China
Prior art keywords
portal frame
cucurbit
crosspiece
installing component
pipe installing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820325785.3U
Other languages
Chinese (zh)
Inventor
汤浪洪
刘文喜
李鸿涛
任运刚
尹振奇
李志刚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Fifth Bureau Installation Engineering Co Ltd
Original Assignee
China Construction Fifth Bureau Installation Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Fifth Bureau Installation Engineering Co Ltd filed Critical China Construction Fifth Bureau Installation Engineering Co Ltd
Priority to CN201820325785.3U priority Critical patent/CN208071138U/en
Application granted granted Critical
Publication of CN208071138U publication Critical patent/CN208071138U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The utility model provides a kind of Pipe installing component, including:Portal frame lifts cucurbit, the suspender for lifting pipeline and holder crosspiece and lifts cucurbit, and the bottom end of portal frame lifting cucurbit is fixedly connected on holder crosspiece lifting cucurbit;Portal frame lifting cucurbit includes portal frame column lifting cucurbit and portal frame transverse beam lifting cucurbit, the bottom end of portal frame column lifting cucurbit lifts cucurbit by lock and is movably connected on holder crosspiece lifting cucurbit, and top is movably connected on portal frame transverse beam lifting cucurbit;Suspender is set on portal frame transverse beam lifting cucurbit.The utility model provides Pipe installing component, and portal frame stud is adjustable, meets the piping component installation of different-diameter pipeline.

Description

Pipe installing component
Technical field
The utility model is related to piping component mounting technique fields, are specifically related to a kind of Pipe installing component.
Background technology
, need to be in construction point elder generation pipe laying holder for being horizontally mounted for large-diameter pipeline in existing work progress, then incite somebody to action It is welded to connect on lifting pipeline to holder, later pipe laying system component parts again.
Traditional piping component is equipped with following several method:
1. first heat preservation wooden block is installed on holder, then again pipe laying and carry out welding and pipe laying component parts;
2. first welded pipe line, after multistage pipeline is connected, by the pre-buried expansion bolt on floor, on expansion bolt Welded suspending hook hangs over cucurbit on suspension hook, and according to the segmented conduit length of connection, point a few place's liftings after slinging pipeline, then are pacified Tubulature road wooden block and piping component;
There are following drawbacks for above method
1) wooden block is first installed, the space between pipe-hanger support and floor becomes smaller, increase lifting pipeline difficulty, due to wooden block without Method is fixed, and needs to adjust pipeline in the welding process, in the welding process for the ease of carrying out more downhand weldings and vertical position welding, is reduced Overhead welding, needs to stir pipeline, and the frictional resistance of wooden block is big, and the wooden block in stirring pipe process is caused to be easy to be detached from from holder, Increase security risk;
2) it also needs to adjust pipeline weld width sometimes, and directly drags pipeline and easily damage wooden block, wooden block is caused to topple;
3) first behind installation wooden block position, if the weld bond of pipeline junction is near wooden block, welding heat is transmitted to wooden block Place, easily causes wooden block and catches fire, cause fire hazard;
4) first welded pipe line, then lift, needs pre-buried many places expansion bolt, after the completion of lifting pipeline, it is also necessary to cut off swollen Swollen bolt, increases difficulty of construction, increases working procedure, fragmentary operation is more, and construction efficiency is low.
Invention content
In order to solve the above-mentioned technical problem, the purpose of this utility model is to provide a kind of Pipe installing component, the installations Component can be suitably used for a variety of installation environments, does not unclamp hoisting rope before installation is complete, avoids all kinds of security risks.
The utility model provides a kind of Pipe installing component, including:Portal frame lifts cucurbit, for lifting hanging for pipeline Tool and holder crosspiece lift cucurbit, and the bottom end of portal frame lifting cucurbit is fixedly connected on holder crosspiece lifting cucurbit;Gate-type Frame lifting cucurbit includes portal frame column lifting cucurbit and portal frame transverse beam lifting cucurbit, and portal frame column lifts calabash The bottom end of reed lifts cucurbit by lock and is movably connected on holder crosspiece lifting cucurbit, and top is movably connected on portal frame cross Beam lifts on cucurbit;Suspender is set on portal frame transverse beam lifting cucurbit.
Further, suspender includes lifting steel sleeve lifting cucurbit and suspension hook lifts cucurbit, and lifting steel sleeve lifts cucurbit It is sheathed on portal frame transverse beam lifting cucurbit, suspension hook lifting cucurbit hang on lifting steel sleeve lifting cucurbit.
Further, lifting steel sleeve lifting cucurbit slides along portal frame transverse beam lifting cucurbit is arranged.
Further, suspender further includes bolt lifting cucurbit, and lifting steel sleeve lifting cucurbit lifts cucurbit by bolt and consolidates Due on portal frame transverse beam lifting cucurbit.
Further, multiple bolt lifting calabashes are opened up on lifting steel sleeve lifting cucurbit and portal frame transverse beam lifting cucurbit The mounting hole of reed, two-by-two adjacent mounting hole interval 5cm.
Further, suspender further includes cucurbit lifting cucurbit and rigging lifting cucurbit, and cucurbit lifting cucurbit hang on suspension hook It lifts on cucurbit, rigging lifting cucurbit hang on the load terminal of cucurbit lifting cucurbit.
Further, Pipe installing component further includes lock lifting cucurbit, and it is horizontal with holder that portal frame column lifts cucurbit Shelves lifting cucurbit lifts cucurbit by lock and is fixedly connected.
Further, lock lifting cucurbit includes lock crosspiece lifting cucurbit, shackle sides shelves lifting cucurbit and fixed plate washer Lift cucurbit, shackle sides shelves lifting cucurbit and fixed plate washer lift cucurbit and be relatively arranged on the two opposite of holder crosspiece lifting cucurbit Side;The both ends of lock crosspiece lifting cucurbit lift cucurbit with shackle sides shelves respectively and fixed plate washer lifting cucurbit is fixedly connected, and prop up Frame crosspiece lifting cucurbit is inserted in the top of lock crosspiece lifting cucurbit.
Further, lock lifting cucurbit includes that the first fixing bolt lifting cucurbit and the second fixing bolt lift cucurbit, First fixing bolt lifts cucurbit and the second fixing bolt lifting cucurbit is arranged side by side, and penetrates fixed plate washer lifting cucurbit and abut In on holder crosspiece lifting cucurbit.
Further, interval installation holds out against nut lifting cucurbit in the one side of holder crosspiece lifting cucurbit, and first fixes spiral shell One end of bolt lifting cucurbit and the second fixing bolt lifting cucurbit screws in respectively to be held out against in nut lifting cucurbit.
The technique effect of the utility model:
The utility model provides Pipe installing component, and portal frame stud is adjustable, meets the pipe of different-diameter pipeline Road component parts installation.It is more than the lifting steel bushing of portal frame crossbeam outside dimension by being arranged size on portal frame crossbeam simultaneously Pipe, it is upper on portal frame crossbeam and steel sleeve to be punched every 5cm, bolt connection the two is used in combination.Bolt can select as needed The hole position locking of different positions.
The utility model provides Pipe installing component, and the lock of portal frame column lower part sets 2 clamping screws, improves lock The reliability of button, places accident.Lock may be locked in holder crosspiece any position, can be applied to the suspension and support of a variety of types, Meet different-diameter to install at the piping component of discharge pipe;
The utility model provides Pipe installing component, is locked by adding portal frame on suspension and support, and by latching Mast-up ensure that the stabilization of structural behaviour, and without being welded and fixed, it is in a row can to meet the integral different-diameter of welding The piping component installation requirement of pipeline.Solve traditional handicraft be lifted on suspension and support pipeline welding be linked to be entirety after, installation The big problem of the piping components difficulty such as pipeline valve member, telescopic joint, heat preservation, wooden block.
The described below of the various embodiments that Pipe installing component according to the present utility model proposes specifically is please referred to, will be made The above and other aspect for obtaining the utility model is apparent.
Description of the drawings
Fig. 1 is pipeline mounting assembly use state schematic front view in the preferred embodiment in the utility model.
Fig. 2 is pipeline mounting assembly use state schematic side view in the preferred embodiment in the utility model.
Fig. 3 is pipeline mounting assembly use state elevational schematic view in the preferred embodiment in the utility model.
Marginal data:
0, portal frame;1, portal frame crossbeam;2, column steel sleeve;21, bolt;3, steel sleeve is lifted;31, hanging ring; 4, portal frame column;5, it latches;51, crosspiece is latched;52, shackle sides shelves;53, fixed plate washer;54, screw rod;55, butterfly screw It is female;56, nut is held out against;57, the first fixing nut;58, the second fixing nut;6, cucurbit is lifted;7, steel pipe;8, hoisting rig; 9, holder;91, holder crosspiece.
Specific implementation mode
The attached drawing constituted part of this application is used to provide a further understanding of the present invention, the utility model Illustrative embodiments and their description are not constituted improper limits to the present invention for explaining the utility model.
Pipe installing component provided by the utility model can be used for horizontal large-diameter pipeline assembling.
Referring to Fig. 1, Pipe installing component provided by the utility model, by above the holder crosspiece 91 for having holder 9 One portal frame 0 is set, realizes the lifting to pipeline 7.By being lifted the pipeline 7 being welded to wooden block 10 On, be conducive to improve construction accuracy rate.In one embodiment, 4 lower part of portal frame column, which is set, to be locked with holder crosspiece 91 Lock 5, portal frame 0 and holder 9 are locked into one, moveable lifting steel sleeve 3 is set on portal frame crossbeam 1, is hung The hanging ring 31 of 3 lower section welded bands hole for hoist of steel loading casing, pipeline 7 is entangled with rigging 8, lifting cucurbit 6 is hung on hanging ring 31, calabash Reed suspension hook catches on rigging 8, and multiple portal frames 0 can be arranged, and will weld integral pipeline 7 and the pipe such as slings, then install wooden block 10 Road component parts is put down pipeline 7 with lifting cucurbit 6, and 10 position of adjustment wooden block in due course, ensures that pipeline 7 is preferable with wooden block 10 Fitting, construction efficiency is high, and safety is secure.Lock 5 herein can be U-shaped structure.Lifting cucurbit 6 herein can be electricity It is dynamic, or manually.The top of holder crosspiece 91 is connected by column casing 2 with portal frame 0.
Referring to Fig. 2~3,4 position of portal frame column is adjustable in Pipe installing component provided by the utility model, in gate-type The lifting steel sleeve 3 that one big two models are put on cruciform bracing 1, it is right on portal frame crossbeam 1 and lifting steel sleeve 3 The mounting hole at multiple intervals is set together, is spaced 5cm between adjacent mounting hole two-by-two, be used in combination bolt 21 by the two be linked to be one it is whole Body, bolt 21 select the hole position locking of different positions, by adjust portal frame column 4 and 0 another column of portal frame it Between spacing, realize portal frame 0 can meet different-diameter pipeline 7 piping component installation demand.Bolt used herein 21 can be all kinds of common bolts, preferably Y types bolt.
Preferably, lock 5 includes lock crosspiece 51, shackle sides shelves 52 and fixed plate washer 53, shackle sides shelves 52 and fixed gear Plate 53 is relatively arranged on the two opposite sides of holder crosspiece 91;Latch crosspiece 51 both ends respectively with shackle sides shelves 52 and fixation plate washer 53 are fixedly connected, and holder crosspiece 91 is inserted in the top of lock crosspiece 51.Lock 5 includes that the first fixing bolt and second fix spiral shell Bolt, the first fixing bolt and the second fixing bolt are arranged side by side, and penetrate fixed plate washer 53 and be connected on holder crosspiece 91.Holder Interval, which is installed, in the one side of crosspiece 91 holds out against nut 56, and one end of the first fixing bolt and the second fixing bolt screws in respectively to be held out against In nut 56.4 lower latch 5 of portal frame column latches and sets the first fixing bolt and the second fixing bolt on 5, will 5 lock of lock It is scheduled on holder crosspiece 91, lock 5 may be locked in 91 any position of holder crosspiece, can be applied to the suspension and support of a variety of types, meet Different-diameter is installed at the piping component of discharge pipe 7;
The front end welding of screw rod 54 on lock 5 holds out against nut 56, is held out against on nut 56 and holder crosspiece 91 with increasing Contact area welds twice fixation plate washer 53 to increase the frictional force that it holds out against on shackle sides shelves 52.First fixing nut 57, it is welded on the web of shackle sides shelves 52, the second fixing nut 58 is welded on fixed plate washer 53, the screw rod on lock 5 54 rear end welding butterfly screw mother 55;Nut 56 is held out against by rotating butterfly screw mother 55, at two with holder crosspiece 91 to be close to, Achieve the purpose that portal frame 0 being fixed on 91 any position of holder crosspiece.
In use, a portal frame 0 is arranged above holder crosspiece 91,4 lower part of portal frame column sets lock 5, will Portal frame column 4 is locked with portal frame crossbeam 1 and holder crosspiece 91.Moveable lifting is set on portal frame crossbeam 1 Point entangles pipeline 7 with rigging 8, and lifting cucurbit 6 is hung on lifting point, and lifting 6 suspension hook of cucurbit catches on rigging 8, and multiple doors are arranged The pipeline 7 for welding integral is sling, then installs the components such as wooden block 10 and piping component by formula frame 0, will with lifting cucurbit 6 Pipeline 7 is put down, and 10 position of adjustment wooden block in due course, ensures that pipeline 7 is preferably bonded with wooden block 10, construction efficiency is high, has safely It ensures.
Those skilled in the art will be clear that the scope of the utility model is not limited to example discussed above, it is possible to it Several changes and modification are carried out, the scope of the utility model limited without departing from the appended claims.Although oneself is through attached The utility model is illustrated and described in detail in figure and specification, but such illustrate and describe only is explanation or schematical, And not restrictive.The utility model is not limited to the disclosed embodiments.
By to attached drawing, the research of specification and claims, those skilled in the art when implementing the utility model It is appreciated that and realizes the deformation of the disclosed embodiments.In detail in the claims, term " comprising " be not excluded for other steps or Element, and indefinite article "one" or "an" be not excluded for it is multiple.That quotes in mutually different dependent claims is certain The fact that measure, does not mean that the combination of these measures cannot be advantageously used.Any reference marker in claims is not Constitute the limitation to the scope of the utility model.

Claims (10)

1. a kind of Pipe installing component, which is characterized in that including:Portal frame (0), suspender and branch for lifting the pipeline The bottom end of frame crosspiece (91), the portal frame (0) is fixedly connected on the holder crosspiece (91);The portal frame (0) Including portal frame column (4) and portal frame crossbeam (1), the bottom end of the portal frame column (4) passes through lock (5) activity It is connected on the holder crosspiece (91), top is movably connected on the portal frame crossbeam (1);The portal frame crossbeam (1) suspender is set on.
2. Pipe installing component according to claim 1, which is characterized in that the suspender include lifting steel sleeve (3) and Suspension hook (31), the lifting steel sleeve (3) are sheathed on the portal frame crossbeam (1), and the suspension hook (31) hang on described It lifts on steel sleeve (3).
3. Pipe installing component according to claim 2, which is characterized in that the lifting steel sleeve (3) is along the gate-type Cruciform bracing (1) sliding setting.
4. Pipe installing component according to claim 2, which is characterized in that the suspender further includes bolt (21), described Lifting steel sleeve (3) is fixed on by the bolt (21) on the portal frame crossbeam (1).
5. Pipe installing component according to claim 4, which is characterized in that the lifting steel sleeve (3) and the gate-type The mounting hole of multiple bolts (21) is opened up on cruciform bracing (1), two-by-two the adjacent mounting hole interval 5cm.
6. the Pipe installing component according to any one of claim 2~5, which is characterized in that the suspender further includes calabash Reed (6) and rigging (8), the cucurbit (6) hang on the suspension hook (31), and the rigging (8) hang on the cucurbit (6) Load terminal.
7. Pipe installing component according to claim 1, which is characterized in that the Pipe installing component further includes lock (5), the portal frame column (4) is fixedly connected with the holder crosspiece (91) by the lock (5).
8. Pipe installing component according to claim 7, which is characterized in that the lock (5) include lock crosspiece (51), Shackle sides shelves (52) and fixed plate washer (53), the shackle sides shelves (52) and the fixed plate washer (53) are relatively arranged on the branch The two opposite sides of frame crosspiece (91);It is described lock crosspiece (51) both ends respectively with the shackle sides shelves (52) and the fixed gear Plate (53) is fixedly connected, and the holder crosspiece (91) is inserted in the top of the lock crosspiece (51).
9. Pipe installing component according to claim 8, which is characterized in that the lock (5) includes the first fixing bolt With the second fixing bolt, first fixing bolt and second fixing bolt are arranged side by side, and penetrate the fixed plate washer (53) it is connected on the holder crosspiece (91).
10. Pipe installing component according to claim 9, which is characterized in that between in the one side of the holder crosspiece (91) Hold out against nut (56) every installation, one end of first fixing bolt and second fixing bolt screw in respectively described in hold out against spiral shell In female (56).
CN201820325785.3U 2018-03-09 2018-03-09 Pipe installing component Expired - Fee Related CN208071138U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820325785.3U CN208071138U (en) 2018-03-09 2018-03-09 Pipe installing component

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820325785.3U CN208071138U (en) 2018-03-09 2018-03-09 Pipe installing component

Publications (1)

Publication Number Publication Date
CN208071138U true CN208071138U (en) 2018-11-09

Family

ID=64038955

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820325785.3U Expired - Fee Related CN208071138U (en) 2018-03-09 2018-03-09 Pipe installing component

Country Status (1)

Country Link
CN (1) CN208071138U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111306363A (en) * 2020-03-11 2020-06-19 中建八局第二建设有限公司 Assembly type fire pump room hoisting construction method and construction structure based on BIM technology
CN111335535A (en) * 2020-03-17 2020-06-26 南京尚艺良品科技有限公司 Ceiling framework structure with open type pipeline fixer

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111306363A (en) * 2020-03-11 2020-06-19 中建八局第二建设有限公司 Assembly type fire pump room hoisting construction method and construction structure based on BIM technology
CN111335535A (en) * 2020-03-17 2020-06-26 南京尚艺良品科技有限公司 Ceiling framework structure with open type pipeline fixer

Similar Documents

Publication Publication Date Title
US6457692B1 (en) Hanger bracket for installing and supporting suspended equipment
CN208071138U (en) Pipe installing component
CN110253195B (en) High-precision pipeline butt joint device
JP2015183375A (en) Ceiling suspending bolt, ceiling material fitting device and universal joint
CN201614731U (en) Novel electric lifting scaffold
CN117735384A (en) Combined lifting appliance for precast pile lifting and precast pile lifting method
CN216078621U (en) Pipeline hoisting device applied to I-shaped steel structure
JP4160609B2 (en) Master rope fixture
CN213484413U (en) Municipal works interlude cable special stand
CN210041237U (en) Bus duct gallows convenient to installation
CN210318833U (en) Single-pipe hoisting support structure for underground passage
JP2015042579A (en) Attitude changing device and method of using attitude changing device
CN209194362U (en) Rod piece connects levelling device between a kind of suspension bridge steel truss beam section
CN215519223U (en) I-shaped beam hanging hanger
CN218441682U (en) Electromechanical equipment hoisting frame for I-shaped steel beam
CN113833289B (en) Shed frame anti-falling system and construction method thereof
CN221621231U (en) Slip fire catching pocket
CN214195185U (en) Installation structure of bent plate for splicing operating room
JP2018080576A (en) Suspending bolt for ceiling and ceiling material fitting device
CN218502563U (en) Suspension hanger for coating oil tank
CN219528491U (en) Hanging mechanism and safety protection device for steel structure building construction
CN220502441U (en) Self-adaptive adjustable pipeline mounting clamp
CN114030977B (en) Hoisting auxiliary device for rapidly installing angle steel bracket of pavement of railway bridge deck system
CN212297950U (en) Novel hoisting piece and hanging bracket
CN217681632U (en) Vertical elevator instrument of body

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20181109

CF01 Termination of patent right due to non-payment of annual fee