CN208136891U - A kind of soft base curing process equipment - Google Patents
A kind of soft base curing process equipment Download PDFInfo
- Publication number
- CN208136891U CN208136891U CN201820666759.7U CN201820666759U CN208136891U CN 208136891 U CN208136891 U CN 208136891U CN 201820666759 U CN201820666759 U CN 201820666759U CN 208136891 U CN208136891 U CN 208136891U
- Authority
- CN
- China
- Prior art keywords
- loading plate
- soft base
- terraced body
- curing process
- construction equipment
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Toys (AREA)
Abstract
The utility model discloses a kind of soft base curing process equipments, including:Loading plate, fixation kit, buoyancy tank and driving assembly, the loading plate is for carrying soft base construction equipment, the fixation kit is assemblied in the top of loading plate with the soft base construction equipment for fixed placement on loading plate, the buoyancy tank is assemblied in the bottom of loading plate so that loading plate floats on beach, and the driving component is assemblied in the avris of loading plate for driving loading plate to move on beach.By using above-mentioned technical proposal, when needing to carry out the cured construction of soft base, soft base construction equipment can be loaded on loading plate by staff, soft base construction equipment is fixed on loading plate followed by fixation kit, staff is followed by driving assembly driving loading plate movement, so that loading plate drives soft base construction equipment to move to job location, in order to which soft base construction equipment carries out the cured construction of soft base to job location on loading plate.
Description
Technical field
The utility model relates to soft base construction equipment, in particular to a kind of soft base curing process equipment.
Background technique
Treatment of soft foundation is called soft foundation processing, if ground is not firm enough before being building, to prevent under building groundwork
The heavy drawing crack accidents such as cause building unstable, need to handle subgrade, its sedimentation are made to become sufficiently solid, improve soft
The process of the degree of consolidation and stability of the ground extremely requirement of design.
Existing soft base, which solidifies the mainstream technology used, to be had, sludge solidification technology, cement mixed pile technology and high-pressure rotary-spray
Technology, existing soft base curing apparatus is being carried out applying some excavations of man-hour requirement, stirred, the auxiliary of perfusion equipment, due to machinery
Heavier-weight, can not freely walk on beach.Existing technology is generally by the way of setting up job platform in advance, by machine
Tool is placed on job platform and constructs, and when needing replacing construction location, needs to dismantle job platform and apply in new
Station is set to be built again.
But the higher cost of operation platform is on the one hand built, the time on the other hand building operation platform needs is longer,
Construction efficiency bottom, so have much room for improvement.
Utility model content
The purpose of the utility model is to provide a kind of soft base curing process equipments, can load soft base construction equipment on beach
Walking and construction, when allowing to carry out soft base solidification construction, staff is not necessarily to erection construction platform, on the one hand reduces and is constructed into
This, on the other hand improves construction efficiency.
The above-mentioned technical purpose of the utility model technical scheme is that:
A kind of soft base curing process equipment, including:
Loading plate, fixation kit, buoyancy tank and driving assembly,
The loading plate is used to carry soft base construction equipment,
The fixation kit is assemblied in the top of loading plate with the soft base construction equipment for fixed placement on loading plate,
The buoyancy tank is assemblied in the bottom of loading plate so that loading plate floats on beach,
The driving component is assemblied in the avris of loading plate for driving loading plate to move on beach.
By using above-mentioned technical proposal, when needing to carry out the cured construction of soft base, staff can be set excavation
The soft base construction equipments such as standby, mixing plant or perfusion equipment are loaded on loading plate, and soft base is constructed followed by fixation kit
Equipment is fixed on loading plate, floats loading plate on beach using the setting of buoyancy tank, staff is followed by driving group
Part drives loading plate movement, so that loading plate drives soft base construction equipment to move to job location, in order to soft base construction equipment
The cured construction of soft base is carried out to job location on loading plate;When allowing to carry out soft base solidification construction, staff is without taking
If operation platform, construction cost is on the one hand reduced, construction efficiency is on the other hand improved.
The utility model it is further, the driving component includes:Engine, Athey wheel group and crawler belt,
The Athey wheel group is assemblied on buoyancy tank,
The engine assembly is used to that Athey wheel group be driven to rotate in buoyancy tank,
The crawler belt is assemblied in Athey wheel group.
By using above-mentioned technical proposal, when needing to move using driving assembly driving loading plate, staff's starting
Engine is rotated by driven by engine Athey wheel group, and then drives caterpillar drive, drives loading plate movement by crawler belt, real
Existing driving of the driving assembly to loading plate.
The utility model it is further, the outer surface of the crawler belt is installed with impelling sheet,
The impelling sheet is arranged perpendicular to the surface of crawler belt.
By using above-mentioned technical proposal, the contact area of crawler belt and beach on the one hand is increased using impelling sheet, thus
The frictional force between crawler belt and beach is increased, impelling sheet pushes beach when another aspect crawler belt rotates, and beach is to the anti-of impelling sheet
Active force is conducive to the traveling of loading plate.
The utility model it is further, the fixation kit includes:Plate is locked, locking plate includes:First latch
With the second latch,
First latch is vertical and affixed with the second latch,
First latch and loading plate, which contradict and pass through bolt, to be locked on loading plate,
Second latch and soft base construction equipment, which contradict and pass through bolt, to be locked in soft base construction equipment.
By using above-mentioned technical proposal, when needing for soft base construction equipment to be fixed on loading plate, staff is first
Locking plate is placed on loading plate, the first latch and loading plate is contradicted, makes the second latch and soft base construction equipment
It contradicts, the first latch is locked on loading plate by bolt then, the second latch is locked at soft base by bolt and is applied
On construction equipment, fixation of the soft base construction equipment on loading plate is realized.
The utility model it is further, fixation kit further includes:Lock ring and cable wire,
Lock ring be installed on loading plate and soft base construction equipment on,
Lock ring on loading plate is connected with the lock ring in soft base construction equipment by cable wire.
By using above-mentioned technical proposal, using the cooperation reinforcing flexible foundation construction equipment of lock ring and cable wire on loading plate
Assembly, has the advantages of simple structure and easy realization.
The utility model it is further, the avris of the loading plate is enclosed equipped with railing.
By using above-mentioned technical proposal, when staff operates soft base construction equipment on loading plate, railing can be with
A possibility that staff throws from loading plate is effectively reduced, improves the safety of construction.
The utility model it is further, an avris of the loading plate is installed with ladder.
By using above-mentioned technical proposal, since the position of loading plate is higher, staff is not easy to climb up loading plate, is holding
The avris setting ladder of support plate is convenient to staff and climbs up loading plate by ladder.
The utility model it is further, the ladder includes:First terraced body and the second terraced body,
Described first terraced body is installed on loading plate,
Described second terraced body is assemblied on the first terraced body along the first terraced body extending direction slidingtype,
Make first when being provided with top of the magnet to slide into the first terraced body in the second terraced body at the top of the described first terraced body
Terraced body and the second terraced body magnetic assemble.
By using above-mentioned technical proposal, when needing using ladder, staff is sliding along the first terraced body by the second terraced body
It is dynamic, so that the second terraced body and ground contradict, staff is convenient to by ladder and climbs up loading plate, when not needing using ladder
When, staff slides into the second terraced body at the top of the first terraced body along the first terraced body, so that the second terraced body and the first terraced body magnetic
Cooperation.
The utility model it is further, an avris of the loading plate is installed with dragging frame.
It is too deep in case of mud depth in the construction process by using above-mentioned technical proposal, the power of driving assembly
When being not enough to that loading plate is driven to move, it is convenient to move on beach using dragging frame dragging loading plate.
In conclusion the utility model has the advantages that:
1. realizing the placement of soft base construction equipment using loading plate, the cooperation using locking plate, lock ring and cable wire is real
Show fixation of the soft base construction equipment on loading plate, floated loading plate on beach using buoyancy tank, utilizes engine, crawler belt
The cooperation of wheel group and crawler belt realizes the driving to loading plate;
2. being convenient to staff using ladder climbs up loading plate, the safety of construction is improved using railing.
Detailed description of the invention
Fig. 1 is the overall structure diagram of soft base curing process equipment in the utility model embodiment;
Fig. 2 is the enlarged drawing in the utility model embodiment in Fig. 1 at A;
Fig. 3 is the overall structure diagram of soft base curing process equipment in the utility model embodiment.
Appended drawing reference:1, loading plate;2, fixation kit;21, plate is locked;211, the first latch;212, the second locking
Plate;22, lock ring;23, cable wire;3, buoyancy tank;4, driving assembly;41, Athey wheel group;411, driving wheel;412, driven wheel;42, it carries out
Band;5, impelling sheet;6, railing;7, ladder;71, the first terraced body;72, the second terraced body;8, magnet;9, frame is pulled;10, soft base is constructed
Equipment.
Specific embodiment
The utility model is described in further detail below in conjunction with attached drawing.
As depicted in figs. 1 and 2, a kind of soft base curing process equipment, including:Loading plate 1, loading plate 1 are excavated for carrying
The soft base construction equipments such as equipment, mixing plant or perfusion equipment 10, the bottom of loading plate 1 are installed with buoyancy tank 3, and buoyancy tank 3 is carrying
The two sides of plate 1 are each provided with one, so that loading plate 1 floats on beach.Rotary type is equipped with Athey wheel group on the side wall of buoyancy tank 3
41, Athey wheel group 41 includes:Driving wheel 411 and several driven wheels 412, the mounted inside of buoyancy tank 3 have engine, driving wheel 411
Be installed on the output shaft of engine, be equipped between driving wheel 411 and driven wheel 412 crawler belt 42, crawler belt 42 and driving wheel 411 and
Driven wheel 412 matches.When needing that loading plate 1 is driven to move on beach, staff starts engine, utilizes engine
It drives driving wheel 411 to rotate, drives crawler belt 42 and driven wheel 412 to rotate using driving wheel 411, and then hold by the drive of crawler belt 42
Support plate 1 moves on beach.The surface of crawler belt 42 is installed with impelling sheet 5, and impelling sheet 5 is arranged perpendicular to crawler belt 42, when crawler belt 42
Impelling sheet 5 pushes beach when rotation, and beach is conducive to the traveling of loading plate 1 to the reaction force of impelling sheet 5.
As depicted in figs. 1 and 2, it is provided with locking plate 21 on loading plate 1, locks plate 21 along soft base construction equipment 10
Be provided at circumferentially spaced it is multiple, locking plate 21 include:First latch 211 and the second latch 212, the first latch 211
It is mutually perpendicular to the second latch 212 and affixed, the first latch 211 contradicts with loading plate 1 and is locked at carrying by bolt
On plate 1, the second latch 212 is contradicted with soft base construction equipment 10 and is locked in soft base construction equipment 10 by bolt, is realized
Fixation of the soft base construction equipment 10 on loading plate 1.Lock ring is installed on loading plate 1 and on the side wall of soft base construction equipment 10
22, cable wire 23 is connected between the lock ring 22 on lock ring 22 and soft base construction equipment 10 on loading plate 1, and further soft base is constructed
Equipment 10 is reinforced on loading plate 1.
As depicted in figs. 1 and 2, the avris of loading plate 1 is installed with railing 6, and railing 6 is enclosed along the circumferential direction of loading plate 1 to be set.Carrying
One avris of plate 1 is installed with ladder 7, and ladder 7 includes:First terraced body 71, the first terraced body 71 are installed on loading plate 1, the first ladder
Slidingtype is equipped with the second terraced body 72 on body 71, and the second terraced body 72 can be along the extending direction sliding of the first terraced body 71, the first terraced body
71 top is installed with magnet 8.When needing using ladder 7, staff slides the second terraced body 72 so that the second terraced body 72
Bottom and ground contradict, be convenient to staff by ladder 7 and climb up loading plate 1, when being without the use of ladder 7, work people
Member can slide the second terraced body 72 so that the top of the second terraced body 72 and 8 magnetic of magnet cooperate.In conjunction with Fig. 3, the one of loading plate 1
Side, which is installed with, pulls frame 9, is moved on beach with dragging loading plate 1 using dragging frame 9 when being short of power in loading plate 1.
The course of work is summarized:When needing to carry out the cured construction of soft base, staff can be set excavating equipment, stirring
The soft base construction equipments such as standby or perfusion equipment 10 are loaded on loading plate 1, are then locked at the first latch 211 by bolt
On loading plate 1, the second latch 212 is locked in soft base construction equipment 10 by bolt, then will be in soft base construction equipment 10
Lock ring 22 and loading plate 1 on lock ring 22 connected by cable wire 23, realize the consolidating on loading plate 1 of soft base construction equipment 10
Fixed, staff then starts engine, is rotated using driven by engine driving wheel 411, drives crawler belt 42 using driving wheel 411
It is rotated with driven wheel 412, and then drives loading plate 1 to move to job location on beach by crawler belt 42, then operate soft base and apply
Construction equipment 10 carries out solidification work to the beach of job location.
This specific embodiment is only the explanation to the utility model, is not limitations of the present invention, ability
Field technique personnel can according to need the modification that not creative contribution is made to the present embodiment after reading this specification, but
As long as all by the protection of Patent Law in the scope of the claims of the utility model.
Claims (9)
1. a kind of soft base curing process equipment, which is characterized in that including:
Loading plate(1), fixation kit(2), buoyancy tank(3)And driving assembly(4),
The loading plate(1)For carrying soft base construction equipment(10),
The fixation kit(2)It is assemblied in loading plate(1)Top with for fixed placement in loading plate(1)On soft base construction
Equipment(10),
The buoyancy tank(3)It is assemblied in loading plate(1)Bottom so that loading plate(1)Float on beach,
The driving component(4)It is assemblied in loading plate(1)Avris with for driving loading plate(1)It is moved on beach.
2. soft base curing process equipment according to claim 1, which is characterized in that the driving component(4)Including:Start
Machine, Athey wheel group(41)And crawler belt(42),
The Athey wheel group(41)It is assemblied in buoyancy tank(3)On,
The engine assembly is in buoyancy tank(3)It is interior with for driving Athey wheel group(41)Rotation,
The crawler belt(42)It is assemblied in Athey wheel group(41)On.
3. soft base curing process equipment according to claim 2, which is characterized in that the crawler belt(42)Outer surface it is fixed
There is impelling sheet(5),
The impelling sheet(5)Perpendicular to crawler belt(42)Surface setting.
4. soft base curing process equipment according to claim 3, which is characterized in that the fixation kit(2)Including:Locking
Plate(21), lock plate(21)Including:First latch(211)With the second latch(212),
First latch(211)With the second latch(212)It is vertical and affixed,
First latch(211)With loading plate(1)It contradicts and passes through bolt and be locked at loading plate(1)On,
Second latch(212)With soft base construction equipment(10)It contradicts and passes through bolt and be locked at soft base construction equipment(10)On.
5. soft base curing process equipment according to claim 4, which is characterized in that fixation kit(2)Further include:Lock ring
(22)And cable wire(23),
Lock ring(22)It is installed in loading plate(1)Upper and soft base construction equipment(10)On,
Loading plate(1)On lock ring(22)And soft base construction equipment(10)On lock ring(22)Pass through cable wire(23)Connection.
6. soft base curing process equipment according to claim 5, which is characterized in that the loading plate(1)Avris enclose and set
There is railing(6).
7. soft base curing process equipment according to claim 6, which is characterized in that the loading plate(1)An avris it is solid
Equipped with ladder(7).
8. soft base curing process equipment according to claim 7, which is characterized in that the ladder(7)Including:First terraced body
(71)With the second terraced body(72),
Described first terraced body(71)It is installed in loading plate(1)On,
Described second terraced body(72)Along the first terraced body(71)Extending direction slidingtype is assemblied in the first terraced body(71)On,
Described first terraced body(71)Top be provided with magnet(8)In the second terraced body(72)Slide into the first terraced body(71)Top
Make the first terraced body when portion(71)With the second terraced body(72)Magnetic assembly.
9. soft base curing process equipment according to claim 7, which is characterized in that the loading plate(1)An avris it is solid
Equipped with dragging frame(9).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820666759.7U CN208136891U (en) | 2018-05-07 | 2018-05-07 | A kind of soft base curing process equipment |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820666759.7U CN208136891U (en) | 2018-05-07 | 2018-05-07 | A kind of soft base curing process equipment |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208136891U true CN208136891U (en) | 2018-11-23 |
Family
ID=64312690
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820666759.7U Active CN208136891U (en) | 2018-05-07 | 2018-05-07 | A kind of soft base curing process equipment |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208136891U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112176806A (en) * | 2020-10-16 | 2021-01-05 | 于胜泉 | Stable road soft foundation treatment method and matched soft foundation treatment construction system |
CN114250761A (en) * | 2021-11-22 | 2022-03-29 | 中国水利水电第五工程局有限公司 | Soft foundation solidification treatment equipment based on Yangtze river flood beach geology |
-
2018
- 2018-05-07 CN CN201820666759.7U patent/CN208136891U/en active Active
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN112176806A (en) * | 2020-10-16 | 2021-01-05 | 于胜泉 | Stable road soft foundation treatment method and matched soft foundation treatment construction system |
CN112176806B (en) * | 2020-10-16 | 2021-10-29 | 于胜泉 | Stable road soft foundation treatment method and matched soft foundation treatment construction system |
CN114250761A (en) * | 2021-11-22 | 2022-03-29 | 中国水利水电第五工程局有限公司 | Soft foundation solidification treatment equipment based on Yangtze river flood beach geology |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN208136891U (en) | A kind of soft base curing process equipment | |
CN101864765A (en) | Two-way stirring based SMW construction method and tri-axial stirring equipment | |
EP0407934A2 (en) | Method for executing monolithic continuous straights or circular structural walls and a machine for realizing such a method | |
CN113322990A (en) | Construction method of lock catch steel pipe pile cofferdam suitable for thin-covering-layer hard riverbed | |
CN210975790U (en) | High-pressure rotary jet grouting drilling machine suitable for windy sand high slope | |
JP6043006B1 (en) | Construction method of underground structure | |
CN108952731A (en) | A kind of construction method in tunnel | |
CN103161158B (en) | Method of reinforcing soft soil layers using layering mixing pile machine | |
CN210087236U (en) | Tunneling equipment | |
CN107653888A (en) | A kind of support meanss and construction method suitable for substrate side walls | |
US3705634A (en) | Universal machine for foundations | |
CN217221212U (en) | A agitating unit that is used for slurry solidification fertile groove to backfill | |
CN115773115A (en) | Vertical shield tunneling system for cutting by multiple circular machine heads and construction method thereof | |
CN213417795U (en) | Grouting device for foundation stabilization | |
CN108842788A (en) | Stiff-core cement soil mixing pile construction method | |
JP3376293B2 (en) | Underground construction method | |
KR20190090421A (en) | Ground Improving Device and Ground Improving Method | |
CN211948368U (en) | Ground is consolidated and is stabilized mixing stirring equipment | |
JP2013204404A (en) | Construction method of steel pipe pile | |
JPH05171641A (en) | Pipe burying excavator | |
CN214887090U (en) | Prevent floating strengthening mechanism | |
JP5865760B2 (en) | Steel pipe press-fitting device moving device and steel pipe press-fitting device installation method | |
CN217810575U (en) | Road and bridge crack reinforced structure | |
CN217811285U (en) | Movable-roof hydraulic caisson excavator | |
JP3255278B2 (en) | Low head steel pipe press-in method and low head steel pipe press machine |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |