CN208184237U - A kind of Construction of Civil Engineering pours device with concrete slab - Google Patents

A kind of Construction of Civil Engineering pours device with concrete slab Download PDF

Info

Publication number
CN208184237U
CN208184237U CN201820690795.7U CN201820690795U CN208184237U CN 208184237 U CN208184237 U CN 208184237U CN 201820690795 U CN201820690795 U CN 201820690795U CN 208184237 U CN208184237 U CN 208184237U
Authority
CN
China
Prior art keywords
teeter chamber
construction
concrete slab
civil engineering
motor
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820690795.7U
Other languages
Chinese (zh)
Inventor
张宁
李治国
谢建平
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ordos vocational college
Original Assignee
Ordos vocational college
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ordos vocational college filed Critical Ordos vocational college
Priority to CN201820690795.7U priority Critical patent/CN208184237U/en
Application granted granted Critical
Publication of CN208184237U publication Critical patent/CN208184237U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • On-Site Construction Work That Accompanies The Preparation And Application Of Concrete (AREA)

Abstract

The utility model discloses a kind of Construction of Civil Engineering to pour device with concrete slab, including bracket, bracket is equipped with a charge pump, charge pump is connected with a charge pipe, bracket is equipped with a teeter chamber, charge pipe extend into the inside of teeter chamber, the top of teeter chamber is equipped with a first motor, first motor is sequentially connected with output shaft, output shaft is equipped with several agitating paddles, and teeter chamber is stretched out in end, and end is equipped with tilting member, discharge nozzle there are two being set below the teeter chamber, two discharge nozzles are sequentially connected with tilting member, the Construction of Civil Engineering is poured in device with concrete slab, uniformly pouring to concrete may be implemented by tilting member, improve the reliability poured;Meanwhile by replacing component, it may be implemented to pour with using synchronous progress, improve the practicability of device, the utility model is designed reasonably is suitble to promote the use of.

Description

A kind of Construction of Civil Engineering pours device with concrete slab
Technical field
The utility model relates to technical field of civil, and in particular to a kind of Construction of Civil Engineering is poured with concrete slab Device.
Background technique
As the development of building trade is increasing to the requirement of concrete slab, may be needed during civil construction It just can be carried out use after wanting different size of concrete slab, concrete slab to need the regular hour after the completion of pouring, it is existing In concrete casting device, only one feed opening, speed of perfusion is slow to be unfavorable for rapid construction, and pours not enough It is even;Moreover, in pouring device, during being poured, after pouring, the mold of next group is needed replacing, in this way Just reduce the efficiency poured.
Utility model content
The utility model is above-mentioned in order to overcome the shortcomings of, provides a kind of Construction of Civil Engineering with concrete slab and pours device.
The utility model achieves the above object through the following technical schemes:
A kind of Construction of Civil Engineering pours device, including bracket with concrete slab, and bracket is equipped with a charge pump, charging Pump is connected with a charge pipe, and bracket is equipped with a teeter chamber, and charge pipe extend into the inside of teeter chamber, the top of teeter chamber Equipped with a first motor, first motor is sequentially connected with output shaft, and output shaft is equipped with several agitating paddles, and end is stretched out and stirred It mixes room, and end is equipped with tilting member, is set below the teeter chamber there are two discharge nozzle, two discharge nozzles are and tilting member Transmission connection;
The tilting member includes half gear for being fixed on output shaft end, and half gear is located at the inside of a swing frame, The front and back inner wall of swing frame is equipped with the tooth that engage with half gear, across a guide rod in the side wall of swing frame, the two of guide rod End is equipped with a fixed link, and the lower section of teeter chamber is fixed on by fixed link, and the side of the swing frame is additionally provided with one Guide rail, guide rail are equipped with both ends sliding slot, are equipped with a pin shaft in each sliding slot, two discharge nozzles pass through corresponding pin shaft respectively It is arranged in sliding slot;
The lower section of the discharge nozzle is equipped with and pours component, and pouring component includes pedestal, and the inside of pedestal is equipped with one second Motor, the second motor drive is connected with shaft, and is connected with a replacement component by rotating shaft transmission, and replacement component includes turning Disk, turntable are equipped with several grooves, are equipped with one in each groove and pour mold, each pour mold and be sequentially connected with one Third motor.
The working principle of the device is that concrete is added in teeter chamber by charge pump, first motor by output shaft come Agitating paddle rotation is controlled, the stirring to concrete is realized, meanwhile, it is poured by discharge nozzle, at this point, half on output shaft Gear will control swing frame and carry out effect swing, then can realize swinging for discharge nozzle, enable to concrete equal Even be poured into pours in mold, the situation for preventing part excessive;After pouring and finishing, the second motor controls turntable by shaft Rotation, by the empty discharge nozzle poured above mold alignment, meanwhile, pour finish it is later pour mold, correspondence will be passed through Third motor push out, come to staff carry out using.
Preferably, second motor is stepper motor.
Preferably, in order to improve the anti-corrosion capability of bracket, the periphery of the bracket is coated with anti-decaying paint.
Preferably, for the cruising ability of realization device, the inside of the pedestal is equipped with battery.
Preferably, the discharge nozzle and teeter chamber are hinged.
The beneficial effects of the utility model are: the Construction of Civil Engineering is poured in device with concrete slab, pass through swing part Uniformly pouring to concrete may be implemented in part, improves the reliability poured;Meanwhile by replacing component, may be implemented to pour It builds and is carried out with using synchronous, improve the practicability of device.
Detailed description of the invention
The utility model will illustrate by example and with reference to the appended drawing, in which:
Fig. 1 is the structural schematic diagram of the utility model;
Fig. 2 is the structural schematic diagram of the tilting member of the utility model;
Fig. 3 is the structural schematic diagram of the replacement component of the utility model.
In figure: 1. brackets, 2. charge pumps, 3. charge pipes, 4. teeter chambers, 5. first motors, 6. output shafts, 7. agitating paddles, 8. swing frame, 9. discharge nozzles, 10. pin shafts, 11. pedestals, 12. turntables, 13. half gears, 14. guide rods, 15. fixed links, 16. lead Rail, 17. shafts, 18. third motors, 19. pour mold, 20. grooves.
Specific embodiment
The utility model is described in further detail presently in connection with attached drawing.These attached drawings are simplified schematic diagram, Only illustrate the basic structure of the utility model in a schematic way, therefore it only shows composition related with the utility model.
As shown in Figure 1-Figure 3, a kind of Construction of Civil Engineering pours device, including bracket 1 with concrete slab, sets on bracket 1 There is a charge pump 2, charge pump 2 is connected with a charge pipe 3, and bracket 1 is equipped with a teeter chamber 4, and charge pipe 3, which is extend into, to be stirred The inside of room 4 is mixed, the top of teeter chamber 4 is equipped with a first motor 5, and first motor 5 is sequentially connected with output shaft 6, output shaft 6 Several agitating paddles 7 are equipped with, and teeter chamber 4 is stretched out in end, and end is equipped with tilting member, the lower section of the teeter chamber 4 is equipped with Two discharge nozzles 9, two discharge nozzles 9 are sequentially connected with tilting member;
The tilting member includes half gear 13 for being fixed on 6 end of output shaft, and half gear 13 is located at a swing frame 8 Inside, the front and back inner wall of swing frame 8 are equipped with the tooth engaged with half gear 13, pass through a guide rod 14 in the side wall of swing frame 8, The both ends of guide rod 14 are equipped with a fixed link 15, and the lower section of teeter chamber 4, the swing frame are fixed on by fixed link 15 8 side is additionally provided with a guide rail 16, and guide rail 16 is equipped with both ends sliding slot, is equipped with a pin shaft 10 in each sliding slot, and two Discharge nozzle 9 is arranged in sliding slot by corresponding pin shaft 10 respectively;
The lower section of the discharge nozzle 9 is equipped with and pours component, and pouring component includes pedestal 11, and the inside of pedestal 11 is equipped with one Second motor, the second motor drive is connected with shaft 17, and is sequentially connected with a replacement component by shaft 17, replaces component Including turntable 12, turntable 12 is equipped with several grooves 20, is equipped with one in each groove 20 and pours mold 19, each pours mould Tool 19 is sequentially connected with a third motor 18.
The working principle of the device is that concrete is added in teeter chamber 4 by charge pump 2, and first motor 5 passes through output shaft 6 rotate to control agitating paddle 7, realize the stirring to concrete, meanwhile, it is poured by discharge nozzle 9, at this point, output shaft 6 On half gear 13 will control swing frame 8 and carry out effect swing, then can realize swinging for discharge nozzle 9, can make Concrete is uniformly poured into and pours in mold 19, the situation for preventing part excessive;After pouring and finishing, the second motor passes through Shaft 17 controls turntable 12 and rotates, by the empty discharge nozzle 9 for pouring the alignment of mold 19 top, meanwhile, it pours and finishes later pour Build mold 19, will be pushed out by corresponding third motor 18, come to staff carry out using.
Preferably, second motor is stepper motor.
Preferably, in order to improve the anti-corrosion capability of bracket 1, the periphery of the bracket 1 is coated with anti-decaying paint.
Preferably, for the cruising ability of realization device, the inside of the pedestal 11 is equipped with battery.
Preferably, the discharge nozzle 9 and teeter chamber 4 are hinged.
Above-mentioned foundation the utility model is enlightenment, and through the above description, relevant staff completely can be not In the range of deviateing this item utility model technical idea, various changes and amendments are carried out.This item utility model it is technical Range is not limited to the contents of the specification, it is necessary to which the technical scope thereof is determined according to the scope of the claim.

Claims (5)

1. a kind of Construction of Civil Engineering pours device with concrete slab, it is characterised in that: including bracket, bracket is equipped with one and adds Material pump, charge pump are connected with a charge pipe, and bracket is equipped with a teeter chamber, and charge pipe extend into the inside of teeter chamber, stirs The top for mixing room is equipped with a first motor, and first motor is sequentially connected with output shaft, and output shaft is equipped with several agitating paddles, and Teeter chamber is stretched out in end, and end is equipped with tilting member, is set below the teeter chamber there are two discharge nozzle, two discharge nozzles are equal It is sequentially connected with tilting member;
The tilting member includes half gear for being fixed on output shaft end, and half gear is located at the inside of a swing frame, is swung The front and back inner wall of frame is equipped with the tooth engaged with half gear, passes through a guide rod in the side wall of swing frame, the both ends of guide rod are equal Equipped with a fixed link, and it being fixed on by fixed link the lower section of teeter chamber, the side of the swing frame is additionally provided with a guide rail, Guide rail is equipped with both ends sliding slot, is equipped with a pin shaft in each sliding slot, two discharge nozzles pass through corresponding pin shaft respectively and are arranged In sliding slot;
The lower section of the discharge nozzle is equipped with and pours component, and pouring component includes pedestal, and the inside of pedestal is equipped with second motor, Second motor drive is connected with shaft, and is connected with a replacement component by rotating shaft transmission, and replacement component includes turntable, turntable Several grooves are equipped with, one is equipped in each groove and pours mold, each pour mold and be sequentially connected with a third electricity Machine.
2. Construction of Civil Engineering according to claim 1 pours device with concrete slab, it is characterised in that: second electricity Machine is stepper motor.
3. Construction of Civil Engineering according to claim 1 pours device with concrete slab, it is characterised in that: the bracket Periphery is coated with anti-decaying paint.
4. Construction of Civil Engineering according to claim 1 pours device with concrete slab, it is characterised in that: the pedestal Inside is equipped with battery.
5. Construction of Civil Engineering according to claim 1 pours device with concrete slab, it is characterised in that: the discharge nozzle It is hinged with teeter chamber.
CN201820690795.7U 2018-05-10 2018-05-10 A kind of Construction of Civil Engineering pours device with concrete slab Expired - Fee Related CN208184237U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820690795.7U CN208184237U (en) 2018-05-10 2018-05-10 A kind of Construction of Civil Engineering pours device with concrete slab

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820690795.7U CN208184237U (en) 2018-05-10 2018-05-10 A kind of Construction of Civil Engineering pours device with concrete slab

Publications (1)

Publication Number Publication Date
CN208184237U true CN208184237U (en) 2018-12-04

Family

ID=64429317

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820690795.7U Expired - Fee Related CN208184237U (en) 2018-05-10 2018-05-10 A kind of Construction of Civil Engineering pours device with concrete slab

Country Status (1)

Country Link
CN (1) CN208184237U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110421690A (en) * 2019-06-21 2019-11-08 浙江双友物流器械股份有限公司 A kind of cement board producing equipment

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110421690A (en) * 2019-06-21 2019-11-08 浙江双友物流器械股份有限公司 A kind of cement board producing equipment

Similar Documents

Publication Publication Date Title
CN107263714A (en) A kind of road construction concrete mixer with floating function of vibrating
CN210732829U (en) High-efficient mixer is used to concrete
CN206184363U (en) Add rapid medicament mixing arrangement for pharmacy department
CN208359079U (en) A kind of blender for concrete mixing plant
CN108099003A (en) A kind of mixed mud agitating device convenient for batch turning
CN108297276A (en) A kind of stirring of concrete and pour integration apparatus
CN208184237U (en) A kind of Construction of Civil Engineering pours device with concrete slab
CN208068563U (en) A kind of stirring of concrete and pour integration apparatus
CN212421763U (en) Stable cement mixer
CN205915496U (en) Stirring cloth equipment
CN212021180U (en) Cement agitating unit for building engineering
CN108380115A (en) A kind of oscillatory type building coating agitating device
CN209699531U (en) A kind of agitating device of over-saturation liquid concrete premixing
CN208343161U (en) A kind of concrete central mix plant
CN107127889B (en) A kind of concrete central mix plant
CN216634878U (en) Refractory material pouring device
CN210651294U (en) High-efficient concrete mixing device is used in water conservancy construction
CN209365012U (en) A kind of horizontal concrete mixer
CN207224268U (en) A kind of dual mixing arrangement of road construction construction concrete
CN207256533U (en) Road construction concrete mixer
CN207189977U (en) A kind of build concrete agitating device
CN216465383U (en) Mixing device capable of quantitatively adding mixing agent for concrete batching research and development
CN204977038U (en) Pour mixer
CN206883912U (en) A kind of construction mixer
CN219054833U (en) Mixing and stirring equipment

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20181204

Termination date: 20190510

CF01 Termination of patent right due to non-payment of annual fee