CN208009601U - A kind of inspection shaft for rain sewage diversion - Google Patents

A kind of inspection shaft for rain sewage diversion Download PDF

Info

Publication number
CN208009601U
CN208009601U CN201820106109.7U CN201820106109U CN208009601U CN 208009601 U CN208009601 U CN 208009601U CN 201820106109 U CN201820106109 U CN 201820106109U CN 208009601 U CN208009601 U CN 208009601U
Authority
CN
China
Prior art keywords
sewage
outlet
shaft
water
rainwater
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820106109.7U
Other languages
Chinese (zh)
Inventor
雷斌
严超君
谭宇星
王纪婷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanchang University
Original Assignee
Nanchang University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanchang University filed Critical Nanchang University
Priority to CN201820106109.7U priority Critical patent/CN208009601U/en
Application granted granted Critical
Publication of CN208009601U publication Critical patent/CN208009601U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Sewage (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

一种用于雨污分流的检查井,包括井筒、挡水盖板、摇把手、卷线轴以及联动线;井筒侧面设有进水口、出水口;出水口包括污水出口、雨水出口;雨水出口设于污水出口上方或污水出口设于雨水出口上方;井筒内紧贴污水出口与雨水出口处设有滑槽,滑槽两端设有限位块;挡水盖板设于滑槽内;井筒上端设有摇把手以及卷线轴,摇把手与卷线轴传动连接;联动线一端固定于卷线轴上,另一端固定于挡水盖板上。由于通过控制挡水盖板在滑槽中上下移动,使得挡水盖板对污水出口或雨水出口进行遮挡,实现雨水和污水分流。

An inspection well for rain and sewage diversion, comprising a well shaft, a water retaining cover plate, a crank handle, a winding shaft and a linkage line; the side of the well shaft is provided with a water inlet and a water outlet; the water outlet includes a sewage outlet and a rainwater outlet; Set above the sewage outlet or the sewage outlet above the rainwater outlet; there is a chute in the wellbore close to the sewage outlet and the rainwater outlet, and limit blocks are set at both ends of the chute; the water retaining cover is set in the chute; There is a crank handle and a bobbin, and the crank handle is connected to the bobbin through transmission; one end of the linkage line is fixed on the bobbin, and the other end is fixed on the water retaining cover. By controlling the water-retaining cover to move up and down in the chute, the water-retaining cover blocks the sewage outlet or the rainwater outlet, thereby realizing the diversion of rainwater and sewage.

Description

一种用于雨污分流的检查井An inspection well for diversion of rain and sewage

技术领域technical field

本申请涉及一种用于雨污分流的检查井,属于市政工程、农村水利领域。The application relates to an inspection well for diverting rainwater and sewage, which belongs to the fields of municipal engineering and rural water conservancy.

背景技术Background technique

当前国家大力倡导雨污分流处理,城市市政通常使用新建雨水渠和污水渠两种渠道进行雨污分流,具有成本高、工程量大的特征。在农村以及一些偏僻贫穷地区新建成本相对低的人工组合湿地处理生活污水,但由于未进行雨污分流,在雨量大的天气时,人工湿地会被雨水冲毁损坏,同时也会造成一定的污染,急需一种雨污分流的装置来进行雨污分流,使污水通过污水管道流入污水处理池处理后再排放,而雨水通过雨水管道直接排放到自然环境中。At present, the country is vigorously advocating rainwater and sewage diversion treatment. Urban municipalities usually use two new channels for rainwater and sewage diversion, which are characterized by high cost and large engineering volume. In rural areas and some remote and poor areas, artificial combined wetlands with relatively low cost are built to treat domestic sewage. However, due to the lack of rain and sewage diversion, in heavy rainfall weather, artificial wetlands will be destroyed by rainwater and cause certain pollution. , there is an urgent need for a rain and sewage diversion device to carry out rain and sewage diversion, so that the sewage flows into the sewage treatment tank through the sewage pipeline for treatment and then discharged, and the rainwater is directly discharged into the natural environment through the rainwater pipeline.

实用新型内容Utility model content

本申请提供一种用于雨污分流的检查井,以对雨污进行分流。The application provides an inspection well for diverting rain and sewage, so as to divert rain and sewage.

根据第一方面,一种实施例中提供一种用于雨污分流的检查井, 包括井筒、挡水盖板、摇把手、卷线轴以及联动线;井筒侧面设有进水口、出水口;出水口包括污水出口、雨水出口;雨水出口设于污水出口上方或污水出口设于雨水出口上方;井筒内紧贴污水出口与雨水出口处设有滑槽,滑槽两端设有限位块;挡水盖板设于滑槽内;井筒上端设有摇把手以及卷线轴,摇把手与卷线轴传动连接;联动线一端固定于卷线轴上,另一端固定于挡水盖板上。According to the first aspect, an embodiment provides an inspection well for rain and sewage diversion, including a well shaft, a water retaining cover, a crank handle, a reel, and a linkage line; the side of the well shaft is provided with a water inlet and a water outlet; The water outlet includes the sewage outlet and the rainwater outlet; the rainwater outlet is set above the sewage outlet or the sewage outlet is set above the rainwater outlet; there is a chute in the shaft close to the sewage outlet and the rainwater outlet, and limit blocks are set at both ends of the chute; The cover plate is set in the chute; the upper end of the shaft is provided with a crank handle and a winding shaft, and the crank handle is connected to the winding shaft through transmission; one end of the linkage line is fixed on the winding shaft, and the other end is fixed on the water retaining cover.

优选地,还包括井盖,井盖通过连接旋钮连接于井筒上,所述井盖上设有把手。Preferably, a well cover is also included, the well cover is connected to the well shaft through a connection knob, and a handle is provided on the well cover.

优选地,所述进水口直径为400mm,出水口直径为300mm。Preferably, the diameter of the water inlet is 400mm, and the diameter of the water outlet is 300mm.

优选地,所述进水口与一出水口均距离井筒底部300mm,另一进水口底部与进水口顶部距离300mm,井筒高度为1500mm。Preferably, the distance between the water inlet and one water outlet is 300mm from the bottom of the wellbore, the distance between the bottom of the other water inlet and the top of the water inlet is 300mm, and the height of the wellbore is 1500mm.

根据第二方面,一种实施例中提供一种用于雨污分流的检查井, 包括:井筒、挡水盖板、浮动装置以及联动线;井筒侧面设有进水口、污水出口、雨水出口;污水出口设于雨水出口上方;井筒内紧贴污水出口与雨水出口处设有滑槽,滑槽两端设有限位块;挡水盖板设于滑槽内;浮动装置漂浮于井筒内的水平上;联动线一端固定在浮动装置上,另一端固定于挡水盖板上。According to the second aspect, an embodiment provides an inspection well for rain and sewage diversion, including: a well shaft, a water retaining cover plate, a floating device, and a linkage line; the side of the well shaft is provided with a water inlet, a sewage outlet, and a rainwater outlet; The sewage outlet is set above the rainwater outlet; there is a chute close to the sewage outlet and the rainwater outlet in the wellbore, and limit blocks are set at both ends of the chute; the water retaining cover is set in the chute; the floating device floats at the level of the wellbore One end of the linkage line is fixed on the floating device, and the other end is fixed on the water retaining cover.

优选地,还包括井盖,井盖通过连接旋钮连接于井筒上,所述井盖上设有把手。Preferably, a well cover is also included, the well cover is connected to the well shaft through a connection knob, and a handle is provided on the well cover.

根据第三方面,一种实施例中提供一种用于雨污分流的检查井, 包括:井筒、挡水盖板、立柱、连杆、浮板;井筒侧面设有进水口、污水出口、雨水出口;雨水出口设于污水出口上方;井筒内紧贴污水出口与雨水出口处设有滑槽;挡水盖板设于滑槽内;立柱一端固定于井筒上,连杆中部铆接于立柱另一端,连杆两端分别连接浮板和挡水盖板。According to the third aspect, an embodiment provides an inspection well for rain and sewage diversion, including: a well shaft, a water retaining cover plate, a column, a connecting rod, and a floating plate; Outlet; the rainwater outlet is set above the sewage outlet; there is a chute in the shaft close to the sewage outlet and the rainwater outlet; the water retaining cover is set in the chute; one end of the column is fixed on the shaft, and the middle part of the connecting rod is riveted to the other end of the column , the two ends of the connecting rod are respectively connected to the floating plate and the water retaining cover plate.

优选地,滑槽两端设有限位块,浮板上设有配重块。Preferably, limit blocks are provided at both ends of the chute, and counterweights are provided on the floating plate.

优选地,所述挡水盖板上设有渗水孔。Preferably, water seepage holes are provided on the water retaining cover plate.

优选地,所述挡水盖板为瓦片。Preferably, the water retaining cover is a tile.

依据上述实施例的用于雨污分流的检查井,由于通过摇把手带动卷线轴旋转,从而实现联动线的收放,联动线再带动挡水盖板在滑槽中上下移动,使得挡水盖板对污水出口或雨水出口进行遮挡,实现雨水和污水分流的目的。进一步,设置井盖并在井盖上设把手,增强安全性能以及便利性。而且从上述结构可以看出,本申请具有结构简单、成本低、操作便利的优势,可适用于广大农村地区。According to the inspection well for rain and sewage diversion in the above-mentioned embodiment, since the winding shaft is driven to rotate by the crank handle, the retraction of the linkage line is realized, and the linkage line drives the water retaining cover to move up and down in the chute, so that the water retaining cover The board shields the sewage outlet or the rainwater outlet to achieve the purpose of diverting rainwater and sewage. Further, the manhole cover is provided and a handle is provided on the manhole cover to enhance safety performance and convenience. Moreover, it can be seen from the above structure that the present application has the advantages of simple structure, low cost and convenient operation, and is applicable to vast rural areas.

附图说明Description of drawings

图1与图2为本申请检查井一实施例立体图。Figure 1 and Figure 2 are perspective views of an embodiment of the inspection well of the present application.

图3为少雨天气手摇式检查井污水流向示意图。Figure 3 is a schematic diagram of the sewage flow of the hand-operated inspection well in drier weather.

图4为多雨天气手摇式检查井雨水和污水流向示意图。Figure 4 is a schematic diagram of the flow of rainwater and sewage in the hand-operated inspection well in rainy weather.

图5与图6为手摇式检查井传动装置示意图。Figure 5 and Figure 6 are schematic diagrams of the transmission device for the manual inspection well.

图7为少雨天气浮板式检查井污水流向示意图。Figure 7 is a schematic diagram of the sewage flow in the floating plate type inspection well in drier weather.

图8为多雨天气浮板式检查井雨水和污水流向示意图。Figure 8 is a schematic diagram of the flow of rainwater and sewage in the floating plate inspection well in rainy weather.

图9和图10为浮板式检查井传动装置示意图。Figure 9 and Figure 10 are schematic diagrams of the driving device for the floating plate inspection well.

具体实施方式Detailed ways

下面通过具体实施方式结合附图对本实用新型作进一步详细说明。其中不同实施方式中类似元件采用了相关联的类似的元件标号。在以下的实施方式中,很多细节描述是为了使得本申请能被更好的理解。然而,本领域技术人员可以毫不费力的认识到,其中部分特征在不同情况下是可以省略的,或者可以由其他元件、材料、方法所替代。在某些情况下,本申请相关的一些操作并没有在说明书中显示或者描述,这是为了避免本申请的核心部分被过多的描述所淹没,而对于本领域技术人员而言,详细描述这些相关操作并不是必要的,他们根据说明书中的描述以及本领域的一般技术知识即可完整了解相关操作。The utility model will be described in further detail below through specific embodiments in conjunction with the accompanying drawings. Wherein, similar elements in different implementations adopt associated similar element numbers. In the following implementation manners, many details are described for better understanding of the present application. However, those skilled in the art can readily recognize that some of the features can be omitted in different situations, or can be replaced by other elements, materials, and methods. In some cases, some operations related to the application are not shown or described in the description, this is to avoid the core part of the application being overwhelmed by too many descriptions, and for those skilled in the art, it is necessary to describe these operations in detail Relevant operations are not necessary, and they can fully understand the relevant operations according to the description in the specification and general technical knowledge in the field.

本文中为部件所编序号本身,例如“第一”、“第二”等,仅用于区分所描述的对象,不具有任何顺序或技术含义。而本申请所说“连接”、“联接”,如无特别说明,均包括直接和间接连接(联接)。The serial numbers assigned to components in this document, such as "first", "second", etc., are only used to distinguish the described objects, and do not have any sequence or technical meaning. The "connection" and "connection" mentioned in this application include direct and indirect connection (connection) unless otherwise specified.

实施例一。Embodiment one.

请参考图1-6,手摇式检查井。Please refer to Figure 1-6, manual inspection well.

用于雨污分流的检查井, 包括井盖1、井筒2、挡水盖板8、摇把手10、卷线盒9以及联动线7;井盖通过连接旋钮连接于井筒上,所述井盖上设有把手。The inspection well for rain and sewage diversion includes well cover 1, well shaft 2, water retaining cover plate 8, crank handle 10, winding box 9 and linkage line 7; the well cover is connected to the well shaft through the connection knob, and the well cover is provided with handle.

卷线轴设于卷线盒9内;井筒2侧面设有进水口3、出水口;出水口包括污水出口5、雨水出口4;雨水出口4设于污水出口5上方。井筒内紧贴污水出口与雨水出口处设有滑槽6,滑槽两端设有限位块;挡水盖板8设于滑槽6内;井筒上端设有摇把手10以及卷线轴,摇把手10与卷线轴传动连接;联动线7一端固定于卷线轴上,另一端固定于挡水盖板8上。挡水盖板宽度略大于污水出口和雨水出口的宽度,挡水盖板高度也略大于污水出口和雨水出口的高度,使挡水盖板能够完全遮挡住污水出口或雨水出口。挡水盖板在联动线的作用下,可在滑槽中上下移动,分别轮换对污水出口和雨水出口进行遮挡,实现污水和雨水的分流。滑槽两端设有限位块,以限制挡水盖板在滑槽中的运动范围。The bobbin is located in the winding box 9; the side of the shaft 2 is provided with a water inlet 3 and a water outlet; the water outlet includes a sewage outlet 5 and a rainwater outlet 4; the rainwater outlet 4 is located above the sewage outlet 5. There is a chute 6 close to the sewage outlet and the rainwater outlet in the shaft, and limit blocks are arranged at both ends of the chute; the water retaining cover 8 is arranged in the chute 6; the upper end of the shaft is provided with a crank handle 10 and a reel, 10 is connected with the bobbin transmission; one end of the linkage line 7 is fixed on the bobbin, and the other end is fixed on the water retaining cover plate 8. The width of the water retaining cover is slightly greater than the width of the sewage outlet and the rainwater outlet, and the height of the water retaining cover is also slightly greater than the height of the sewage outlet and the rainwater outlet, so that the water retaining cover can completely block the sewage outlet or the rainwater outlet. Under the action of the linkage line, the water-retaining cover can move up and down in the chute to block the sewage outlet and the rainwater outlet in rotation respectively, so as to realize the diversion of sewage and rainwater. Limiting blocks are provided at both ends of the chute to limit the movement range of the water retaining cover in the chute.

其中,进水口直径为400mm,出水口直径为300mm。进水口与一出水口均距离井筒底部300mm,另一进水口底部与进水口顶部距离300mm,井筒高度为1500mm。Among them, the diameter of the water inlet is 400mm, and the diameter of the water outlet is 300mm. The distance between the water inlet and one water outlet is 300mm from the bottom of the wellbore, the distance between the bottom of the other water inlet and the top of the water inlet is 300mm, and the height of the wellbore is 1500mm.

在上述实施例的基础上,由于是通过人工控制挡水盖板的位置,污水出口也可改设于雨水出口上方,不影响本实用新型的实现。On the basis of the above embodiment, because the position of the water retaining cover is manually controlled, the sewage outlet can also be relocated above the rainwater outlet, which does not affect the realization of the utility model.

其中,井筒可由工厂预制,采用塑料一体成型,保证了井与进水口、出水口连接处无渗漏可能性。滑槽采用不锈钢材料,挡水盖板采用瓦片。上述结构不仅成本低,不生锈,质量有保障,而且省去了在施工现场繁琐的支模,养护,拆卸的工序,减少了施工污染,达到优质、省时、高效、轻便、环保等优点。Among them, the well shaft can be prefabricated by the factory, and it is integrally formed with plastic to ensure that there is no possibility of leakage at the connection between the well, the water inlet and the water outlet. The chute is made of stainless steel, and the water retaining cover is made of tiles. The above-mentioned structure not only has low cost, no rust, and guaranteed quality, but also saves the cumbersome procedures of formwork support, maintenance, and disassembly at the construction site, reduces construction pollution, and achieves the advantages of high quality, time saving, high efficiency, portability, and environmental protection. .

手摇式检查井工作原理如下:The working principle of the manual inspection well is as follows:

当晴朗或者雨量较小天气,参考图3,通过摇把手10将挡水盖板8提起,控制其遮挡住雨水出口4,生活污水通过进水口3进入检查井内部,再通过污水出口5排放至人工湿地等处理池处理完毕后排放至附近河流。当雨量较大天气,参考图4,通过摇把手10将挡水盖板8下放,使挡水盖板8盖住污水出口5,检查井内水面逐渐升高,直到高于雨水出口4底部,检查井内水直接通过雨水出口4排向附近河流,雨停后,摇动摇把手10带动挡水盖板8上移,重新将挡水盖板8置于雨水出口4处,使生活污水从污水出口5排出。When the weather is sunny or the rainfall is small, refer to Figure 3, lift the water retaining cover 8 through the crank handle 10, and control it to cover the rainwater outlet 4, domestic sewage enters the inspection well through the water inlet 3, and then discharges through the sewage outlet 5 to Constructed wetlands and other treatment pools are discharged to nearby rivers after treatment. When the rainfall is heavy, refer to Figure 4, lower the water retaining cover 8 by shaking the handle 10, so that the water retaining cover 8 covers the sewage outlet 5, and the water level in the inspection well rises gradually until it is higher than the bottom of the rainwater outlet 4. The water in the well is directly discharged to the nearby river through the rainwater outlet 4. After the rain stops, shake the crank handle 10 to drive the water retaining cover 8 to move upward, and place the water retaining cover 8 at the rainwater outlet 4 again, so that domestic sewage can flow from the sewage outlet 5 discharge.

进水口、出水口与外部输水管之间的连接采用镶嵌方式,在塑料管中用一个与塑料管直径相当的PVC硬管连接,将塑料管剪开后穿在硬管上用铁丝拧紧即可,保证连接处严密可靠不会渗水。The connection between the water inlet, the water outlet and the external water pipe is inlaid. A PVC hard pipe with the same diameter as the plastic pipe is used to connect the plastic pipe. After cutting the plastic pipe, put it on the hard pipe and tighten it with iron wire. , to ensure that the connection is tight and reliable without water seepage.

用于雨污分流的井筒按照总设计图纸在工厂内规模生产,不仅可以保证构件质量,提高构件精度,而且在施工现场可以直接进行安装,达到省工、高效、轻便、便于运输安装且施工无污染等优点。采用与排水管相同的塑料材质,相同的基础形式,可以有效地解决管道与井的接口连接问题,避免了不均匀沉降,大大提高了管道和井的抗渗性,有利于排水管道的长期安全使用。The well shafts used for rain and sewage diversion are produced on a large scale in the factory according to the general design drawings, which can not only ensure the quality of the components and improve the accuracy of the components, but also can be directly installed on the construction site, achieving labor saving, high efficiency, lightness, convenient transportation and installation, and construction. Pollution etc. Using the same plastic material and the same basic form as the drainage pipe can effectively solve the problem of the interface connection between the pipe and the well, avoid uneven settlement, greatly improve the impermeability of the pipe and the well, and benefit the long-term safety of the drainage pipe use.

实施例二。Embodiment two.

请参考图1-2以及图7-10,浮板式检查井。Please refer to Figure 1-2 and Figure 7-10, floating plate inspection well.

用于雨污分流的检查井, 包括:井盖1、井筒2、挡水盖板8、立柱12、连杆11、浮板14、配置块13;井筒侧面设有进水口3、污水出口5、雨水出口4;雨水出口4设于污水出口5上方;井筒2内紧贴污水出口与雨水出口处设有滑槽6;挡水盖板8设于滑槽6内;立柱12一端固定于井筒底部,连杆11中部铆接于立柱顶部,连杆11一端连接浮板13,另一端通过连接片15和挡水盖板连接,连接片固定于挡水盖板上。The inspection well for rain and sewage diversion includes: well cover 1, well shaft 2, water retaining cover plate 8, column 12, connecting rod 11, floating plate 14, configuration block 13; the side of the well shaft is provided with water inlet 3, sewage outlet 5, The rainwater outlet 4; the rainwater outlet 4 is set above the sewage outlet 5; the shaft 2 is provided with a chute 6 close to the sewage outlet and the rainwater outlet; the water retaining cover 8 is set in the chute 6; one end of the column 12 is fixed at the bottom of the shaft , the middle part of the connecting rod 11 is riveted on the top of the column, one end of the connecting rod 11 is connected to the floating plate 13, and the other end is connected to the water retaining cover plate through the connecting piece 15, and the connecting piece is fixed on the water retaining cover plate.

