CN208074268U - A kind of prefabricated mat piece of municipal pipeline - Google Patents

A kind of prefabricated mat piece of municipal pipeline Download PDF

Info

Publication number
CN208074268U
CN208074268U CN201820431547.0U CN201820431547U CN208074268U CN 208074268 U CN208074268 U CN 208074268U CN 201820431547 U CN201820431547 U CN 201820431547U CN 208074268 U CN208074268 U CN 208074268U
Authority
CN
China
Prior art keywords
conduit
clamping plate
pedestal
lantern ring
wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820431547.0U
Other languages
Chinese (zh)
Inventor
王晶晶
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201820431547.0U priority Critical patent/CN208074268U/en
Application granted granted Critical
Publication of CN208074268U publication Critical patent/CN208074268U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Road Paving Structures (AREA)

Abstract

The utility model discloses a kind of prefabricated mat pieces of municipal pipeline, including bed course, the top of the bed course is fixed with pedestal, the top of the pedestal is equipped with conduit, the conduit is fitted closely with pedestal, it is placed with cushion block at gap between the conduit and bed course, clamping plate is equipped at left and right sides of the pedestal, the clamping plate is connected by first rotating shaft with pedestal.The prefabricated mat piece of the municipal pipeline, pass through the cooperation of first rotating shaft and clamping plate, clamping plate is rotated around first rotating shaft, it is fitted closely together with the outer wall of conduit, conduit is clamped, prevent conduit from shifting during normal come into operation, to be difficult to repair, by the cooperation of fixture block and card slot, pass through the cooperation of cross bar and bull stick, the end of clamping plate is fixed, the fixation to clamping plate is reinforced by the cooperation of top plate and the first lantern ring by the cooperation of connecting rod and compressed spring, ensure that the clamping plate of conduit both sides will not be detached with conduit, good fixing effect.

Description

A kind of prefabricated mat piece of municipal pipeline
Technical field
The utility model is related to the prefabricated mat piece technical field of municipal pipeline, specially a kind of prefabricated mat piece of municipal pipeline.
Background technology
The step of traditional municipal pipeline construction is first grooving, then slot bottom is carried out it is smooth, complete slot bottom it is smooth after One layer of mortar is poured thereon, is finally laid with municipal pipeline, in equal mortar hardenings process, so that entire construction period is elongated, is being carried out When slot bottom is smooth, since construction period elongates, the technical issues of having infiltration, leads to not be laid with pipeline, such as applies Number include bed course and connector for 201320086562.3 patent, although which solves the problems, such as infiltration, but in day Poor to the fixed effect of pipeline during being often laid with, pipeline can be detached with mat piece to ineffective.
Utility model content
The purpose of this utility model is to provide a kind of prefabricated mat pieces of municipal pipeline, to solve to propose in above-mentioned background technology The problem of.
To achieve the above object, the utility model provides the following technical solutions:A kind of prefabricated mat piece of municipal pipeline, including pad The top of layer, the bed course is fixed with pedestal, and the top of the pedestal is equipped with conduit, and the conduit is fitted closely with pedestal, institute It states and is placed with cushion block at the gap between conduit and bed course, clamping plate is equipped at left and right sides of the pedestal, the clamping plate passes through First rotating shaft is connected with pedestal, and the clamping plate is movably connected with pedestal, and the outer wall of the clamping plate and conduit fits closely, the folder Cross bar is fixed on the right side of plate, the right side bottom end of the cross bar is equipped with bull stick, and the bull stick is connected by the second shaft with cross bar, The cross bar is connected with rotarod activity, fixture block is connected on the left of the bull stick, the left side of the fixture block is equipped with montant, described perpendicular The right side of bar is equipped with card slot, and the card slot is mutually clamped with fixture block, and the montant is connected with conduit, the inner tip of the conduit Equipped with connecting rod, the connecting rod is connected by bearing with conduit, and the outer wall center of the connecting rod is socketed with compression bullet The outer wall left and right sides of spring, the connecting rod is socketed with the first lantern ring, and first lantern ring is fitted closely with compressed spring, institute The top for stating the first lantern ring is fixed with top plate, and the top plate is fitted closely with bull stick.
Preferably, it is equipped with strut at left and right sides of the top of the bed course, the top outer wall of the strut is socketed with second Lantern ring is connected with pressing plate on the right side of second lantern ring, and the left side outer wall of second lantern ring is equipped with nut, the nut It is internally provided with bolt, the bolts and nuts screw thread is connected, and bolt is fitted closely with strut.
Preferably, the top of the strut is connected with block.
Preferably, the bottom dead center position of the pressing plate is equipped with sponge block, and the sponge block is adjacent with clamping plate and cross bar.
Preferably, the bottom end outer wall of the strut is welded with sleeve.
Compared with prior art, the utility model has the beneficial effects that:The prefabricated mat piece of the municipal pipeline, passes through pedestal and pad The cooperation of block, is supported conduit, and by the cooperation of first rotating shaft and clamping plate, clamping plate is rotated around first rotating shaft, with conduit Outer wall fit closely together, conduit is clamped, prevents conduit from shifting during normal come into operation, from And be difficult to repair, by the cooperation of fixture block and card slot, by the cooperation of cross bar and bull stick, the end of clamping plate is fixed, is led to The cooperation for crossing connecting rod and compressed spring reinforces the fixation to clamping plate, it is ensured that conduit two by the cooperation of top plate and the first lantern ring The clamping plate of side will not be detached with conduit, and good fixing effect is easy to use, and practical performance is strong.
Description of the drawings
FIG. 1 is a schematic structural view of the utility model;
Fig. 2 be the first lantern ring of Fig. 1, connecting rod and compressed spring attachment structure schematic diagram;
Fig. 3 be the cross bar of Fig. 1, the second shaft and bull stick attachment structure schematic diagram;
Fig. 4 is the attachment structure schematic diagram of the strut of Fig. 1, the second lantern ring and pressing plate.
In figure:1, bed course, 2, pedestal, 3, conduit, 4, cushion block, 5, first rotating shaft, 6, clamping plate, 7, cross bar, the 8, second shaft, 9, bull stick, 10, fixture block, 11, montant, 12, card slot, 13, top plate, the 14, first lantern ring, 15, connecting rod, 16, compressed spring, 17, Bearing, 18, strut, the 19, second lantern ring, 20, pressing plate, 21, nut, 22, bolt, 23, block, 24, sponge block, 25, sleeve.
Specific implementation mode
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work The every other embodiment obtained, shall fall within the protection scope of the present invention.
- 4 are please referred to Fig.1, the utility model provides a kind of technical solution:A kind of prefabricated mat piece of municipal pipeline, including bed course 1, the top of bed course 1 is fixed with pedestal 2, and the top of pedestal 2 is equipped with conduit 3, right during to municipal pipeline Embedment Construction The foundation pit bottom end dug out in advance is plastered using concrete, bed course 1 is formed, before concrete does not solidify, by pedestal 2 with same Deng spacing along conduit 3 laying direction place, use, conduit 3 and bottom are can proceed with when concrete reaches use intensity Seat 2 fits closely, and cushion block 4 is placed at the gap between conduit 3 and bed course 1, and the left and right sides of pedestal 2 is equipped with clamping plate 6, folder Plate 6 is connected by first rotating shaft 5 with pedestal 2, and conduit 3 is placed into the top of pedestal 2 using lifting device, in conduit 3 and pad Cushion block 4 to be placed in gap between layer 1 to be filled up, sub-mount 2 is supported conduit 3, the clamping plate 6 that the company's of pulling envelope is surveyed, Clamping plate 6 is rotated around first rotating shaft 5, until the inner wall of clamping plate 6 and the outer wall of conduit 3 are in close contact, clamping plate 6 and pedestal 2 It is movably connected, clamping plate 6 and the outer wall of conduit 3 fit closely, and the right side of clamping plate 6 is fixed with cross bar 7, and the right side bottom end of cross bar 7 is set There are bull stick 9, bull stick 9 to be connected with cross bar 7 by the second shaft 8, cross bar 7 is movably connected with bull stick 9, and the left side of bull stick 9 is connected with Fixture block 10 pulls bull stick 9, and second shaft 8 of the bull stick 9 around 7 end of cross bar is rotated, 9 band of bull stick during rotation Dynamic fixture block 10 rotates together, and until the card slot 12 inside fixture block 10 and montant 11 is to contact, unclamps top plate 13, compressed spring 16 restore original elastic stage, push top plate 13 closely to fit together with bull stick 9 by the first lantern ring 14, complete to leading The left side of the fixation of pipe 3, fixture block 10 is equipped with montant 11, and the right side of montant 11 is equipped with card slot 12, and card slot 12 mutually blocks with fixture block 10 It connects, montant 11 is connected with conduit 3, and the inner tip of conduit 3 is equipped with connecting rod 15, and connecting rod 15 passes through bearing 17 and 3 phase of conduit Even, the outer wall center of connecting rod 15 is socketed with compressed spring 16, and the coefficient of elasticity of compressed spring 16 is 5N/CM to 10N/CM Between, it is socketed with the first lantern ring 14 at left and right sides of the outer wall of connecting rod 15, the first lantern ring 14 is fitted closely with compressed spring 16, The top of first lantern ring 14 is fixed with top plate 13, and the top plate 13 of both sides is pulled to center, and top plate 13 drives the first lantern ring 14 It is slided on the outer wall of connecting rod 15, while first lantern ring 14 at both ends applies pressure, compression to compressed spring 16 simultaneously Because elastic deformation occurs for the elastic property of itself, top plate 13 fits closely spring 16 with bull stick 9, at left and right sides of the top of bed course 1 It is equipped with strut 18, before being laid with 1 concrete of bed course and not solidifying, places strut 18, after waiting for concrete hardening, strut 18 It is fixed, the top outer wall of strut 18 is socketed with the second lantern ring 19, and the right side of the second lantern ring 19 is connected with pressing plate 20, the second lantern ring 19 left side outer wall is equipped with nut 21, and nut 21 is internally provided with bolt 22, and bolt 22 is connected with 21 screw thread of nut, and bolt 22 fit closely with strut 18, and the top of strut 18 is connected with block 23, prevent the second lantern ring 19 from being detached with strut 18, pressing plate 20 Bottom dead center position be equipped with sponge block 24, sponge block 24 is adjacent with clamping plate 6 and cross bar 7, is protected to the structure of catheter tip Shield, the bottom end outer wall of strut 18 are welded with sleeve 25, are consolidated to junction.
During to municipal pipeline Embedment Construction, plastered using concrete the foundation pit bottom end dug out in advance, Bed course 1 is formed, before concrete does not solidify, pedestal 2 is placed with same spacing along the laying direction of conduit 3, in coagulation Soil can proceed with use when reaching use intensity, conduit 3 is placed into the top of pedestal 2 using lifting device, conduit 3 with It places cushion block 4 in gap between bed course 1 to be filled up, sub-mount 2 is supported conduit 3, the clamping plate that the company's of pulling envelope is surveyed 6, clamping plate 6 is rotated around first rotating shaft 5, until the inner wall of clamping plate 6 and the outer wall of conduit 3 are in close contact, to center Pull the top plate 13 of both sides, top plate 13 drives the first lantern ring 14 to be slided on the outer wall of connecting rod 15, while the of both ends One lantern ring 14 applies pressure to compressed spring 16 simultaneously, and compressed spring 16 is because elastic deformation occurs for the elastic property of itself, in this Bull stick 9 is pulled simultaneously, and second shaft 8 of the bull stick 9 around 7 end of cross bar is rotated, and bull stick 9 drives card during rotation Block 10 rotates together, and until the card slot 12 inside fixture block 10 and montant 11 is to contact, unclamps top plate 13, compressed spring 16 is extensive The elastic stage to begin is restored, pushes top plate 13 closely to fit together with bull stick 9 by the first lantern ring 14, completes to conduit 3 Fixation.
In the description of the present invention, it should be understood that term " coaxial ", " bottom ", " one end ", " top ", " in The orientation of the instructions such as portion ", " other end ", "upper", " side ", " top ", "inner", " front ", " center ", " both ends " or position are closed System is to be based on the orientation or positional relationship shown in the drawings, and is merely for convenience of describing the present invention and simplifying the description, rather than Indicate or imply that signified device or element must have a particular orientation, with specific azimuth configuration and operation, therefore cannot It is construed as a limitation of the present invention.
In the present invention unless specifically defined or limited otherwise, term " installation ", " setting ", " connection ", " Gu Calmly ", the terms such as " being screwed on " shall be understood in a broad sense, for example, it may be being fixedly connected, may be a detachable connection, or integral; It can be mechanical connection, can also be electrical connection;It can be directly connected, can also indirectly connected through an intermediary, it can be with It is the interaction relationship of the connection or two elements inside two elements, unless otherwise restricted clearly, for this field For those of ordinary skill, the concrete meaning of above-mentioned term in the present invention can be understood as the case may be.
While there has been shown and described that the embodiments of the present invention, for the ordinary skill in the art, It is appreciated that can these embodiments be carried out with a variety of variations in the case where not departing from the principles of the present invention and spirit, repaiied Change, replace and modification, the scope of the utility model are defined by the appended claims and the equivalents thereof.

Claims (5)

1. a kind of prefabricated mat piece of municipal pipeline, including bed course (1), it is characterised in that:The top of the bed course (1) is fixed with pedestal (2), the top of the pedestal (2) is equipped with conduit (3), and the conduit (3) fits closely with pedestal (2), the conduit (3) and pad It is placed with cushion block (4) at gap between layer (1), clamping plate (6), the clamping plate (6) are equipped at left and right sides of the pedestal (2) It is connected with pedestal (2) by first rotating shaft (5), the clamping plate (6) is movably connected with pedestal (2), the clamping plate (6) and conduit (3) outer wall fits closely, and cross bar (7) is fixed on the right side of the clamping plate (6), and the right side bottom end of the cross bar (7), which is equipped with, to be turned Bar (9), the bull stick (9) are connected by the second shaft (8) with cross bar (7), and the cross bar (7) is movably connected with bull stick (9), institute It states and is connected with fixture block (10) on the left of bull stick (9), the left side of the fixture block (10) is equipped with montant (11), the right side of the montant (11) Side is equipped with card slot (12), and the card slot (12) is mutually clamped with fixture block (10), and the montant (11) is connected with conduit (3), described The inner tip of conduit (3) is equipped with connecting rod (15), and the connecting rod (15) is connected by bearing (17) with conduit (3), described The outer wall center of connecting rod (15) is socketed with compressed spring (16), is socketed at left and right sides of the outer wall of the connecting rod (15) There are the first lantern ring (14), first lantern ring (14) to be fitted closely with compressed spring (16), the top of first lantern ring (14) It is fixed with top plate (13), the top plate (13) fits closely with bull stick (9).
2. the prefabricated mat piece of a kind of municipal pipeline according to claim 1, it is characterised in that:The top of the bed course (1) is left Right both sides are equipped with strut (18), and the top outer wall of the strut (18) is socketed with the second lantern ring (19), second lantern ring (19) pressing plate (20) is connected on the right side of, the left side outer wall of second lantern ring (19) is equipped with nut (21), the nut (21) be internally provided with bolt (22), the bolt (22) is connected with nut (21) screw thread, and bolt (22) and strut (18) are tight Closely connected conjunction.
3. the prefabricated mat piece of a kind of municipal pipeline according to claim 2, it is characterised in that:The top of the strut (18) is solid It is connected to block (23).
4. the prefabricated mat piece of a kind of municipal pipeline according to claim 2, it is characterised in that:In the bottom end of the pressing plate (20) Heart position is equipped with sponge block (24), and the sponge block (24) is adjacent with clamping plate (6) and cross bar (7).
5. the prefabricated mat piece of a kind of municipal pipeline according to claim 2, it is characterised in that:Outside the bottom end of the strut (18) Wall is welded with sleeve (25).
CN201820431547.0U 2018-03-29 2018-03-29 A kind of prefabricated mat piece of municipal pipeline Expired - Fee Related CN208074268U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820431547.0U CN208074268U (en) 2018-03-29 2018-03-29 A kind of prefabricated mat piece of municipal pipeline

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820431547.0U CN208074268U (en) 2018-03-29 2018-03-29 A kind of prefabricated mat piece of municipal pipeline

Publications (1)

Publication Number Publication Date
CN208074268U true CN208074268U (en) 2018-11-09

Family

ID=64042290

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820431547.0U Expired - Fee Related CN208074268U (en) 2018-03-29 2018-03-29 A kind of prefabricated mat piece of municipal pipeline

Country Status (1)

Country Link
CN (1) CN208074268U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110453684A (en) * 2018-05-07 2019-11-15 中国石油化工股份有限公司 Ground anchor structure is used in sunken tankers installation

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110453684A (en) * 2018-05-07 2019-11-15 中国石油化工股份有限公司 Ground anchor structure is used in sunken tankers installation

Similar Documents

Publication Publication Date Title
CN205502577U (en) A thimble assembly for buried sleeve one shot forming construction in piping shaft
CN204024679U (en) Buried water stop fastening devices in a kind of tunnel lining hoop
CN204098918U (en) Dimensional parameters multiple degrees of freedom is adjustable uses shield launching bracket repeatedly
CN105442760A (en) Steel bar connection mode used for connection among prefabricated reinforced concrete members
CN208074268U (en) A kind of prefabricated mat piece of municipal pipeline
CN208329214U (en) A kind of connection structure
CN207034453U (en) A kind of Water supplying tube joint
CN210770664U (en) Novel steel bushing steel frame hollow pipe support
CN107165468A (en) A kind of power network electric pole reinforces the construction method of heightening device
CN210389612U (en) Cement duct production process is with solidification accelerating device
CN209703710U (en) A kind of novel embedded part conduit
CN209604089U (en) A kind of external hanging type preburied component and shield duct piece
CN203487548U (en) Connecting structure of transformer substation steel bracket and concrete foundation joint
CN217421200U (en) Shield constructs shaping tunnel section of jurisdiction and prevents wrong platform device
CN207260191U (en) A kind of class rectangle pipe gallery section of jurisdiction connection structure
CN207092104U (en) A kind of steel-pipe pile attachment structure
CN210660120U (en) Shield tunnel segment convenient to consolidate
CN204646267U (en) A kind of corrugated steel Tunnel structure
CN210397930U (en) Cement culvert pipe erection support
CN203863807U (en) Grouting sleeve locating device for housing industrialization pre-cast concrete component
CN207314348U (en) A kind of fixed structure of flare template
CN201818095U (en) Novel embedded structure for composite pipe bodies
CN206267856U (en) A kind of shield tunnel piecing devices for there is interior hydraulic pressure
CN221093525U (en) Assembled building tower machine connection structure
CN201474290U (en) Scaffold lapping component

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20181109

Termination date: 20190329

CF01 Termination of patent right due to non-payment of annual fee