CN208105313U - A kind of device for the overturning of prefabricated underground pipe gallery framework of steel reinforcement - Google Patents

A kind of device for the overturning of prefabricated underground pipe gallery framework of steel reinforcement Download PDF

Info

Publication number
CN208105313U
CN208105313U CN201820441484.7U CN201820441484U CN208105313U CN 208105313 U CN208105313 U CN 208105313U CN 201820441484 U CN201820441484 U CN 201820441484U CN 208105313 U CN208105313 U CN 208105313U
Authority
CN
China
Prior art keywords
side frame
chassis
overturning
steel reinforcement
support
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820441484.7U
Other languages
Chinese (zh)
Inventor
刘营
匡志强
王建军
邓李坚
刘卓
李彩霞
苏湘华
蒋严波
邵羽
林广泰
杨威
张敏
邓李航
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangxi Road and Bridge Engineering Group Co Ltd
Original Assignee
Guangxi Road and Bridge Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangxi Road and Bridge Engineering Group Co Ltd filed Critical Guangxi Road and Bridge Engineering Group Co Ltd
Priority to CN201820441484.7U priority Critical patent/CN208105313U/en
Application granted granted Critical
Publication of CN208105313U publication Critical patent/CN208105313U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model discloses a kind of devices for the overturning of prefabricated underground pipe gallery framework of steel reinforcement, including support and rollover stand, the rollover stand hinge connects the support, the rollover stand includes chassis, the first side frame, the second side frame and third side frame, the lower end of first side frame is fixedly connected with the chassis in one end close to the support, the chassis is fixed in the lower end of second side frame, the chassis is equipped with overturning lifting lug far from one end of the support, and the upper end of first side frame, which is equipped with, resets lifting lug.It is horizontal for hooking overturning lifting lug to be placed on framework of steel reinforcement in rollover stand by vertical tilting with gantry crane, it can rapidly, continuously realize the overturning of multiple frameworks of steel reinforcement, structure is simple, it uses flexible and convenient, so that operation more procedure, streamlined, production efficiency is improved, and to the injury very little of framework of steel reinforcement during overturning.

Description

A kind of device for the overturning of prefabricated underground pipe gallery framework of steel reinforcement
Technical field
The utility model relates to piping lane technical field of construction, especially a kind of to be used for prefabricated underground pipe gallery framework of steel reinforcement The device of overturning.
Background technique
Current most of piping lanes are located at arterial street, and vehicle flowrate is big, the density of population is high, Nearby Structure is various etc., and need Take the measures such as enclosing road closure, substantially increase construction cost, at the same need to put into a large amount of fund and energy go the progress of grabbing and The problems such as construction safety, traffic congestion caused by enclosing is closed a road to traffic, brings huge pressure to Urban Operation.To shorten work of constructing Phase, underground pipe gallery framework of steel reinforcement can use prefabricated mode, during prefabricated framework of steel reinforcement, for convenience of operating, improve The binding efficiency of framework of steel reinforcement, prefabricated framework of steel reinforcement are all made of vertical binding, and vertical framework of steel reinforcement will lead to casting and come out Concrete structure upper surface out-of-flatness, be unable to satisfy requirement, thus tie with reinforcing bar completion after need to be turned into It is horizontal, then it is poured concrete.But by vertical framework of steel reinforcement overturn for horizontal framework of steel reinforcement it is more difficult, and overturn It is easy to damage framework of steel reinforcement in the process.
Utility model content
In view of the above-mentioned problems, providing a kind of device for the overturning of prefabricated underground pipe gallery framework of steel reinforcement, steel is solved Tendons skeleton is horizontal more difficulty by vertical tilting, and switching process is easy the problem of damaging to framework of steel reinforcement.
In order to achieve the above objectives, technical solution used by the utility model is:One kind being used for prefabricated underground pipe gallery The device of framework of steel reinforcement overturning, including
Support, the support are fixed on ground;And
Rollover stand, the rollover stand include chassis, the first side frame, the second side frame and third side frame, the chassis and first Side frame is rectangle, and one end hinge of the chassis connects the support, and the lower end of first side frame is fixedly connected on institute Chassis is stated close to the upper surface of one end of the support, the upper surface of the chassis, institute are fixed in the lower end of second side frame It states the second side frame to be fixedly connected close to one end of the support with one end of first side frame, the lower end of the third side frame is solid Due to the chassis, the third side frame close to one end of the support and first side frame far from second side frame one End is fixedly connected, and the chassis is equipped with overturning lifting lug far from one end of the support, and the upper end of first side frame, which is equipped with, to be resetted Lifting lug.
Further, the lower end surface of the one end of the chassis far from the support is fixedly connected with for keeping the chassis Horizontal bottom supporting block.Keep chassis level be convenient for by framework of steel reinforcement lifting get on, and by framework of steel reinforcement lifting get on when pair The injury of framework of steel reinforcement is less.
Further, the lateral surface of the upper end of first side frame is fixedly connected with for described first after being held turned over The collateral bracer of side frame level.Shaking of framework of steel reinforcement during overturning is reduced, to reduce the injury to framework of steel reinforcement.
Further, second side frame is identical with third side cage structure, and second side frame and third side frame hang down respectively It directly is respectively perpendicular to the chassis in first side frame, second side frame and third side frame, second side frame is by one The upper end of first side frame is fixed in brace and several reinforcing bars composition, one end of the brace, the brace it is another The one end of the chassis far from the support is fixed at end, and the chassis, the reinforcing bar are fixed in the lower end of the reinforcing bar Upper end be fixed on the middle part of the brace.Brace and reinforcing bar position the framework of steel reinforcement of two sides enough, and keep the second side frame It is secured with third side frame, and reduced the contact of the second side frame and third side frame with framework of steel reinforcement to the greatest extent, to reduce the The injury of two side frames and third side frame to framework of steel reinforcement.
Further, the chassis includes more crossbeams and two stringers, and the more crossbeams are parallel to each other, described in two Stringer is parallel to each other, and beam vertical is set between two stringers in stringer, the crossbeam, and the both ends of the crossbeam are solid respectively Surely the stringer is connected.
Further, first side frame includes more root posts and a cross bar, and the more columns are parallel to each other, described Uprights vertical is in the cross bar, and the cross bar is parallel to the chassis, and the lower end of the column is fixed on the chassis, described The upper end of column is fixedly connected with the cross bar.
By implementing above-mentioned technical proposal, the beneficial effects of the utility model are:
A kind of device for the overturning of prefabricated underground pipe gallery framework of steel reinforcement of the utility model is equipped with rollover stand, overturning One end hinge connecting support of frame need to only be hung the framework of steel reinforcement bound on rollover stand with gantry crane, then with gantry suspension hook Firmly rollover stand is rotated by 90 ° by overturning lifting lug, can be overturn vertical framework of steel reinforcement as horizontal framework of steel reinforcement, by horizontal steel After tendons skeleton is hung away, reset lifting lug only need to be hooked with gantry crane, rollover stand can be resetted, continue next framework of steel reinforcement Overturning.The utility model can rapidly, continuously realize the overturning of multiple frameworks of steel reinforcement, and structure is simple, use flexible side Just, so that operation more procedure, streamlined, improve production efficiency, and during overturning to the injury of framework of steel reinforcement very It is small.
Detailed description of the invention
Fig. 1 is a kind of structural representation of the device for the overturning of prefabricated underground pipe gallery framework of steel reinforcement of the utility model Figure;
Wherein, 1- support, 2- chassis, the first side frame of 3-, the second side frame of 4-, 5- third side frame, 6- overturn lifting lug, and 7- resets Lifting lug, the bottom 8- supporting block, the collateral bracer of 9-.
Specific embodiment
The specific implementation of utility model is further illustrated below in conjunction with attached drawing.
It please refers to shown in Fig. 1, a kind of device for the overturning of prefabricated underground pipe gallery framework of steel reinforcement, including two supports 1 and a rollover stand, support 1 is equipped with bottom plate, sets that there are four bolts hole on bottom plate, and four bolts hole are inserted in and are embedded in concrete The bolt on ground, then support 1 is fixed on bolt with nut, support 1 can be fixed on ground.Rollover stand includes one Chassis 2, first side frames, 3, second side frames 4 and a third side frame 5, the first side frame 3, the second side frame 4 and third side Frame 5 is respectively perpendicular the upper surface for being fixed on chassis 2, and the first side frame 3, the second side frame 4 and third side frame 5 are set to chassis 2 Periphery, the second side frame 4 is parallel with third side frame 5, and the second side frame 4 and third side frame 5 are respectively perpendicular the first side frame 3, and Two side frames 4 and third side frame 5 are located at the same side of the first side frame 3, the one end and the first side frame 3 of the second side frame 4 close to support 1 One end is fixedly connected, and third side frame 5 is fixedly connected with the first side frame 3 far from one end of the second side frame 4 close to one end of support 1. Chassis 2 is rectangular frame, and one end of chassis 2 passes through pin hinge connecting support 1, the following table of the one end of chassis 2 far from support 1 Face is fixedly connected with the bottom supporting block 8 for keeping the level of chassis 2.The lower end of first side frame 3 is fixedly connected with chassis 2 in close to branch One end of seat 1 is fixedly connected on the outside of the upper end of first side frame 3 for horizontal collateral of the first side frame 3 after being held turned over Bracer 9.Chassis 2 is equipped with overturning lifting lug 6 far from one end of support 1, and the upper end of the first side frame 3, which is equipped with, resets lifting lug 7.
In the present embodiment, chassis 2 includes four crossbeams and two stringers, and four crossbeams are parallel to each other, and two stringers are mutual In parallel, crossbeam is set between two stringers, and for beam vertical in stringer, the both ends of crossbeam are respectively fixedly connected with stringer, between crossbeam The connecting rod of reinforcing crossmember is used for equipped with several, the both ends of connecting rod to be respectively fixedly connected with two adjacent crossbeams.First side Frame 3 includes that four columns and a cross bar, four columns are parallel to each other, and the lower end of column is perpendicularly fixed at chassis 2 close to support 1 Stringer upper surface on, the upper end of column is vertically fixedly connected with cross bar, and cross bar is parallel to stringer, be equipped between column for plus Gu the stabiliser bar of column, the both ends of stabiliser bar are respectively fixedly connected with adjacent two root posts.5 knot of second side frame 4 and third side frame Structure is identical, and the second side frame 4 is made of a brace and a reinforcing bar, and the cross bar of the first side frame 3 is fixed in one end of brace One end, the other end of brace are fixed on one end of stringer of the chassis 2 far from support 1, and brace is perpendicular to stringer, the lower end of reinforcing bar It is fixed on chassis 2, the middle part of brace is fixed in the upper end of reinforcing bar.Brace and reinforcing bar position the framework of steel reinforcement of two sides enough, And the secured of the second side frame 4 and third side frame 5 is kept, and reduced the second side frame 4 and third side frame 5 and framework of steel reinforcement to the greatest extent Contact, to reduce the injury to framework of steel reinforcement of the second side frame 4 and third side frame 5.
A kind of device for the overturning of prefabricated underground pipe gallery framework of steel reinforcement of the utility model is equipped with rollover stand, overturning One end hinge connecting support 1 of frame need to only be hung the framework of steel reinforcement bound on rollover stand with gantry crane, then with gantry suspension hook Firmly rollover stand is rotated by 90 ° by overturning lifting lug 6, can be overturn vertical framework of steel reinforcement as horizontal framework of steel reinforcement, will be horizontal After framework of steel reinforcement is hung away, it need to only be hooked with gantry crane and reset lifting lug 7, rollover stand can resetted, continue next reinforcing bar The overturning of frame.The utility model can rapidly, continuously realize the overturning of multiple frameworks of steel reinforcement, and structure is simple, uses spirit It is living convenient, so that operation more procedure, streamlined, improve production efficiency, and to the wound of framework of steel reinforcement during overturning Evil very little.
Above description is the detailed description for the preferable possible embodiments of the utility model, but embodiment is not limited to The patent claim of the utility model, the same changes or modifications completed under technical spirit suggested by all the utility model Change, should belong to the covered the scope of the patents of the utility model.

Claims (6)

1. a kind of device for the overturning of prefabricated underground pipe gallery framework of steel reinforcement, it is characterised in that:Including
Support, the support are fixed on ground;And
Rollover stand, the rollover stand include chassis, the first side frame, the second side frame and third side frame, the chassis and the first side frame It is rectangle, one end hinge of the chassis connects the support, and the lower end of first side frame is fixedly connected on the bottom For frame close to the upper surface of one end of the support, the upper surface of the chassis is fixed in the lower end of second side frame, and described Two side frames are fixedly connected close to one end of the support with one end of first side frame, and the lower end of the third side frame is fixed on The chassis, the third side frame are solid close to the one end of one end and first side frame far from second side frame of the support Fixed connection, the chassis are equipped with overturning lifting lug far from one end of the support, and the upper end of first side frame, which is equipped with, resets lifting lug.
2. a kind of device for the overturning of prefabricated underground pipe gallery framework of steel reinforcement according to claim 1, feature exist In:The lower end surface of the one end of the chassis far from the support is fixedly connected with for keeping the bottom of the chassis level to support Block.
3. a kind of device for the overturning of prefabricated underground pipe gallery framework of steel reinforcement according to claim 1, feature exist In:The lateral surface of the upper end of first side frame is fixedly connected with for the collateral of first side frame level after being held turned over Bracer.
4. a kind of device for the overturning of prefabricated underground pipe gallery framework of steel reinforcement according to claim 3, feature exist In:Second side frame is identical with third side cage structure, and second side frame and third side frame are respectively perpendicular to first side Frame, second side frame and third side frame are respectively perpendicular to the chassis, and second side frame is added by a brace and several The upper end of first side frame is fixed in solid rod composition, one end of the brace, and the other end of the brace is fixed on the bottom The chassis is fixed in the one end of frame far from the support, the lower end of the reinforcing bar, and institute is fixed in the upper end of the reinforcing bar State the middle part of brace.
5. a kind of device for the overturning of prefabricated underground pipe gallery framework of steel reinforcement according to claim 2, feature exist In:The chassis includes more crossbeams and two stringers, and the more crossbeams are parallel to each other, and two stringers are parallel to each other, Beam vertical is set between two stringers in stringer, the crossbeam, and the both ends of the crossbeam are respectively fixedly connected with described vertical Beam.
6. a kind of device for the overturning of prefabricated underground pipe gallery framework of steel reinforcement according to claim 4, feature exist In:First side frame includes more root posts and a cross bar, and the more columns are parallel to each other, and the uprights vertical is in described Cross bar, the cross bar are parallel to the chassis, and the lower end of the column is fixed on the chassis, and the upper end of the column is fixed Connect the cross bar.
CN201820441484.7U 2018-03-30 2018-03-30 A kind of device for the overturning of prefabricated underground pipe gallery framework of steel reinforcement Expired - Fee Related CN208105313U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820441484.7U CN208105313U (en) 2018-03-30 2018-03-30 A kind of device for the overturning of prefabricated underground pipe gallery framework of steel reinforcement

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820441484.7U CN208105313U (en) 2018-03-30 2018-03-30 A kind of device for the overturning of prefabricated underground pipe gallery framework of steel reinforcement

Publications (1)

Publication Number Publication Date
CN208105313U true CN208105313U (en) 2018-11-16

Family

ID=64122080

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820441484.7U Expired - Fee Related CN208105313U (en) 2018-03-30 2018-03-30 A kind of device for the overturning of prefabricated underground pipe gallery framework of steel reinforcement

Country Status (1)

Country Link
CN (1) CN208105313U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110467110A (en) * 2019-09-04 2019-11-19 成都城投城建科技有限公司 A kind of turnover mechanism and method for turning suitable for assembled under-traverse tunnel

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110467110A (en) * 2019-09-04 2019-11-19 成都城投城建科技有限公司 A kind of turnover mechanism and method for turning suitable for assembled under-traverse tunnel

Similar Documents

Publication Publication Date Title
CN104806011B (en) Raft board post poured band formwork for placing
CN110485264A (en) A kind of center pier great cantilever bent cap and its construction method
CN209699487U (en) A kind of turnover type precast box beam steel bar colligation moulding bed
CN207974601U (en) A kind of large size earthing concrete tank dome steel support structure
CN208105313U (en) A kind of device for the overturning of prefabricated underground pipe gallery framework of steel reinforcement
CN106958233B (en) For pouring the hydraulic self-lifting formula cantilever form construction method of Arch Dam Concrete
CN205840892U (en) Ditch mould bases is surveyed in self-propelled tunnel
CN208563375U (en) A kind of tipping arrangement for prefabricated pipe gallery framework of steel reinforcement
CN207361652U (en) Moving device for large steel pipe
CN102995560B (en) Thin-wall hollow pier lifting frame and use method thereof
CN108797380B (en) Suspension construction device and construction method for suspension irrigation continuous beam bracket
CN103835294A (en) Concrete casting frame for construction of cast-in-place pile and using method
CN207293909U (en) A kind of precast beam reinforced bar skeleton hanging apparatus
CN210002829U (en) shear wall ligature installation operation platform
CN206129292U (en) Novel landing stage platform truck
CN207727997U (en) Concrete floor slab placement construction frame body platform structure for building construction
CN208220167U (en) Detachable elevator shaft operating platform
CN219384478U (en) Precast beam template hoist
CN205741886U (en) A kind of extension die shoe frame for the construction of bridge rectangle pier
CN221194195U (en) Can have enough to meet need scaffold frame operation platform
CN218061291U (en) Triangular reinforcing cross rod for operation frame
CN212404855U (en) A mounting structure that is used for construction platform that steel-pipe pile support set up
CN218030221U (en) Chute trolley for tunnel concreting
CN214364939U (en) Fastener type steel pipe lattice column supporting structure
CN210561670U (en) Falsework and arch frame combined structure for cast-in-place concrete bridge

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CP02 Change in the address of a patent holder

Address after: 530200 No.21 Pingle Avenue, Liangqing District, Nanning City, Guangxi Zhuang Autonomous Region

Patentee after: GUANGXI ROAD AND BRIDGE ENGINEERING GROUP Co.,Ltd.

Address before: 530011 Zhonghua Road 17, Xingning District, the Guangxi Zhuang Autonomous Region, Nanning

Patentee before: GUANGXI ROAD AND BRIDGE ENGINEERING GROUP Co.,Ltd.

CP02 Change in the address of a patent holder
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20181116

CF01 Termination of patent right due to non-payment of annual fee