CN208073549U - A kind of mobile tunnel construction relay pump drainage water installations - Google Patents

A kind of mobile tunnel construction relay pump drainage water installations Download PDF

Info

Publication number
CN208073549U
CN208073549U CN201820184720.1U CN201820184720U CN208073549U CN 208073549 U CN208073549 U CN 208073549U CN 201820184720 U CN201820184720 U CN 201820184720U CN 208073549 U CN208073549 U CN 208073549U
Authority
CN
China
Prior art keywords
header tank
water
pump
immersible pump
mobile tunnel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820184720.1U
Other languages
Chinese (zh)
Inventor
卢伟
姚红伟
段小龙
申永江
张辉
罗斌智
黄久宾
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Central South University
China Railway Tunnel Group Co Ltd CRTG
Original Assignee
Central South University
China Railway Tunnel Group Co Ltd CRTG
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Central South University, China Railway Tunnel Group Co Ltd CRTG filed Critical Central South University
Priority to CN201820184720.1U priority Critical patent/CN208073549U/en
Application granted granted Critical
Publication of CN208073549U publication Critical patent/CN208073549U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Sewage (AREA)

Abstract

A kind of mobile tunnel construction relay pump drainage water installations, including header tank, the header tank is connected with water inlet pipe and drainpipe, the one end of the water inlet pipe far from header tank is connect with water pump, bottom is equipped with immersible pump in the header tank, outlet pipe is connected at the top of the immersible pump, the control dial plate that control immersible pump opens and closes is provided on the header tank side wall, low water level electronic level switch and high water level electronic level switch, the angle of the header tank bottom four in the control dial plate electrical connection header tank are equipped with universal wheel and wheel clamp device.The beneficial effects of the utility model are:It can achieve the purpose that lasting draining, catch pit is replaced with header tank, breach limitation of the catch pit because of all many conditions such as terrain;It is simple in structure, easy to make, easy to remove, floor space is small, can be repeatedly used for a long, and efficiently solve long range counter-slope drainage problem, improve constructing tunnel efficiency.

Description

A kind of mobile tunnel construction relay pump drainage water installations
Technical field
The utility model is related to tunnel counter-slope construction field, especially a kind of mobile tunnel construction relay pump drainage water dress It sets.
Background technology
Tunnel construction generally comprises the tunnel construction engineering of highway, railway, water conservancy, electric power etc., when tunnel is in water enrichment area When middle construction, has and the depth of water is descended to enter tunnel in large quantities, and according to current construction ability and the prior art of " long tunnel hand-to-hand fight in tights ", it is long Big tunnel generally 1 ~ 5 inclined shaft of setting, the slope construction to main tunnel are generally counter-slope construction, i.e., enter main tunnel by inclined shaft and apply Sump is arranged in inclined shaft and main tunnel intersection in work(Sump), the water of main tunnel is introduced into sump, then the classification of catchmenting in sump Inclined shaft is discharged.Classification draining generally requires catch pit is arranged in inclined shaft, and the setting of catch pit is not only time-consuming and laborious, but also can be because The pump drainage that catchments causes sewage to flow over not in time, influences in-cavity construction environment.
Utility model content
The purpose of this utility model is just to provide a kind of mobile tunnel construction relay pump drainage water installations, effectively solves Problem is stated, constructing tunnel efficiency is improved.
To achieve the goals above, technical solution used by the utility model is:
The utility model is related to a kind of mobile tunnel construction relay pump drainage water installations, including header tank, the header tanks It is connected with water inlet pipe and drainpipe, the one end of the water inlet pipe far from header tank is connect with water pump, and bottom is set in the header tank There is immersible pump, outlet pipe is connected at the top of the immersible pump, the control that control immersible pump opens and closes is provided on the header tank side wall Dial plate, the control dial plate are electrically connected low water level electronic level switch and high water level electronic level switch in header tank, The angle of the header tank bottom four is equipped with universal wheel and wheel clamp device.
The side of the header tank connection outlet pipe is equipped with discharge opening and overflow port, and discharge opening is under header tank side Portion, top of the overflow port in header tank side.
The low level electronic level switch is located at same level, the high water level electronic type water level with immersible pump bottom surface Switch is located at same level with overflow port lower end.
The box cover that catchments is equipped with handle I, handle II and venthole.
Compared with existing tunnel counter-slope takes out water discharge technology, the utility model has the beneficial effects that:The utility model structure letter List, is easy installation at conveniently moving, while meeting the draining of tunnel counter-slope and needing, can repeatedly utilize, less cost, shortening is built If the duration.
Description of the drawings
Fig. 1 is the structural schematic diagram of the utility model;
Fig. 2 is the utility model position view in inclined shaft.
In figure, 1, header tank;2, water inlet pipe;3, outlet pipe;4, discharge opening;5, overflow port;6, venthole;7, immersible pump; 8, control dial plate;9, low water level electronic level switch;10, high water level electronic level switch;11, handle I;12, handle II; 13, universal wheel;14, wheel clamp device;15, water pump.
Specific implementation mode
Explanation and specific implementation mode are described in further details the utility model below in conjunction with the accompanying drawings:
The relay pump drainage water installations as shown, a kind of mobile tunnel is constructed, including header tank 1, the header tank 1 connect There are water inlet pipe 2 and drainpipe 3, the one end of the water inlet pipe 2 far from header tank 1 to be connect with water pump 15, bottom in the header tank 1 Equipped with immersible pump 7,7 top of the immersible pump connects outlet pipe 3, and control immersible pump 7 is provided on 1 side wall of the header tank and is opened and closed Control dial plate 8, the control dial plate 8 be electrically connected header tank 1 in low water level electronic level switch 9 and high water level electronic type Water level switch 10, the header tank 1 bottom four angle are equipped with universal wheel 13 and wheel clamp device 14.
The side that the header tank 1 connects outlet pipe 3 is equipped with discharge opening 4 and overflow port 5, and discharge opening 4 is in 1 side of header tank Lower part, top of the overflow port 5 in 1 side of header tank.
The low level electronic level switch 9 is located at same level, the high water level electronic type water with 7 bottom surface of immersible pump Bit switch 10 is located at same level with 5 lower end of overflow port.
The box cover that catchments is equipped with handle I 11, handle II 12 and venthole 6.
The utility model is set to tunnel slope appropriate location, and quantity can determine as needed, is used for constructing tunnel relay Pump drainage water.Infiltration and construction water are extracted by water pump 15 in tunnel enters through water inlet pipe 2 in header tank 1, is equipped on header tank 1 Control dial plate 8 can show water level conditions in header tank 1, with the raising of water level in header tank 1, when water level attains to a high place electronics When formula water level switch 10, the automatic opening of immersible pump 7 is drained, when water level is reduced to low level electronic level switch 9, diving Pump 7 is automatically stopped, also can by the opening of 8 manual control immersible pump 7 of control dial plate, stop.
The water in header tank 1 is pumped out into tunnel by outlet pipe 3 by the immersible pump 7 in header tank 1, in header tank 1 Remaining water can be discharged by discharge opening 4;It is more than overflow when water pump 15 is drawn into the construction water of header tank 1 by water inlet pipe 2 When mouth 5, the water in header tank 1 can be flowed out from gap 5, prevent the water in header tank 1 from overflowing;1 upper cover of header tank can open, Dirt or maintenance immersible pump 7 in header tank 1 can be cleared up after opening upper cover by handle I 11;There are four the installations of 1 bottom of header tank Universal wheel 13 and wheel clamp device 14, to facilitate the movement and fixation of header tank;Handle II is installed on lid on header tank 1 12, facilitate lifting or dragging.
The beneficial effects of the utility model are:It can achieve the purpose that lasting draining, catch pit is replaced with header tank, break through Limitation of the catch pit because of all many conditions such as terrain;It is simple in structure, easy to make, easy to remove, floor space is small, can grow Phase Reusability, and long range counter-slope drainage problem is efficiently solved, improve constructing tunnel efficiency.
It is the prior art not state part in the above content carefully, therefore does not run business into particular one and state.

Claims (4)

  1. The relay pump drainage water installations 1. a kind of mobile tunnel is constructed, including header tank(1), it is characterised in that:The header tank(1) It is connected with water inlet pipe(2)And drainpipe(3), the water inlet pipe(2)Far from header tank(1)One end and water pump(15)Connection, institute State header tank(1)Interior bottom is equipped with immersible pump(7), the immersible pump(7)Top connects outlet pipe(3), the header tank(1)Side Control immersible pump is provided on wall(7)The control dial plate of keying(8), the control dial plate(8)It is electrically connected header tank(1)Interior is low Electronic water level formula water level switch(9)With high water level electronic level switch(10), header tank (1) bottom four angle is equipped with Universal wheel(13)And wheel clamp device(14).
  2. 2. a kind of mobile tunnel construction relay pump drainage water installations according to claim 1, it is characterised in that:The header tank (1)Connect outlet pipe(3)Side be equipped with discharge opening(4)And overflow port(5), discharge opening(4)In header tank(1)Under side Portion, overflow port(5)In header tank(1)The top of side.
  3. 3. a kind of mobile tunnel construction relay pump drainage water installations according to claim 1, it is characterised in that:The low water level Electronic level switch(9)With immersible pump(7)Bottom surface is located at same level, the high water level electronic level switch(10)With Overflow port(5)Lower end is located at same level.
  4. 4. a kind of mobile tunnel construction relay pump drainage water installations according to claim 1, it is characterised in that:The header tank (1)Upper lid is equipped with handle I(11), handle II(12)And venthole(6).
CN201820184720.1U 2018-02-02 2018-02-02 A kind of mobile tunnel construction relay pump drainage water installations Expired - Fee Related CN208073549U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820184720.1U CN208073549U (en) 2018-02-02 2018-02-02 A kind of mobile tunnel construction relay pump drainage water installations

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820184720.1U CN208073549U (en) 2018-02-02 2018-02-02 A kind of mobile tunnel construction relay pump drainage water installations

Publications (1)

Publication Number Publication Date
CN208073549U true CN208073549U (en) 2018-11-09

Family

ID=64036945

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820184720.1U Expired - Fee Related CN208073549U (en) 2018-02-02 2018-02-02 A kind of mobile tunnel construction relay pump drainage water installations

Country Status (1)

Country Link
CN (1) CN208073549U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108266225A (en) * 2018-02-02 2018-07-10 中铁隧道局集团有限公司 A kind of mobile tunnel construction relay pump drainage water installations

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108266225A (en) * 2018-02-02 2018-07-10 中铁隧道局集团有限公司 A kind of mobile tunnel construction relay pump drainage water installations

Similar Documents

Publication Publication Date Title
CN206220235U (en) A kind of integral intelligent pumping plant
CN207812587U (en) A kind of effective anti-block apparatus of construction drainage
CN203782853U (en) Hydrodynamic self-control initial rainwater abandoning device
CN203284881U (en) Intelligent integrated sewage lifting device
CN208685753U (en) A kind of municipal box culvert sewage converging system
CN106930397B (en) A kind of biological delaying basin that initial rainwater can be persistently handled within the dry spell
CN208073549U (en) A kind of mobile tunnel construction relay pump drainage water installations
CN108266225A (en) A kind of mobile tunnel construction relay pump drainage water installations
CN221074352U (en) Automatic water draining device
CN202038895U (en) Full-automatic deslagging, oil separating and lifting integrated equipment
CN202073172U (en) On-pump type sewage lifting device
CN203701210U (en) Automatic water drainage device for recycle water collection pool
CN208229479U (en) A kind of sewage treatment scum collector
CN210857472U (en) Bury formula dispersion regulation storage battery system
CN209323544U (en) A kind of construction site drainage system
CN107587593A (en) Online device for treating rain water with waterpower tipping bucket flusher
CN210367318U (en) Oil-separating sand-settling device for sewage of villages and towns
CN204134276U (en) A kind of skimmer device
CN206143280U (en) Rare earth extraction device
CN209162980U (en) Rainwater sewage flow distributing device
CN208634046U (en) A kind of river water extraction safety device
CN206859242U (en) The one-stop automation drainage arrangement of multiple spot
CN207761021U (en) Online device for treating rain water with bottom-open type structure flusher
CN207324175U (en) A kind of environment-friendly sewage sedimentation basin
CN112127393A (en) Anti system of floating of basement

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20181109