CN208103726U - Build lifting handgrip - Google Patents
Build lifting handgrip Download PDFInfo
- Publication number
- CN208103726U CN208103726U CN201820431780.9U CN201820431780U CN208103726U CN 208103726 U CN208103726 U CN 208103726U CN 201820431780 U CN201820431780 U CN 201820431780U CN 208103726 U CN208103726 U CN 208103726U
- Authority
- CN
- China
- Prior art keywords
- lifting
- girder
- lifting lug
- building
- supporting rod
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
The utility model discloses a kind of building lifting handgrips, including girder, the two sides of the girder length direction are equipped with support plate, the girder lower end is symmetrically arranged with the supporting rod of two V-structures, adjusting rod is equipped between the supporting rod and support plate, the two sides in the width of main beam direction have been detachably attached to lifting lug, and two are played lifting lug and are symmetrical arranged;The building lifting handgrip of the utility model, plays lifting lug and is removably attached to girder, convenient for carrying out replacement operation after playing lifting lug damage;Meanwhile symmetrically playing a lifting lugs using two and being lifted by crane, compared to individually playing lifting lug, high stability when lifting can avoid building materials during lifting and topple over to fall.
Description
Technical field
The utility model relates to the realm of building construction more particularly to a kind of building lifting handgrips.
Background technique
Building is the general name of building and structures, is people to meet social life needs, utilizes grasped object
Matter technological means, and the artificial environment created with certain scientific law, geomantic omen theory and aesthetic principle.Building is that people use
Soil, brick, watt, one kind for constituting of the construction materials such as stone material, timber, reinforced concrete is for human habitation and the space that uses, such as house, bridge
Beam, workshop, gymnasium, cave dwelling, water tower, temple etc..It needs to lift by crane building materials using crane in existing architectural process,
Building materials are hung and set suitable position, a kind of handgrip convenient for grabbing building materials is thus needed to mention to realize reduction operating procedure
High working efficiency.
Chinese patent CN204661133U discloses a kind of building lifting handgrip, including handgrip girder, on handgrip girder
Equipped with rise a lifting lug, handgrip girder two sides be equipped with support plate, handgrip girder lower end two sides be equipped with supporting rod, the V-shaped structure of supporting rod,
Adjusting rod is equipped between each supporting rod and support plate;In lifting, supporting rod opens under the action of adjusting rod, then closes
Conjunction is quickly grabbed building materials.However, being connected by welding manner with girder due to playing lifting lug, replacement is difficult after playing lifting lug damage
Degree is big;And be only arranged one and play lifting lug, in lifting, stability is insufficient, is easy to cause building materials to topple over and falls, causes safe thing
Therefore.
It is therefore desirable to a kind of building lifting handgrip, convenient for the replacement operation after playing lifting lug damage, and while lifting by crane, is steady
Qualitative height avoids building materials from toppling over and falls.
Utility model content
In view of this, the purpose of this utility model is to provide a kind of building lifting handgrip, convenient for playing lifting lug damage
Replacement operation afterwards, and stability is high when lifting, avoids building materials from toppling over and falls.
Building the lifting handgrip, including girder of the utility model, the two sides of the girder length direction are equipped with support plate,
The girder lower end is symmetrically arranged with the supporting rod of two V-structures, and adjusting rod, the master are equipped between the supporting rod and support plate
The two sides in beam width direction have been detachably attached to lifting lug, and two are played lifting lug and are symmetrical arranged.
Preferably, described lifting lug is made of metal material and is equipped with a lifting eye and one is used to pass through with girder
The connected connecting hole of fixing bolt is also integrally formed with a positioning column on described lifting lug, and the girder is equipped with one and is used for
With positioning column form-fit and cooperate the post holes of positioning.
Preferably, the adjusting rod is cylinder or hydraulic cylinder.
Preferably, the support plate is connected by welding manner with girder;The supporting rod passes through articulated manner and girder
It is connected, described lifting lug is located in the middle part of girder.
Preferably, the clamping face of the supporting rod is equipped with wearing layer.
