CN208056127U - A kind of basement shear wall post-cast strip prefabricated board - Google Patents
A kind of basement shear wall post-cast strip prefabricated board Download PDFInfo
- Publication number
- CN208056127U CN208056127U CN201820481111.2U CN201820481111U CN208056127U CN 208056127 U CN208056127 U CN 208056127U CN 201820481111 U CN201820481111 U CN 201820481111U CN 208056127 U CN208056127 U CN 208056127U
- Authority
- CN
- China
- Prior art keywords
- basement
- cast strip
- prefabricated board
- shear wall
- lateral cover
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
Abstract
The utility model discloses a kind of basement shear wall post-cast strip prefabricated board, including prefabricated board ontology, the prefabricated board ontology is made of several sequentially connected lateral cover boards of length direction along post-cast strip;For the lateral cover board by two-layer two-way reinforcement by rectangular configuration made of concreting, each lateral cover board is equipped with the water-stopping pull rod that several one end extend vertically into lateral cover board;The prefabricated board ontology is connected by each water-stopping pull rod is parallel to the basement inner template of prefabricated board ontology, side of the basement inner template far from the prefabricated board ontology, which is equipped with, is used to support the fixed mechanism of basement inner template, in each underground room the distance between template and prefabricated board ontology side close to each other for basement shear wall thickness;In being provided with cleanout in the basement inner template of post-cast strip lower part.The utility model has the characteristics that, convenient for waterproof construction and backfill operation, field to be poured suitable for basement shear wall post-cast strip.
Description
Technical field
The utility model belongs to technical field of building construction, specifically, it is pre- to be related to a kind of basement shear wall post-cast strip
Making sheet.
Background technology
With the development of building technology, shear wall building is more and more, and monomer area is increasing;Shear wall basement is set
It is also very universal to set post-cast strip, because concreting is later at post-cast strip, outer wall of basement waterproof homework, fertile slot backfill operation by
Its influence is unable to integral construction;For this problem, usual way is in the past:Build 120mm thickness, diameter 1500mm semicircle bricks by laying bricks or stones
It builds well and is used as retaining wall, operating personnel, which will enter in brick well, installs alter-pouring strips mould plate, and post-cast strip carries out again after the completion of pouring
Waterproof, backfill operation at post-cast strip;Often brick well extrusion, and narrow space in well when backfill, operation is not
Just, to cannot ensure backfill and waterproof construction quality in well.
Utility model content
The utility model is provided and is cut convenient for waterproof construction and the basement of backfill operation after the completion of a kind of post-cast strip pours
Power wall post-cast strip prefabricated board.
To achieve the above object, technical solution used by the utility model is as follows:
A kind of basement shear wall post-cast strip prefabricated board, including prefabricated board ontology, the prefabricated board ontology is by several edges
The sequentially connected lateral cover board of length direction of post-cast strip is constituted;The lateral cover board is poured by two-layer two-way reinforcement by concrete
Rectangular configuration made of building, each lateral cover board are equipped with the water-stopping pull rod that several one end extend vertically into lateral cover board;It is described pre-
Making sheet ontology is connected by each water-stopping pull rod is parallel to the basement inner template of prefabricated board ontology, and the basement inner template is remote
Side from the prefabricated board ontology is equipped with the fixed mechanism for being used to support basement inner template, in each underground room template with it is prefabricated
The distance between plate ontology side close to each other is the thickness of basement shear wall;In in the basement of post-cast strip lower part
Cleanout is provided in template.
Preferably, the fixed mechanism includes being fixed on each basement inner template far from the lateral cover board side side
Keel on face, the keel remotely descend parallel equipped with fixed by the water-stopping pull rod on the side side of indoor template
Steel frame pipe, each steel frame pipe are parallel with basement inner template.
Preferably, the keel are made of several lumps of wood disposed in parallel, and the both ends of each lumps of wood are along the underground
The short transverse of room shear wall extends, and each lumps of wood is vertically arranged with each steel frame pipe.
Preferably, the two-layer two-way reinforcement is made of two groups of reinforcing bar groups parallel with the lateral cover board, each group reinforcing bar
It is mutually parallel between the reinforcing bar of group, and is to be mutually perpendicular between the reinforcing bar of two groups of reinforcing bar groups.
Preferably, the water-stopping pull rod stretches into one end of the lateral cover board and is welded on the arrangement of reinforcement.
Preferably, the lateral cover board width is 500mm, a length of that 300mm is added on the basis of the width of post-cast strip, and thickness is
120mm;The water-stopping pull rod is four, and each water-stopping pull rod is respectively 100mm and lateral cover board with the long back gauge of lateral cover board
Short side distance be at four points of 250mm, the length of each water-stopping pull rod is that 200mm is added on the basis of shear wall's thickness.
The utility model is as a result of above-mentioned structure, and compared with prior art, acquired technological progress is:
Prefabricated board ontology described in the utility model is made of several lateral cover boards, and prefabricated board ontology passes through in water-stopping pull rod and basement
Template is connected, after metope reaches plastering, does waterproof condition, prefabricated board outer body is plastered, waterproof, backfill are applied
Work;Thus, it is used as retaining wall instead of semicircle brick well is built at post-cast strip by laying bricks or stones so that waterproof, backfill at post-cast strip are made
Industry process is unaffected, it is ensured that backfill and waterproof construction quality;Also, items exterior components and post-cast strip coagulation at post-cast strip
Soil pour can independent construction, create condition for each outdoor process rapid construction of basement post-pouring zone;The institute of post-cast strip lower part
It states and is provided with cleanout in basement inner template, facilitate the cleaning of sundries in post-cast strip;Sealing is placed using the lateral cover board
Pull rod, and basement inner template is installed using the water-stopping pull rod, it is easy to operate, and save manpower.
Description of the drawings
Attached drawing is used to provide a further understanding of the present invention, and a part for constitution instruction, with this practicality
Novel embodiment for explaining the utility model, does not constitute limitations of the present invention together.
In the accompanying drawings:
Fig. 1 is the structural schematic diagram of the utility model embodiment;
Fig. 2 is the sectional view of A-A in Fig. 1.
Mark component:The lateral cover boards of 1-, 2- arrangements of reinforcement, 3- water-stopping pull rods, 4- basement inner templates, the 5- lumps of wood, 6- steel frame pipes,
7- basement shear walls, 8- basements bottom surface, 9- cleanouts.
Specific implementation mode
The preferred embodiment of the utility model is illustrated below in conjunction with attached drawing.It should be appreciated that described herein excellent
It selects embodiment to be only used for describing and explaining the present invention, is not used to limit the utility model.
A kind of basement shear wall post-cast strip prefabricated board of embodiment
The utility model embodiment discloses a kind of basement shear wall post-cast strip prefabricated board, as shown in Figure 1 and Figure 2, including
Prefabricated board ontology, basement inner template 4 and fixed mechanism.
Wherein, prefabricated board ontology is made of the sequentially connected lateral cover board of several length directions along post-cast strip 1;Laterally
Rectangular configuration made of concreting of the cover board 1 by two-layer two-way reinforcement 2 by label C30, and two-layer two-way reinforcement 2 by with
Two groups of parallel reinforcing bar groups of lateral cover board 1 are constituted, and are mutually parallel between the reinforcing bar of each group reinforcing bar group, the reinforcing bars of two groups of reinforcing bar groups it
Between to be mutually perpendicular to, arrangement of reinforcement 2 is 12@of diameter, 100 reinforcing bars (grade III steel);It is vertical it to be provided with several one end on each lateral cover board 1
The water-stopping pull rod 3 of lateral cover board 1 is stretched into, one end that each water-stopping pull rod 3 stretches into lateral cover board 1 is welded on arrangement of reinforcement 2.
The width of lateral cover board 1 is 500mm, a length of that 300mm, thickness 120mm are added on the basis of the width of post-cast strip;Sealing
Pull rod 3 is four, and each water-stopping pull rod 3 is respectively 100mm with the long back gauge of lateral cover board 1 and the short side distance of lateral cover board 1
At four points of 250mm, the length of each water-stopping pull rod 3 is that 200mm is added on the basis of shear wall's thickness.
Basement inner template 4 is fixedly connected by each water-stopping pull rod 3 with prefabricated board ontology, and basement inner template 4 with it is pre-
Making sheet ontology is mutually parallel, and fixed mechanism is arranged in side of the basement inner template 4 far from prefabricated board ontology, is used to support ground
Lower interior template 4;Fixed mechanism includes being fixed in each underground room template 4 far from the keel on 1 side side of lateral cover board, dragon
Bone is remotely arranged in parallel with through 3 fixed steel frame pipe 6 of water-stopping pull rod on the side side of lower indoor template 4, each steel frame pipe 6
It is parallel with basement inner template 4;Wherein, keel are made of several lumps of wood 5 disposed in parallel, and the both ends of each lumps of wood 5 are along underground
The short transverse of room shear wall 7 extends, and each lumps of wood 5 is vertically arranged with each steel frame pipe 6.
The distance between template 4 and prefabricated board ontology side close to each other are basement shear wall 7 in each underground room
Thickness;It is provided with cleanout 9 in the basement inner template 4 of post-cast strip lower part, cleanout 9 topmost has the height of basement bottom surface 8
Degree is 500mm.
The utility model embodiment to install process as follows:
First, lateral cover board 1, and 1 room shear wall 7 located underground of lateral cover board are piled up successively along the length direction of post-cast strip
Outside, then install basement inner template 4, the inside of 4 room shear wall 7 located underground of basement inner template;Later, dragon is installed
Bone, keel branch are located on side side of the basement inner template 4 far from lateral cover board 1;Then, will be arranged by water-stopping pull rod 3
Steel frame pipe 6 on keel is tightened, to realize that lateral cover board 1 and basement inner template 4 are clamped in the shear wall at post-cast strip
On, and post-cast strip is located in the space of the two clamping;It is provided with cleanout 9 in the basement inner template 4 of post-cast strip lower part, cleans
The height that mouth 9 topmost has basement bottom surfaces 8 are 500mm;After 7 face of basement shear wall reaches plastering, does waterproof condition,
Prefabricated board outer body is plastered, waterproof, backfill are constructed;Post-cast strip casting concrete, post-cast strip to be achieved pour condition,
After sundries in basement inner template 4 is cleaned out, then install indoor bottom 500mm templates, casting concrete.
Finally it should be noted that:The above descriptions are merely preferred embodiments of the present invention, is not limited to this
Utility model, although the utility model is described in detail with reference to the foregoing embodiments, for those skilled in the art
For, it still can be with technical scheme described in the above embodiments is modified, or to which part technical characteristic
Carry out equivalent replacement.Within the spirit and principle of the utility model, any modification, equivalent replacement, improvement and so on,
It should be included within the scope of the utility model claims protection.
Claims (6)
1. a kind of basement shear wall post-cast strip prefabricated board, it is characterised in that:Including prefabricated board ontology, the prefabricated board ontology by
The sequentially connected lateral cover board of several length directions along post-cast strip is constituted;The lateral cover board is passed through by two-layer two-way reinforcement
Rectangular configuration made of concreting, each lateral cover board are equipped with the sealing drawing that several one end extend vertically into lateral cover board
Bar;The prefabricated board ontology is connected by each water-stopping pull rod is parallel to the basement inner template of prefabricated board ontology, the underground
Side of the indoor template far from the prefabricated board ontology, which is equipped with, is used to support the fixed mechanism of basement inner template, in each underground room
The distance between template and prefabricated board ontology side close to each other are the thickness of basement shear wall;Institute in post-cast strip lower part
It states and is provided with cleanout in basement inner template.
2. a kind of basement shear wall post-cast strip prefabricated board according to claim 1, it is characterised in that:The fixed mechanism
Including being fixed on each basement inner template far from the keel on the lateral cover board side side, the keel remotely under
Parallel be equipped with passes through the fixed steel frame pipe of the water-stopping pull rod, each steel frame pipe and basement on the side side of indoor template
Inner template is parallel.
3. a kind of basement shear wall post-cast strip prefabricated board according to claim 2, it is characterised in that:If the keel by
The dry lumps of wood disposed in parallel is constituted, and the both ends of each lumps of wood extend along the short transverse of the basement shear wall, each side
It is wooden to be vertically arranged with each steel frame pipe.
4. a kind of basement shear wall post-cast strip prefabricated board according to claim 1, it is characterised in that:The double-layer double-direction
Arrangement of reinforcement is made of two groups of reinforcing bar groups parallel with the lateral cover board, is mutually parallel between the reinforcing bar of each group reinforcing bar group, and two groups
It is to be mutually perpendicular between the reinforcing bar of reinforcing bar group.
5. a kind of basement shear wall post-cast strip prefabricated board according to claim 1, it is characterised in that:The water-stopping pull rod
The one end for stretching into the lateral cover board is welded on the arrangement of reinforcement.
6. a kind of basement shear wall post-cast strip prefabricated board according to claim 1, it is characterised in that:The lateral cover board
Width is 500mm, a length of that 300mm, thickness 120mm are added on the basis of the width of post-cast strip;The water-stopping pull rod is four, is respectively stopped
Water pull rod is 100mm with the long back gauge of lateral cover board respectively, is at four points of 250mm with the short side distance of lateral cover board,
The length of each water-stopping pull rod is that 200mm is added on the basis of shear wall's thickness.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820481111.2U CN208056127U (en) | 2018-04-04 | 2018-04-04 | A kind of basement shear wall post-cast strip prefabricated board |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820481111.2U CN208056127U (en) | 2018-04-04 | 2018-04-04 | A kind of basement shear wall post-cast strip prefabricated board |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208056127U true CN208056127U (en) | 2018-11-06 |
Family
ID=63986942
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820481111.2U Active CN208056127U (en) | 2018-04-04 | 2018-04-04 | A kind of basement shear wall post-cast strip prefabricated board |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208056127U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109826239A (en) * | 2019-03-14 | 2019-05-31 | 中兴文物建筑装饰工程有限公司 | A kind of poured band of outer wall of basement structure and its construction method |
CN113293803A (en) * | 2021-05-20 | 2021-08-24 | 江苏乐建建设有限公司 | Basement outer wall post-cast strip precast slab blocking piece and blocking construction method |
-
2018
- 2018-04-04 CN CN201820481111.2U patent/CN208056127U/en active Active
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109826239A (en) * | 2019-03-14 | 2019-05-31 | 中兴文物建筑装饰工程有限公司 | A kind of poured band of outer wall of basement structure and its construction method |
CN109826239B (en) * | 2019-03-14 | 2024-02-06 | 中兴文物建筑装饰工程有限公司 | Basement outer wall post-pouring strip structure and construction method thereof |
CN113293803A (en) * | 2021-05-20 | 2021-08-24 | 江苏乐建建设有限公司 | Basement outer wall post-cast strip precast slab blocking piece and blocking construction method |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN104631512B (en) | Hang modulus method after-pouring band beam-slab construction method | |
CN207499455U (en) | A kind of shaping tool fixture for the anti-bank construction of secondary structure masonry | |
CN209194768U (en) | A kind of lightweight concrete slat door separation structure of the window | |
CN208056127U (en) | A kind of basement shear wall post-cast strip prefabricated board | |
CN206859453U (en) | A kind of modified insulated wall light steel skeleton | |
CN206706844U (en) | A kind of alter-pouring strips mould plate installs construction | |
CN211923107U (en) | Formwork-supporting-free structure of constructional column in wall | |
CN211228607U (en) | Integrally formed construction structure of outer wall and bottom plate of cast-in-place concrete structure of structure | |
CN206859272U (en) | The interim block structure of outer wall of basement pouring after settlement | |
CN104912209B (en) | Bars In Poured Concrete Slab reserved holes of pipes plugging device and processing and plugging construction method | |
CN209277547U (en) | Turnover hole hanging die assisting in blocking reserved hole | |
CN209620278U (en) | Concrete anti-bank template structure with can have enough to meet need reinforcing bar inside lining | |
CN207944710U (en) | The narrow expansion joint Split form reinforcement system of shear wall structure | |
CN209989847U (en) | Shear force wall post-cast strip prefabricated plate closing device | |
CN215926411U (en) | Narrow space post-cast strip formwork device in advance | |
CN204690801U (en) | Formwork erecting structure is hung in basement roof ater-casting | |
CN208717952U (en) | A kind of reserved passage construction device of basement post-pouring zone | |
CN207048314U (en) | A kind of shaping type stair wooden model board component | |
CN205743005U (en) | Inflatable adjustable concrete structural slab hole to be provided construction mould | |
CN211774798U (en) | Wall body corner constructional column exempts from formwork structure | |
CN209211892U (en) | One kind can be used for overhanging the molding light instrument in i-beam structure hole | |
CN104594546B (en) | The preparation method of a kind of fibre-cement pipe brick, body of wall and fibre-cement pipe brick | |
CN208056625U (en) | A kind of toilet drop plate hangs mould | |
CN208167766U (en) | A kind of simple and fast connection precast concrete plate fetal membrane | |
CN208122026U (en) | A kind of assembled steel template concrete shear force wall |