作为本实用新型的优选实施方式,滑槽两端设有限位块,以限制挡水盖板在滑槽中的运动范围。As a preferred embodiment of the present invention, limit blocks are provided at both ends of the chute to limit the movement range of the water retaining cover in the chute.

作为本实用新型的优选实施方式,浮板上设有配重块,以使浮板更好地升降。As a preferred embodiment of the present invention, a counterweight is provided on the floating plate to make the floating plate lift better.

作为本实用新型的优选实施方式,挡水盖板上设有渗水孔,在井筒中水位下降后,通过渗水孔慢慢向污水出口排水,以使浮板更好地下降。As a preferred embodiment of the present utility model, a seepage hole is provided on the water retaining cover plate, and after the water level in the wellbore drops, water is slowly discharged to the sewage outlet through the seepage hole, so that the floating plate can be lowered better.

作为本实用新型的优选实施方式,所述挡水盖板为瓦片。As a preferred embodiment of the present utility model, the water retaining cover plate is a tile.

浮板式检查井工作原理如下。The working principle of the floating plate inspection well is as follows.

当晴朗或者雨量较小天气时,请参考图7,由于井筒内水位低,水面不足以浮起浮板,浮板位于交底位置,同时通过连杆作用,使挡水盖板升高位于雨水入口处,生活污水通过进水口3进入检查井内部,再通过污水出口5排放至人工湿地等处理池处理完毕后排放至附近河流。当雨量较大天气,请参考图8,水量逐渐增大,检查井内水面逐渐增高,浮板14上浮,带动挡水盖板8下移,挡水盖板8遮挡住污水出口5。检查井内水面继续升高,直到高于雨水出口4底部,检查井内水直接通过雨水出口4排向附近河流,雨停后,检查井内积水通过盖板底部两个小透水孔缓慢排入污水出口5,进入处理池处理,水面降低过程中,浮板14下降,带动挡水盖板8上移,污水出口5逐渐被打开,恢复正常生活污水处理状态。When the weather is sunny or the rainfall is small, please refer to Figure 7. Due to the low water level in the shaft, the water surface is not enough to float the floating plate. The domestic sewage enters the inspection well through the water inlet 3, and then is discharged to the artificial wetland and other treatment pools through the sewage outlet 5, and then discharged to the nearby river after treatment. When the rainfall is heavy, please refer to Fig. 8, the water volume increases gradually, the water surface in the inspection well increases gradually, the floating plate 14 floats up, drives the water retaining cover 8 to move down, and the water retaining cover 8 blocks the sewage outlet 5. The water level in the inspection well continues to rise until it is higher than the bottom of the rainwater outlet 4, and the water in the inspection well is directly discharged to the nearby river through the rainwater outlet 4. After the rain stops, the accumulated water in the inspection well is slowly discharged into the sewage outlet through the two small permeable holes at the bottom of the cover plate 5. Enter the treatment tank for treatment. During the process of lowering the water level, the floating plate 14 descends, driving the water retaining cover 8 to move upward, and the sewage outlet 5 is gradually opened to restore the normal domestic sewage treatment state.

实施例三:用于雨污分流的检查井, 包括:井筒、挡水盖板、浮动装置以及联动线;井筒侧面设有进水口、污水出口、雨水出口;污水出口设于雨水出口上方;井筒内紧贴污水出口与雨水出口处设有滑槽,滑槽两端设有限位块;挡水盖板设于滑槽内;浮动装置漂浮于井筒内的水平上;联动线一端固定在浮动装置上,另一端固定于挡水盖板上。Embodiment 3: An inspection well for rain and sewage diversion, including: a shaft, a water retaining cover, a floating device, and a linkage line; the side of the shaft is provided with a water inlet, a sewage outlet, and a rainwater outlet; the sewage outlet is located above the rainwater outlet; the shaft There is a chute close to the sewage outlet and rainwater outlet, and limit blocks are set at both ends of the chute; the water retaining cover is set in the chute; the floating device floats on the level of the shaft; one end of the linkage line is fixed on the floating device The other end is fixed on the water retaining cover.

作为本实用新型的优选实施方式,还包括井盖,井盖通过连接旋钮连接于井筒上,所述井盖上设有把手。As a preferred embodiment of the present utility model, it also includes a well cover, the well cover is connected to the well shaft through a connection knob, and the well cover is provided with a handle.

以上应用了具体个例对本实用新型进行阐述,只是用于帮助理解本实用新型,并不用以限制本实用新型。对于本实用新型所属技术领域的技术人员,依据本实用新型的思想,还可以做出若干简单推演、变形或替换。The above uses specific examples to illustrate the utility model, which is only used to help understand the utility model, and is not intended to limit the utility model. For those skilled in the technical field to which the utility model belongs, some simple deduction, deformation or replacement can also be made according to the idea of the utility model.

Claims (10)

1.一种用于雨污分流的检查井, 其特征在于包括:井筒、挡水盖板、摇把手、卷线轴以及联动线;1. An inspection well for rain and sewage diversion, characterized in that it includes: a shaft, a water retaining cover, a crank handle, a winding shaft and a linkage line; 井筒侧面设有进水口、出水口;出水口包括污水出口、雨水出口;雨水出口设于污水出口上方或污水出口设于雨水出口上方;井筒内紧贴污水出口与雨水出口处设有滑槽,滑槽两端设有限位块;挡水盖板设于滑槽内;There are water inlets and outlets on the side of the well shaft; the water outlets include sewage outlets and rainwater outlets; the rainwater outlets are set above the sewage outlets or the sewage outlets are set above the rainwater outlets; there are chutes in the shaft close to the sewage outlets and rainwater outlets. There are limit blocks at both ends of the chute; the water retaining cover is set in the chute; 井筒上端设有摇把手以及卷线轴,摇把手与卷线轴传动连接;联动线一端固定于卷线轴上,另一端固定于挡水盖板上。The upper end of the shaft is provided with a crank handle and a winding shaft, and the crank handle is connected to the winding shaft through transmission; one end of the linkage line is fixed on the winding shaft, and the other end is fixed on the water retaining cover. 2.如权利要求1所述的用于雨污分流的检查井, 其特征在于:还包括井盖,井盖通过连接旋钮连接于井筒上,所述井盖上设有把手。2. The inspection well for rain and sewage diversion according to claim 1, characterized in that it further comprises a well cover, the well cover is connected to the shaft through a connection knob, and a handle is provided on the well cover. 3.如权利要求1所述的用于雨污分流的检查井, 其特征在于:所述进水口直径为400mm,出水口直径为300mm。3. The inspection well for diverting rain and sewage according to claim 1, characterized in that: the diameter of the water inlet is 400 mm, and the diameter of the water outlet is 300 mm. 4.如权利要求1所述的用于雨污分流的检查井, 其特征在于:所述进水口与一出水口均距离井筒底部300mm,另一进水口底部与进水口顶部距离300mm,井筒高度为1500mm。4. The inspection well for diversion of rain and sewage according to claim 1, characterized in that: the distance between the water inlet and the first water outlet is 300mm from the bottom of the shaft, and the distance between the bottom of the other water inlet and the top of the water inlet is 300mm, and the height of the shaft is It is 1500mm. 5.一种用于雨污分流的检查井, 其特征在于包括:井筒、挡水盖板、浮动装置以及联动线;5. An inspection well for rain and sewage diversion, characterized by comprising: a shaft, a water retaining cover, a floating device and a linkage line; 井筒侧面设有进水口、污水出口、雨水出口;污水出口设于雨水出口上方;井筒内紧贴污水出口与雨水出口处设有滑槽,滑槽两端设有限位块;挡水盖板设于滑槽内;There are water inlet, sewage outlet and rainwater outlet on the side of the shaft; the sewage outlet is set above the rainwater outlet; a chute is provided in the shaft close to the sewage outlet and rainwater outlet, and limit blocks are provided at both ends of the chute; the water retaining cover is set in the chute; 浮动装置漂浮于井筒内的水平上;联动线一端固定在浮动装置上,另一端固定于挡水盖板上。The floating device floats on the level in the shaft; one end of the linkage line is fixed on the floating device, and the other end is fixed on the water retaining cover. 6.如权利要求5所述的用于雨污分流的检查井, 其特征在于:还包括井盖,井盖通过连接旋钮连接于井筒上,所述井盖上设有把手。6. The inspection well for diverting rain and sewage according to claim 5, characterized in that it further comprises a well cover, the well cover is connected to the shaft through a connection knob, and a handle is provided on the well cover. 7.一种用于雨污分流的检查井, 其特征在于包括:井筒、挡水盖板、立柱、连杆、浮板;7. An inspection well for diversion of rain and sewage, characterized in that it includes: a shaft, a water retaining cover, a column, a connecting rod, and a floating plate; 井筒侧面设有进水口、污水出口、雨水出口;雨水出口设于污水出口上方;井筒内紧贴污水出口与雨水出口处设有滑槽;挡水盖板设于滑槽内;There are water inlet, sewage outlet and rainwater outlet on the side of the shaft; the rainwater outlet is set above the sewage outlet; a chute is installed in the shaft close to the sewage outlet and rainwater outlet; the water retaining cover is installed in the chute; 立柱一端固定于井筒上,连杆中部铆接于立柱另一端,连杆两端分别连接浮板和挡水盖板。One end of the column is fixed on the shaft, the middle part of the connecting rod is riveted to the other end of the column, and the two ends of the connecting rod are respectively connected to the floating plate and the water retaining cover. 8.如权利要求7所述的用于雨污分流的检查井, 其特征在于:滑槽两端设有限位块,浮板上设有配重块。8. The inspection well for diverting rain and sewage according to claim 7, characterized in that: limit blocks are provided at both ends of the chute, and counterweights are provided on the floating plate. 9.如权利要求7所述的用于雨污分流的检查井, 其特征在于:所述挡水盖板上设有渗水孔。9. The inspection well for rain and sewage diversion according to claim 7, characterized in that: the water retaining cover plate is provided with seepage holes. 10.如权利要求1、5、7任一所述的用于雨污分流的检查井, 其特征在于:所述挡水盖板为瓦片。10. The inspection well for diverting rain and sewage according to any one of claims 1, 5, and 7, characterized in that: the water retaining cover plate is a tile.
CN201820106109.7U 2018-01-23 2018-01-23 A kind of inspection shaft for rain sewage diversion Expired - Fee Related CN208009601U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820106109.7U CN208009601U (en) 2018-01-23 2018-01-23 A kind of inspection shaft for rain sewage diversion

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820106109.7U CN208009601U (en) 2018-01-23 2018-01-23 A kind of inspection shaft for rain sewage diversion

Publications (1)

Publication Number Publication Date
CN208009601U true CN208009601U (en) 2018-10-26

Family

ID=63883324

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820106109.7U Expired - Fee Related CN208009601U (en) 2018-01-23 2018-01-23 A kind of inspection shaft for rain sewage diversion

Country Status (1)

Country Link
CN (1) CN208009601U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108560683A (en) * 2018-01-23 2018-09-21 南昌大学 A kind of inspection shaft for rain sewage diversion

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108560683A (en) * 2018-01-23 2018-09-21 南昌大学 A kind of inspection shaft for rain sewage diversion

Similar Documents

Publication Publication Date Title
CN108412026B (en) Hydraulic automatic control intercepting sewer
CN104532947B (en) Underground open storage tank
CN201835375U (en) Gutter inlet with non-point source pollution controlling function
CN205421504U (en) Abandon STREAMING inlet for stom water
CN111472429A (en) A rainy day overflow pollution control system for urban combined pipe network
CN209353440U (en) Road rainwater storage and drainage system for sponge city
CN220058038U (en) Building foundation pit ponding cleaning device
CN208009601U (en) A kind of inspection shaft for rain sewage diversion
CN108560683A (en) A kind of inspection shaft for rain sewage diversion
CN110397142A (en) A system and method for flushing and diverting municipal sewage pipes
CN110180255A (en) A kind of wastewater recycling system
CN201581485U (en) Box type sewage lifting equipment
CN210857472U (en) Bury formula dispersion regulation storage battery system
CN203821566U (en) Electric separate system pipe network shutoff well
CN112081227A (en) Construction rainfall drainage structures
CN211772533U (en) Town road drainage structures
CN107119781A (en) A kind of automatic sewage collection system of urban flood control and drainage and method
CN111255042A (en) Ecological tree pool with floater for automatically controlling initial rainwater drainage and working method
CN214993966U (en) A drainage and diversion device for high water permeability in a water-rich environment
CN206591600U (en) A kind of drainage tank
CN212641711U (en) Prevent flowing backward rainwater box culvert and cut dirty pump station
CN204401774U (en) Underground open type storage pond
CN211228839U (en) Inclined integrated pump station with cleaning device
CN209162980U (en) Rainwater sewage flow distributing device
CN211499096U (en) Ecological water bank with river-following pollution self-control function

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20181026

Termination date: 20200123