of second mounting portion Outer diameter it is equal, be provided with through-hole on first mounting portion and communicated with the second mounting portion, the spray looped pipeline pass through second installation Portion connects with spray supervisor.Due to the sprayed slurry that also to circulate in spray looped pipeline, in order to reinforce spraying looped pipeline and spray supervisor's Between connecting bracket mounting shell, mounting shell on one side increases and sprays the contact surface between supervisor, another side also increase with The contact surface between looped pipeline is sprayed, guarantees the stability of spray looped pipeline.
The spray looped pipeline is arranged in pairs, and symmetrical about spray supervisor's axis.Spray supervisor two sides are carried out Uniform sprinkling, avoids the formation of dead angle, while saving sprayed slurry.
Every it is described spray looped pipeline on slurries spray port at least one the underface of support girder is set.Guarantee cigarette Gas will not escape immediately below support girder.
The spray supervisor gradually becomes smaller along sprayed slurry flow direction caliber.It is gradually contracted according to sprayed slurry flow direction Small diameter tube keeps overpressure.
The cross section of the pipe collar is L shape.Pipe collar is to expand and spray the contact area between being responsible in this way, is prevented pair Spray supervisor's surface scratching, and the contact area with support secondary beam is expanded, it is fixed convenient for pipe collar and support secondary beam.
The spray angle of the slurries spray port is between 80~120 degree.Best spray angles are formed, angle too small is covered Capping is too small, and it is excessively sparse that the excessive sprayed slurry of angle forms droplet.
Spacing between adjacent pipe collar is 1.6~2.0 meters.Specifically too short to will cause pipe collar waste, distance is too greatly to single The load-bearing requirements of pipe collar are high.
Detailed description of the invention
Fig. 1 is the cross-sectional view of the utility model wet desulfuration tower;
Fig. 2 is A-A cross-sectional view in Fig. 1.
Specific embodiment
The embodiment of the present invention is described below in detail, examples of the embodiments are shown in the accompanying drawings.Below with reference to The embodiment of attached drawing description is exemplary, it is intended to is used to explain the present invention, and is not considered as limiting the invention.
In the description of the present invention, it is to be understood that, term " center ", " longitudinal direction ", " transverse direction ", " length ", " width ", The instructions such as " thickness ", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom" "inner", "outside" Orientation or positional relationship is to be based on the orientation or positional relationship shown in the drawings, and is merely for convenience of the description present invention and simplification is retouched It states, rather than the device or element of indication or suggestion meaning must have a particular orientation, be constructed and operated in a specific orientation, Therefore it is not considered as limiting the invention.
In addition, term " first ", " second " are used for descriptive purposes only and cannot be understood as indicating or suggesting relative importance Or implicitly indicate the quantity of indicated technical characteristic.Define " first " as a result, the feature of " second " can be expressed or Implicitly include at least one this feature.
Refering to fig. 1, Fig. 2 is the embodiment of the utility model wet desulfuration tower, wet desulfuration tower, including 1 He of support girder Spray supervisor 2, the support girder 1 two are one group, and support secondary beam 3, the spray are equipped between two support girders 1 Supervisor 2 is arranged in parallel with support girder 1, and the spray supervisor 2 is equipped with slurries spray port 4, and the spray supervisor 2 passes through pipe collar 5 are fixed on the lower section of support secondary beam 3, and the pipe collar 5 is bolted on support secondary beam at U-shaped, the both ends of the pipe collar 5 On, in order to increase intensity, every end can be fixed by two groups of bolts.
The setting support secondary beam 3 between support girder 1, by supporting secondary beam 3 that can both consolidate to two support girders 1 Surely guarantee its stability, and setting spray supervisor 2 can spray slurries below support secondary beam 3, to prevent flue gas from branch It supports and escapes at girder 1, recycle pipe collar 5 that spray supervisor 2 is suspended on 3 lower section of support secondary beam, guarantee that spray supervisor 2 is steady in a long-term Operation, and the slurries sprayed will not be washed into support girder 1 and secondary beam, improve the uniformly distributed property of flue gas flow field, improve desulfurization effect Rate extends the service life of spraying layer, improves the safe operation reliability of desulphurization system.
Further, it is possible to be equipped with the spray looped pipeline 6 vertical with support girder 1 on spray supervisor 2, the spray is secondary It also is provided with slurries spray port 4 on pipe 6, to expand spray coverage area, prevents flue gas from escaping.
It since spray 6 weight of looped pipeline is also heavier, and sprays looped pipeline 6 and is only fixed with spray supervisor 2, in order to guarantee to spray looped pipeline 6 stability, spray looped pipeline 6 are fixed on spray supervisor 2 by mounting shell 7, and the mounting shell 7 includes 71 He of the first mounting portion Second mounting portion 72, first mounting portion 71 is arc-shaped, and arc-shaped corresponding central angle is less than 180 degree, first peace Dress portion 71 is fixed on spray 2 outer circle walls of supervisor, increases the contact area between spray supervisor 2, second mounting portion 72 be hollow cylinder, and the inner hole of second mounting portion 72 is equal with the spray outer diameter of looped pipeline 6, is opened on first mounting portion 71 There is through-hole to communicate with the second mounting portion 72, the spray looped pipeline 6 passes through the second mounting portion 72 and connects with spray supervisor 2, passes through peace Dress shell 7 increases and sprays the connection between supervisor 2 and spray looped pipeline 6, provides enough strength supports, ensure that spray is secondary The stabilization of 6 position of pipe.
Spray looped pipeline 6 can also be arranged in pairs, and be distributed about spray 2 axisymmetricals of supervisor, and every institute simultaneously Stating the slurries spray port 4 on spray looped pipeline 6, the underface of support girder 1 is arranged at least one, is not easy to form dead angle, allows spray Drench the covering of slurries gamut.
In view of slurries spray supervisor 2 in more flow it is smaller, in order to keep spray supervisor 2 in each position pressure one It causes, the spray supervisor 2 gradually becomes smaller along sprayed slurry flow direction caliber, which, which becomes smaller, can be the change of duration caliber It is small, it is also possible to become smaller every one section of caliber.
Pipe collar 5 generally uses cross section for L shape, can both increase the contact surface between pipe collar 5 and spray supervisor 2 in this way Product can also increase pipe collar 5 and support the contact area between secondary beam 3, facilitate being fixedly connected for pipe collar 5, and adjacent pipe collar 5 Between spacing control at 1.6~2.0 meters, the too long weight for being not easy to bear spray supervisor 2 more demanding to pipe collar 5 of spacing, and Spacing is too short, to arrange pipe collar 5 more, will cause waste.
In addition the spray angle general control of blade spray port forms best spray angles, angle between 80~120 degree It is too small to spend small covering surface, it is excessively sparse that the excessive sprayed slurry of angle forms droplet.
The technical solution for increasing the present apparatus under the support girder 1 in normal wet desulfuration tower, to 1 lower section of support girder Region carry out slurries covering, thus avoid flue gas from the region escape, ensure that the efficiency of gas cleaning, make discharge can reach Mark.
The foregoing is merely specific embodiment of the utility model, but the technical characteristics of the utility model is not limited to This, in the field of the utility model, made changes or modifications all cover practical new at this any those skilled in the art Among the scope of the patents of type.

Claims (9)

1. wet desulfuration tower, it is characterised in that: including support girder and spray supervisor, the support girder two be one group, two Support secondary beam is equipped between support girder described in root, the spray supervisor is arranged in parallel with support girder, on the spray supervisor Equipped with slurries spray port, the spray supervisor is fixed on the lower section of support secondary beam by pipe collar, and the pipe collar is at U-shaped, the pipe The both ends of hoop are each attached on spray secondary beam.
2. wet desulfuration tower as described in claim 1, it is characterised in that: the spray supervisor is equipped with vertical with support girder Spray looped pipeline, also be provided with slurries spray port on the spray looped pipeline.
3. wet desulfuration tower as claimed in claim 2, it is characterised in that: the spray looped pipeline is fixed on spray by mounting shell On supervisor, the mounting shell includes the first mounting portion and the second mounting portion, and first mounting portion is arc-shaped and arc-shaped right Central angle is answered to be less than 180 degree, first mounting portion is fixed on spray supervisor's outer circle wall, and second mounting portion is hollow The inner hole of cylinder, second mounting portion is equal with the spray outer diameter of looped pipeline, is provided with through-hole and second on first mounting portion Mounting portion communicates, and the spray looped pipeline passes through the second mounting portion and connects with spray supervisor.
4. wet desulfuration tower as claimed in claim 2, it is characterised in that: the spray looped pipeline is arranged in pairs, and about spray Leaching supervisor's axis is symmetrical.
5. wet desulfuration tower as claimed in claim 4, it is characterised in that: the slurries spray port on the every spray looped pipeline is extremely Rare one is arranged in the underface of support girder.
6. wet desulfuration tower as described in claim 1, it is characterised in that: the spray supervisor manages along sprayed slurry flow direction Diameter gradually becomes smaller.
7. wet desulfuration tower as described in claim 1, it is characterised in that: the cross section of the pipe collar is L shape.
8. wet desulfuration tower as described in claim 1, it is characterised in that: the spray angle of the slurries spray port 80~ Between 120 degree.
9. wet desulfuration tower as described in claim 1, it is characterised in that: the spacing between adjacent pipe collar is 1.6~2.0 meters.
CN201820575630.5U 2018-04-20 2018-04-20 Wet desulfuration tower Expired - Fee Related CN208212890U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820575630.5U CN208212890U (en) 2018-04-20 2018-04-20 Wet desulfuration tower

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820575630.5U CN208212890U (en) 2018-04-20 2018-04-20 Wet desulfuration tower

Publications (1)

Publication Number Publication Date
CN208212890U true CN208212890U (en) 2018-12-11

Family

ID=64512475

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820575630.5U Expired - Fee Related CN208212890U (en) 2018-04-20 2018-04-20 Wet desulfuration tower

Country Status (1)

Country Link
CN (1) CN208212890U (en)

Similar Documents

Publication Publication Date Title
CN207871876U (en) A kind of wet desulphurization swirling flow atomizing spray equipment
CN103055684B (en) Device and process for effectively removing sulfur trioxide in smoke through natural alkali
CN102049187A (en) FGD (flue gas desulfurization) exhaust device without GGH (gas-gas heater) and chimney
CN208212890U (en) Wet desulfuration tower
CN108339669A (en) A kind of Wet type electric dust-removing device removing fine particle
CN203043838U (en) Device for effectively removing sulfur trioxide flue gas by using natural alkali
CN205084619U (en) System for sulfur trioxide in coal -fired flue gas of desorption power plant
CN107243248A (en) A kind of folded plate type gas-liquid part flow arrangement
CN201719963U (en) No-GGH FGD desulphurized smoke emission device and chimney
CN201244442Y (en) Spraying tube
CN208526226U (en) A kind of spray equipment of protection against erosion supporting beam
CN209865709U (en) Annular spraying pipe network of desulfurization absorption tower
CN208340471U (en) A kind of three-level desulfurizer of flue
CN208145733U (en) A kind of shunt spray equipment suitable for wet desulphurization
CN202105574U (en) Desulfurization tower with direct dehumidification chimney
CN209752590U (en) Flue gas all standing desulfurization spray set
CN209333488U (en) A kind of high efficiency denitration device being uniformly mixed convenient for flue gas with ammonia
CN207970671U (en) A kind of oil oven tail gas desulfurization device
CN207102121U (en) Demisting separator
CN112058041A (en) Cluster type desulfurizing tower
CN206295797U (en) A kind of wet desulphurization device with floating angle steel tower disk
CN205216568U (en) Avoid desulfurization absorption tower of flue gas escape
CN207734846U (en) Flue gas denitrification system
CN205361069U (en) Novel vortex street thoughtlessly spouts ammonia by force device
CN204952654U (en) Connection structure of desulfurization absorption tower thick liquid spray piping and nozzle

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20181211

CF01 Termination of patent right due to non-payment of annual fee