CN207988364U - A kind of waste material utilizes framework of steel reinforcement shaper - Google Patents

A kind of waste material utilizes framework of steel reinforcement shaper Download PDF

Info

Publication number
CN207988364U
CN207988364U CN201820011699.5U CN201820011699U CN207988364U CN 207988364 U CN207988364 U CN 207988364U CN 201820011699 U CN201820011699 U CN 201820011699U CN 207988364 U CN207988364 U CN 207988364U
Authority
CN
China
Prior art keywords
reinforcing bar
waste material
steel reinforcement
card slot
shaper
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201820011699.5U
Other languages
Chinese (zh)
Inventor
刘成
江绪芫
周伟
屈小飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
No 2 Engineering Co Ltd of CCCC First Highway Engineering Co Ltd
CCCC First Highway Engineering Co Ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201820011699.5U priority Critical patent/CN207988364U/en
Application granted granted Critical
Publication of CN207988364U publication Critical patent/CN207988364U/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Reinforcement Elements For Buildings (AREA)

Abstract

The utility model discloses a kind of waste materials, and framework of steel reinforcement shaper, the first reinforcing bar waste material to be utilized to be mutually perpendicular to fixed reinforcing bar card slot with the first reinforcing bar waste material;Wherein, each reinforcing bar card slot is made of two second reinforcing bar waste materials, and in two second reinforcing bar waste materials are generally aligned in the same plane, and it parallel is welded on the first reinforcing bar waste material, by the way that reinforcing bar waste material is welded, it is fabricated to the reinforcing bar card slot positioning mold of wall, column, beam, and it is bound with framework of steel reinforcement, deviation does not occur for reinforcing bar when ensure that shearing wall size and casting concrete, facilitate the construction of wall, beam steel, so that reinforcing bar waste material has been obtained reasonable utilization, avoids the waste of bar material.

Description

A kind of waste material utilizes framework of steel reinforcement shaper
Technical field
The utility model is related to construction waste reutilization technology field, more particularly to a kind of waste material is shaped using framework of steel reinforcement Mold.
Background technology
Reinforcing bar is that the essential component part of modern architecture and concrete and other construction materials constitute society In most building constructions material.
In building construction process, the construction in the especially residential building building of large area can use a large amount of reinforcing bar, according to making With the demand of method and architectural design, bar material can be processed into different semi-finished product for using, in process can Many waste materials are generated, and waste material can not be utilized directly, often all recycled as waste product, causes the wave of bar material Take.
Therefore, the utilization rate for how improving reinforcing bar waste material avoids the waste of bar material, be those skilled in the art urgently The technical issues of solution.
Invention content
In view of this, the purpose of this utility model is to provide a kind of waste materials to utilize framework of steel reinforcement shaper, according to wall The design spacing of column dimension and construction reinforced bar welds reinforcing bar waste material, and the reinforcing bar card slot positioning mould of wall, column, beam is made Tool, facilitates the construction of wall, beam steel part, reinforcing bar waste material is made to be reasonably used, improve the utilization of reinforcing bar waste material Rate.
To achieve the goals above, the utility model adopts the following technical solution:
A kind of waste material utilizes framework of steel reinforcement shaper, including:First reinforcing bar waste material and reinforcing bar card slot;Wherein, Mei Gesuo It states reinforcing bar card slot and is enclosed with the first reinforcing bar waste material by two second reinforcing bar waste materials and set, and two second reinforcing bar waste materials In being generally aligned in the same plane, and parallel vertical is fixed on the first reinforcing bar waste material;And the two neighboring reinforcing bar card slot it Between distance be equal to construction reinforced bar designed distance.
Preferably, the first reinforcing bar waste material is connected by welding with the second reinforcing bar waste material.
Position and design spacing of the reinforcing bar card slot according to construction reinforced bar in framework of steel reinforcement, are arranged with corresponding spacing first On reinforcing bar waste material, it is the pre-set spacing of framework of steel reinforcement to ensure spacing in card slot of wall, beam steel just, without because The improper deformation for causing framework of steel reinforcement of constant spacing.
Preferably, the size of the reinforcing bar card slot is configured according to the size of the diameter of construction reinforced bar.
A kind of waste material disclosed by the utility model utilize framework of steel reinforcement shaper, by reinforcing bar waste material according to wall column size with And the design spacing of wall beam reinforcing bar is welded, and banding fixed is carried out with wall beam reinforcing bar, the position for strengthening wall column reinforcing bar is accurate True property makes wall not shift when carrying out concreting, facilitates the construction of wall, beam steel part, and it is useless to improve reinforcing bar The utilization rate of material avoids the waste of bar material.
Description of the drawings
In order to illustrate the embodiment of the utility model or the technical proposal in the existing technology more clearly, below will be to embodiment Or attached drawing needed to be used in the description of the prior art is briefly described, it should be apparent that, the accompanying drawings in the following description is only It is the embodiments of the present invention, for those of ordinary skill in the art, without creative efforts, also Other attached drawings can be obtained according to the attached drawing of offer.
Fig. 1 is the schematic diagram that waste material provided by the utility model utilizes framework of steel reinforcement shaper;
Fig. 2 is the structure chart that waste material provided by the utility model utilizes framework of steel reinforcement shaper;
Fig. 3 is the usage state diagram that waste material provided by the utility model utilizes framework of steel reinforcement shaper.
Specific implementation mode
The following will be combined with the drawings in the embodiments of the present invention, carries out the technical scheme in the embodiment of the utility model Clearly and completely describe, it is clear that the described embodiments are only a part of the embodiments of the utility model, rather than whole Embodiment.Based on the embodiments of the present invention, those of ordinary skill in the art are without making creative work The every other embodiment obtained, shall fall within the protection scope of the present invention.
The utility model embodiment discloses a kind of waste material and utilizes framework of steel reinforcement shaper, by carrying out reinforcing bar waste material Welding, be fabricated to the reinforcing bar card slot positioning mold of wall, column, beam, and bound with framework of steel reinforcement, ensure that shearing wall size and Deviation does not occur for reinforcing bar when casting concrete, facilitates the construction of wall, beam steel, so that reinforcing bar waste material has been obtained reasonable utilization, keeps away The waste of bar material is exempted from.Referring to Fig. 1, the utility model provides a kind of waste material and utilizes framework of steel reinforcement shaper, including: First reinforcing bar waste material 1 and reinforcing bar card slot 2;Wherein, each reinforcing bar card slot 2 is by two second reinforcing bar waste materials 3 and the first reinforcing bar waste material 1 encloses and sets, and in two second reinforcing bar waste materials 3 are generally aligned in the same plane, and parallel vertical is fixed on the first reinforcing bar waste material 1; And the distance between two neighboring reinforcing bar card slot 2 is equal to the designed distance of construction reinforced bar.
It needs to stress, in conjunction with attached drawing 2 and attached drawing 3, reinforcing bar card slot refers to by the first waste material in the utility model The space being set as is enclosed after reinforcing bar and two the second waste material reinforcement weldings parallel to each other, construction reinforced bar during Specific construction Insertion is enclosed in the space set, and sizing is played the role of.
On the one hand framework of steel reinforcement shaper provided by the utility model using waste material takes full advantage of steel bar meter and produces The characteristics of raw waste material, the processing complicated without other can turn waste into wealth, fully demonstrate green construction;On the other hand, sharp Reinforcement location and its spacing can be accurately controlled with the mold, and has arranged that the reinforcing bar of completion will not be in concreting It shifts in journey, strengthens the accuracy of the position of wall column reinforcing bar, wall beam size and shape is ensured, ensure that construction Quality.
In Specific construction, construction reinforced bar and reinforcing bar card slot 2 fixed thereto are implanted into wall column together and bound, because There is reinforcing bar card slot 2 mutually to be fixed with framework of steel reinforcement, construction reinforced bar is further ensured on the basis of binding to shift, and added The strong accuracy of wall column reinforcement location.
In order to advanced optimize above-mentioned technical proposal, the first reinforcing bar waste material 1 and the second reinforcing bar waste material 3 are by welding It is connected.
Using such design method, the position of the construction reinforced bar in framework of steel reinforcement and its spacing can accurately be controlled System, will not shift in concreting, ensure that construction reinforced bar position will not be sent out in wall, beam after the completion of concrete construction It is raw to change, so that wall, beam size and shape has been obtained abundant guarantee.
In order to advanced optimize above-mentioned technical proposal, the size of reinforcing bar card slot 2 according to the size of the diameter of construction reinforced bar into Row setting.
The size of reinforcing bar card slot 2 can be welded according to the size of the diameter of construction reinforced bar used in framework of steel reinforcement, to the greatest extent Amount reduces the gap between reinforcing bar and reinforcing bar card slot 2, and the shaper of the utility model is allow more perfectly to be bonded with reinforcing bar, Keep connection more firm on the basis of binding.
In some specific embodiments of the utility model, for the wall column reinforcing bar cloth that steel reinforcing difficulty itself is larger It sets, the framework of steel reinforcement shaper that multigroup the utility model can be used is combined banding fixed, facilitates construction, is improving The difficulty of project construction is reduced while wall column reinforcement construction quality.
A kind of waste material provided by the utility model is described in detail using framework of steel reinforcement shaper above, this It applies specific case in text to be expounded the principles of the present invention and embodiment, the explanation of above example is It is used to help understand the method and its core concept of the utility model;Meanwhile for those of ordinary skill in the art, according to this The thought of utility model, there will be changes in the specific implementation manner and application range, in conclusion the content of the present specification It should not be construed as a limitation of the present invention.
Each embodiment is described by the way of progressive in this specification, the highlights of each of the examples are with other The difference of embodiment, just to refer each other for identical similar portion between each embodiment.For device disclosed in embodiment For, since it is corresponded to the methods disclosed in the examples, so description is fairly simple, related place is said referring to method part It is bright.
The foregoing description of the disclosed embodiments enables professional and technical personnel in the field to realize or use this practicality new Type.Various modifications to these embodiments will be apparent to those skilled in the art, and determine herein The General Principle of justice can be realized in other embodiments without departing from the spirit or scope of the present utility model.Cause This, the utility model is not intended to be limited to the embodiments shown herein, and is to fit to and principles disclosed herein The widest range consistent with features of novelty.

Claims (3)

1. a kind of waste material utilizes framework of steel reinforcement shaper, which is characterized in that including:First reinforcing bar waste material (1) and reinforcing bar card slot (2);Wherein, each reinforcing bar card slot (2) enclosed by two second reinforcing bar waste materials (3) and the first reinforcing bar waste material (1) set and At, and in two second reinforcing bar waste materials (3) are generally aligned in the same plane, and parallel vertical is fixed on the first reinforcing bar waste material (1) on;And the distance between two neighboring described reinforcing bar card slot (2) is equal to the designed distance of construction reinforced bar.
2. a kind of waste material according to claim 1 utilizes framework of steel reinforcement shaper, which is characterized in that first reinforcing bar Waste material (1) is connected by welding with the second reinforcing bar waste material (3).
3. a kind of waste material according to claim 2 utilizes framework of steel reinforcement shaper, which is characterized in that the reinforcing bar card slot (2) size is configured according to the size of the diameter of construction reinforced bar.
CN201820011699.5U 2018-01-04 2018-01-04 A kind of waste material utilizes framework of steel reinforcement shaper Expired - Fee Related CN207988364U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201820011699.5U CN207988364U (en) 2018-01-04 2018-01-04 A kind of waste material utilizes framework of steel reinforcement shaper

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201820011699.5U CN207988364U (en) 2018-01-04 2018-01-04 A kind of waste material utilizes framework of steel reinforcement shaper

Publications (1)

Publication Number Publication Date
CN207988364U true CN207988364U (en) 2018-10-19

Family

ID=63818740

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201820011699.5U Expired - Fee Related CN207988364U (en) 2018-01-04 2018-01-04 A kind of waste material utilizes framework of steel reinforcement shaper

Country Status (1)

Country Link
CN (1) CN207988364U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113482154A (en) * 2021-08-05 2021-10-08 苏州达康建筑科技有限公司 Assembly type beam-column joint structure, device and installation method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113482154A (en) * 2021-08-05 2021-10-08 苏州达康建筑科技有限公司 Assembly type beam-column joint structure, device and installation method

Similar Documents

Publication Publication Date Title
CN107989274B (en) Reinforcing steel bar locating plate for construction of building upright post
CN205058277U (en) Prefabricated T girder iron muscle mould
CN210659276U (en) Template positioning device for thickness of shear wall and concrete protective layer
CN102441625B (en) Wire cutting mechanism for full-automatic rebar tying machine
CN205653782U (en) Mould is repaired to bored concrete pile pile head
CN207988364U (en) A kind of waste material utilizes framework of steel reinforcement shaper
CN209533739U (en) A kind of energy-saving prefabricated component assembly type overlapping board mold
CN214696902U (en) Different intensity grade concrete placement shaping isolating device of beam column node
CN105421341A (en) Large-diameter pile foundation reinforcement cage manufacturing method
KR20120004049A (en) Site reinforcing method of thick wall with using plant welded steel bar frames
CN210031723U (en) Diversion tunnel inverted arch template anti-floating device
CN204867878U (en) Steel grating mould
CN105350718A (en) Reinforcement permanency beam formwork and manufacturing method for concrete structural member with shearing resistance
CN206539005U (en) Formwork structure for narrow and small movement joint both sides shear wall construction
CN201512946U (en) Barrel storeroom sliding form system structure
CN104153386A (en) Tool-type steel die of pile foundation pile cap surrounding facade cushion layer and construction method of tool-typed steel die
CN212772789U (en) Assembled building reinforced concrete member
CN200992775Y (en) Welded steel fabric mesh
CN209228033U (en) Regularization template external corner reinforcing device
CN207377122U (en) A kind of mold fixing piece and fixed frame
CN208502072U (en) A kind of stirrup assembling structure
CN209394979U (en) A kind of high-precision cover board reinforcing bar positioning one-time-shaped mould
CN201850700U (en) Secondary beam of corrugated web H-shaped steel floor and supporting support rod
CN105696729A (en) Combined constructional column capable of being recycled and reutilized in wall
CN205975369U (en) A reinforcing bar pinion rack template that is used for case liang fuwanjuchu

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20191023

Address after: 100020 Beijing, Guanzhuang, Chaoyang District, Zhou

Co-patentee after: NO.2 ENGINEERING CO., LTD. OF CCCC FIRST HIGHWAY ENGINEERING Co.,Ltd.

Patentee after: CHINA FIRST HIGHWAY ENGINEERING Co.,Ltd.

Address before: 215000 Suzhou Changjiang Road, Jiangsu 879 No.

Patentee before: Liu Cheng

CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20181019

Termination date: 20210104