By above disclosure, the utility model has following advantageous effects:
The building lifting handgrip of the utility model, plays lifting lug and is removably attached to girder, convenient for playing lifting lug
Replacement operation is carried out after damage;Meanwhile symmetrically playing a lifting lugs using two and being lifted by crane, compared to individually playing lifting lug, when lifting
High stability, building materials are toppled over and are fallen during can avoid lifting.
Detailed description of the invention
Fig. 1 is the structural schematic diagram of the utility model.
Specific embodiment
It is with reference to the accompanying drawing and specific real to make those skilled in the art better understand the technical solution of the utility model
Applying example, the utility model is described in further detail.
Fig. 1 is the structural schematic diagram of the utility model, as shown in the figure:Building the lifting handgrip, including master of the present embodiment
The two sides of beam 1,1 length direction of girder are equipped with support plate 2, and 1 lower end of girder is symmetrically arranged with the supporting rod of two V-structures
3, adjusting rod 4 is equipped between the supporting rod 3 and support plate 2, the two sides of 1 width direction of girder removably connect
It is connected to lifting lug 5, two are played lifting lug 5 and are symmetrical arranged;Left and right directions shown in 1 length direction of girder, that is, Fig. 1;Support plate 2 can
It is integrally formed, can also be connected with girder 1 by welding manner with girder 1;Supporting rod 3 is V-shaped, angle be 100 ° -150 ° it
Between;Supporting rod 3 is connected by articulated manner with girder 1, and supporting rod 3 opens under the action of adjusting rod 4, is then closed building materials
Quickly grabbed, it is easy to operate, and chucking power is big;Adjusting rod 4 is preferably cylinder or hydraulic cylinder, and cylinder, hydraulic cylinder can be remote
Journey manipulation, is grabbed with facilitating;It plays lifting lug 5 and is located at 1 middle part of girder, to improve lifting stability;Lifting lug 5 is played with detachable side
Formula is connected to girder 1, convenient for carrying out replacement operation after playing lifting lug 5 and damaging;Meanwhile lifting lug 5 is symmetrically played using two and is carried out
Lifting, compared to individually playing lifting lug 5, high stability when lifting can avoid building materials during lifting and topple over to fall.
In the present embodiment, described lifting lug 5 be made of metal material and be equipped with a lifting eye 51 and one for
Girder 1 passes through the connecting hole 52 that fixing bolt 6 is connected, and is also integrally formed with a positioning column 53, the girder on described lifting lug 5
1 is equipped with the post holes (not shown) for being used for 53 form-fit of positioning column and cooperating positioning;Lifting lug 5 is each played to pass through
Positioning column 53 and connecting hole 52 are fixedly connected with girder 1, and since positioning column 53 is integrally provided on lifting lug, one need to be only used in assembly
A fixing bolt can reduce the dosage of fixing bolt 6, and one and the cooperation of fixing bolt 6 need to be only processed on girder 1
The processing of screw hole, post holes is then relatively easy, therefore can reduce amount of machining, improves production efficiency;Preferably, positioning column 53 is vertical
Lifting lug 5 is arranged in, and positioning column 53, connecting hole 52 and lifting eye 51 are distributed in isosceles triangle, positioning column 53 and connecting hole
52 are located at the lower section of lifting eye 51 and are located along the same line.
In the present embodiment, the clamping face of the supporting rod 3 is equipped with wearing layer 7;Wearing layer 7 can be rubber structure, no
It reduced by only the abrasion of supporting rod 3, and supporting rod 3 can be increased to the chucking power of building materials.
The principles of the present invention and embodiment are explained finally, it is stated that applying specific case herein
It states, the core concept of the above embodiments are only used to help understand the utility model, is not departing from the utility model original
In the case where reason, can also to the utility model, some improvement and modification can also be carried out, these improvement and modification also fall into guarantor of the invention
It protects in range.
Claims (5)
1. a kind of building lifting handgrip, including girder, the two sides of the girder length direction are equipped with support plate, under the girder
End is symmetrically arranged with the supporting rod of two V-structures, and adjusting rod is equipped between the supporting rod and support plate, it is characterised in that:It is described
The two sides in width of main beam direction have been detachably attached to lifting lug, and two are played lifting lug and are symmetrical arranged.
2. building lifting handgrip according to claim 1, it is characterised in that:Described lifting lug is made of metal material
And it is equipped with a lifting eye and a connecting hole for being connected with girder by fixing bolt, it is also integrally set on described lifting lug
There is a positioning column, the girder is equipped with the post holes for being used for positioning column form-fit and cooperating positioning.
3. building lifting handgrip according to claim 2, it is characterised in that:The adjusting rod is cylinder or hydraulic cylinder.
4. building lifting handgrip according to claim 3, it is characterised in that:The support plate passes through welding manner and master
Beam is connected;The supporting rod is connected by articulated manner with girder, and described lifting lug is located in the middle part of girder.
5. building lifting handgrip according to claim 4, it is characterised in that:The clamping face of the supporting rod is equipped with resistance to
Grind layer.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820431780.9U CN208103726U (en) | 2018-03-28 | 2018-03-28 | Build lifting handgrip |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820431780.9U CN208103726U (en) | 2018-03-28 | 2018-03-28 | Build lifting handgrip |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208103726U true CN208103726U (en) | 2018-11-16 |
Family
ID=64123265
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820431780.9U Expired - Fee Related CN208103726U (en) | 2018-03-28 | 2018-03-28 | Build lifting handgrip |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208103726U (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111379222A (en) * | 2019-12-18 | 2020-07-07 | 中铁建设集团基础设施建设有限公司 | Multi-section type prefabricated box girder transportation and hydraulic installation equipment |
-
2018
- 2018-03-28 CN CN201820431780.9U patent/CN208103726U/en not_active Expired - Fee Related
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111379222A (en) * | 2019-12-18 | 2020-07-07 | 中铁建设集团基础设施建设有限公司 | Multi-section type prefabricated box girder transportation and hydraulic installation equipment |
CN111379222B (en) * | 2019-12-18 | 2022-04-01 | 中铁建设集团基础设施建设有限公司 | Multi-section type prefabricated box girder transportation and hydraulic installation equipment |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN208103726U (en) | Build lifting handgrip | |
CN207244452U (en) | A kind of suspension bridge vice saddle adjusting apparatus in place | |
CN208103776U (en) | Building materials boom hoisting | |
CN209556342U (en) | Architectural engineering plane template | |
CN206359210U (en) | A kind of processing of steel construction is with stablizing lowering or hoisting gear | |
CN106495061B (en) | Stable lifting device for steel structure machining | |
CN109835828A (en) | A kind of both arms building tooling crane | |
CN211414309U (en) | Plate turnover forming machine for climbing frame | |
CN209685144U (en) | A kind of bridge construction suspension arrangement | |
CN207685682U (en) | A kind of bridge hoisting mechanism | |
CN209352424U (en) | A kind of hoisting prefabricated part of embedded small hoisting ring group | |
CN206375555U (en) | Build lifting machinery manipulator | |
CN207109601U (en) | A kind of bridge construction Hanging Basket slip support abutment | |
CN206487128U (en) | A kind of Guiding Support Elevating Scaffold | |
CN205777582U (en) | A kind of concrete pier base moulding bed assembled for large-scale steel structure body | |
CN109809298A (en) | A kind of multi-use architecture tooling crane | |
CN214658777U (en) | Three rotatable jack bases | |
CN204266663U (en) | A kind of area of heavy rainfull building uses Multifunctional rain-proof canopy | |
CN208516906U (en) | Device is removed in the simple promotion of mold | |
CN205500545U (en) | Hoisting device for tower crane | |
CN207686341U (en) | A kind of building machinery supporting rack | |
CN217229926U (en) | Tensile hanging flower basket that building engineering used | |
CN108502741A (en) | A kind of truss-like gantry crane's supporting legs | |
CN109835827A (en) | A kind of method and building suitable for frame structure building underground increasing layer | |
CN209429165U (en) | A kind of civil construction retaining wall structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20181116 Termination date: 20190328 |