CN208122346U - A kind of prefabrication superimposed sheet positioning tool - Google Patents

A kind of prefabrication superimposed sheet positioning tool Download PDF

Info

Publication number
CN208122346U
CN208122346U CN201820226843.7U CN201820226843U CN208122346U CN 208122346 U CN208122346 U CN 208122346U CN 201820226843 U CN201820226843 U CN 201820226843U CN 208122346 U CN208122346 U CN 208122346U
Authority
CN
China
Prior art keywords
handrail
superimposed sheet
pedestal
prefabrication
positioning tool
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820226843.7U
Other languages
Chinese (zh)
Inventor
张亚运
刘庆成
马蒸
王挺
金铖丞
吕俊勇
李强
阚红火
施如霞
娄力栋
黄晓栋
常波
梅献忠
陈鹏
韦忠智
张江
王坚
程骥
郭士新
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Construction Engineering Group Co Ltd
Original Assignee
Zhejiang Construction Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Construction Engineering Group Co Ltd filed Critical Zhejiang Construction Engineering Group Co Ltd
Priority to CN201820226843.7U priority Critical patent/CN208122346U/en
Application granted granted Critical
Publication of CN208122346U publication Critical patent/CN208122346U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model relates to a kind of prefabrication superimposed sheets to position tool, including handrail and pedestal;The lower end surface of handrail and the lower end surface of pedestal are generally aligned in the same plane, and pedestal is vertical at the side of handrail;Gasket is fitted on the other side of handrail, the width of gasket is adapted with the length that superimposed sheet is shelved;Gasket is respectively arranged on the two sides of handrail with pedestal and is oppositely arranged.The positioning tool construction is simply ingenious, and by the way that the lower end surface of handrail and pedestal lower end surface to be disposed on the same plane, so that the positioning tool construction intensity is higher, stability is stronger, can effectively ensure that the service life of the positioning tool;By being fixed with beam form; control superimposed sheet shelving length; superimposed sheet is facilitated to lift; it avoids carrying out secondary agitate to superimposed sheet; the quality of the finished products such as effective protection superimposed sheet and template; the expenditure that cost of labor is saved while reducing labour person works' intensity is conducive to the positioning tool and promotes and apply in the market.

Description

A kind of prefabrication superimposed sheet positioning tool
Technical field
The utility model relates to technical field of building construction, specifically a kind of prefabrication superimposed sheet positions work Tool.
Background technique
Building industrialization is the inevitable direction of Building Trade in China sustainable development, is to raise labour productivity, improve engineering Quality and technological progress, the important channel for realizing construction industry transition and upgrade.Implementing building industrialization building technology can be greatly decreased Recruitment shortens the construction period, improves worker's operating condition, reduces labor intensity, meets the requirement of " four sections, one environmental protection ", is China's building Enterprise, building trade Transformation Development blessing road, flourish at home.
For the prefabricated components that assembled architecture mainly uses at this stage for superimposed sheet, precast stair etc., beam and column component is general For cast-in-place structural, according to national building standard atlas 15G366-1《Truss bars concrete folding plate(60mm thickness bottom plate)》Node Tectonic sieving, superimposed sheet are 10mm in the shelving length of intermediate support and collateral seat.Currently, the form of construction work routinely taken is to hold Weight frame sets up completion, carries out superimposed sheet lifting after the completion of curb girder mould is fixed.
But in existing assembled architecture lifting operation, shelving width when often encountering superimposed sheet lifting can not Primary to guarantee, primary lifting also needs to reuse crowbar after the completion to be agitated, and is also unfavorable for mould while increasing lifting workload The finished product protection of plate and superimposed sheet.
Summary of the invention
The utility model is to provide a kind of prefabrication superimposed sheet to overcome above-mentioned defect in the prior art Positioning tool, the positioning tool construction is simply ingenious, by fixing control superimposed sheet shelving length with beam form, superimposed sheet is facilitated to hang Dress, avoid it is secondary agitate, effective protection finished product saves artificial, is conducive to the positioning tool and promotes and apply in the market.
In order to achieve the above-mentioned object of the invention, the utility model uses following technical scheme:A kind of prefabrication is folded Plywood positions tool, including handrail and pedestal;The lower end surface of the handrail and the lower end surface of the pedestal are generally aligned in the same plane, institute State the side that pedestal is vertical at the handrail;Gasket, the width and superimposed sheet of gasket are fitted on the other side of the handrail The length shelved is adapted;The gasket is respectively arranged on the two sides of the handrail with the pedestal and is oppositely arranged.
As a kind of preferred embodiment of the utility model, the gasket with a thickness of the iron plate of 10mm by being made.
As a kind of preferred embodiment of the utility model, the lower end surface of the gasket, handrail and pedestal is respectively positioned on same flat On face.
As a kind of preferred embodiment of the utility model, the handrail is rhs-structure.
As a kind of preferred embodiment of the utility model, the length of the handrail is 750mm~850mm.
As a kind of preferred embodiment of the utility model, the length of the handrail is 800mm.
As a kind of preferred embodiment of the utility model, the pedestal is rhs-structure.
As a kind of preferred embodiment of the utility model, the length of the pedestal is 100mm~200mm.
As a kind of preferred embodiment of the utility model, the length of the pedestal is 150mm.
As a kind of preferred embodiment of the utility model, the contact surface of the handrail and pedestal is the inclined-plane in 45° angle.
Compared with prior art, the beneficial effects of the utility model are as follows:One of the utility model is prefabricated assembled It builds superimposed sheet and positions tool, the positioning tool construction is simply ingenious, by the way that the lower end surface of handrail and pedestal lower end surface to be arranged In the same plane, so that the positioning tool construction intensity is higher, stability is stronger, can effectively ensure that making for the positioning tool Use the service life;By being fixed with beam form, superimposed sheet shelving length is controlled, superimposed sheet is facilitated to lift, avoids carrying out superimposed sheet secondary It agitates, the quality of the finished products such as effective protection superimposed sheet and template, is saved while reducing labour person works' intensity artificial The expenditure of cost is conducive to the positioning tool and promotes and apply in the market.
Detailed description of the invention
Fig. 1 is the main view of prefabrication superimposed sheet positioning tool in this implementation;
Fig. 2 is the perspective view of prefabrication superimposed sheet positioning tool in this implementation;
Fig. 3 is the use state diagram of prefabrication superimposed sheet positioning tool in this implementation;
Fig. 4 is the structural schematic diagram of handrail in prefabrication superimposed sheet positioning tool in this implementation;
Fig. 5 is the structural schematic diagram of pedestal in prefabrication superimposed sheet positioning tool in this implementation.
Appended drawing reference:1, handrail;2, pedestal;3, gasket.
Specific embodiment
It elaborates with reference to the accompanying drawing to the embodiment of the present invention.
Embodiment:As shown in Fig. 1 to 5, a kind of prefabrication superimposed sheet positioning tool, which includes helping The height of hand 1 and pedestal 2, handrail 1 is higher than the height of pedestal 2, and in the process, handrail 1 plays fixture, will overlap board In 1 side of handrail, on the one hand pedestal 2 and 1 right angle setting of handrail avoid the positioning tool location from tilting, influence putting for superimposed sheet It sets;On the other hand it can effectively ensure that the service life of the positioning tool.
In order to guarantee the structural strength of pedestal 2 Yu 1 junction of handrail, the contact surface that pedestal 2 can be in contact with handrail 1 is equal It is arranged to the inclined-plane of 45° angle, reduces the probability of pedestal 2 and the fracture of 1 junction of handrail, pedestal 2 and handrail 1 can be also integrally formed Setting, so that the positioning tooling strength is high, service life is long.
The other side of handrail 1, which is equipped with, facilitates superimposed sheet once to shelve, and avoids the gasket 3 for repeatedly agitating adjustment, and gasket 3 pastes It closes on the side of handrail 1, is oppositely arranged with pedestal 2, is i.e. gasket 3 and pedestal 2 two sides that are separately mounted to handrail 1, gasket 3 Width is identical as the length that superimposed sheet needs to shelve, and example superimposed sheet is 10mm in the shelving length of intermediate support and collateral seat, then Gasket 3 with a thickness of 10mm.
Gasket 3 is made of iron plate, simple and practical in structure, and cost is relatively low, convenient for the positioning tool in building engineering field It promotes and applies.
Superimposed sheet in the prior art is difficult to precisely primary lifting molding, needs repeatedly to agitate adjustment, in the process, right Superimposed sheet and template can all cause largely to damage, and reduce the service life of superimposed sheet and template, in the present embodiment Width gasket 3 compatible with superimposed sheet shelving length is provided in positioning tool, when placement, superimposed sheet directly can be placed once On gasket 3, without carrying out secondary to superimposed sheet or template or repeatedly agitating, while raising construction efficiency, Neng Gouyou Effect guarantees the yield rate of superimposed sheet.
The lower end surface of handrail 1 and the lower end surface of pedestal 2 are in the same plane, enhance the positioning tool in installation process In stability.
In order to further enhance the stability of positioning tool in use, the probability to fall is reduced, gasket 3 is helped The lower end surface of hand 1 and pedestal 2 is respectively positioned on same plane.
The simple, rhs-structure easy to use for structure of handrail 1 is steady in placement process in order to which superimposed sheet is effectively ensured It is qualitative, avoid its shaking amplitude in placement process excessive, the length of handrail 1 is 750mm~850mm, is intercepted in the present embodiment Length is 800mm, and specification is the square tube of 30*30mm as handrail 1.
Pedestal 2 can also be rhs-structure, in order to guarantee the stability of positioning tool during the installation process, increase positioning work Have the contact area between other fixing pieces, increasing friction force, the length of pedestal 2 is 100mm~200mm, in the present embodiment Intercepted length is 150mm, and specification is the square tube of 30*30mm as pedestal 2.
As shown in figure 3, in lifting component work progress, before superimposed sheet lifting, first by the positioning tool in the present embodiment It is placed on patch beam among beam to shelve, then by construction personnel that pedestal 2 is fixed, handrail 1 is pasted when prefabricated board is shelved and is slowly fallen, it is real Now it is accurately positioned.
Prefabrication superimposed sheet in the present embodiment positions tool, and the positioning tool construction is simply ingenious, passes through The lower end surface of handrail 1 and 2 lower end surface of pedestal are disposed on the same plane, so that the positioning tool construction intensity is higher, stablized Property is stronger, can effectively ensure that the service life of the positioning tool;By fixing with beam form, superimposed sheet shelving length, side are controlled Just superimposed sheet lift, avoid to superimposed sheet carry out it is secondary agitate, the quality of the finished products such as effective protection superimposed sheet and template reduces The expenditure that cost of labor is saved while labour person works' intensity is conducive to the positioning tool and promotes and answer in the market With.
The foregoing description of the disclosed embodiments enables those skilled in the art to implement or use the present invention. Various modifications to these embodiments will be readily apparent to those skilled in the art, as defined herein General Principle can be realized in other embodiments without departing from the spirit or scope of the present invention;Therefore, of the invention It is not intended to be limited to the embodiments shown herein, and is to fit to and the principles and novel features disclosed herein phase one The widest scope of cause.
Although appended drawing reference in figure is used more herein:1, handrail;2, pedestal;3, the terms such as gasket, but do not arrange A possibility that except other terms are used.The use of these items is only for be more convenient to describe and explain the sheet of the utility model Matter;It is contrary to the spirit of the present invention to interpret them as any one of the additional limitations.

Claims (10)

1. a kind of prefabrication superimposed sheet positions tool, it is characterised in that:Including handrail(1)And pedestal(2);It is described to help Hand(1)Lower end surface and the pedestal(2)Lower end surface be generally aligned in the same plane, the pedestal(2)It is vertical at the handrail(1) Side;The handrail(1)The other side on be fitted with gasket(3), gasket(3)The length shelved with superimposed sheet of width mutually fit Match;The gasket(3)With the pedestal(2)It is respectively arranged on the handrail(1)Two sides and be oppositely arranged.
2. a kind of prefabrication superimposed sheet according to claim 1 positions tool, it is characterised in that:The gasket (3)By being made with a thickness of the iron plate of 10mm.
3. a kind of prefabrication superimposed sheet according to claim 1 or 2 positions tool, it is characterised in that:It is described Gasket(3), handrail(1)And pedestal(2)Lower end surface be respectively positioned on same plane.
4. a kind of prefabrication superimposed sheet according to claim 1 positions tool, it is characterised in that:The handrail (1)For rhs-structure.
5. a kind of prefabrication superimposed sheet according to claim 4 positions tool, it is characterised in that:The handrail (1)Length be 750mm~850mm.
6. a kind of prefabrication superimposed sheet according to claim 5 positions tool, it is characterised in that:The handrail (1)Length be 800mm.
7. a kind of prefabrication superimposed sheet according to claim 1 or 4 positions tool, it is characterised in that:It is described Pedestal(2)For rhs-structure.
8. a kind of prefabrication superimposed sheet according to claim 7 positions tool, it is characterised in that:The pedestal (2)Length be 100mm~200mm.
9. according to a kind of prefabrication superimposed sheet positioning tool according to any one of claims 8, it is characterised in that:The pedestal (2)Length be 150mm.
10. according to a kind of prefabrication superimposed sheet positioning tool described in claim 1, it is characterised in that:The handrail (1)With pedestal(2)Contact surface be inclined-plane in 45° angle.
CN201820226843.7U 2018-02-08 2018-02-08 A kind of prefabrication superimposed sheet positioning tool Active CN208122346U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820226843.7U CN208122346U (en) 2018-02-08 2018-02-08 A kind of prefabrication superimposed sheet positioning tool

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820226843.7U CN208122346U (en) 2018-02-08 2018-02-08 A kind of prefabrication superimposed sheet positioning tool

Publications (1)

Publication Number Publication Date
CN208122346U true CN208122346U (en) 2018-11-20

Family

ID=64207310

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820226843.7U Active CN208122346U (en) 2018-02-08 2018-02-08 A kind of prefabrication superimposed sheet positioning tool

Country Status (1)

Country Link
CN (1) CN208122346U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109518952A (en) * 2018-12-28 2019-03-26 云南建投第二建设有限公司 One kind is for the support of assembled architecture primary and secondary beam nodes, positioning, plate device
CN112064849A (en) * 2020-04-22 2020-12-11 扬州市润泽建设工程有限公司 Construction method for accurately hoisting and preventing slurry leakage of assembled laminated slab

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109518952A (en) * 2018-12-28 2019-03-26 云南建投第二建设有限公司 One kind is for the support of assembled architecture primary and secondary beam nodes, positioning, plate device
CN109518952B (en) * 2018-12-28 2023-10-20 云南建投第二建设有限公司 Be used for assembled building primary and secondary beam node to support, location, template device
CN112064849A (en) * 2020-04-22 2020-12-11 扬州市润泽建设工程有限公司 Construction method for accurately hoisting and preventing slurry leakage of assembled laminated slab
CN112064849B (en) * 2020-04-22 2022-04-29 扬州市润泽建设工程有限公司 Construction method for accurately hoisting and preventing slurry leakage of assembled laminated slab

Similar Documents

Publication Publication Date Title
CN106869489A (en) Super High Core Walls Structure level and vertical synchronous construction top module system and construction method
CN208122346U (en) A kind of prefabrication superimposed sheet positioning tool
CN206581626U (en) A kind of adjustable assembled supporting construction
CN105735625A (en) Side form supporting system for terrace construction
CN107100283A (en) A kind of assembled wallboard connector and its installation method
CN205637522U (en) A side form support system for terrace construction
CN204899108U (en) Node structure is hung futilely to marble
CN209741895U (en) Connection structure of assembled elevator steel construction and base
CN205259593U (en) Whole spelling formula template of cast -in -place floor and support system
CN201730350U (en) Adjustable assembly type steel structure temporary structure support for structure post-cast strip
CN204687050U (en) A kind of mould of precast concrete rectangular beam
CN208197158U (en) A kind of reinforcing bar tire suspender of precast segment box beam
CN204960324U (en) Suspension type floor formwork support device
CN210659296U (en) Pouring funnel
CN207211467U (en) A kind of combined type floor support plate constructing structure for steel building
CN207048326U (en) A kind of suspension type platform for equipment interlayer
CN217175307U (en) Non-dismantling die assembly type composite floor slab
CN204979710U (en) Frame is put in wallboard exhibition
CN219773603U (en) Large-bay large-depth template supporting device
CN213710403U (en) Detachable bottom plate support
CN213710402U (en) A bottom plate support for steel bar is quilted and is put up building carrier plate
CN205464059U (en) A equipment for prefabricating equalizer ring reinforcing bar
CN215631538U (en) Detachable adjustable hanging basket hanging piece device
CN213710401U (en) Can dismantle bottom plate support of steel bar quilting frame building carrier plate
CN111042519A (en) Early-dismantling system for building with beam and plate structure containing floor slab formwork

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant