CN208122167U - Operating room top wall panel and operation room wallboard system - Google Patents

Operating room top wall panel and operation room wallboard system Download PDF

Info

Publication number
CN208122167U
CN208122167U CN201820062043.6U CN201820062043U CN208122167U CN 208122167 U CN208122167 U CN 208122167U CN 201820062043 U CN201820062043 U CN 201820062043U CN 208122167 U CN208122167 U CN 208122167U
Authority
CN
China
Prior art keywords
wall panel
top wall
slot
guide rail
sliding block
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820062043.6U
Other languages
Chinese (zh)
Inventor
张国卫
陆丹
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHANGHAI FENGSHEN ENVIRONMENTAL EQUIPMENT ENGINEERING Co Ltd
Original Assignee
SHANGHAI FENGSHEN ENVIRONMENTAL EQUIPMENT ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHANGHAI FENGSHEN ENVIRONMENTAL EQUIPMENT ENGINEERING Co Ltd filed Critical SHANGHAI FENGSHEN ENVIRONMENTAL EQUIPMENT ENGINEERING Co Ltd
Priority to CN201820062043.6U priority Critical patent/CN208122167U/en
Application granted granted Critical
Publication of CN208122167U publication Critical patent/CN208122167U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Finishing Walls (AREA)

Abstract

The utility model provides operating room top wall panel and operation room wallboard system, operating room top wall panel include:Top wall panel ontology is plate, and buckle is arranged in around top wall panel ontology, and keel are fixed on the wall, and is provided with and the corresponding slot in position that buckles in the front of keel, wherein buckle includes:Two connectors, front end are trapezoidal card, and end is fixedly connected on welding piece, there is scheduled distance between two connectors, U-shaped structure, card slot is collectively formed with welding piece, behind trapezoidal card, card slot is stuck in the edge of slot, limit film, behind card slot, it when card slot is stuck in the edge of slot, is connected on slot, limitation buckle moves forward, welding piece is welded on the periphery of top wall panel ontology.Quick installation exercise may be implemented in entire operation room wallboard system.

Description

Operating room top wall panel and operation room wallboard system
Technical field
The utility model relates to a kind of operating room top wall panel, the utility model further relates to operation room wallboard system, belongs to Interior decoration field.
Background technique
The mounting means of traditional wall cornice sheathing be scene with screw with bore mode install it is fixed, Major Difficulties be behaviour It is big to make difficulty, live borehole accuracy is not high, and height adjustment installation is not time-consuming and laborious for flatness.
Utility model content
The purpose of this utility model is to provide a kind of operating room top wall panel and operation room wallboard systems, on solving State problem.
The utility model uses following technical solution:
The utility model provides a kind of operating room top wall panel, which is characterized in that including:Top wall panel ontology is plate, Buckle, is arranged in around top wall panel ontology, and keel are fixed on the wall, and is provided with the position with buckle in the front of keel Corresponding slot, wherein buckle includes:Two connectors, front end are trapezoidal card, and end is fixedly connected on welding piece On, there is scheduled distance between two connectors, U-shaped structure, card slot, positioned at trapezoidal card is collectively formed with welding piece Below, card slot is stuck in the edge of slot, and limit film, when card slot is stuck in the edge of slot, is connected to slotting behind card slot On slot, limitation buckle moves forward, and welding piece is welded on the periphery of top wall panel ontology.
Further, the operating room top wall panel of the utility model, also has the feature that:Wherein, the two of trapezoidal card It is in 90 degree of angles between a inclined-plane.
Further, the operating room top wall panel of the utility model, also has the feature that:Wherein, the width of limit film Greater than the width of trapezoidal card.
The utility model also provides a kind of operation room wallboard system, which is characterized in that including:Above-mentioned operating room upper walls Plate and operating room bottom wall panel, operating room bottom wall panel include:Bottom wall panel ontology is arranged in parallel with top wall panel ontology, Bottom support frame, support frame and multiple guide rails being disposed longitudinally on support frame with rectangle;First sliding block, it is vertical to connect In the lower part of bottom wall panel ontology, the first sliding block matches with guide rail, and the first sliding block is slided along guide rail, has on the first sliding block recessed Slot;Collision bead is arranged in guide rail, matches with the groove location in the first sliding block and block in a groove.
Further, the operation room wallboard system of the utility model, also has the feature that:Also tool is sliding there are two second Block is vertically connected on the left and right sides on the top of bottom wall panel ontology.
Further, the operation room wallboard system of the utility model, also has the feature that:Wherein, the shape of guide rail is It is provided with the rectangle frame of strip gab on one side, the cross sectional shape of the first sliding block is "convex" shaped, is matched with the shape of guide rail.
Further, the operation room wallboard system of the utility model, also has the feature that:Wherein, bottom support frame Outside is skirting board, and one end of guide rail is fixedly connected with skirting board.
Further, the operation room wallboard system of the utility model, also has the feature that:Wherein, guide rail and frame it Between to be detachably connected.
Further, the operation room wallboard system of the utility model, also has the feature that:Wherein, the number of the first sliding block Amount is two, is connected to the left and right sides of bottom wall panel body lower part.
Further, the operation room wallboard system of the utility model, also has the feature that, further includes:Back frame.If It sets behind bottom support frame 12 and upwardly extends, the upper end of the back frame is fixedly connected with the keel.
The beneficial effect of utility model
The operating room top wall panel and operation room wallboard system of the utility model, as long as being buckled above wallboard when installation Then slot on alignment keel slides into slot makes buckle mutually be engaged fixation with slot.Installation accuracy is of less demanding, It is time saving and energy saving, the live wallboard installation exercise time is reduced, reduces the consolidation service time at scene, cost can be substantially reduced.
Further, the operation room wallboard system of the utility model, after keel and bottom support frame are set, bottom wall panel By the connection type of sliding block and guide rail, quickly wallboard can be replaced, so that the drop in later maintenance also as far as possible The low influence to indoor environment.
Therefore, quick installation exercise may be implemented in entire operation room wallboard system.
Detailed description of the invention
Fig. 1 is the installation relation schematic diagram of wallboard body and support frame;
Fig. 2 is the schematic diagram that top wall panel is aligned with keel;
Fig. 3 is the structural schematic diagram after top wall panel and keel fastening;
Fig. 4 is buckle schematic diagram corresponding with slot;
Fig. 5 is the schematic diagram after buckle and slot engaging;
