CN208056613U - A kind of overhanging type framed bent sets up structure - Google Patents

A kind of overhanging type framed bent sets up structure Download PDF

Info

Publication number
CN208056613U
CN208056613U CN201721517053.6U CN201721517053U CN208056613U CN 208056613 U CN208056613 U CN 208056613U CN 201721517053 U CN201721517053 U CN 201721517053U CN 208056613 U CN208056613 U CN 208056613U
Authority
CN
China
Prior art keywords
less
bent frame
cantilevered
vertical
bar
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201721517053.6U
Other languages
Chinese (zh)
Inventor
王登银
蒋胜祥
何展国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Huadong Engineering Corp Ltd
Original Assignee
PowerChina Huadong Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Huadong Engineering Corp Ltd filed Critical PowerChina Huadong Engineering Corp Ltd
Priority to CN201721517053.6U priority Critical patent/CN208056613U/en
Application granted granted Critical
Publication of CN208056613U publication Critical patent/CN208056613U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Devices Affording Protection Of Roads Or Walls For Sound Insulation (AREA)

Abstract

本实用新型提供了一种悬挑式排架搭设结构,包括悬挑梁、连墙件、柔性拉锚绳、立杆、大横杆、小横杆、剪刀撑;悬挑梁设置斜撑;所述连墙件与岩面夹角为45~90°;所述柔性拉锚绳一端连接连墙件,另一端和悬挑梁连接;立杆的底部设置在支撑平台上,支撑平台焊接在悬挑梁上;所述大横杆沿排架的长度方向设置,大横杆和立杆用扣件连接,左右相邻的两段大横杆间搭接并用扣件固定;所述小横杆铺设在大横杆上面,小横杆不与岩面直接接触;剪刀撑的斜杆与大横杆连接。本实用新型提高了悬挑式排架的稳定性,保证施工安全,且搭设方便简单,适用于水利水电、交通桥梁、矿山中的高陡边坡支护等类似工程。

The utility model provides a cantilevered bent frame erecting structure, comprising cantilevered beams, wall parts, flexible anchor ropes, vertical poles, large horizontal bars, small horizontal bars, and scissors braces; the cantilevered beams are provided with diagonal braces; The angle between the wall part and the rock face is 45-90°; one end of the flexible anchor rope is connected to the wall part, and the other end is connected to the cantilever beam; the bottom of the pole is set on the support platform, and the support platform is welded on On the cantilever beam; the large horizontal bar is arranged along the length direction of the bent frame, the large horizontal bar and the vertical bar are connected by fasteners, and the left and right adjacent two sections of large horizontal bars are overlapped and fixed by fasteners; the small horizontal bar The poles are laid on the large crossbars, and the small crossbars are not in direct contact with the rock face; the inclined bars of the scissor brace are connected with the large crossbars. The utility model improves the stability of the cantilever bent frame, ensures construction safety, and is convenient and simple to erect, and is suitable for water conservancy and hydropower, traffic bridges, high and steep side slope support in mines and similar projects.

Description

一种悬挑式排架搭设结构A cantilevered bent frame erection structure

技术领域technical field

本发明涉及一种悬挑式排架搭设结构及施工方法,主要适用于水利水电、交通桥梁、矿山中的高陡边坡支护等类似工程。The invention relates to a cantilevered bent frame erecting structure and a construction method, which are mainly applicable to water conservancy and hydropower, traffic bridges, high and steep side slope support in mines and similar projects.

背景技术Background technique

排架亦称脚手架,指施工现场为工人操作并解决垂直和水平运输而搭设的各种支架,其由钢管、扣件等组成。随着国家基础设施建设的高速发展,排架搭设的高度也越来越高,安全生产风险显著增加。据国家安全部门统计,工程中的安全事故伤亡人数中,由于排架失事造成的占比超过60%。Bent frame, also known as scaffolding, refers to various supports erected on the construction site for workers to operate and solve vertical and horizontal transportation. It is composed of steel pipes, fasteners, etc. With the rapid development of national infrastructure construction, the height of racking is getting higher and higher, and the risk of safety production has increased significantly. According to the statistics of the national security department, among the casualties of safety accidents in the project, more than 60% were caused by the accident of racking.

排架主要分为两种,即落地式排架和悬挑式排架,前者由于可以搭设在地基上,安全可靠性有一定的保证;而悬挑式排架无基础,属于悬空排架,安全风险极大。There are two main types of bent racks, namely, floor bent racks and cantilevered bent racks. The former can be erected on the foundation, so the safety and reliability are guaranteed to a certain extent; while the cantilever bent racks have no foundation and belong to suspended bent racks. The security risk is huge.

发明内容Contents of the invention

本发明首先要解决的技术问题是:针对上述存在的问题,提供一种悬挑式排架搭设结构,主要适用于水利水电、交通桥梁、矿山中的高陡边坡支护等类似工程。本发明所采用的技术方案是:The first technical problem to be solved by the present invention is to provide a cantilever bent frame erection structure for the above existing problems, which is mainly suitable for water conservancy and hydropower, traffic bridges, high and steep slope support in mines and other similar projects. The technical scheme adopted in the present invention is:

一种悬挑式排架搭设结构,其特征在于包括悬挑梁、连墙件、柔性拉锚绳、立杆、大横杆、小横杆、剪刀撑;A cantilevered bent frame erection structure is characterized in that it includes cantilever beams, wall parts, flexible anchor ropes, vertical poles, large horizontal bars, small horizontal bars, and scissors braces;

悬挑梁设置斜撑;所述连墙件与岩面夹角为45~90°;所述柔性拉锚绳一端连接连墙件,另一端和悬挑梁连接;立杆的底部设置在支撑平台上,支撑平台焊接在悬挑梁上;所述大横杆沿排架的长度方向设置,大横杆和立杆用扣件连接,左右相邻的两段大横杆间搭接并用扣件固定;所述小横杆铺设在大横杆上面,小横杆不与岩面直接接触;剪刀撑的斜杆与大横杆连接。The cantilever beam is provided with diagonal braces; the angle between the wall part and the rock face is 45-90°; one end of the flexible anchor rope is connected to the wall part, and the other end is connected to the cantilever beam; the bottom of the vertical rod is set on the support On the platform, the support platform is welded on the cantilever beam; the large horizontal bar is arranged along the length direction of the bent frame, the large horizontal bar and the vertical bar are connected by fasteners, and the left and right adjacent two sections of large horizontal bars are overlapped and connected with buckles. The parts are fixed; the small crossbar is laid on the large crossbar, and the small crossbar does not directly contact with the rock face; the inclined bar of the scissors brace is connected with the large crossbar.

进一步地,当悬挑式排架高度大于12m时,所述悬挑排架搭设结构设置有多层悬挑梁。Further, when the height of the cantilevered bent frame is greater than 12m, the erected structure of the cantilevered bent frame is provided with multi-layered cantilevered beams.

进一步地,悬挑梁采用16#槽钢,悬挑梁间距L按立杆纵距设置,每一纵距设置一根;入岩锚固长度不小于2.5m;斜撑采用12#槽钢,入岩一般按照2.0m左右控制;悬挑梁与斜撑的夹角Q一般取30~45°。Further, the cantilever beams are made of 16# channel steel, and the spacing L of the cantilever beams is set according to the vertical distance of the vertical pole, and one is set for each vertical distance; the anchorage length into the rock is not less than 2.5m; The rock is generally controlled at about 2.0m; the angle Q between the cantilever beam and the diagonal brace is generally 30-45°.

进一步地,连墙件采用插筋。Further, the wall-connecting parts adopt inserting ribs.

进一步地,连墙件采用插筋,插筋应采用不小于φ25mm的螺纹钢筋;连墙件插筋长不小于1.0m,入岩不小于0.6m,外露0.4m。Further, the wall parts adopt inserting bars, and the inserting bars should adopt threaded steel bars not less than φ25mm; the length of the inserting bars of the wall parts is not less than 1.0m, the entry into the rock is not less than 0.6m, and the exposed area is 0.4m.

进一步地,柔性拉锚绳采用Φ16mm钢绳,柔性拉锚绳与水平面成上倾30~45°,拉锚绳两端采用绳卡固定成环,每端不少于3道绳卡。Further, the flexible anchor rope adopts a Φ16mm steel rope, and the flexible anchor rope is inclined 30-45° from the horizontal plane. Both ends of the anchor rope are fixed into a ring with rope clips, and each end is not less than 3 rope clips.

进一步地,支撑平台采用16#槽钢,焊接在悬挑梁的上部,立杆底部放入支撑平台的16# 槽钢凹槽内;每根立杆对应支撑平台槽钢部位焊接Φ25mm的螺纹钢筋将立杆固定于支撑平台槽钢凹槽上,外侧立杆固定点距离悬挑梁端部不小于0.1m。Further, the support platform is made of 16# channel steel, which is welded on the upper part of the cantilever beam, and the bottom of the vertical pole is placed in the groove of the 16# channel steel of the support platform; each vertical pole is welded with a Φ25mm threaded steel bar corresponding to the channel steel part of the support platform. The vertical rod is fixed on the channel steel groove of the supporting platform, and the fixed point of the outer vertical rod is not less than 0.1m from the end of the cantilever beam.

进一步地,所述立杆的搭接长度不小于1m,连接处用不少于三个扣件固定;所述大横杆的搭接长度不小于1m,连接处用不少于三个扣件固定。Further, the overlapping length of the vertical bar is not less than 1m, and the connection is fixed with no less than three fasteners; the overlapping length of the large horizontal bar is not less than 1m, and the connection is fixed with no less than three fasteners fixed.

进一步地,剪刀撑采用与大横杆相同钢管材料,设置时按照横向到底、纵向到边的原则;每道剪刀撑宽度不小于4跨,且不小于6m宽,剪刀撑的斜杆与地面的倾角在45~60°之间。Furthermore, the scissors bracing is made of the same steel pipe material as the large horizontal bar, and it is set according to the principle of horizontal bottom and vertical to edge; the width of each scissor brace is not less than 4 spans, and the width is not less than 6m. The inclination angle is between 45° and 60°.

本发明还提供了一种悬挑式排架搭设结构的施工工法,其特征在于包括以下步骤:The present invention also provides a construction method of a cantilevered bent frame erecting structure, which is characterized in that it includes the following steps:

(1)基础岩面清理,(1) Foundation rock surface cleaning,

施工前将基础岩面的危石进行系统清理,防止在后续施工中危石脱落;Before the construction, the dangerous stones on the foundation rock surface shall be systematically cleaned to prevent the dangerous stones from falling off in the subsequent construction;

(2)悬挑梁设置,(2) cantilever beam setting,

悬挑式排架底部设置悬挑梁2,悬挑梁采用16#槽钢,悬挑梁间距L按悬挑架架体立杆纵距设置,每一纵距设置一根;悬挑梁悬挑长度按2.0m设置,入岩锚固长度不小于2.5m,悬挑梁设置斜撑,斜撑采用12#槽钢,入岩一般按照2.0m左右控制;悬挑梁与斜撑的夹角 Q一般取30~45°;当悬挑式排架高度大于12m时,在垂直高度上分层设置悬挑梁;Cantilever beams 2 are set at the bottom of the cantilever bent frame. The cantilever beams are made of 16# channel steel. The cantilever length is set according to 2.0m, the anchorage length into the rock is not less than 2.5m, the cantilever beam is equipped with diagonal braces, and the diagonal braces are made of 12# channel steel, and the rock entry is generally controlled according to about 2.0m; the angle between the cantilever beam and the diagonal brace Generally, 30-45° is taken; when the height of the cantilever bent frame is greater than 12m, the cantilever beams are arranged layer by layer on the vertical height;

(3)连墙件设置:(3) Setting of connecting wall parts:

连墙件采用插筋,插筋应采用不小于φ25mm的螺纹钢筋,插筋与基础岩面夹角为45~90 °,具体根据现场地形条件确定,在地形条件允许的情况下,取45°;连墙件插筋长不小于1.0m,入岩不小于0.6m,外露0.4m;连墙件按照设计间排距进行布设,对于高度超过24m的悬挑式排架,间排距不得小于两步两跨;Inserting bars are used for connecting wall parts, and the inserting bars should be threaded steel bars not less than φ25mm. The angle between the inserting bars and the foundation rock surface is 45-90°, which is determined according to the site terrain conditions. If the terrain conditions permit, 45° is used. ; The length of the inserted ribs of the wall parts shall not be less than 1.0m, the length of the intrusion into the rock shall not be less than 0.6m, and the exposed area shall be 0.4m; two steps and two strides;

(4)柔性拉锚绳连接(4) flexible anchor rope connection

柔性拉锚绳采用Φ16mm钢绳,与悬挑梁外端绳卡固定,拉锚绳与水平面成上倾45°角,拉锚绳两端采用绳卡固定成环,每端不少于3道绳卡,并分别与连墙件和悬挑梁套接;The flexible anchor rope adopts Φ16mm steel rope, which is fixed with the outer end of the cantilever beam. The anchor rope and the horizontal plane form an upward angle of 45°. , and respectively socketed with the wall parts and cantilever beams;

(5)立杆连接和设置(5) Pole connection and setting

立杆的底部设置在支撑平台上,支撑平台采用16#槽钢,支撑平台焊接在悬挑梁上,立杆底部放入支撑平台的16#槽钢凹槽内;每根立杆对应槽钢部位焊接Φ25mm的螺纹钢筋将立杆固定于槽钢凹槽上,外侧立杆固定点距离悬挑梁端部不小于0.1m;The bottom of the pole is set on the support platform, the support platform is made of 16# channel steel, the support platform is welded on the cantilever beam, the bottom of the pole is placed in the groove of the 16# channel steel of the support platform; Weld the Φ25mm threaded steel bar to fix the pole on the groove of the channel steel, and the distance from the fixed point of the outer pole to the end of the cantilever beam is not less than 0.1m;

(6)大横杆设置(6) Large crossbar setting

大横杆和立杆用扣件连接,左右相邻的两段大横杆间搭接并用扣件固定,搭接长度不小于1m,不少于三个扣件;The large horizontal bar and the vertical bar are connected with fasteners, and the left and right adjacent two sections of large horizontal bars are overlapped and fixed with fasteners. The overlapping length is not less than 1m and not less than three fasteners;

(7)小横杆设置(7) Small horizontal bar setting

小横杆铺设在大横杆上部,两者用扣件固定,小横杆采用与大横杆相同的钢管材料;小横杆不与基础岩面直接接触,两者相隔距离一般在0.2m左右;The small horizontal bar is laid on the upper part of the large horizontal bar, and the two are fixed with fasteners. The small horizontal bar is made of the same steel pipe material as the large horizontal bar; the small horizontal bar is not in direct contact with the foundation rock surface, and the distance between the two is generally about 0.2m ;

(8)剪刀撑设置(8) Scissors setting

剪刀撑的斜杆与大横杆连接,剪刀撑采用与大横杆相同钢管材料,设置时按照横向到底、纵向到边的原则;每道剪刀撑宽度不小于4跨,且不小于6m宽,剪刀撑的斜杆与地面的倾角在45~60°之间。The oblique bar of the scissors brace is connected with the large crossbar, and the scissors brace is made of the same steel pipe material as the large crossbar, and it is set according to the principle of horizontal bottom and vertical edge; the width of each scissors brace is not less than 4 spans and not less than 6m wide. The inclination angle between the oblique bar of the scissors brace and the ground is between 45° and 60°.

本发明提高了悬挑式排架的稳定性,保证施工安全,且搭设方便简单,适用于水利水电、交通桥梁、矿山中的高陡边坡支护等类似工程。The invention improves the stability of the cantilever bent frame, ensures construction safety, is convenient and simple to erect, and is suitable for water conservancy and hydropower, traffic bridges, high and steep side slope support in mines and similar projects.

附图说明:Description of drawings:

图1是本发明悬挑式排架搭设结构实施例在一个典型局部的正面示意图。Fig. 1 is a front schematic view of a typical part of the embodiment of the cantilevered bent frame erecting structure of the present invention.

图2是本发明悬挑式排架搭设结构实施例在另一个典型局部的剖面图。Fig. 2 is a cross-sectional view of another typical part of the embodiment of the cantilevered bent frame erecting structure of the present invention.

图3是立杆和大横杆被扣件固定的示意图。Fig. 3 is a schematic diagram of the vertical bar and the large horizontal bar being fixed by fasteners.

图4是连墙件的示意图。Fig. 4 is a schematic diagram of the wall connecting piece.

图5是大横杆搭接并被扣件固定的示意图。Fig. 5 is a schematic diagram of the overlapping of large crossbars and being fixed by fasteners.

具体实施方式Detailed ways

参照附图。本发明所提供的悬挑式排架搭设结构,包括悬挑梁2、连墙件3、柔性拉锚绳4、立杆5、大横杆6、小横杆7、剪刀撑8。Refer to attached picture. The cantilevered bent frame erection structure provided by the present invention includes cantilever beams 2 , wall parts 3 , flexible anchor ropes 4 , vertical poles 5 , large crossbars 6 , small crossbars 7 , and scissor braces 8 .

本发明一种悬挑排架搭设结构施工方法的实施方式为:The embodiment of the construction method of a cantilever bent frame erecting structure of the present invention is as follows:

a.基础岩面1清理:如附图2所示,为保证排架搭设、运行及拆除过程中的安全,施工前将基础岩面1的危石进行系统清理,防止在后续施工中危石脱落,危及下部施工人员、设备安全。a. Cleaning of foundation rock surface 1: As shown in Figure 2, in order to ensure the safety during the erection, operation and dismantling of the bent frame, the dangerous rocks on the foundation rock surface 1 are systematically cleaned before construction to prevent dangerous stones in subsequent construction If it falls off, it will endanger the safety of the construction personnel and equipment in the lower part.

b.悬挑梁2设置:悬挑式排架底部设置悬挑梁2,悬挑梁2一般采用16#槽钢,悬挑梁2间距L按悬挑架架体立杆5纵距设置,每一纵距设置一根。悬挑梁2悬挑长度L1一般按 2.0m设置,入岩锚固长度L2不小于2.5m,悬挑梁2设置斜撑20,斜撑一般采用12#槽钢,斜撑总长6.5m,入岩一般按照2.0m左右控制。悬挑梁2与斜撑20的夹角Q一般取30~45 °,角度不易过小,具体取值依据现场地形条件决定。b. Cantilever beam 2 setting: the cantilever beam 2 is set at the bottom of the cantilever bent frame. The cantilever beam 2 is generally made of 16# channel steel. Set one for each longitudinal distance. The cantilever length L1 of the cantilever beam 2 is generally set at 2.0m, and the anchorage length L2 into the rock is not less than 2.5m. Generally, it is controlled according to about 2.0m. The included angle Q between the cantilever beam 2 and the diagonal brace 20 is generally taken as 30-45°, and the angle should not be too small, and the specific value is determined according to the site topographical conditions.

为确保排架安全,当悬挑式排架高度大于12m时,应在垂直高度上分层设置悬挑梁2,悬挑梁2的层高H一般为8~12m,具体取值视排架整体高度确定。In order to ensure the safety of the bent frame, when the height of the cantilevered bent frame is greater than 12m, the cantilever beam 2 should be arranged in layers on the vertical height. The height H of the cantilever beam 2 is generally 8-12m, and the specific value depends on The overall height is determined.

c.连墙件3设置:悬挑式排架连墙件3采用插筋,插筋应采用不小于φ25mm的螺纹钢筋,插筋与基础岩面1夹角为45~90°,具体根据现场地形条件确定,在地形条件允许的情况下,取45°;连墙件3插筋长不小于1.0m,入岩不小于0.6m,外露0.4m;连墙件3按照设计间排距进行布设,对于高度超过24m的悬挑式排架,间排距不得小于两步两跨。c. Setting of wall connecting piece 3: the cantilevered bent frame connecting wall piece 3 adopts inserting ribs, and the inserting ribs should adopt threaded steel bars not less than φ25mm, and the angle between the inserting ribs and the foundation rock surface 1 is 45-90°, depending on the site The terrain conditions are determined, and if the terrain conditions permit, take 45°; the length of the inserted reinforcement of the connecting wall part 3 is not less than 1.0m, the length of the inserted rock is not less than 0.6m, and the exposed area is 0.4m; the connecting wall parts 3 are arranged according to the row spacing between the design , for cantilevered bent frames with a height exceeding 24m, the distance between rows shall not be less than two steps and two spans.

d.柔性拉锚绳4连接:柔性拉锚绳4采用Φ16mm钢绳与悬挑梁2外端绳卡固定,拉锚绳4与水平面成上倾45°角,拉锚绳4两端采用绳卡固定成环40,每端不少于3道绳卡,并分别与连墙件外露部分和悬挑梁2套接。d. Connection of the flexible anchor rope 4: The flexible anchor rope 4 is fixed with a Φ16mm steel rope and the outer end rope of the cantilever beam 2. The anchor rope 4 and the horizontal plane form an upward angle of 45°. The clips are fixed into a ring 40, with no less than 3 rope clips at each end, and are respectively socketed with the exposed part of the wall part and the cantilever beam 2.

e.立杆5设置:排架的立杆5设置在支撑平台21上,支撑平台21采用16#槽钢,支撑平台21焊接在悬挑梁2上,立杆5底部放入支撑平台21的16#槽钢凹槽内。每根立杆5对应槽钢部位焊接Φ25mm、L=0.2m的螺纹钢筋将立杆固定于槽钢凹槽上,外侧立杆固定点距离悬挑梁2端部不小于0.1m。e. Pole 5 setting: the vertical pole 5 of the bent frame is set on the support platform 21, the support platform 21 adopts 16# channel steel, the support platform 21 is welded on the cantilever beam 2, and the bottom of the vertical pole 5 is put into the support platform 21 16# channel steel groove. Each upright pole 5 is welded with Φ25mm, L=0.2m threaded steel bars corresponding to the channel steel part to fix the upright pole on the groove of the channel steel, and the distance from the fixed point of the outer upright pole to the end of the cantilever beam 2 is not less than 0.1m.

f.大横杆6设置:大横杆6和立杆5用扣件9连接,左右相邻的两段大横杆间搭接并用扣件9固定,大横杆6宜采用6m的钢管,以减少搭接,搭接时,搭接长度不小于1m,不少于三个扣件。f. Large horizontal bar 6 setting: the large horizontal bar 6 and the vertical bar 5 are connected with fasteners 9, and the left and right adjacent two sections of large horizontal bars are overlapped and fixed with fasteners 9. The large horizontal bar 6 should be a 6m steel pipe. In order to reduce lap joints, when lap joints, the length of the lap joints shall not be less than 1m, and shall not be less than three fasteners.

g.小横杆7设置:小横杆7铺设在大横杆6上部,两者用扣件9固定,小横杆7采用与大横杆6相同钢管材料;小横杆7不应与基础岩面1直接接触,两者相隔距离一般在0.2m 左右。g. Small crossbar 7 setting: The small crossbar 7 is laid on the upper part of the large crossbar 6, and the two are fixed with fasteners 9. The small crossbar 7 is made of the same steel pipe material as the large crossbar 6; the small crossbar 7 should not be connected with the foundation The rock face 1 is in direct contact, and the distance between the two is generally about 0.2m.

h.剪刀撑8设置:剪刀撑的斜杆与大横杆用扣件9连接,剪刀撑8采用与大横杆6相同钢管材料,设置时要求按照横向到底、纵向到边的原则;每道剪刀撑8宽度不应小于4 跨,且不应小于6m宽,剪刀撑8的斜杆与地面的倾角应在45~60°之间。h. Setting of scissors brace 8: The oblique bar of scissors brace is connected with the large horizontal bar with fastener 9, and the scissors brace 8 is made of the same steel pipe material as that of the large horizontal bar 6, and it is required to follow the principle of horizontal to bottom and vertical to edge when setting; The width of the scissors brace 8 should not be less than 4 spans, and should not be less than 6m wide, and the inclination angle between the oblique bar of the scissors brace 8 and the ground should be between 45° and 60°.

上述说明并非对本发明的限制,本发明也并不限于上述举例,本技术领域的普通技术人员,在本发明的范围内,做出的变化、改添加或替换,都应属于本发明的保护范围。The above description is not a limitation of the present invention, and the present invention is not limited to the above examples. Those of ordinary skill in the art, within the scope of the present invention, make changes, additions or substitutions, which should belong to the protection scope of the present invention .

Claims (9)

1.一种悬挑式排架搭设结构,其特征在于包括悬挑梁、连墙件、柔性拉锚绳、立杆、大横杆、小横杆、剪刀撑;1. A cantilevered bent frame erecting structure is characterized in that it comprises cantilever beams, wall parts, flexible anchor ropes, vertical bars, large cross bars, small cross bars, and scissors braces; 悬挑梁设置斜撑;Cantilever beams are provided with diagonal braces; 所述连墙件与岩面夹角为45~90°;The angle between the wall connecting piece and the rock face is 45-90°; 所述柔性拉锚绳一端连接连墙件,另一端和悬挑梁连接;One end of the flexible anchor rope is connected to the wall part, and the other end is connected to the cantilever beam; 立杆的底部设置在支撑平台上,支撑平台焊接在悬挑梁上;The bottom of the pole is set on the support platform, and the support platform is welded on the cantilever beam; 所述大横杆沿排架的长度方向设置,大横杆和立杆用扣件连接,左右相邻的两段大横杆间搭接并用扣件固定;The large horizontal bar is arranged along the length direction of the bent frame, the large horizontal bar and the vertical bar are connected by fasteners, and the left and right adjacent two sections of large horizontal bars are overlapped and fixed by fasteners; 所述小横杆铺设在大横杆上面,小横杆不与岩面直接接触;The small crossbar is laid on the large crossbar, and the small crossbar is not in direct contact with the rock surface; 剪刀撑的斜杆与大横杆连接。The oblique bar of the scissors brace is connected with the large cross bar. 2.如权利要求1所述的一种悬挑式排架搭设结构,其特征在于当悬挑式排架高度大于12m时,所述悬挑排架搭设结构设置有多层悬挑梁。2. A cantilevered bent frame erection structure according to claim 1, wherein when the cantilevered bent frame height is greater than 12m, the cantilevered bent frame erected structure is provided with multi-layered cantilevered beams. 3.如权利要求1所述的一种悬挑式排架搭设结构,其特征在于悬挑梁采用16#槽钢,悬挑梁间距L按立杆纵距设置,每一纵距设置一根;入岩锚固长度不小于2.5m;斜撑采用12#槽钢,入岩一般按照2.0m左右控制;悬挑梁与斜撑的夹角Q一般取30~45°。3. A kind of cantilevered bent frame erection structure as claimed in claim 1, characterized in that the cantilevered beam adopts 16# channel steel, the distance L of the cantilevered beam is set according to the vertical distance of the vertical pole, and one vertical distance is set for each vertical distance. ; The anchorage length into the rock is not less than 2.5m; the diagonal brace adopts 12# channel steel, and the rock entry is generally controlled at about 2.0m; the angle Q between the cantilever beam and the diagonal brace is generally 30-45°. 4.如权利要求1所述的一种悬挑式排架搭设结构,其特征在于连墙件采用插筋。4. A cantilevered bent frame erecting structure as claimed in claim 1, characterized in that the connecting wall parts are made of inserted ribs. 5.如权利要求1所述的一种悬挑式排架搭设结构,其特征在于连墙件采用插筋,插筋应采用不小于φ25mm的螺纹钢筋;连墙件插筋长不小于1.0m,入岩不小于0.6m,外露0.4m。5. A cantilevered bent frame erection structure as claimed in claim 1, characterized in that the wall parts are inserted ribs, and the inserted ribs should be threaded steel bars not less than φ25mm; the length of the inserted ribs of the wall parts is not less than 1.0m , not less than 0.6m into the rock, and 0.4m exposed. 6.如权利要求1所述的一种悬挑式排架搭设结构,其特征在于柔性拉锚绳采用Φ16mm钢绳,柔性拉锚绳与水平面成上倾30~45°,拉锚绳两端采用绳卡固定成环,每端不少于3道绳卡。6. A cantilevered bent frame erection structure as claimed in claim 1, characterized in that the flexible anchor rope adopts a Φ16mm steel rope, the flexible anchor rope is inclined 30-45° from the horizontal plane, and the two ends of the anchor rope are Use rope clips to fix it into a ring, with no less than 3 rope clips at each end. 7.如权利要求1所述的一种悬挑式排架搭设结构,其特征在于支撑平台采用16#槽钢,焊接在悬挑梁的上部,立杆底部放入支撑平台的16#槽钢凹槽内;每根立杆对应支撑平台槽钢部位焊接Φ25mm的螺纹钢筋将立杆固定于支撑平台槽钢凹槽上,外侧立杆固定点距离悬挑梁端部不小于0.1m。7. A kind of cantilevered bent frame erecting structure as claimed in claim 1, characterized in that the support platform adopts 16# channel steel, which is welded on the top of the cantilever beam, and the bottom of the vertical pole is put into the 16# channel steel of the support platform In the groove; each vertical pole is welded with Φ25mm threaded steel bar corresponding to the channel steel part of the supporting platform to fix the vertical pole on the channel steel groove of the supporting platform, and the distance from the fixed point of the outer vertical pole to the end of the cantilever beam is not less than 0.1m. 8.如权利要求1所述的一种悬挑式排架搭设结构,其特征在于所述立杆的搭接长度不小于1m,连接处用不少于三个扣件固定;所述大横杆的搭接长度不小于1m,连接处用不少于三个扣件固定。8. A cantilevered bent frame erection structure as claimed in claim 1, characterized in that the overlapping length of the vertical rods is not less than 1m, and the joints are fixed with no less than three fasteners; the large horizontal The lap length of the rods is not less than 1m, and the joints are fixed with not less than three fasteners. 9.如权利要求1所述的一种悬挑式排架搭设结构,其特征在于剪刀撑采用与大横杆相同钢管材料,设置时按照横向到底、纵向到边的原则;每道剪刀撑宽度不小于4跨,且不小于6m宽,剪刀撑的斜杆与地面的倾角在45~60°之间。9. A kind of cantilevered bent frame erection structure as claimed in claim 1, characterized in that the scissors bracing adopts the same steel pipe material as the large horizontal bar, and is set according to the principle of horizontally to the bottom and vertically to the side; the width of each scissors brace Not less than 4 spans, and not less than 6m wide, the inclination angle between the oblique bar of the scissors brace and the ground is between 45° and 60°.
CN201721517053.6U 2017-11-14 2017-11-14 A kind of overhanging type framed bent sets up structure Active CN208056613U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201721517053.6U CN208056613U (en) 2017-11-14 2017-11-14 A kind of overhanging type framed bent sets up structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201721517053.6U CN208056613U (en) 2017-11-14 2017-11-14 A kind of overhanging type framed bent sets up structure

Publications (1)

Publication Number Publication Date
CN208056613U true CN208056613U (en) 2018-11-06

Family

ID=63997861

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201721517053.6U Active CN208056613U (en) 2017-11-14 2017-11-14 A kind of overhanging type framed bent sets up structure

Country Status (1)

Country Link
CN (1) CN208056613U (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108104460A (en) * 2017-11-14 2018-06-01 中国电建集团华东勘测设计研究院有限公司 A kind of overhanging type framed bent sets up structure and construction method
CN113530192A (en) * 2021-08-16 2021-10-22 中国铁道科学研究院集团有限公司 Multi-support cantilevered scaffolding structure for ultra-high vertical rock slope
CN113738086A (en) * 2021-09-10 2021-12-03 重庆一零七市政建设工程有限公司 High and steep dangerous rock attached type operation platform

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108104460A (en) * 2017-11-14 2018-06-01 中国电建集团华东勘测设计研究院有限公司 A kind of overhanging type framed bent sets up structure and construction method
CN113530192A (en) * 2021-08-16 2021-10-22 中国铁道科学研究院集团有限公司 Multi-support cantilevered scaffolding structure for ultra-high vertical rock slope
CN113530192B (en) * 2021-08-16 2023-03-31 中国铁道科学研究院集团有限公司 Multi-support overhanging scaffold structure of ultrahigh vertical rock slope
CN113738086A (en) * 2021-09-10 2021-12-03 重庆一零七市政建设工程有限公司 High and steep dangerous rock attached type operation platform

Similar Documents

Publication Publication Date Title
CN104453197B (en) High Large Cantilever concrete structural steel shape supports platform
CN108104460A (en) A kind of overhanging type framed bent sets up structure and construction method
CN103276886B (en) Overhanging frame at position of high-rise building sloping roof outer eave window and construction method thereof
CN206053274U (en) The external scaffolding device of the perpendicular BAIYE outer visor of skyscraper and glass curtain wall dual-purpose
CN208056613U (en) A kind of overhanging type framed bent sets up structure
CN102888979A (en) Joint processing and constructing method of overhanging scaffold at large cantilever balcony
CN104234447B (en) Deep foundation ditch tool-type hangs stair
CN205369229U (en) But walking hoisting frame suitable for manual hole digging pile steel reinforcement cage is laid
CN205242264U (en) A security operating platform for pier stud
CN103334580B (en) Section steel tripod in a kind of overhanging scaffold and connection system for guide rail
CN217353430U (en) Detachable movable scaffold
CN205330140U (en) Tall support rack of structure encorbelments greatly in high altitude
CN207538430U (en) Framed bent sets up structure under a kind of MODEL OVER COMPLEX TOPOGRAPHY
CN202227276U (en) Mobile platform applied on bridge pier template
CN211229426U (en) A self-supporting steel pipe scaffolding system
CN203684102U (en) Prefabricated girder support system erected at the junction span of the ramp bridge and the main line bridge
CN203559570U (en) Operating platform for steel pipe support frame overhung on surrounding columns
CN215718762U (en) Support structure for synchronous construction of station and shield
CN103015696B (en) A kind of outer protection layer of hanging basket for super high-rise building
CN104963697B (en) A kind of portable steel pipe framed bent of concrete construction
CN109371983A (en) A kind of foundation pit protection device for railway bridge
CN212270687U (en) Steel pipe support temporary pier for inclined main and auxiliary arch cross section
CN211228141U (en) A New Type of T-beam Diaphragm Construction Platform Cross Bracing
CN201053199Y (en) Large template pylon
CN207609194U (en) A quick loading and unloading protective railing device

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant