CN208123629U - Outdoor overhead lifting pipeline equipment - Google Patents

Outdoor overhead lifting pipeline equipment Download PDF

Info

Publication number
CN208123629U
CN208123629U CN201820473865.3U CN201820473865U CN208123629U CN 208123629 U CN208123629 U CN 208123629U CN 201820473865 U CN201820473865 U CN 201820473865U CN 208123629 U CN208123629 U CN 208123629U
Authority
CN
China
Prior art keywords
fixed frame
arm
hanger
outdoor overhead
pipeline equipment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820473865.3U
Other languages
Chinese (zh)
Inventor
沙雨亭
吴国珍
韦小玲
焦浩
贠杰
黄慧
刘志丽
郝懿
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
No2 Building Engineering Co Ltd Beijing Municipal Building Co
Original Assignee
No2 Building Engineering Co Ltd Beijing Municipal Building Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by No2 Building Engineering Co Ltd Beijing Municipal Building Co filed Critical No2 Building Engineering Co Ltd Beijing Municipal Building Co
Priority to CN201820473865.3U priority Critical patent/CN208123629U/en
Application granted granted Critical
Publication of CN208123629U publication Critical patent/CN208123629U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Supports For Pipes And Cables (AREA)

Abstract

The utility model relates to lifting pipeline technical fields, disclose a kind of outdoor overhead lifting pipeline equipment.The utility model includes the fixed frame that pipeline stand top is arranged in, the hanger of riser tubing, and the jack of connection hanger and fixed frame top;The rectangular frame that fixed frame is vertically arranged, long edge pipeline stand direction setting, lower part are fixedly connected by anchor ear with pipeline stand top, and top is provided with suspension arrangement;Jack is suspended on suspension arrangement, and lifting end and hanger mount;Hanger is native glyph framework, including the central upright stanchion being vertically arranged, the lower cross-arm and the upper cross-arm in the middle part of centrally disposed upright bar of centrally disposed upright bar bottom end, central upright stanchion top offer hanging hole, and the both ends of upper cross-arm and lower cross-arm are respectively arranged with vertical bar.The utility model structure is simple, and convenient for operation, difficulty of construction is small, and construction efficiency is high, and occupied area is small, is suitable for constructing in narrow zone.

Description

Outdoor overhead lifting pipeline equipment
Technical field
The utility model relates to lifting pipeline technical fields, more particularly to a kind of outdoor overhead lifting pipeline equipment.
Background technique
With the development of society, not only new building is more and more, but also the old building of many old towns is also required to carry out Renovation and pipeline modification.In order to realize construction of environmental protection, mostly all change electricity transformation in progress coal, " coal changes electricity " technology uses air-source The pattern of heat pump central heating, the pipeline specifications for needing to be laid with are more, and quantity is big, and the duration is tight.For many old towns and existing build The transformation built, difficulty is larger, some roads are narrow or the biggish region of residential density in, subterranean pipe line is laid with very multiple It is miscellaneous, it can not ensure and excavate road surface, and without impinging on existing pipe network, therefore can not be by the pipe laying of transformation in underground, it usually needs it will It is lifted into height in the air, and general solution mainly uses crane, pipeline is hung to high-altitude, then fix with upright bar, takes up an area Area is larger, more demanding to construction site;Due to the limitation of objective construction environment, some narrow regions, which are not available, is hung Vehicle, difficulty of construction is very big, can only scene by other tools, manual board is hung, and not only wastes a large amount of human resources, but also construct Inefficiency, difficulty of construction is big.
Utility model content
It is simple that the utility model provides a kind of structure, and convenient for operation, difficulty of construction is small, and construction efficiency is high, and occupied area is small, Suitable for the outdoor overhead lifting pipeline equipment constructed in narrow zone.
Technical problems to be solved are:For pipe network improving engineering, pipe laying can not be needed to be arranged in underground The case where high-altitude, is taken up a large area using crane lifting, more demanding to construction site;Some narrow regions are not available Crane, difficulty of construction is very big, can only be live by other tools, and manual board is hung, and not only wastes a large amount of human resources, Er Qieshi Work inefficiency, difficulty of construction is big.
In order to solve the above technical problems, the utility model adopts the following technical solution:
The utility model outdoor overhead lifting pipeline equipment, the fixed frame including pipeline stand top is arranged in are promoted The hanger of pipeline, and the jack of connection hanger and fixed frame top;
The rectangular frame that fixed frame is vertically arranged, long edge pipeline stand direction setting, lower part passes through anchor ear and pipe Road stand top is fixedly connected, and top is provided with suspension arrangement;
Jack is suspended on suspension arrangement, and lifting end and hanger mount;
Hanger is native glyph framework, including the central upright stanchion being vertically arranged, the lower cross-arm of centrally disposed upright bar bottom end and Upper cross-arm in the middle part of centrally disposed upright bar, central upright stanchion top offer hanging hole, the both ends difference of upper cross-arm and lower cross-arm It is provided with vertical bar.
The utility model outdoor overhead lifting pipeline equipment, further, the anchor ear quantity is no less than 2, up and down simultaneously Column arrangement is arranged on the one side of fixed frame, is detachably fixed by bolt and fixed frame.
The utility model outdoor overhead lifting pipeline equipment further includes further lateral baffle, the lateral baffle number Amount is 2, is separately positioned below anchor ear, on the lateral wall of two long side of fixed frame.
The utility model outdoor overhead lifting pipeline equipment further includes further positive stop strip, and the positive stop strip level is set It sets above anchor ear, positive stop strip both ends are fixedly connected with fixed frame.
The utility model outdoor overhead lifting pipeline equipment, further, the lateral baffle, positive stop strip are set with anchor ear It sets on the same side of fixed frame.
The utility model outdoor overhead lifting pipeline equipment, further, the suspension arrangement include suspended cross-beam and consolidate Fixed board, the fixed plate quantity are 2, are symmetricly set on the lateral wall of two long side of fixed frame, and one end and fixed frame weld Fixation is connect, the other end extends horizontally outward, and extension and anchor ear are separately positioned on opposite two sides of fixed frame, and two Suspended cross-beam is provided between extension.
The utility model outdoor overhead lifting pipeline equipment, further, the both ends of the upper cross-arm and lower cross-arm are distinguished It is provided with fixing sleeve, the fixing sleeve is corresponding up and down, is vertically arranged, and the bar is vertically inserted on same vertical direction Fixing sleeve in.
The utility model outdoor overhead lifting pipeline equipment, further, the fixing sleeve are internal diameter no more than 40mm's Round steel pipe.
The utility model outdoor overhead lifting pipeline equipment is further horizontally disposed on the surrounding side wall of the bar There is a limit plate, limit plate is at a distance from bar bottom end and the distance between upper cross-arm upper surface to lower cross-arm lower surface is consistent.
The utility model outdoor overhead lifting pipeline equipment, further, the height of the bar are not less than central upright stanchion Height.
The utility model outdoor overhead lifting pipeline equipment has the advantages that compared with prior art:
The utility model outdoor overhead lifting pipeline equipment is used to pipeline being lifted to high-altitude, is mounted on pipeline stand top Portion, structure is simple, and convenient for production, at low cost, difficulty of construction is low, and it is convenient to operate, and construction efficiency is high;The utility model is detachable It is fixed, it is easy to demolition, it may be reused, scene turnover utilization rate is high;The utility model occupied area is small, and it is narrow to be suitable for road Field construction that is narrow, being not suitable for occupancy large-area construction place, it is applied widely.
It is respectively provided with positive stop strip and lateral baffle on the fixed frame of the utility model, determines when positive stop strip is easily installed Position, avoids fixed frame installation site too low, is not easy to pipeline and fixes;And lateral baffle then avoids fixed frame from moving left and right, The installation difficulty for greatly reducing fixed frame, improves construction efficiency.
Hanger setting in native character form structure, can at most be lifted 4 root canal roads simultaneously, substantially increase and apply by the utility model Work efficiency rate;And it is provided with bar in hanger two sides, it avoids pipeline from sliding, improves working security.Hanger passes through on jack It mentions, hangs rise and can according to need and be adjusted, application is more flexible.
The outdoor overhead lifting pipeline equipment of the utility model is described further with reference to the accompanying drawing.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the utility model outdoor overhead lifting pipeline equipment;
Fig. 2 is the main view of fixed frame;
Fig. 3 is the side view of fixed frame;
Fig. 4 is the main view of hanger;
Fig. 5 is the side view of hanger;
Fig. 6 is the utility model use state diagram.
Appended drawing reference:
1- pipeline stand;2- fixed frame;3- anchor ear;The side 4- is to baffle;5- positive stop strip;61- fixed plate;62- suspension is horizontal Bar;7- hanger;71- central upright stanchion;Cross-arm under 72-;The upper cross-arm of 73-;74- hanging hole;8- jack;9- bar;91- fixing sleeve; 92- limit plate.
Specific embodiment
As shown in Figure 1, the utility model outdoor overhead lifting pipeline equipment includes that the fixation on 1 top of pipeline stand is arranged in Frame 2, the hanger 7 of riser tubing, and the jack 8 of connection hanger 7 and 2 top of fixed frame.
As shown in Figures 2 and 3, the rectangular frame that fixed frame 2 is vertically arranged is welded by the enclosing of 12.6 channel steels, Long 1 direction of edge pipeline stand of rectangular frame is arranged, and lower part is fixedly connected by anchor ear 3 with 1 top of pipeline stand, anchor ear 3 Quantity is no less than 2, and upper and lower laid out in parallel is arranged on the one side of fixed frame 2, detachable with rectangular frame by bolt Fixed, round steel of the anchor ear 3 using diameter not less than 20mm is made;Divide below anchor ear 3, on the lateral wall of 2 liang of long sides of fixed frame It is not provided with lateral baffle 4, fixed frame 2 is avoided to move left and right, of length no more than 30mm is not less than the angle of 50mm for hem width Steel;The top of anchor ear 3, it is horizontally disposed have positive stop strip 5, positioning when being easily installed avoids 2 installation site of fixed frame too low, inconvenient It is fixed in pipeline;5 both ends of positive stop strip are fixedly connected with fixed frame 2, and the angle steel of 50mm, lateral baffle 4, limit are not less than for hem width Position item 5 is arranged on the same side of fixed frame 2 with anchor ear 3;2 top of fixed frame is provided with suspension arrangement, suspension dress It sets including suspended cross-beam 62 and fixed plate 61,61 quantity of fixed plate is 2, is symmetricly set on the outside of 2 liang of long sides of fixed frame On wall, one end is welded and fixed with fixed frame 2, and the other end extends horizontally outward, and extension and anchor ear 3 are separately positioned on fixed frame On two opposite sides of frame 2, suspended cross-beam 62 is provided between two extensions, fixed plate 61 is thickness not less than 20mm's Steel plate, suspended cross-beam 62 are the steel pipe that outer diameter is not less than 40mm.
Jack 8 is suspended in suspended cross-beam 62, and lifting end and hanger 7 mount.
As shown in Figure 4 and Figure 5, hanger 7 is native glyph framework, centrally disposed including the central upright stanchion 71 being vertically arranged The upper cross-arm 73 at 71 middle part of lower cross-arm 72 and centrally disposed upright bar of 71 bottom end of upright bar, the length of lower cross-arm 72 and upper cross-arm 73 It is identical, pipeline is placed respectively on lower cross-arm 72 and upper cross-arm 73;Hanging hole 74 is offered at the top of central upright stanchion 71, is used for and jack 8 lifting end mounting;The both ends of upper cross-arm 73 and lower cross-arm 72 are respectively arranged with fixing sleeve 91, and fixing sleeve 91 is not more than for internal diameter The round steel pipe of 40mm corresponds to up and down, is vertically arranged, in the fixing sleeve 91 on same vertical direction, is inserted with bar vertically 9, the height of bar 9 is not less than the height of central upright stanchion 71, and being horizontally disposed on the surrounding side wall of bar 9 has limit plate 92, limits The minimum side length of plate 92 is not less than the internal diameter of fixing sleeve 91, and limit plate 92 is at a distance from 9 bottom end of bar and 73 upper surface of upper cross-arm Consistent to the distance between lower 72 lower surface of cross-arm, hanger 7 is welded using 20# channel steel, and bar 9 is that outer diameter is not more than 32mm Round steel pipe.
As shown in fig. 6, the application method of the utility model outdoor overhead lifting pipeline equipment, specific as follows:
Step 1: according to detail design demand, the upper interval setting pipeline stand 1 along pipeline to be laid;
Step 2: fixed frame 2 is arranged in each pipeline stand 1;
Step 3: hanging jack 8 at the top of fixed frame 2;
Step 4: the interval of hanger 7 is folded on pipeline, and binding and fixing, the position of each hanger 7 and pipeline stand 1 It corresponds, each hanger 7 can at most lift 4 root canal roads simultaneously, and after pipeline fixes, bar 9 is inserted into the fixation of hanger 7 In set 91, pipeline is avoided to tumble;
Step 5: the lifting end of hanger 7 and jack 8 is mounted, several hangers 7 lift by crane simultaneously, pipeline are hung and rises to pipeline 1 top mounting location of stand;
Step 6: pipe laying;
Step 7: transferring hanger 7 after the completion of Pipe installing, jack 8 and fixed frame 2 are successively removed, is reused, into The installation of the next length of tubing of row.
Embodiment described above is only that preferred embodiments of the present invention are described, not practical to this Novel range is defined, and under the premise of not departing from the spirit of the design of the utility model, those of ordinary skill in the art are to this The various changes and improvements that the technical solution of utility model is made should all fall into the protection that the utility model claims book determines In range.

Claims (10)

1. outdoor overhead lifting pipeline equipment, it is characterised in that:Including being arranged in pipeline stand(1)The fixed frame on top(2), The hanger of riser tubing(7), and connection hanger(7)With fixed frame(2)The jack on top(8);
Fixed frame(2)The rectangular frame being vertically arranged, long edge pipeline stand(1)Direction setting, lower part passes through anchor ear(3) With pipeline stand(1)Top is fixedly connected, and top is provided with suspension arrangement;
Jack(8)It is suspended on suspension arrangement, lifting end and hanger(7)Mounting;
Hanger(7)For native glyph framework, including the central upright stanchion being vertically arranged(71), centrally disposed upright bar(71)Under bottom end Cross-arm(72)With centrally disposed upright bar(71)The upper cross-arm at middle part(73), central upright stanchion(71)Top offers hanging hole (74), upper cross-arm(73)With lower cross-arm(72)Both ends be respectively arranged with vertical bar(9).
2. outdoor overhead lifting pipeline equipment according to claim 1, it is characterised in that:The anchor ear(3)Quantity is many In 2, upper and lower laid out in parallel is arranged in fixed frame(2)One side on, pass through bolt and fixed frame(2)It is detachable solid It is fixed.
3. outdoor overhead lifting pipeline equipment according to claim 1, it is characterised in that:It further include lateral baffle(4), institute State lateral baffle(4)Quantity is 2, is separately positioned on anchor ear(3)Lower section, fixed frame(2)On the lateral wall of two long sides.
4. outdoor overhead lifting pipeline equipment according to claim 3, it is characterised in that:It further include positive stop strip(5), described Positive stop strip(5)It is horizontally set on anchor ear(3)Top, positive stop strip(5)Both ends and fixed frame(2)It is fixedly connected.
5. outdoor overhead lifting pipeline equipment according to claim 4, it is characterised in that:The lateral baffle(4), limit Item(5)And anchor ear(3)It is arranged in fixed frame(2)Same side on.
6. outdoor overhead lifting pipeline equipment according to claim 1, it is characterised in that:The suspension arrangement includes suspension Cross bar(62)And fixed plate(61), the fixed plate(61)Quantity is 2, is symmetricly set on fixed frame(2)Outside two long sides On side wall, one end and fixed frame(2)It is welded and fixed, the other end extends horizontally outward, extension and anchor ear(3)It is separately positioned on Fixed frame(2)On two opposite sides, suspended cross-beam is provided between two extensions(62).
7. outdoor overhead lifting pipeline equipment according to claim 1, it is characterised in that:The upper cross-arm(73)With lower cross Load(72)Both ends be respectively arranged with fixing sleeve(91), the fixing sleeve(91)It corresponds to, be vertically arranged, the bar up and down(9) It is vertically inserted into the fixing sleeve being located on same vertical direction(91)It is interior.
8. outdoor overhead lifting pipeline equipment according to claim 7, it is characterised in that:The fixing sleeve(91)For internal diameter Round steel pipe no more than 40mm.
9. outdoor overhead lifting pipeline equipment according to claim 1, it is characterised in that:The bar(9)Four sides Being horizontally disposed on wall has limit plate(92), limit plate(92)With bar(9)The distance of bottom end and upper cross-arm(73)Upper surface is under Cross-arm(72)The distance between lower surface is consistent.
10. outdoor overhead lifting pipeline equipment according to claim 1, it is characterised in that:The bar(9)Height not Less than central upright stanchion(71)Height.
CN201820473865.3U 2018-04-04 2018-04-04 Outdoor overhead lifting pipeline equipment Active CN208123629U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820473865.3U CN208123629U (en) 2018-04-04 2018-04-04 Outdoor overhead lifting pipeline equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820473865.3U CN208123629U (en) 2018-04-04 2018-04-04 Outdoor overhead lifting pipeline equipment

Publications (1)

Publication Number Publication Date
CN208123629U true CN208123629U (en) 2018-11-20

Family

ID=64193597

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820473865.3U Active CN208123629U (en) 2018-04-04 2018-04-04 Outdoor overhead lifting pipeline equipment

Country Status (1)

Country Link
CN (1) CN208123629U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114838205A (en) * 2021-02-02 2022-08-02 中国石油化工股份有限公司 Suspension type support tube plate

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114838205A (en) * 2021-02-02 2022-08-02 中国石油化工股份有限公司 Suspension type support tube plate

Similar Documents

Publication Publication Date Title
CN204551483U (en) A kind of to be used for " Two walls unite as one " ground-connecting-wall-Vierendeel girder Joint's connection fabrication
CN205639870U (en) A pipeline gallows is synthesized in heavy construction
CN103993745B (en) A kind of conversion beam integral hoisting device for rapid and hanging method thereof
CN212000657U (en) Long-span corrugated steel web horizontal positioning device
CN207143708U (en) Hoisting type foundation pit-crossing comprehensive steel trestle
CN201176703Y (en) Tripod for construction of hyperbola cooling tower cylinder
CN208123629U (en) Outdoor overhead lifting pipeline equipment
CN102733608B (en) Construction method for spray head layer of granulation tower
CN102926554B (en) Steel hanging seat formwork support and construction method thereof
CN204592560U (en) A kind of adjustable cable crane span structure support supported for curved wall
CN201284551Y (en) Suspension type simple platform for work high above ground
CN204126238U (en) Steel plate shear force wall operation platform and bracing frame thereof
CN206591525U (en) Pipe trench entirety punching block suspension device
CN206554500U (en) Steel structure concrete, which is poured, uses adjustable transverse support bar
CN210482377U (en) Assembled gallows of utility tunnel pipeline
CN204801846U (en) Civil engineering pipe fitting rack
CN215802536U (en) Novel hyperboloid curtain skeleton
CN207312995U (en) One kind self-control bridge-collision-avoidance wall form hanging device
CN207453461U (en) Supporting frame
CN105152039A (en) Super-long attachment device for slope building tower crane and slope building reverse-sequence construction method
CN202031308U (en) Inverted-hanging type scaffold
CN204960324U (en) Suspension type floor formwork support device
CN210066506U (en) Aerial work platform for erecting steel pipe pile support
CN204081433U (en) Steel structural roof liner profiled sheet construction Special-purpose hanger basket support