Fig. 6 is the partial enlarged view at guide rail and sliding block;
Fig. 7 is the sectional view of guide rail;
Fig. 8 is the sectional view of sliding block.
Specific embodiment
Illustrate specific embodiment of the present utility model below in conjunction with attached drawing.
As shown in Figure 1,
Operation room wallboard system includes:Operating room top wall panel and operating room bottom wall panel.
Operating room top wall panel includes:Top wall panel ontology 23, buckle 30 and keel 24.
Top wall panel ontology 23 is plate.
As shown in figure 4, buckle 30, is arranged in around top wall panel ontology 23.
Keel 24, are fixed on the wall, and are provided with slot 31 corresponding with the position of buckle 30 in the front of keel 24.
Buckling 30 includes:Two connectors, front end are trapezoidal card 26, and end is fixedly connected on welding piece 29, There is scheduled distance between two connectors, U-shaped structure is collectively formed with welding piece 29.In the present embodiment, two Scheduled distance between connector is set as 8mm, this distance, which can according to need, in other embodiments is adjusted It is whole.
Card slot 27, behind trapezoidal card 26, card slot 27 is stuck in the edge of slot 31.
Limit film 28, when card slot 27 is stuck in the edge of slot 31, is connected on slot 31 behind card slot 27, Limitation buckle 30 moves forward, and welding piece 29 is welded on the periphery of top wall panel ontology 23.
It is in 90 degree of angles between two inclined-planes of trapezoidal card 26.Trapezoidal card 26 be one similar to right-angled trapezium structure, Outwardly, inclination is face-up at trapezoidal upper bottom.The width of limit film 28 is greater than the width of trapezoidal card 26.Here width refers to Fig. 5 Width on longitudinal direction under shown state.
As shown in figures 1 to 6, operating room bottom wall panel includes:Wallboard body 11, bottom support frame 12, guide rail 13, first Sliding block 14, collision bead 15.
Socket 17 and voltage electricity display screen 18 are provided in wallboard body 11.
Bottom support frame 12, support frame and multiple guide rails 13 being disposed longitudinally on support frame with rectangle.Bottom The outside of support frame 12 is skirting board 16.One end of guide rail 13 is fixedly connected with skirting board, and the other end is connected to behind support frame Back frame 22 on.Back frame 22 is arranged in behind bottom support frame 12 and upwardly extends, the upper end of back frame 22 It is fixedly connected with keel.
As shown in fig. 6, the first sliding block 14, is vertically connected on the lower part of wallboard body 11, the first sliding block 14 and 13 phase of guide rail Matching, the first sliding block 14 are slided along guide rail 13, have groove (not shown) on the first sliding block 14.The quantity of first sliding block 14 It is two, is connected to the left and right sides of 11 lower part of wallboard body.
Collision bead 15 is arranged in guide rail 13, matches with the groove location in the first sliding block 14 and block in a groove.Installation When wallboard body, when sliding block is pushed inwardly into bottom along guide rail, the card of collision bead 15 in a groove fixes wallboard body.
In other embodiments, two the second sliding blocks can also be set again, be vertically connected on the upper of wallboard body 11 The left and right sides in portion.To provide more firm installation effect.
As shown in Figure 6 and Figure 7, the shape of guide rail 13 is the rectangle frame for being provided with strip gab on one side, the external ruler of guide rail 13 It is very little to be:25mm×18.5mm×560mm.The wall thickness d of guide rail 13 is 2mm.H1=25mm in figure, h2=18.5mm.560mm is to lead The length of rail 13.H3=9.25, then the width of the strip gab on guide rail 13 is 6.5mm.
As shown in figure 8, the cross sectional shape of the first sliding block 14 is "convex" shaped, match with the shape of guide rail 13.First is sliding The external dimensions of block is:16.5mm×21mm×240mm.H4=21mm in Fig. 8, h5=13.7mm, h6=6.5m, h7= 16.5mm.It can be seen that the width of 14 upper ledge of the first sliding block is 6.5mm, it is embedded just below the strip gab that width is similarly 6.5mm In.
It is detachably connected between guide rail 13 and frame by bolt, so that when the width of wallboard changes, Huo Zhechong When new design wallboard, it can match with new wallboard body as long as the installation site for adjusting each guide rail 13.
This product is using standardized production, and all installation hole locations are all to have millwork to make, tolerance very little side Just in-site installation.Guide rail is fixed between skirting board when installation, and sliding block is fixed on behind wallboard, solid with standard sections punching screw It is fixed.Installation wallboard injects sliding block in guide rail and is pushed to bottom, and inside has collision bead to fix.It can be with using the installation that guide rail carries out wallboard It allows between operation room wallboard and arbitrarily exchanges, install also more convenient.
This product is primarily adapted for use in hospital, medical electronics, medical workshop, aerospace, biology laboratory, food processing life It produces workshop and other wallboards for needing particular surroundings is installed, due to using standard modular production method, substantially reduce system It makes the period, simple installation is quick.

Claims (10)

1. a kind of operating room top wall panel, which is characterized in that including:
Top wall panel ontology is plate,
Buckle, is arranged in around top wall panel ontology,
Keel are fixed on the wall, and are provided with slot corresponding with the position of the buckle in the front of keel,
Wherein, the buckle includes:
Two connectors, front end are trapezoidal card, and end is fixedly connected on welding piece, are had between two connectors U-shaped structure is collectively formed with welding piece in scheduled distance,
Card slot, behind the trapezoidal card, the card slot is stuck in the edge of the slot,
Limit film, when card slot is stuck in the edge of the slot, abuts on the slot, limit behind the card slot Fabrication button moves forward,
Welding piece is welded on the periphery of the top wall panel ontology.
2. operating room top wall panel as described in claim 1, it is characterised in that:
It wherein, is in 90 degree of angles between two inclined-planes of the trapezoidal card.
3. operating room top wall panel as described in claim 1, it is characterised in that:
Wherein, the width of the limit film is greater than the width of the trapezoidal card.
4. a kind of operation room wallboard system, which is characterized in that including:
Operating room top wall panel and operating room bottom wall panel as described in claim 1,
The operating room bottom wall panel includes:
Bottom wall panel ontology is arranged in parallel with the top wall panel ontology,
Bottom support frame, support frame and multiple guide rails being disposed longitudinally on the support frame with rectangle;
First sliding block is vertically connected on the lower part of the bottom wall panel ontology, and first sliding block matches with the guide rail, institute It states the first sliding block to slide along the guide rail, there is groove on first sliding block;
Collision bead is arranged in the guide rail, matches with the groove location in the first sliding block and be stuck in the groove.
5. operation room wallboard system as claimed in claim 4, it is characterised in that:
Also there are two the second sliding blocks for tool, are vertically connected on the left and right sides on the top of the bottom wall panel ontology.
6. operation room wallboard system as claimed in claim 4, it is characterised in that:
Wherein, the shape of the guide rail is the rectangle frame for being provided with strip gab on one side, and the cross sectional shape of first sliding block is "convex" shaped matches with the shape of the guide rail.
7. operation room wallboard system as claimed in claim 4, it is characterised in that:
Wherein, the outside of the bottom support frame is skirting board, and one end of the guide rail is fixedly connected with the skirting board.
8. operation room wallboard system as claimed in claim 4, it is characterised in that:
It wherein, is to be detachably connected between the guide rail and the support frame.
9. operation room wallboard system as claimed in claim 4, it is characterised in that:
Wherein, the quantity of first sliding block is two, is connected to the left and right sides of bottom wall panel body lower part.
10. operation room wallboard system as claimed in claim 4, which is characterized in that further include:
Back frame is arranged in behind the support frame of bottom and upwardly extends, and the upper end of the back frame and the keel are solid Fixed connection.
CN201820062043.6U 2018-01-15 2018-01-15 Operating room top wall panel and operation room wallboard system Active CN208122167U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820062043.6U CN208122167U (en) 2018-01-15 2018-01-15 Operating room top wall panel and operation room wallboard system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820062043.6U CN208122167U (en) 2018-01-15 2018-01-15 Operating room top wall panel and operation room wallboard system

Publications (1)

Publication Number Publication Date
CN208122167U true CN208122167U (en) 2018-11-20

Family

ID=64205944

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820062043.6U Active CN208122167U (en) 2018-01-15 2018-01-15 Operating room top wall panel and operation room wallboard system

Country Status (1)

Country Link
CN (1) CN208122167U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112627329A (en) * 2020-12-21 2021-04-09 中国电建集团华东勘测设计研究院有限公司 Quick-construction clamping pin type anticorrosion wood mounting method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112627329A (en) * 2020-12-21 2021-04-09 中国电建集团华东勘测设计研究院有限公司 Quick-construction clamping pin type anticorrosion wood mounting method

Similar Documents

Publication Publication Date Title
CN208122167U (en) Operating room top wall panel and operation room wallboard system
CN104748491A (en) Refrigeration equipment and door structure thereof
CN104197616B (en) The refrigerator door of band aobvious control plate embedded box installing mechanism and refrigerator
CN217563597U (en) Corner connecting piece for photovoltaic steel frame, photovoltaic frame and photovoltaic module
CN208127535U (en) The DC/DC module hot-plug construction recycled for retired battery
CN201999471U (en) Part conveying device
CN211622635U (en) Wall combination template device
CN212405804U (en) Stone toilet wall assembly
CN210696715U (en) Skirting structure
CN209574024U (en) A kind of mounting structure of sparerib shelf
CN203618243U (en) Chassis reinforcing airborne electronic module
CN207632274U (en) Elevator calling box
CN106906931B (en) Plug-in type hidden frame glass curtain wall
CN202868921U (en) Air-conditioner
CN220928480U (en) Electric box decoration component
CN208379846U (en) A kind of energy-saving light-weight wallboard
CN203398439U (en) Multi-slot card insertion guiding device, circuit board and electric device
CN217907284U (en) Aluminum alloy curtain rail
CN201433647Y (en) Quick install door and window frame
CN220814646U (en) Wallboard external corner mounting structure
CN210805031U (en) A frame structure and mould strip display screen for mould strip display screen
CN207878793U (en) Wallboard socket integrated apparatus
CN113882667B (en) Combined mechanism of aluminum die and PC (polycarbonate) wallboard and mounting method
CN109667378A (en) A kind of lightgage steel joist fast joint structure
CN213979454U (en) Quick mounting structure of horizontal decoration wing

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant