CN208023561U - A kind of slip casting pilework - Google Patents

A kind of slip casting pilework Download PDF

Info

Publication number
CN208023561U
CN208023561U CN201820467866.7U CN201820467866U CN208023561U CN 208023561 U CN208023561 U CN 208023561U CN 201820467866 U CN201820467866 U CN 201820467866U CN 208023561 U CN208023561 U CN 208023561U
Authority
CN
China
Prior art keywords
stake holes
grouting
slip casting
hole
aperture
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820467866.7U
Other languages
Chinese (zh)
Inventor
吴民利
周子舟
韩陆洋
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
BGI ENGINEERING CONSULTANTS Ltd
Original Assignee
BGI ENGINEERING CONSULTANTS Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by BGI ENGINEERING CONSULTANTS Ltd filed Critical BGI ENGINEERING CONSULTANTS Ltd
Priority to CN201820467866.7U priority Critical patent/CN208023561U/en
Application granted granted Critical
Publication of CN208023561U publication Critical patent/CN208023561U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Abstract

The utility model is related to a kind of slip casting pileworks, including stake holes, exhaust pipe and the Grouting Pipe being vertically arranged in ground, and the bottom of stake holes is inserted into stake holes and is abutted in the lower end of Grouting Pipe, and the upper end of Grouting Pipe is stretched out the aperture of stake holes and is connected to and in communication with filling system;The lower end of exhaust pipe is placed in stake holes, and the aperture of stake holes is stretched out in the upper end;Exhaust pipe leans on Grouting Pipe and is fixedly connected with the top of Grouting Pipe;Under-filled in stake holes has hole inner filling material, and forms hole inner filling material layer, from the upper end of hole inner filling material layer to being filled with aperture sealing of hole material between the aperture of stake holes in stake holes, and forms the aperture sealing of hole bed of material;The top of the hole inner filling material layer is inserted into the lower end of the exhaust pipe, the utility model is after grouting pile is formed, filling system stops slip casting when grouting pressure maximum is gradually increased to 1.0MPa, grout material slurries have diffused in the ground of stake holes periphery the filling and solidification for carrying out hole at this time, and low-pressure grouting may be implemented.

Description

A kind of slip casting pilework
Technical field
The utility model is related to injecting treatment fields, more particularly to one kind of basement process is carried out to indoor existing miscellaneous fill Slip casting pilework.
Background technology
Miscellaneous fill is artificial unordered backfill formation, and foundation bearing capacity is relatively low, generally cannot directly as soil supporting layer, but In engineering construction, especially when basis uses the strip footing either single layer, multi-storey building or workshop of isolated footing, one As basement process only is carried out to the miscellaneous fill under basic scope, it is higher that foundation load is such as delivered in bearing capacity under ground using stake Stratum in, and carry out treatment (about 30cm thickness) as miscellaneous fill is often only simple within the scope of room cubsoil other than basis Afterwards with regard to the construction of the indoor waterproof of progress or concrete topping, for a long time, although miscellaneous fill overlying doors structure load is not high, But because miscellaneous fill is less closely knit, porosity is big in soil, does not complete, from consolidating, itself to will produce sedimentation, indoor earth's surface is caused to send out Raw sedimentation, pre-buried underground utilities indoor at this time may be damaged, and especially the pipelines such as water, heating power once settle change up and down Shape is damaged leakage, and miscellaneous fill is impregnated and caused the collapsibility banketed by percolating water, and flooring will generate bigger Sedimentation or differential settlement, the normal use on extreme influence ground within doors, therefore permanent work is both needed to in compartment The miscellaneous fill of table structural load is handled.
Although there are many method for processing foundation at present, because being located in interior, large scale equipment can not march into the arena construction at all, so just Method is extremely limited, at present there are mainly two types of interior room cubsoil method for processing foundation:(1) cushion is dug out, that is, digs out miscellaneous fill, is changed The construction material being filled into, because constructing indoors, big machinery can not pass in and out and construct, can only hand excavation, therefore this A method is generally adapted the smaller miscellaneous fill of processing thickness, when miscellaneous fill is thicker, such as exceeds 1.0m, then uneconomical.(2) conventional High-pressure slip-casting method, i.e. vibration sink to slip casting steel pipe, inject cement mortar by Grouting Pipe high pressure (general 3-5 MPa) to reach Cure the purpose of miscellaneous fill, but because of the inhomogeneities of miscellaneous fill, high-pressure slip-casting slurries flow to no controllability, are as a result exactly miscellaneous Banketing, it is uneven to reinforce, and miscellaneous fill intensity after slip casting in part improves, intensity does not improve substantially after room cubsoil in part is reinforced, Slip casting effect is uneven, while uncontrollable grouting serous fluid is seized every opportunity under high pressure, indoor section pipeline such as heating power pipe trench So that it is can not operate normally etc. filling, causes secondary loss.
Utility model content
Technical problem to be solved in the utility model is in view of the deficiencies of the prior art, to provide a kind of slip casting pilework, At least one to solve the above technical problems.
The technical solution that the utility model solves above-mentioned technical problem is as follows:A kind of slip casting pilework, including be vertically arranged The lower end of stake holes, exhaust pipe in ground and Grouting Pipe, the Grouting Pipe is inserted into the stake holes and abuts the stake holes The upper end of bottom, the Grouting Pipe is stretched out the aperture of the stake holes and is connected to and in communication with filling system;Under the exhaust pipe End is placed in the stake holes, and the aperture of the stake holes is stretched out in the upper end;The exhaust pipe lean on the Grouting Pipe and with the note The top of slurry pipe is fixedly connected;Under-filled in the stake holes has hole inner filling material, and forms hole inner filling material layer, the stake In hole from the upper end of the hole inner filling material layer between the aperture of the stake holes be filled with aperture sealing of hole material, and formed aperture envelope The hole bed of material;The top of the hole inner filling material layer is inserted into the lower end of the exhaust pipe.
The utility model has the beneficial effects that:By the way that the Grouting Pipe in stake holes is arranged, institute is stretched out in the upper end of the Grouting Pipe It states stake holes and is connected to and in communication with filling system, the injecting treatment to ground may be implemented;Grouting Pipe and exhaust pipe are put into described After stake holes, hole inner filling material is inserted and forms hole inner filling material layer in the stake holes, reinject aperture sealing of hole material formed it is closely knit The aperture sealing of hole bed of material, the sturdy stabilization of the aperture sealing of hole bed of material can so that the grout material slurries injected during slip casting will not be from Aperture is emerged, but by being filled and being cured, slip casting in the void diffusion of stake holes side wall to the gap of stake holes periphery ground The ground of stake and stake periphery after grout material fills curing process is with regard to form compound foundation, the structure lotus of shared flooring It carries, achievees the purpose that consolidated subsoil, improves its bearing capacity;During slip casting, it can observe whether stake holes has filled by exhaust pipe Full grout material, the slip casting in stake holes when normal pressure, waits for that slip casting feed liquid surface moves up and to the upper end pulp of exhaust pipe, shows that stake holes has been filled Full grout material, has formed grouting pile at this time in stake holes, then bending exhaust pipe and seals, and the slip casting pressure of filling system is gradually increased Grout material slurries are diffused in the ground of stake holes periphery the filling and solidification for carrying out hole by power;It may be implemented in normal pressure and be less than The curing process to ground is completed under the grouting pressure of 1.0MPa;The utility model is by grout material filling curing process Base, ground after processing are the major volume portions of composite foundation, except a small amount of slag for generating stake own vol when site operation Native outer, generation dregs amount is less, belongs to environmental protection construction, Green civilization construction.
Based on the above technical solution, the utility model can also do following improvement.
Further, the hole inner filling material further includes grout material slurries, and the grout material slurries are passed through by the filling system The Grouting Pipe fills the hole inner filling material layer.
It is using above-mentioned further advantageous effect:Grout material slurries fill the hole inner filling material through the Grouting Pipe The grouting pressure of filling system is gradually increased by the cementing formation grouting pile of solidification in layer, hole inner filling material and grout material slurries, will Grout material slurries diffuse in the ground of stake holes periphery the filling and solidification for carrying out hole
Further, Grouting Pipe includes integrally formed slip casting connecting tube and grouting tube, slip casting connecting tube upper end connection note Slurry system, lower end connect the upper end of grouting tube, and the lower end of grouting tube is connected to the bottom of stake holes;It is offered on grouting tube Several slurry outlets;The slip casting connecting tube is located at the aperture sealing of hole bed of material, and the grouting tube is located at the hole inner filling material Layer.
It is using above-mentioned further advantageous effect:It may be implemented grout material slurries being injected into hole by slurry outlet and fill out Charge layer.
Further, the slurry outlet is horizontal runs through the grouting tube, and the two neighboring slurry outlet between the upper and lower every It is arranged and is mutually perpendicular to;The pulp bore dia 5mm, 4~6cm of the two neighboring pulp pitch of holes.
Further, closure is covered on slurry outlet, closure is outer to be tied with adhesive tape;The tube bottom of Grouting Pipe is tied with the glue for back cover Band.
It is using above-mentioned further advantageous effect:Closure is covered on slurry outlet, closure is outer to be tied with adhesive tape;Grouting Pipe Tube bottom is tied with the adhesive tape for back cover, is that will not enter sundries such as hole inner filling material in Grouting Pipe before slip casting to protect Starting the surge of grouting behind shaft or drift lining slurry liquid Deng, slip casting will can easily block and adhesive tape is washed open, realize grout material slurries The purpose come out from slurry outlet.
Further, the upper layer of the ground is miscellaneous fill layer, and lower layer is original state soil layer, 80~100mm of the stake holes diameter, The stake holes is inserted into the original state soil layer and its bottom hole is 50cm at a distance from the upper end of the undisturbed soil.
Further, the bottom end of the exhaust pipe is 60cm at a distance from the aperture.
Further, the height of the aperture sealing of hole bed of material is 50cm.
Further, hole inner filling material is rubble, and grain size is 0.5~2.0cm.
Further, the maximum grouting pressure of filling system is 1.0MPa.
Advantageous effect using above-mentioned further scheme is:Compared to conventional high-pressure grouting method, the utility model waits noting After starching stake formation, filling system stops slip casting when grouting pressure maximum is gradually increased to 1.0MPa, grout material slurries have expanded at this time It is dissipated to the filling and solidification for carrying out hole in the ground of stake holes periphery, low-pressure grouting may be implemented.
Description of the drawings
Fig. 1 is a kind of grouting pile schematic diagram of the utility model;
Fig. 2 is a kind of grouting pile slip casting schematic diagram of the utility model;
Fig. 3 is that the utility model carries out processing figure to ground;
Fig. 4 is the utility model grouting tube schematic diagram.
In attached drawing, parts list represented by the reference numerals are as follows:
1, ground, 11, miscellaneous fill layer, 12, original state soil layer, 2, stake holes, 3, hole inner filling material layer, 4, Grouting Pipe, 41, slip casting Connecting tube, 42, grouting tube, 421, slurry outlet, 5, exhaust pipe, 6, the aperture sealing of hole bed of material, 7, block, 8, adhesive tape, 9, grout material Slurries, 13, filling system.
Specific implementation mode
The principles of the present invention and feature are described below in conjunction with attached drawing, example is served only for explaining this practicality It is novel, it is not intended to limit the scope of the utility model.
As shown in Figs. 1-3, a kind of slip casting pilework, including stake holes 2, exhaust pipe 5 and Grouting Pipe 4 in ground 1, the note The bottom of the stake holes 2 is inserted into the stake holes 2 and is abutted in the lower end of slurry pipe 4, and the stake holes is stretched out in the upper end of the Grouting Pipe 4 It 2 and is connected to and in communication with filling system 13;The lower end of the exhaust pipe 5 is placed in the stake holes 2, and the stake holes is stretched out in the upper end 2 aperture;The exhaust pipe 5 leans on the Grouting Pipe 4 and is fixedly connected with the top of the Grouting Pipe 4;Under the stake holes 2 End filling hole inner filling material forms hole inner filling material layer 3, and the aperture of upper end to the stake holes 2 of the hole inner filling material layer 3 is filled out It fills aperture sealing of hole material and forms the aperture sealing of hole bed of material 6;The top of the hole inner filling material layer 3 is inserted into the lower end of the exhaust pipe 5;Institute The bottom for stating exhaust pipe 5 is 60cm at a distance from the aperture;The height of the aperture sealing of hole bed of material 6 is 50cm;It is filled in hole Material is rubble, and grain size is 0.5~2.0cm;Grout material slurries 9, the maximum of filling system 13 are equipped in the filling system 13 Grouting pressure is 1.0MPa;The upper layer of the ground 1 is miscellaneous fill layer 11, and lower layer is original state soil layer 12,2 diameter 80 of the stake holes The bottom hole of~100mm, the stake holes 2 are inserted into the original state soil layer 12 and are at a distance from the upper end of the original state soil layer 12 50cm。
By being arranged the Grouting Pipe 4 in stake holes 2, the upper end of the Grouting Pipe 4 stretch out the stake holes 2 and with filling system 13 It is connected to and in communication with, the injecting treatment to ground 1 may be implemented;Grouting Pipe 4 and exhaust pipe 5 are put into after the stake holes 2, will be in hole Filler material, which is inserted, forms hole inner filling material layer 3 in the stake holes 2, reinject aperture sealing of hole material and form the closely knit aperture sealing of hole bed of material 6, the sturdy stabilization of the aperture sealing of hole bed of material 6 can make the grout material slurries 9 injected during slip casting not emerge from aperture, and It is to be filled and cured in the void diffusion to the gap of 2 periphery ground 1 of stake holes by 2 side wall of stake holes, grouting pile and stake week While the ground 1 after grout material fills curing process is with regard to form compound foundation 1, the structural load of shared flooring reaches To consolidated subsoil 1, improve the purpose of its bearing capacity;During slip casting, it can observe whether stake holes 2 has been filled with by exhaust pipe 5 Grout material, the slip casting in stake holes 2 when normal pressure, waits for that slip casting feed liquid surface moves up and to the upper end pulp of exhaust pipe 5, shown stake holes 2 Full of grout material, grouting pile having been formed in stake holes 2 at this time, then bending exhaust pipe 5 and having been sealed, the note of filling system 13 is gradually increased Pressure is starched, grout material slurries 9 are diffused in 2 periphery ground 1 of stake holes to the filling and solidification for carrying out hole.
As shown in Figs. 1-3, the hole inner filling material further includes grout material slurries 9, and the grout material slurries 9 are by filling system 13 fill the hole inner filling material layer 3 through the Grouting Pipe 4.
Grout material slurries 9 fill the hole inner filling material layer 3, hole inner filling material and grout material slurries 9 through the Grouting Pipe 4 By curing cementing formation grouting pile, the grouting pressure of filling system 13 is gradually increased, grout material slurries 9 are diffused into stake holes 2 The filling and solidification of hole are carried out in periphery ground 1.
As shown in Figs. 1-3, Grouting Pipe 4 includes integrally formed slip casting connecting tube 41 and grouting tube 42, slip casting connecting tube 41 upper ends connect filling system 13, and lower end connects the upper end of grouting tube 42, and the lower end of grouting tube 42 is connected to the bottom of stake holes 2 Portion;Several slurry outlets 421 are offered on grouting tube 42;The slip casting connecting tube 41 is located at the aperture sealing of hole bed of material 6, described Grouting tube 42 is located at the hole inner filling material layer 3.It may be implemented grout material slurries 9 being injected into hole by slurry outlet 421 Fill the bed of material 3.
As shown in Figs 1-4, slurry outlet 421 is horizontal runs through the grouting tube 42, and the two neighboring slurry outlet 421 Between the upper and lower every being arranged and be mutually perpendicular to;The slurry outlet 421 diameter 5mm, 421 4~6cm of spacing of the two neighboring slurry outlet.
As shown in figure 4, a slurry outlet 421 is horizontal to form two correspondences through the grouting tube 42 on grouting tube 42 Hole, and the two neighboring slurry outlet 421 is covered with closure 7 between the upper and lower every being arranged and being mutually perpendicular on slurry outlet 421, envelope It is tied with adhesive tape 8 outside stifled 7;The tube bottom of Grouting Pipe 4 is tied with the adhesive tape 8 for back cover, and closure 7 is covered on slurry outlet 421, blocks 7 It is tied with adhesive tape 8 outside;The tube bottom of Grouting Pipe 4 is tied with the adhesive tape 8 for back cover, and being will not in Grouting Pipe 4 before slip casting in order to protect Into sundries such as the inner filling material of hole, the surge that slip casting starts grouting behind shaft or drift lining slurry liquid 9 will can easily block 7 Hes Adhesive tape 8 is washed open, realizes the purpose that grout material slurries 9 come out from slurry outlet 421.
The course of work of the present embodiment is:Slip casting connecting tube 41 and grouting tube 42 on same root plastic tube, wherein on 80~100cm of portion is slip casting connecting tube 41, and lower part is grouting tube 42, and the exhaust pipe 5 is bound with iron wire in grouting tube 42 Outside;In stake holes 2, the slip casting connecting tube 41 with the exhaust pipe 5 and grouting tube 42 are put into bottom hole, then artificial filling Under hole inner filling material to 2 aperture absolute altitude of stake holes at 50cm, while the position for adjusting the slip casting connecting tube 41 is allowed in stake holes 23 Centre position, the indoor making aperture sealing of hole material in scene, aperture sealing of hole material is filled up at the aperture absolute altitude of stake holes 2 later, and With reinforcing bar vibration compacting, the aperture sealing of hole bed of material 6 is formed, indoor maintenance carries out Cementer work after 2~3 days, when slip casting first passes through note It starches connecting tube 41 and grouting tube 42 and carries out common pressure grouting, wait for that the grout material slurries 9 move up in stake holes 2 and to exhaust pipe 5 Exposed nozzle pulp shows that stake holes 2 has been filled with grout material slurries 9, at this time the hole inner filling material and grout material slurries 9 in stake holes 2 Formed non-fine concrete grouting pile, then bending exhaust pipe 5 and bind on exhaust pipe 5, grouting pressure maximum is gradually increased extremely Stop slip casting when 1.0MPa, grout material slurries 9 diffuse to 2 periphery miscellaneous fill layer 11 of stake holes by 2 Sidewall spacers of stake holes at this time Filling and curing process, such grouting pile and stake periphery miscellaneous filling out after grout material slurries 9 fill curing process are carried out in gap Soil layer 11 reaches with regard to form compound foundation 1, shared flooring structural load and reinforces miscellaneous fill layer 11, improves its carrying The purpose of power.
Wherein, hole inner filling material is rubble, and 0.5~2.0cm of grain size, filling height is from 2 bottom hole of stake holes to aperture absolute altitude At lower 50cm;Aperture sealing of hole material is live hand mixed concrete, and intensity C20 is filled described on hole inner filling material top Reinforcing bar vibration compacting is used in combination until stopping at 2 aperture absolute altitude of stake holes in aperture sealing of hole material.The aperture sealing of hole bed of material 6 need to carry out intensity and support Shield, indoor curing time:At least 48 hours in summer, at least 72 hours winter.
Grout material slurries 9 are plain-water slurry, strength of cement grade P.O 42.5, the ratio of mud 0.6~0.8, grout material slurries 9 Entered in the stake holes 2 full of hole inner filling material by Grouting Pipe 4 by filling system 13,2 inner pore air of stake holes passes through exhaust pipe 5 Discharge, until grout material slurries 9 are flowed out in 5 exposed aperture of exhaust pipe, grout material slurries 9 have been at this time for slip casting always under normal pressure Full of all gaps in stake holes 2 and hole inner filling material, 2 endoporus inner filling material of stake holes and grout material slurries 9 cure cementing, formation Non-fine concrete grouting pile.
After non-fine concrete grouting pile is formed, then bending exhaust pipe 5 and with iron wire binding on exhaust pipe 5, gradually carry Stop slip casting when high grouting pressure is to 1.0MPa, grout material slurries 9 diffuse to 2 periphery of stake holes by 2 Sidewall spacers of stake holes at this time Miscellaneous fill layer 11 gap in filled and cured, such grouting pile and periphery are through the cured miscellaneous fill layer of grout filling 11 with regard to form compound foundation 1, achievees the purpose that reinforce miscellaneous fill layer 11, improves its bearing capacity.
Stake holes 2 is laid in 40~50cm by horizontal and vertical spacing, every grouting pile is applied with above-mentioned technique Work, more grouting piles and periphery fill cured miscellaneous fill layer 11 with regard to full wafer composite foundation 1 in forming chamber through grout material slurries 9, Surface infrastructure load in shared room.
The present embodiment has the beneficial effect that:The sturdy stabilization of the aperture sealing of hole bed of material can make the note injected during slip casting Slurry slurries will not emerge from aperture, but by being filled in the void diffusion of stake holes side wall to the gap of stake holes periphery ground It fills out and cures, the ground of grouting pile and stake periphery after grout material fills curing process is with regard to form compound foundation, shared room The structural load on interior ground achievees the purpose that consolidated subsoil, improves its bearing capacity, and the utility model is filled by grout material slurries Curing process ground is filled out, ground after processing is the major volume portion of composite foundation, except generating grouting pile when site operation Outside a small amount of dregs of own vol, generation dregs amount is less, belongs to environmental protection construction, Green civilization construction.It compares and conventional high-pressure Grouting method, after grouting pile is formed, filling system stops the utility model when grouting pressure maximum is gradually increased to 1.0MPa Slip casting, at this time grout material slurries diffused in the ground of stake holes periphery carry out hole filling and solidification, may be implemented low pressure note Slurry.
In the description of this specification, reference term " embodiment one ", " embodiment two ", " example ", " specific example " or The description of " some examples " etc. means that specific method, device or feature described in conjunction with this embodiment or example are contained in this reality With in novel at least one embodiment or example.In the present specification, schematic expression of the above terms are necessarily directed to Be identical embodiment or example.Moreover, description specific features, method, apparatus or feature can any one or it is more It can be combined in any suitable manner in a embodiment or example.In addition, without conflicting with each other, those skilled in the art can The feature of different embodiments or examples described in this specification and different embodiments or examples to be combined.
The above is only the preferred embodiment of the present invention, is not intended to limit the utility model, all in this practicality Within novel spirit and principle, any modification, equivalent replacement, improvement and so on should be included in the guarantor of the utility model Within the scope of shield.

Claims (10)

1. a kind of slip casting pilework, which is characterized in that including stake holes, exhaust pipe and the Grouting Pipe being vertically arranged in ground, institute The bottom of the stake holes is inserted into the stake holes and is abutted in the lower end for stating Grouting Pipe, and the stake holes is stretched out in the upper end of the Grouting Pipe Aperture and be connected to and in communication with filling system;The lower end of the exhaust pipe is placed in the stake holes, and the stake is stretched out in the upper end The aperture in hole;The exhaust pipe leans on the Grouting Pipe and is fixedly connected with the top of the Grouting Pipe;Under in the stake holes Portion is filled with hole inner filling material, and forms hole inner filling material layer, from the upper end of the hole inner filling material layer to institute in the stake holes It states and is filled with aperture sealing of hole material between the aperture of stake holes, and form the aperture sealing of hole bed of material;Described in the lower end of the exhaust pipe is inserted into The top of hole inner filling material layer.
2. a kind of slip casting pilework according to claim 1, it is characterised in that, the hole inner filling material further includes slip casting slurry Liquid, the grout material slurries fill the hole inner filling material layer by the filling system through the Grouting Pipe.
3. a kind of slip casting pilework according to claim 1, it is characterised in that, the Grouting Pipe includes integrally formed slip casting Connecting tube and grouting tube, slip casting connecting tube upper end connect filling system, and lower end connects the upper end of the grouting tube, institute The lower end for stating grouting tube is connected to the bottom of the stake holes;Several slurry outlets are offered on the grouting tube;The slip casting Connecting tube is located at the aperture sealing of hole bed of material, and the grouting tube is located at the hole inner filling material layer.
4. a kind of slip casting pilework according to claim 3, it is characterised in that, the slurry outlet is horizontal to run through the slip casting Floral tube, and the two neighboring slurry outlet is between the upper and lower every being arranged and be mutually perpendicular to;The pulp bore dia 5mm, two neighboring institute State 4~6cm of pulp pitch of holes.
5. a kind of slip casting pilework according to claim 3, which is characterized in that closure is covered on the slurry outlet, it is described It is tied with adhesive tape outside blocking;The tube bottom of the Grouting Pipe is tied with the adhesive tape for back cover.
6. a kind of slip casting pilework according to claim 1, which is characterized in that the upper layer of the ground is miscellaneous fill layer, under Layer is original state soil layer, 80~100mm of the stake holes diameter, the stake holes be inserted into the original state soil layer and its bottom hole with it is described The distance of the upper end of undisturbed soil is 50cm.
7. a kind of slip casting pilework according to claim 1, it is characterised in that, the bottom end of the exhaust pipe and the stake holes The distance in aperture is 60cm.
8. a kind of slip casting pilework according to claim 1, it is characterised in that, the height of the aperture sealing of hole bed of material is 50cm。
9. a kind of slip casting pilework according to claim 1, which is characterized in that the hole inner filling material is rubble, grain size For 0.5~2.0cm.
10. a kind of slip casting pilework according to claim 1, it is characterised in that, the maximum grouting pressure of the filling system For 1.0MPa.
CN201820467866.7U 2018-04-03 2018-04-03 A kind of slip casting pilework Expired - Fee Related CN208023561U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820467866.7U CN208023561U (en) 2018-04-03 2018-04-03 A kind of slip casting pilework

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820467866.7U CN208023561U (en) 2018-04-03 2018-04-03 A kind of slip casting pilework

Publications (1)

Publication Number Publication Date
CN208023561U true CN208023561U (en) 2018-10-30

Family

ID=63909020

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820467866.7U Expired - Fee Related CN208023561U (en) 2018-04-03 2018-04-03 A kind of slip casting pilework

Country Status (1)

Country Link
CN (1) CN208023561U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109736302A (en) * 2019-02-28 2019-05-10 长江勘测规划设计研究有限责任公司 High-pressure rotary jet grouting pile Grouting Pipe plugging structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109736302A (en) * 2019-02-28 2019-05-10 长江勘测规划设计研究有限责任公司 High-pressure rotary jet grouting pile Grouting Pipe plugging structure
CN109736302B (en) * 2019-02-28 2023-12-19 长江勘测规划设计研究有限责任公司 High-pressure jet grouting pile grouting pipe plugging structure

Similar Documents

Publication Publication Date Title
CN103074891B (en) Double-layer plastic sleeve bulk material and concrete stiffness core composite pile and construction method thereof
CN204059124U (en) A kind of sand drain strong rammer grouting behind shaft or drift lining foundation reinforcing structure
CN102433876B (en) Multi-compartment casing composite pile and construction method thereof
CN101858077B (en) Construction method of composite foundation with bagged compacting and slurry cementing small-diameter gravel pile
CN102146679A (en) Construction method for complex geological section earth pressure balance shield passing middle air shaft
CN103469701B (en) On-the-spot integrated form is prepared Foam lightweight soil and is filled high ferro roadbed construction method
CN105239555A (en) Method for treating soft soil foundation through combination of bagged grouting gravel pile and vacuum preloading
CN104499479A (en) Dig-hole pile construction method based on penetration of sand gravel backfilling layer
CN101285309A (en) Compound support method for deep foundation pit of tall buildings
CN108560542A (en) A kind of waste tire cladding builds the two-directed reinforcement and its construction method of slag
CN110106883A (en) A kind of Real-time Feedback grouting method for correcting subway tunnel horizontal distortion
CN108677912A (en) A kind of CFG core sands stone built pile, its composite foundation constituted and construction method
CN105386610A (en) Protective construction method for natural-foundation ancient architectures at top of asymmetric deep foundation pit
CN114575355A (en) Soil protection and descent construction method
CN208023561U (en) A kind of slip casting pilework
CN104763127A (en) Heavy load resisting and acid-preventing terrace and construction method thereof
CN104141304B (en) The construction method of a kind of extrusion molding preformed pile stiff-core cement soil Y shape stake
CN101793027B (en) Core-grouted static pressure anchor rod pile
CN105780764A (en) Light cemented soil composite mixing pile
CN111424695B (en) Seepage-proofing and leakage-stopping method for deep-buried karst pipeline
CN105804045A (en) Equipment for strengthening deep soft soil foundation by vacuum preloading of filter well and method
CN106917402A (en) A kind of CFG pile precast piles head and CFG pile construction methods
CN207525774U (en) A kind of cantilever retaining wall structure
CN201635072U (en) Centrally grouted static-pressured anchor pile former
CN104775414A (en) Super-soft dredger fill surface layer solidification crusting and foundation treatment method

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20181030

CF01 Termination of patent right due to non-payment of annual fee