CN208009601U - A kind of inspection shaft for rain sewage diversion - Google Patents

A kind of inspection shaft for rain sewage diversion Download PDF

Info

Publication number
CN208009601U
CN208009601U CN201820106109.7U CN201820106109U CN208009601U CN 208009601 U CN208009601 U CN 208009601U CN 201820106109 U CN201820106109 U CN 201820106109U CN 208009601 U CN208009601 U CN 208009601U
Authority
CN
China
Prior art keywords
outlet
cover board
water
pit shaft
sewer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820106109.7U
Other languages
Chinese (zh)
Inventor
雷斌
严超君
谭宇星
王纪婷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanchang University
Original Assignee
Nanchang University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanchang University filed Critical Nanchang University
Priority to CN201820106109.7U priority Critical patent/CN208009601U/en
Application granted granted Critical
Publication of CN208009601U publication Critical patent/CN208009601U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Sewage (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

A kind of inspection shaft for rain sewage diversion, including pit shaft, water blocking cover board, crank hand, spool and train line;Pit shaft side is equipped with water inlet, water outlet;Water outlet includes outlet of sewer, rainwater outlet;Rainwater outlet is set to above outlet of sewer or outlet of sewer is set to above rainwater outlet;Pit shaft inner close fitting outlet of sewer is equipped with limited block with sliding slot, sliding slot both ends are equipped at rainwater outlet;Water blocking cover board is set in sliding slot;Pit shaft upper end is equipped with crank hand and spool, and crank hand is sequentially connected with spool;Train line one end is fixed on spool, and the other end is fixed on water blocking cover board.Due to being moved up and down in sliding slot by controlling water blocking cover board so that water blocking cover board blocks outlet of sewer or rainwater outlet, realizes rainwater and sewage separation.

Description

A kind of inspection shaft for rain sewage diversion
Technical field
This application involves a kind of inspection shafts for rain sewage diversion, belong to municipal works, rural water conservancy field.
Background technology
Current country vigorously advocates rain sewage diversion processing, and Municipal is usually using two kinds of canals of newly-built stormwater channel and sewer Road carries out rain sewage diversion, has feature of high cost, quantities is big.In rural area and some remote poor newly-built cost phases in area To low artificial combination wetland variation sanitary sewage, but due to not carrying out rain sewage diversion, in the big weather of rainfall, artificial swamp It can be destroyed by rush of water damage by rainwater, while will also result in certain pollution, be badly in need of a kind of device of rain sewage diversion to carry out rain sewage diversion, It is discharged again after so that sewage is flowed into treatment tank processing by sewage conduct, and rainwater is directly discharged to nature by storm sewer In environment.
Utility model content
The application provides a kind of inspection shaft for rain sewage diversion, to be shunted to rain dirt.
According in a first aspect, providing a kind of inspection shaft for rain sewage diversion, including pit shaft, water blocking in a kind of embodiment Cover board, crank hand, spool and train line;Pit shaft side is equipped with water inlet, water outlet;Water outlet includes outlet of sewer, rain Water out;Rainwater outlet is set to above outlet of sewer or outlet of sewer is set to above rainwater outlet;Pit shaft inner close fitting outlet of sewer With at rainwater outlet limited block is equipped with equipped with sliding slot, sliding slot both ends;Water blocking cover board is set in sliding slot;Pit shaft upper end is equipped with crank hand And spool, crank hand are sequentially connected with spool;Train line one end is fixed on spool, and the other end is fixed on water deflector cover On plate.
Preferably, further include well lid, well lid is connected to by connecting knob on pit shaft, and the well lid is equipped with handle.
Preferably, a diameter of 400mm of the water inlet, a diameter of 300mm of water outlet.
Preferably, the water inlet and a water outlet are apart from wellbore bottom 300mm, another water inlet bottom and water inlet Distance from top 300mm, pit shaft height are 1500mm.
According to second aspect, a kind of inspection shaft for rain sewage diversion is provided in a kind of embodiment, including:Pit shaft, water blocking Cover board, floating installation and train line;Pit shaft side is equipped with water inlet, outlet of sewer, rainwater outlet;Outlet of sewer is set to rainwater Outlet top;Pit shaft inner close fitting outlet of sewer is equipped with limited block with sliding slot, sliding slot both ends are equipped at rainwater outlet;Water blocking cover board is set In in sliding slot;Floating installation floats in the level in pit shaft;Train line one end is fixed on floating installation, and the other end is fixed on On water blocking cover board.
Preferably, further include well lid, well lid is connected to by connecting knob on pit shaft, and the well lid is equipped with handle.
According to the third aspect, a kind of inspection shaft for rain sewage diversion is provided in a kind of embodiment, including:Pit shaft, water blocking Cover board, column, connecting rod, kickboard;Pit shaft side is equipped with water inlet, outlet of sewer, rainwater outlet;Rainwater outlet is set to outlet of sewer Top;Sliding slot is equipped at pit shaft inner close fitting outlet of sewer and rainwater outlet;Water blocking cover board is set in sliding slot;Column one end is fixed on On pit shaft, it is riveted on the column other end in the middle part of connecting rod, connecting rod two end is separately connected kickboard and water blocking cover board.
Preferably, sliding slot both ends are equipped with limited block, and kickboard is equipped with clump weight.
Preferably, the water blocking cover board is equipped with water seepage hole.
Preferably, the water blocking cover board is tile.
According to the inspection shaft for rain sewage diversion of above-described embodiment, due to being rotated by crank hand-motion spool, from And realize the folding and unfolding of train line, train line drives water blocking cover board to be moved up and down in sliding slot again so that water blocking cover board goes out sewage Mouth or rainwater outlet are blocked, and realize the purpose of rainwater and sewage separation.Further, well lid is set and sets handle on well lid Hand enhances security performance and convenience.And from the above as can be seen that the application has simple in structure, at low cost, behaviour Make convenient advantage, is applicable to the vast rural areas.
Description of the drawings
Fig. 1 and Fig. 2 is one embodiment stereogram of the application inspection shaft.
Fig. 3 is that weather hand-rail type inspection shaft sewage short of rain flows to schematic diagram.
Fig. 4 is that rainy weather hand-rail type inspection shaft rainwater and sewage flow to schematic diagram.
Fig. 5 and Fig. 6 is hand-rail type inspection shaft transmission device schematic diagram.
Fig. 7 is that weather floating-board type inspection shaft sewage short of rain flows to schematic diagram.
Fig. 8 is that rainy weather floating-board type inspection shaft rainwater and sewage flow to schematic diagram.
Fig. 9 and Figure 10 is floating-board type inspection shaft transmission device schematic diagram.
Specific implementation mode
The utility model is described in further detail below by specific implementation mode combination attached drawing.It is wherein different to implement Similar component uses associated similar element numbers in mode.In the following embodiments, many datail descriptions are In order to enable the application can be better understood.However, those skilled in the art can be without lifting an eyebrow recognize, which part Feature is dispensed in varied situations, or can be substituted by other elements, material, method.In some cases, Some relevant operations of the application are there is no display in the description or describe, this is the core in order to avoid the application It is flooded by excessive description, and to those skilled in the art, these relevant operations, which are described in detail, not to be necessary, They can completely understand relevant operation according to the general technology knowledge of description and this field in specification.
It is herein component institute serialization number itself, such as " first ", " second " etc., is only used for distinguishing described object, Without any sequence or art-recognized meanings.And " connection ", " connection " described in the application, unless otherwise instructed, include directly and It is indirectly connected with(Connection).
Embodiment one.
- 6 are please referred to Fig.1, hand-rail type inspection shaft.
For the inspection shaft of rain sewage diversion, including well lid 1, pit shaft 2, water blocking cover board 8, crank hand 10, winding box 9 and Train line 7;Well lid is connected to by connecting knob on pit shaft, and the well lid is equipped with handle.
Spool is set in winding box 9;2 side of pit shaft is equipped with water inlet 3, water outlet;Water outlet include outlet of sewer 5, Rainwater outlet 4;Rainwater outlet 4 is set to 5 top of outlet of sewer.Sliding slot 6 is equipped at pit shaft inner close fitting outlet of sewer and rainwater outlet, Sliding slot both ends are equipped with limited block;Water blocking cover board 8 is set in sliding slot 6;Pit shaft upper end is equipped with crank hand 10 and spool, crank hand 10 are sequentially connected with spool;7 one end of train line is fixed on spool, and the other end is fixed on water blocking cover board 8.Water blocking cover board Width is slightly larger than the width of outlet of sewer and rainwater outlet, and water blocking cover board height is also slightly larger than the height of outlet of sewer and rainwater outlet Degree, enables water blocking cover board to shelter from outlet of sewer or rainwater outlet completely.Water blocking cover board, can be in cunning under the action of train line It is moved up and down in slot, outlet of sewer and rainwater outlet are blocked in rotation respectively, realize the shunting of sewage and rainwater.Sliding slot two End is equipped with limited block, to limit motion range of the water blocking cover board in sliding slot.
Wherein, a diameter of 400mm of water inlet, a diameter of 300mm of water outlet.Water inlet and a water outlet are apart from pit shaft bottom Portion 300mm, another water inlet bottom and water inlet distance from top 300mm, pit shaft height are 1500mm.
On the basis of the above embodiments, by then passing through the position of manual control water blocking cover board, outlet of sewer can also change Above rainwater outlet, the realization of the utility model is not influenced.
Wherein, pit shaft can be by prefabrication, and use is integrally moulded, ensure that well and water inlet, water outlet junction Ne-leakage possibility.Sliding slot uses stainless steel material, water blocking cover board to use tile.Above structure is not only at low cost, non-corrosive, matter Formwork that is secure, and eliminating cumbersome at the construction field (site) is measured, is conserved, the process of dismounting reduces construction pollution, reaches excellent Matter, it is time saving, efficient, light, environmentally friendly the advantages that.
Hand-rail type inspection shaft operation principle is as follows:
When sunny or rainfall is compared with microweather, with reference to figure 3, water blocking cover board 8 is lifted by crank hand 10, it is controlled and blocks Firmly rainwater outlet 4, sanitary sewage are entered inside inspection shaft by water inlet 3, then are emitted into artificial swamp etc. by outlet of sewer 5 Processing pond is emitted into river nearby after being disposed.When the larger weather of rainfall, with reference to figure 4, by crank hand 10 by water blocking cover board 8 Decentralization, makes water blocking cover board 8 cover outlet of sewer 5, and the water surface gradually rises in inspection shaft, until being higher than 4 bottom of rainwater outlet, checks Water is directly by 4 row of rainwater outlet to neighbouring river in well, after rain stops, shakes crank hand 10 and water blocking cover board 8 is driven to move up, again Water blocking cover board 8 is placed at rainwater outlet 4, sanitary sewage is made to be discharged from outlet of sewer 5.
Connection between water inlet, water outlet and external water-supply-pipe uses mosaic mode, with one and modeling in plastic tube The comparable PVC hard tubes connection of expects pipe diameter, is through on hard tube after plastic tube is cut off and is tightened with iron wire, ensure that junction is tight It is close reliably to seep water.
Pit shaft large-scale production in factory according to overall design drawing for rain sewage diversion, can not only ensure component matter Amount improves component precision, and can directly be installed at the construction field (site), reach saving of labor, it is efficient, light, be readily transported peace It fills and constructs the advantages that pollution-free.Using plastic material identical with drainpipe, identical base form can efficiently solve The interface connectivity problem of pipeline and well, avoids differential settlement, substantially increases the impermeability of pipeline and well, is conducive to drain The long-term safety of pipeline uses.
Embodiment two.
Please refer to Fig.1-2 and Fig. 7-10, floating-board type inspection shaft.
For the inspection shaft of rain sewage diversion, including:Well lid 1, pit shaft 2, water blocking cover board 8, column 12, connecting rod 11, kickboard 14, configuration block 13;Pit shaft side is equipped with water inlet 3, outlet of sewer 5, rainwater outlet 4;Rainwater outlet 4 is set on outlet of sewer 5 Side;Sliding slot 6 is equipped at 2 inner close fitting outlet of sewer of pit shaft and rainwater outlet;Water blocking cover board 8 is set in sliding slot 6;12 one end of column is solid Due to wellbore bottom, 11 middle part of connecting rod is riveted at the top of column, and 11 one end of connecting rod connects kickboard 13, and the other end passes through connection sheet 15 It is connected with water blocking cover board, connection sheet is fixed on water blocking cover board.
As preferred embodiments of the present invention, sliding slot both ends are equipped with limited block, to limit water blocking cover board in sliding slot In motion range.
As preferred embodiments of the present invention, kickboard is equipped with clump weight, so that kickboard preferably lifts.
As preferred embodiments of the present invention, water blocking cover board is equipped with water seepage hole, in the wellbore after water level decreasing, It is slowly drained to outlet of sewer by water seepage hole, so that kickboard preferably declines.
As preferred embodiments of the present invention, the water blocking cover board is tile.
Floating-board type inspection shaft operation principle is as follows.
When sunny or rainfall is compared with microweather, referring to FIG. 7, due in pit shaft water level it is low, the water surface is not enough to float floating Plate, kickboard is located at position of telling somebody what one's real intentions are, while being acted on by connecting rod, so that water blocking cover board is increased and is located at rainwater inlet, sanitary sewage is logical It crosses water inlet 3 to enter inside inspection shaft, then is emitted into after the processing ponds such as artificial swamp are disposed and is emitted by outlet of sewer 5 Neighbouring river.When the larger weather of rainfall, referring to FIG. 8, water gradually increases, the water surface gradually increases in inspection shaft, in kickboard 14 It is floating, drive water blocking cover board 8 to move down, water blocking cover board 8 shelters from outlet of sewer 5.The water surface continues to increase in inspection shaft, until being higher than rain 4 bottom of water out, water is directly by 4 row of rainwater outlet to neighbouring river in inspection shaft, and after rain stops, inspection shaft internal water accumulation passes through lid The small permeable hole in two, board bottom portion is slowly discharged into outlet of sewer 5, and into processing pond processing, during the water surface reduces, kickboard 14 declines, Water blocking cover board 8 is driven to move up, outlet of sewer 5 is gradually opened, and restores normal life sewage disposal state.
Embodiment three:For the inspection shaft of rain sewage diversion, including:Pit shaft, water blocking cover board, floating installation and train line; Pit shaft side is equipped with water inlet, outlet of sewer, rainwater outlet;Outlet of sewer is set to above rainwater outlet;Pit shaft inner close fitting sewage Outlet is equipped with limited block with sliding slot, sliding slot both ends are equipped at rainwater outlet;Water blocking cover board is set in sliding slot;Floating installation floats on In level in pit shaft;Train line one end is fixed on floating installation, and the other end is fixed on water blocking cover board.
Further include well lid as preferred embodiments of the present invention, well lid is connected to by connecting knob on pit shaft, The well lid is equipped with handle.
Use above specific case is illustrated the utility model, is merely used to help understand the utility model, and Not limiting the utility model.For those skilled in the art of the present invention, the think of according to the utility model Think, several simple deductions, deformation can also be made or replaces.

Claims (10)

1. a kind of inspection shaft for rain sewage diversion, it is characterised in that including:Pit shaft, water blocking cover board, crank hand, spool with And train line;
Pit shaft side is equipped with water inlet, water outlet;Water outlet includes outlet of sewer, rainwater outlet;Rainwater outlet goes out set on sewage Above mouthful or outlet of sewer is set to above rainwater outlet;Sliding slot, sliding slot are equipped at pit shaft inner close fitting outlet of sewer and rainwater outlet Both ends are equipped with limited block;Water blocking cover board is set in sliding slot;
Pit shaft upper end is equipped with crank hand and spool, and crank hand is sequentially connected with spool;Spiral is fixed in train line one end On axis, the other end is fixed on water blocking cover board.
2. being used for the inspection shaft of rain sewage diversion as described in claim 1, it is characterised in that:Further include well lid, well lid passes through company It connects knob to be connected on pit shaft, the well lid is equipped with handle.
3. being used for the inspection shaft of rain sewage diversion as described in claim 1, it is characterised in that:The water inlet is a diameter of 400mm, a diameter of 300mm of water outlet.
4. being used for the inspection shaft of rain sewage diversion as described in claim 1, it is characterised in that:The water inlet and a water outlet Apart from wellbore bottom 300mm, another water inlet bottom and water inlet distance from top 300mm, pit shaft height is 1500mm.
5. a kind of inspection shaft for rain sewage diversion, it is characterised in that including:Pit shaft, water blocking cover board, floating installation and linkage Line;
Pit shaft side is equipped with water inlet, outlet of sewer, rainwater outlet;Outlet of sewer is set to above rainwater outlet;Pit shaft inner close fitting Outlet of sewer is equipped with limited block with sliding slot, sliding slot both ends are equipped at rainwater outlet;Water blocking cover board is set in sliding slot;
Floating installation floats in the level in pit shaft;Train line one end is fixed on floating installation, and the other end is fixed on water blocking On cover board.
6. being used for the inspection shaft of rain sewage diversion as claimed in claim 5, it is characterised in that:Further include well lid, well lid passes through company It connects knob to be connected on pit shaft, the well lid is equipped with handle.
7. a kind of inspection shaft for rain sewage diversion, it is characterised in that including:Pit shaft, water blocking cover board, column, connecting rod, kickboard;
Pit shaft side is equipped with water inlet, outlet of sewer, rainwater outlet;Rainwater outlet is set to above outlet of sewer;Pit shaft inner close fitting Sliding slot is equipped at outlet of sewer and rainwater outlet;Water blocking cover board is set in sliding slot;
Column one end is fixed on pit shaft, is riveted on the column other end in the middle part of connecting rod, connecting rod two end is separately connected kickboard and water blocking Cover board.
8. being used for the inspection shaft of rain sewage diversion as claimed in claim 7, it is characterised in that:Sliding slot both ends are equipped with limited block, float Plate is equipped with clump weight.
9. being used for the inspection shaft of rain sewage diversion as claimed in claim 7, it is characterised in that:The water blocking cover board, which is equipped with, to be oozed Water hole.
10. the inspection shaft for rain sewage diversion as described in claim 1,5,7 is any, it is characterised in that:The water blocking cover board For tile.
CN201820106109.7U 2018-01-23 2018-01-23 A kind of inspection shaft for rain sewage diversion Expired - Fee Related CN208009601U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820106109.7U CN208009601U (en) 2018-01-23 2018-01-23 A kind of inspection shaft for rain sewage diversion

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820106109.7U CN208009601U (en) 2018-01-23 2018-01-23 A kind of inspection shaft for rain sewage diversion

Publications (1)

Publication Number Publication Date
CN208009601U true CN208009601U (en) 2018-10-26

Family

ID=63883324

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820106109.7U Expired - Fee Related CN208009601U (en) 2018-01-23 2018-01-23 A kind of inspection shaft for rain sewage diversion

Country Status (1)

Country Link
CN (1) CN208009601U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108560683A (en) * 2018-01-23 2018-09-21 南昌大学 A kind of inspection shaft for rain sewage diversion

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108560683A (en) * 2018-01-23 2018-09-21 南昌大学 A kind of inspection shaft for rain sewage diversion

Similar Documents

Publication Publication Date Title
CN206360068U (en) Pond is collected by filtration in a kind of rain water drainage
CN207812864U (en) A kind of rainwater recovery device
CN206157855U (en) Automatic initial rainwater discarding device of control
CN205421504U (en) Abandon STREAMING inlet for stom water
CN203834623U (en) Single building balcony sewage and rainwater shunting device
CN207392409U (en) A kind of Mobyneb Vatch basin system
CN105625555B (en) A kind of rainwater shunting of combined system, regulate and store and processing system
CN112012306A (en) Sewage intercepting well of residential area and using method thereof
CN211395907U (en) Road type integrated intelligent sewage intercepting well
CN106836440A (en) A kind of dirty shunting self-con-tained unit of rain
CN208009601U (en) A kind of inspection shaft for rain sewage diversion
CN105672444B (en) Rainwater division processing system based on combined system pipe network
CN212336238U (en) Sewage intercepting well of residential area
CN203256886U (en) Inspection well for preventing sundries from overflowing
CN108560683A (en) A kind of inspection shaft for rain sewage diversion
CN104975649A (en) Separate system type initial rainwater regulation and storage pool
CN205636892U (en) Reposition of redundant personnel of regional burst rainwater, regulation and processing system based on mixed flow tubulation net
CN103967107B (en) Be suitable for the preliminary-stage rainwater flow-discarding well building rainwater utilization
CN206655297U (en) A kind of dirty shunting self-con-tained unit of rain
CN210797260U (en) Bridge drainage structures
CN206233346U (en) A kind of road surface drainage structure
CN104929232A (en) Flood storage pond
CN107675790A (en) One kind cuts dirty antiflood valve
CN209162980U (en) Rainwater sewage flow distributing device
CN208201937U (en) A kind of anti-clogging well lid

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20181026

Termination date: 20200123

CF01 Termination of patent right due to non-payment of annual fee