CN208010361U - A kind of half hiding support node of the plug-in conduit of shield tunnel - Google Patents
A kind of half hiding support node of the plug-in conduit of shield tunnel Download PDFInfo
- Publication number
- CN208010361U CN208010361U CN201820311227.1U CN201820311227U CN208010361U CN 208010361 U CN208010361 U CN 208010361U CN 201820311227 U CN201820311227 U CN 201820311227U CN 208010361 U CN208010361 U CN 208010361U
- Authority
- CN
- China
- Prior art keywords
- conduit
- hole
- backing plate
- installation
- internal thread
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Landscapes
- Lining And Supports For Tunnels (AREA)
Abstract
The utility model is that the plug-in conduit of a kind of shield tunnel half hides support node, it is characterized in that, including bearing, conduit, bolt and backing plate, the bearing includes otic placode, pedestal and internal thread hole, the top of the otic placode is provided with the bolthole of the connection of the anchor pole for directly being used with concrete pipe sheet, the lower part of the otic placode connects with pedestal, and internal thread hole is arranged in the bottom surface of the pedestal;Installation through-hole is provided on the conduit, the installation through-hole connects with the internal thread hole;The backing plate is equipped with through-hole, and positioned at the outside of the conduit, the through-hole of the backing plate connects with the installation through-hole of conduit, the front end of the bolt sequentially passes through the through-hole of the backing plate and the installation through-hole of conduit and in the internal thread hole, and the bolt end is located at the outside of the conduit and backing plate.Premised on not destroying precast concrete section of jurisdiction, the novel base for supporting node being attached using existing anchor hole, the joints are big, and exposed component is few.
Description
Technical field
The utility model belongs to shield tunnel neck, and in particular to is used for close-connected the one of plug-in conduit and shield tunnel
The plug-in conduit of kind shield tunnel half hides support node.
Background technology
Shield-tunneling construction is that precast concrete section of jurisdiction is gradually mounted on to tunnel surrounding during mechanically-propelled, prevents tunnel
Road caves in.Shield tunnel gut line and the conventional method of equipment installation are by expansion bolt come fixing bracket.Installation expansion
It needs to drill when bolt, this hole causes to damage to precast concrete pipe sector-meeting, destroys its structure, influences its stress, while also depositing
Percolating water hidden danger.Expansion bolt will produce loosening under dynamic loading, influence its anchor force.Applicant earlier application one kind
The plug-in conduit of shield tunnel hides bearing section, and backing plate and bolt are located at the inner cavity of conduit, sets suitable for the loads such as pipeline are smaller
Standby can use hides bearing installation fixation.But the equipment such as escape route it is larger when, hide bearing by the built-in limitation of bolt
It cannot be satisfied requirement.It needs a kind of to increase stress, and exposed bearing that cannot be too many at this time.
Utility model content
In order to overcome the destruction precast concrete section of jurisdiction of the plug-in conduit of existing shield tunnel, installation procedure be complicated, construction compared with
Slowly the installation of pipeline, the deficiency of troublesome maintenance, are influenced, the utility model provides a kind of half hiding branch of the plug-in conduit of shield tunnel
Block node, premised on not destroying precast concrete section of jurisdiction, the novel base for supporting node being attached using existing anchor hole should
Joints are big, and exposed component is few.
Technical solution adopted by the utility model to solve its technical problems is:
A kind of half hiding support node of the plug-in conduit of shield tunnel, including bearing, conduit, bolt and backing plate, the bearing
Including otic placode, pedestal and internal thread hole, the top of the otic placode is provided with the connection of the anchor pole for directly being used with concrete pipe sheet
Bolthole, the lower part of the otic placode connects with pedestal, and internal thread hole is arranged in the bottom surface of the pedestal;Peace is provided on the conduit
Through-hole is filled,
The installation through-hole connects with the internal thread hole;The backing plate is equipped with through-hole and the outside positioned at the conduit,
The backing plate through-hole connects with the installation through-hole of conduit, and the front end of the bolt sequentially passes through the through-hole and conduit of the backing plate
Installation through-hole and in the internal thread hole, the bolt end is located at the outside of the conduit and backing plate.
The technical principle that the above-mentioned plug-in conduit of shield tunnel half hides support node is:The bolthole opened in support lug can
The anchor pole connection directly used with concrete pipe sheet, ensure that and carry out erection support under the premise of not destroying concrete pipe sheet, prop up
The internal thread hole of seat connects with the mounting hole of conduit, and then the front end of bolt sequentially passes through the installation of the through-hole and conduit of backing plate
Through-hole is simultaneously mounted in internal thread hole, to achieve the effect that smoothly to install conduit.Half hides bearing due to only revealing outside conduit
Go out one piece of backing plate, a bolt head, it is considerably less on the headroom influence in tunnel, but its stress-bearing capability increases very much, can meet
The installation of the big component such as life channel.
Further, the cross-sectional length of the backing plate is more than the opening of conduit and the length less than or equal to conduit section.
Further, the conduit installation through-hole is slotted hole.The design of slotted hole is finely tuned convenient for conduit.
The beneficial effects of the utility model are mainly manifested in:
1, structure design needs are met, effective connection of bearing and concrete pipe sheet is solved from node, avoids
Damage of the secondary construction to section of jurisdiction, half hiding bearing only expose one piece of backing plate, a bolt head, in tunnel outside conduit
Headroom influence it is considerably less, but its stress-bearing capability increase can much meet life channel etc. greatly component installation.
2,2, construction cost is low.The expense for reducing secondary trepanning avoids the maintenance cost caused by trepanning.
3, construction efficiency is high.The bearing can be installed along with when installing section of jurisdiction in the notch of section of jurisdiction, and the later stage can directly pacify
Dress.The method is simple and practicable, and effect is apparent.
Description of the drawings
Fig. 1 is support node elevation.
Fig. 2 is support node axonometric drawing;
Fig. 3 a are bearing elevation;
Fig. 3 b are bearing sectional views;
Fig. 4 is conduit trepanning schematic diagram.
Fig. 5 is bearing and section of jurisdiction connecting node.
As shown in the figure:1, bearing, 2, conduit, 3, backing plate, 4, bolt, 11, otic placode, 12, pedestal, 13, internal thread hole, 14,
Bolthole, 21, installation through-hole, 31, backing plate through-hole, 5, anchor pole, 6, concrete pipe sheet.
Specific implementation mode
The utility model is further described below in conjunction with the accompanying drawings.
Referring to Fig.1~Fig. 5, a kind of half hiding support node of the plug-in conduit of shield tunnel, including bearing 1, conduit 2, bolt 4
With backing plate 3, the bearing includes otic placode 11, pedestal 12, internal thread hole 13, and the top of the otic placode is provided with for directly with coagulation
The bolthole 14 for the anchor pole connection that native section of jurisdiction uses, the lower part of the otic placode connect with pedestal, in the bottom surface setting of the pedestal
Threaded hole;Installation through-hole 21 is provided on the conduit, the installation through-hole connects with the internal thread hole;The backing plate is equipped with logical
Hole 31 and the outside for being located at the conduit, the through-hole of the backing plate and connecting for conduit, the front end of the bolt sequentially pass through institute
State the through-hole of backing plate and the mounting hole of conduit and in the internal thread hole, the bolt end be located at the conduit with
The outside of backing plate.
The technical principle that the above-mentioned plug-in conduit of shield tunnel half hides support node is:The bolthole 14 opened in support lug
It can directly be connected with the anchor pole 5 that concrete pipe sheet uses, ensure that and branch is installed under the premise of not destroying concrete pipe sheet 6
Seat, the internal thread hole of bearing connect with the mounting hole of conduit, and then the front end of bolt sequentially passes through the through-hole and conduit of backing plate
Installation through-hole and in the internal thread hole, to achieve the effect that smoothly to install conduit.Half hides bearing due in conduit
It is outer only to expose one piece of backing plate, a bolt head, it is considerably less on the headroom influence in tunnel, but its stress-bearing capability increases very much,
The installation of the big component such as life channel can be met.
The plug-in conduit of the shield tunnel half hides the installation method of support node, includes the following steps:
The first step:The size of anchor pole notch first reserved according to concrete pipe sheet to determine the apparent size and shape of bearing,
Ensure that conduit can be close to the installation of section of jurisdiction surface.
Second step:The installation of bearing, when section of jurisdiction is installed, erection support, the primary completion of guarantee construction need not weigh simultaneously
It is new to unclamp anchor pole erection support again.
Third walks:Slotted hole is opened up according to the position of section of jurisdiction anchor pole slot on conduit.
4th step:Conduit is fixed with bolt corresponding with bearing internal thread hole, and bolt requires that internal thread cannot be longer than
Depth+conduit height+plate thickness, and be screwed into depth and must meet code requirement.
Claims (3)
1. a kind of plug-in conduit of shield tunnel half hides support node, which is characterized in that including bearing, conduit, bolt and backing plate,
The bearing includes otic placode, pedestal and internal thread hole, and the top of the otic placode is provided with for directly being used with concrete pipe sheet
The bolthole of anchor pole connection, the lower part of the otic placode connect with pedestal, and internal thread hole is arranged in the bottom surface of the pedestal;The conduit
On be provided with installation through-hole, the installation through-hole connects with the internal thread hole;The backing plate is equipped with through-hole, and is located at the conduit
Outside, the through-hole of the backing plate connects with the installation through-hole of conduit, and the front end of the bolt sequentially passes through the logical of the backing plate
The installation through-hole of hole and conduit is simultaneously mounted in the internal thread hole, the bolt end be located at the conduit and backing plate outside
Side.
2. the plug-in conduit of a kind of shield tunnel according to claim 1 half hides support node, which is characterized in that the pad
The cross-sectional length of plate is more than the opening of conduit and the length less than or equal to conduit section.
3. the plug-in conduit of a kind of shield tunnel according to claim 1 half hides support node, which is characterized in that the slot
Road through-hole is slotted hole.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820311227.1U CN208010361U (en) | 2018-03-07 | 2018-03-07 | A kind of half hiding support node of the plug-in conduit of shield tunnel |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201820311227.1U CN208010361U (en) | 2018-03-07 | 2018-03-07 | A kind of half hiding support node of the plug-in conduit of shield tunnel |
Publications (1)
Publication Number | Publication Date |
---|---|
CN208010361U true CN208010361U (en) | 2018-10-26 |
Family
ID=63887422
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201820311227.1U Active CN208010361U (en) | 2018-03-07 | 2018-03-07 | A kind of half hiding support node of the plug-in conduit of shield tunnel |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN208010361U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109441536A (en) * | 2018-12-26 | 2019-03-08 | 彭健 | A kind of hangers victory assembling device and installation method |
WO2021088717A1 (en) * | 2019-11-05 | 2021-05-14 | 京东数科海益信息科技有限公司 | Hanging structure, tunnel rail hanging robot, and tunnel |
-
2018
- 2018-03-07 CN CN201820311227.1U patent/CN208010361U/en active Active
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109441536A (en) * | 2018-12-26 | 2019-03-08 | 彭健 | A kind of hangers victory assembling device and installation method |
WO2021088717A1 (en) * | 2019-11-05 | 2021-05-14 | 京东数科海益信息科技有限公司 | Hanging structure, tunnel rail hanging robot, and tunnel |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206204995U (en) | The tall and big side wall one side formwork erection of open trench tunnel agent structure | |
CN208010361U (en) | A kind of half hiding support node of the plug-in conduit of shield tunnel | |
CN214884337U (en) | High-rise large-span overhanging steel structure | |
CN208364136U (en) | A kind of combination fastener of embedded sleeve barrel and rear-mounted conduit | |
CN107859533A (en) | A kind of plug-in conduit of shield tunnel hides support node and its installation method | |
CN207879388U (en) | A kind of hiding support node of the plug-in conduit of shield tunnel | |
CN206874312U (en) | A kind of novel shield tunnel pre-buried channel flow dedicated shock-proof support | |
CN207353810U (en) | A kind of multiple field cable support being easily installed | |
CN209669889U (en) | Suspension type riding track assembled attached wall fashioned iron English truss | |
CN210372398U (en) | Threaded connection type nodular cast iron flange pipe | |
CN208733817U (en) | A kind of assembling type steel structure building Special-Shaped Column | |
CN202248218U (en) | Structure for connecting drainage open trenches with drainage inspection well | |
CN210134665U (en) | Plate mounting structure for reconstructing outer vertical face of existing building | |
CN205909184U (en) | Energy -conserving street lamp fixing device | |
CN219315980U (en) | Series-connection type installed integrated pump station | |
CN220151686U (en) | Detachable rear-expanded bottom anchor bolt | |
CN217540121U (en) | High and cold area construction sewage treatment system | |
CN215445353U (en) | Embedded pipeline installation base | |
CN220666276U (en) | Water supply and drainage pipeline pipe gallery | |
CN219386331U (en) | Long and short combined pile supporting structure | |
CN217175422U (en) | Socket joint formula canopy support | |
CN214090380U (en) | Promote device of assembled composite wall panel bolted connection anti-seismic performance | |
CN220706666U (en) | Drain pipe connection structure | |
CN216277076U (en) | Balcony reinforcing and reforming supporting device for old building | |
CN221321238U (en) | Prefabricated air conditioner plate structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CB03 | Change of inventor or designer information |
Inventor after: Xu Feisheng Inventor after: Dai Yajun Inventor before: Xu Feisheng |
|
CB03 | Change of inventor or designer information |