CN208010361U - A kind of half hiding support node of the plug-in conduit of shield tunnel - Google Patents

A kind of half hiding support node of the plug-in conduit of shield tunnel Download PDF

Info

Publication number
CN208010361U
CN208010361U CN201820311227.1U CN201820311227U CN208010361U CN 208010361 U CN208010361 U CN 208010361U CN 201820311227 U CN201820311227 U CN 201820311227U CN 208010361 U CN208010361 U CN 208010361U
Authority
CN
China
Prior art keywords
conduit
hole
backing plate
installation
internal thread
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201820311227.1U
Other languages
Chinese (zh)
Inventor
徐飞生
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Haote Energy Saving System Engineering Co Ltd
Original Assignee
Zhejiang Haote Energy Saving System Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Haote Energy Saving System Engineering Co Ltd filed Critical Zhejiang Haote Energy Saving System Engineering Co Ltd
Priority to CN201820311227.1U priority Critical patent/CN208010361U/en
Application granted granted Critical
Publication of CN208010361U publication Critical patent/CN208010361U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Lining And Supports For Tunnels (AREA)

Abstract

The utility model is that the plug-in conduit of a kind of shield tunnel half hides support node, it is characterized in that, including bearing, conduit, bolt and backing plate, the bearing includes otic placode, pedestal and internal thread hole, the top of the otic placode is provided with the bolthole of the connection of the anchor pole for directly being used with concrete pipe sheet, the lower part of the otic placode connects with pedestal, and internal thread hole is arranged in the bottom surface of the pedestal;Installation through-hole is provided on the conduit, the installation through-hole connects with the internal thread hole;The backing plate is equipped with through-hole, and positioned at the outside of the conduit, the through-hole of the backing plate connects with the installation through-hole of conduit, the front end of the bolt sequentially passes through the through-hole of the backing plate and the installation through-hole of conduit and in the internal thread hole, and the bolt end is located at the outside of the conduit and backing plate.Premised on not destroying precast concrete section of jurisdiction, the novel base for supporting node being attached using existing anchor hole, the joints are big, and exposed component is few.

Description

A kind of half hiding support node of the plug-in conduit of shield tunnel
Technical field
The utility model belongs to shield tunnel neck, and in particular to is used for close-connected the one of plug-in conduit and shield tunnel The plug-in conduit of kind shield tunnel half hides support node.
Background technology
Shield-tunneling construction is that precast concrete section of jurisdiction is gradually mounted on to tunnel surrounding during mechanically-propelled, prevents tunnel Road caves in.Shield tunnel gut line and the conventional method of equipment installation are by expansion bolt come fixing bracket.Installation expansion It needs to drill when bolt, this hole causes to damage to precast concrete pipe sector-meeting, destroys its structure, influences its stress, while also depositing Percolating water hidden danger.Expansion bolt will produce loosening under dynamic loading, influence its anchor force.Applicant earlier application one kind The plug-in conduit of shield tunnel hides bearing section, and backing plate and bolt are located at the inner cavity of conduit, sets suitable for the loads such as pipeline are smaller Standby can use hides bearing installation fixation.But the equipment such as escape route it is larger when, hide bearing by the built-in limitation of bolt It cannot be satisfied requirement.It needs a kind of to increase stress, and exposed bearing that cannot be too many at this time.
Utility model content
In order to overcome the destruction precast concrete section of jurisdiction of the plug-in conduit of existing shield tunnel, installation procedure be complicated, construction compared with Slowly the installation of pipeline, the deficiency of troublesome maintenance, are influenced, the utility model provides a kind of half hiding branch of the plug-in conduit of shield tunnel Block node, premised on not destroying precast concrete section of jurisdiction, the novel base for supporting node being attached using existing anchor hole should Joints are big, and exposed component is few.
Technical solution adopted by the utility model to solve its technical problems is:
A kind of half hiding support node of the plug-in conduit of shield tunnel, including bearing, conduit, bolt and backing plate, the bearing Including otic placode, pedestal and internal thread hole, the top of the otic placode is provided with the connection of the anchor pole for directly being used with concrete pipe sheet Bolthole, the lower part of the otic placode connects with pedestal, and internal thread hole is arranged in the bottom surface of the pedestal;Peace is provided on the conduit Through-hole is filled,
The installation through-hole connects with the internal thread hole;The backing plate is equipped with through-hole and the outside positioned at the conduit, The backing plate through-hole connects with the installation through-hole of conduit, and the front end of the bolt sequentially passes through the through-hole and conduit of the backing plate Installation through-hole and in the internal thread hole, the bolt end is located at the outside of the conduit and backing plate.
The technical principle that the above-mentioned plug-in conduit of shield tunnel half hides support node is:The bolthole opened in support lug can The anchor pole connection directly used with concrete pipe sheet, ensure that and carry out erection support under the premise of not destroying concrete pipe sheet, prop up The internal thread hole of seat connects with the mounting hole of conduit, and then the front end of bolt sequentially passes through the installation of the through-hole and conduit of backing plate Through-hole is simultaneously mounted in internal thread hole, to achieve the effect that smoothly to install conduit.Half hides bearing due to only revealing outside conduit Go out one piece of backing plate, a bolt head, it is considerably less on the headroom influence in tunnel, but its stress-bearing capability increases very much, can meet The installation of the big component such as life channel.
Further, the cross-sectional length of the backing plate is more than the opening of conduit and the length less than or equal to conduit section.
Further, the conduit installation through-hole is slotted hole.The design of slotted hole is finely tuned convenient for conduit.
The beneficial effects of the utility model are mainly manifested in:
1, structure design needs are met, effective connection of bearing and concrete pipe sheet is solved from node, avoids Damage of the secondary construction to section of jurisdiction, half hiding bearing only expose one piece of backing plate, a bolt head, in tunnel outside conduit Headroom influence it is considerably less, but its stress-bearing capability increase can much meet life channel etc. greatly component installation.
2,2, construction cost is low.The expense for reducing secondary trepanning avoids the maintenance cost caused by trepanning.
3, construction efficiency is high.The bearing can be installed along with when installing section of jurisdiction in the notch of section of jurisdiction, and the later stage can directly pacify Dress.The method is simple and practicable, and effect is apparent.
Description of the drawings
Fig. 1 is support node elevation.
Fig. 2 is support node axonometric drawing;
Fig. 3 a are bearing elevation;
Fig. 3 b are bearing sectional views;
Fig. 4 is conduit trepanning schematic diagram.
Fig. 5 is bearing and section of jurisdiction connecting node.
As shown in the figure:1, bearing, 2, conduit, 3, backing plate, 4, bolt, 11, otic placode, 12, pedestal, 13, internal thread hole, 14, Bolthole, 21, installation through-hole, 31, backing plate through-hole, 5, anchor pole, 6, concrete pipe sheet.
Specific implementation mode
The utility model is further described below in conjunction with the accompanying drawings.
Referring to Fig.1~Fig. 5, a kind of half hiding support node of the plug-in conduit of shield tunnel, including bearing 1, conduit 2, bolt 4 With backing plate 3, the bearing includes otic placode 11, pedestal 12, internal thread hole 13, and the top of the otic placode is provided with for directly with coagulation The bolthole 14 for the anchor pole connection that native section of jurisdiction uses, the lower part of the otic placode connect with pedestal, in the bottom surface setting of the pedestal Threaded hole;Installation through-hole 21 is provided on the conduit, the installation through-hole connects with the internal thread hole;The backing plate is equipped with logical Hole 31 and the outside for being located at the conduit, the through-hole of the backing plate and connecting for conduit, the front end of the bolt sequentially pass through institute State the through-hole of backing plate and the mounting hole of conduit and in the internal thread hole, the bolt end be located at the conduit with The outside of backing plate.
The technical principle that the above-mentioned plug-in conduit of shield tunnel half hides support node is:The bolthole 14 opened in support lug It can directly be connected with the anchor pole 5 that concrete pipe sheet uses, ensure that and branch is installed under the premise of not destroying concrete pipe sheet 6 Seat, the internal thread hole of bearing connect with the mounting hole of conduit, and then the front end of bolt sequentially passes through the through-hole and conduit of backing plate Installation through-hole and in the internal thread hole, to achieve the effect that smoothly to install conduit.Half hides bearing due in conduit It is outer only to expose one piece of backing plate, a bolt head, it is considerably less on the headroom influence in tunnel, but its stress-bearing capability increases very much, The installation of the big component such as life channel can be met.
The plug-in conduit of the shield tunnel half hides the installation method of support node, includes the following steps:
The first step:The size of anchor pole notch first reserved according to concrete pipe sheet to determine the apparent size and shape of bearing, Ensure that conduit can be close to the installation of section of jurisdiction surface.
Second step:The installation of bearing, when section of jurisdiction is installed, erection support, the primary completion of guarantee construction need not weigh simultaneously It is new to unclamp anchor pole erection support again.
Third walks:Slotted hole is opened up according to the position of section of jurisdiction anchor pole slot on conduit.
4th step:Conduit is fixed with bolt corresponding with bearing internal thread hole, and bolt requires that internal thread cannot be longer than Depth+conduit height+plate thickness, and be screwed into depth and must meet code requirement.

Claims (3)

1. a kind of plug-in conduit of shield tunnel half hides support node, which is characterized in that including bearing, conduit, bolt and backing plate, The bearing includes otic placode, pedestal and internal thread hole, and the top of the otic placode is provided with for directly being used with concrete pipe sheet The bolthole of anchor pole connection, the lower part of the otic placode connect with pedestal, and internal thread hole is arranged in the bottom surface of the pedestal;The conduit On be provided with installation through-hole, the installation through-hole connects with the internal thread hole;The backing plate is equipped with through-hole, and is located at the conduit Outside, the through-hole of the backing plate connects with the installation through-hole of conduit, and the front end of the bolt sequentially passes through the logical of the backing plate The installation through-hole of hole and conduit is simultaneously mounted in the internal thread hole, the bolt end be located at the conduit and backing plate outside Side.
2. the plug-in conduit of a kind of shield tunnel according to claim 1 half hides support node, which is characterized in that the pad The cross-sectional length of plate is more than the opening of conduit and the length less than or equal to conduit section.
3. the plug-in conduit of a kind of shield tunnel according to claim 1 half hides support node, which is characterized in that the slot Road through-hole is slotted hole.
CN201820311227.1U 2018-03-07 2018-03-07 A kind of half hiding support node of the plug-in conduit of shield tunnel Active CN208010361U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820311227.1U CN208010361U (en) 2018-03-07 2018-03-07 A kind of half hiding support node of the plug-in conduit of shield tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820311227.1U CN208010361U (en) 2018-03-07 2018-03-07 A kind of half hiding support node of the plug-in conduit of shield tunnel

Publications (1)

Publication Number Publication Date
CN208010361U true CN208010361U (en) 2018-10-26

Family

ID=63887422

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820311227.1U Active CN208010361U (en) 2018-03-07 2018-03-07 A kind of half hiding support node of the plug-in conduit of shield tunnel

Country Status (1)

Country Link
CN (1) CN208010361U (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109441536A (en) * 2018-12-26 2019-03-08 彭健 A kind of hangers victory assembling device and installation method
WO2021088717A1 (en) * 2019-11-05 2021-05-14 京东数科海益信息科技有限公司 Hanging structure, tunnel rail hanging robot, and tunnel

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109441536A (en) * 2018-12-26 2019-03-08 彭健 A kind of hangers victory assembling device and installation method
WO2021088717A1 (en) * 2019-11-05 2021-05-14 京东数科海益信息科技有限公司 Hanging structure, tunnel rail hanging robot, and tunnel

Similar Documents

Publication Publication Date Title
CN206204995U (en) The tall and big side wall one side formwork erection of open trench tunnel agent structure
CN208010361U (en) A kind of half hiding support node of the plug-in conduit of shield tunnel
CN214884337U (en) High-rise large-span overhanging steel structure
CN208364136U (en) A kind of combination fastener of embedded sleeve barrel and rear-mounted conduit
CN107859533A (en) A kind of plug-in conduit of shield tunnel hides support node and its installation method
CN207879388U (en) A kind of hiding support node of the plug-in conduit of shield tunnel
CN206874312U (en) A kind of novel shield tunnel pre-buried channel flow dedicated shock-proof support
CN207353810U (en) A kind of multiple field cable support being easily installed
CN209669889U (en) Suspension type riding track assembled attached wall fashioned iron English truss
CN210372398U (en) Threaded connection type nodular cast iron flange pipe
CN208733817U (en) A kind of assembling type steel structure building Special-Shaped Column
CN202248218U (en) Structure for connecting drainage open trenches with drainage inspection well
CN210134665U (en) Plate mounting structure for reconstructing outer vertical face of existing building
CN205909184U (en) Energy -conserving street lamp fixing device
CN219315980U (en) Series-connection type installed integrated pump station
CN220151686U (en) Detachable rear-expanded bottom anchor bolt
CN217540121U (en) High and cold area construction sewage treatment system
CN215445353U (en) Embedded pipeline installation base
CN220666276U (en) Water supply and drainage pipeline pipe gallery
CN219386331U (en) Long and short combined pile supporting structure
CN217175422U (en) Socket joint formula canopy support
CN214090380U (en) Promote device of assembled composite wall panel bolted connection anti-seismic performance
CN220706666U (en) Drain pipe connection structure
CN216277076U (en) Balcony reinforcing and reforming supporting device for old building
CN221321238U (en) Prefabricated air conditioner plate structure

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CB03 Change of inventor or designer information

Inventor after: Xu Feisheng

Inventor after: Dai Yajun

Inventor before: Xu Feisheng

CB03 Change of inventor or designer information